Second Floor Renovation by Contract

download Second Floor Renovation by Contract

of 78

Transcript of Second Floor Renovation by Contract

  • 8/11/2019 Second Floor Renovation by Contract

    1/78

    Project : PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING

    Location : Pilar Street, Zamboanga City

    Scope of Work :A. NON ENGINEERING BASIC COST

    I. PERMIT & FEES

    II. CONSTRUCTION SAFETY & HEALTH PROGRAM

    III. CONSTRUCTION OF ONE (1) UNIT TEMPORARY FACILITY

    B. ENGINEERING BASIC COST

    A. RENOVATION OF SECOND FLOOR

    I. MOBILIZATION/DEMOBILIZATION

    III. CONSTRUCTION OF TEMPORARY OFFICE

    IV. MASONRY WORKS

    IX. ELECTRICAL WORKS

    X. PAINTING WORKS

    XI. FIXTURES AND OFFICE EQUIPMENT

    B. CONSTRUCTION OF COOP OFFICE/CANTEEN & STORAGE ROOM (FLOOR AREA = 65.87 SQ.M.)

    I. MOBILIZATION

    II. LAYOUTING WORKS

    III. CONCRETING WORKS

    IV. MASONRY WORKS

    V. CARPENTRY WORKS

    VI. ROOFING WORKS

    VII. STEEL WORKS

    VIII. ELECTRICAL WORKS

    IX. PLUMBING WORKS

    X. PAINTING WORKS

    XI. DEMOBILIZATION

    PROJECT COST :

    Qty. Unit Unit

    A. NON ENGINEERING BASIC COST

    I. PERMIT & FEES

    1. Building Permit 1 lot 15,0

    DIRECT COST

    II. CONSTRUCTION SAFETY & HEALTH PROGRAM

    1. Public Safety & Health Program 1 lot 20,0

    DIRECT COST

    III. CONSTRUCTION OF ONE (1) UNIT TEMPORARY FACILITY

    A. Material:

    12 - pcs. 2" x 4" x 10' Coco Lumber 80 bd.ft.

    14 - pcs. 2" x 3" x 10' Coco Lumber 70 bd.ft.

    20 - pcs. 2" x 2" x 10' Coco Lumber 67 bd.ft.

    Guage 26 x 1.20m x 2.40m Corrugated G.I. Roof Sheet 16 pcs. 2

    Gauge 26 x 1.20m x 2.40m G.I. Plain Sheet 1 pc. 4

    12mm Thick x 1.20m x 2.40m Ordinary Plywood 14 pcs. 7

    2" C.W. Umbrella Roofing Nail 2 kgs. 6

    3" C.W. Nail 2 kgs. 64" C.W. Nail 2 kgs. 6

    3-1/2" Loose Pin Hinges 2 pcs. 21

    Republic of the Philippines

    ZAMBOANGA CITY WATER DISTRICT

    Pilar Street, Zamboanga City

    VI. CARPENTRY WORKS

    VII. PLUMBING WORKS

    VIII. SPRINKLER SYSTEM

    5,901,401.00Php

    BILL OF MATERIALS & COST ESTIMATES

    ITEM DESCRIPTION

  • 8/11/2019 Second Floor Renovation by Contract

    2/78

    B. ENGINEERING BASIC COST

    A. RENOVATION OF SECOND FLOOR

    I. MOBILIZATION/DEMOBILIZATION 1 lot 40,0

    DIRECT COST

    II. DEMOLITION WORKS AND CLEARING

    A. Labor:

    4 - Skilled Worker 45 days 38 - Laborers 45 days 3

    B. Equipment Rental/Fuel:

    1 - Unit Dump Truck 25 days 5,0

    Diesel/Fuel 250 liters

    DIRECT COST

    III. CONSTRUCTION OF TEMPORARY OFFICE

    A. Materials:

    Partition & Cubicle Work:

    6mm thk x 1.20m x 2.40m Ordinary Plywood 52 shts. 3

    220 pcs. - 2" x 3" x 8' Red Lauan Wood 880 bd.ft.

    Concrete Nail 4" 6 kgs.

    CW Nail 2-1/2" 4 kgs.

    Electrical Work (58 Outlets):

    48" Industrial Ceiling Fan (3-Blade, 80 Watts Power, 220V, Ceiling Type) 14 units 6,0

    8 Branch Panel Board Box, Bolt-On Type 1 pc. 5,0

    100 Ampere Circuit Breaker, Bolt-On, 230 Volts, 2P 1 pc. 1,4

    20 Ampere Circuit Breaker, Bolt-On, 230 Volts, 2P 8 pcs. 5

    22mm2THW Stranded Wire 22 mtrs. 2

    3.5mm2TW Stranded Wire 6 rolls 6,3

    14/2c Flat Cord 75 mtrs.

    40 Watts Fluorescent Lamp, Box Type Assembly 24 pcs. 2

    2-Gang Switch (Flush Type) w/ Plate 3 pcs. 1

    3-Gang Convenience Outlet, Surface Type 30 pcs.

    Duplex Convenience Outlet w/ Plate 15 pcs. 112mm Hook 30 pcs.

    2"x4"x2" Utility Box 18 pcs.

    4"x4" Junction Box 30 pcs.

    4"x4" Junction Box Cover 30 pcs.

    20mm FlexibleConduit 250 mtrs.

    25mm x 3m Electrical Molding Conduit 38 pcs. 1

    #14 G.I. Tie-wire 5 kgs.

    12mm Insulated Staple 1 box

    Rubber Tape 3 pcs.

    Electrical Tape 1 pc.

    Tarpaulin Canvass Lona, S200, 7mmthk x 1.83m x 50m/roll (Color White) 1 roll 7,7

    19mm x 6.00m G.I. Pipe, Sch. 40 14 pcs. 6

    4mm thk x 38mm x 6.00m Flat Bar 1 pc. 58mm x 25mm Ordinary Bolt, w/ Nut & Washer (Full Threaded) 28 pcs.

    50mm x 6.00m G.I. Pipe, Sch. 40 16 pcs. 1,8

    8mm Nylon Rope (600 ft./roll) 0.25 roll 18,4

    B. Labor:

    3 - Carpenters 15 days 3

    1 - Electrician 15 days 3

    4 - Laborers 15 days 3

    DIRECT COST

    IV. MASONRY WORKS

    A. Materials:

    Portland Cement 90 bags 2Washed Sand 3 cu.m. 1,0Fine Sand (For Plastering) 0.25 cu.m. 1,3100mm x 200mm x 400mm CHB 350 pcs.

  • 8/11/2019 Second Floor Renovation by Contract

    3/78

    3 - Masons 10 days 3

    3 - Laborers 10 days 3

    DIRECT COST

    V. TILE WORKS

    A. Materials:

    Tile Grout 15 packs 1

    600mm x 600mm x Granite Tiles 1160 pcs. 2300mm x 300mm Ceramic Tiles 1280 pcs.

    20mm thk. 0.60m x 2.13m Granite Slab 4 units 6,5

    6mm Tile Trim 6 pcs. 2

    B. Labor:

    3 - Masons 25 days 3

    3 - Laborers 25 days 3

    DIRECT COST

    VI. CARPENTRY WORKS

    A. Materials:

    1. CEILING WORKS3.50mm thk. 1.20m x 2.40m Hardiflex Lite Ceiling Board 140 pcs. 4

    6mm thk x 1.20m x 2.40m Marine Plywood 12 shts. 419mm thk x 1.20m x 2.40m Marine Plyboard 24 shts. 1,11" x 2" x 8' Red Lauan Wood 16 bd.ft.

    2" x 2" x 8' Red Lauan Wood 1800 bd.ft.4" Concrete Nail 10 kgs.3" CW Nail 27 kgs.

    2' CW Nail 10 kgs.2" Finishing Nail 5 kgs.Hardi Nail 33 kgs. 11" x 5" x 8' Baseboard 60 pcs. 1

    2. WALLING/PARTITION AND CUBICLE WORKS2" x 4" x 10' Red Lauan Wood 1068 bd.ft.6mm thk x 1.20m x 2.40m Ordinary Plywood 110 shts. 34" CW Nail 20 kgs.

    3" CW Nail 15 kgs.2" CW Nail 10 kgs.1" Finishing Nail 7 kgs.

    1" x 5" x 8' Baseboard 150 pcs. 1

    3. FABRICATION OF OFFICE TABLES, CABINET & SHELVE

    6mm thk x 1.20m x 2.40m Ordinary Plywood 15 shts. 3

    20mm thk x 1.20m x 2.40m Plyboard 98 shts. 9400mm Length Roller Slide 139 setsDrawer Lock 139 sets 1

    Drawer Handle 139 setsUpholstery Cloth 53 mtrs. 1Solvent (Rugby) 6 gals. 53" CW Nail 1 kg.

    2" Finishing Nail 30 kgs.

    1-1/2" Finishing Nail 20 kgs.1" Finishing Nail 7 kgs.

    1" x 1" Wooden Nosing 30 bd.ft.1" x 2" Wooden Nosing 45 bd.ft.25mm x 6.00 Stainless Tubing 1 pcs. 910mm x 50mm Stainless Bolt w/ Nut & Washer 20 pcs.

    2" x 4" x 10' Red Lauan Wood 30 bd.ft.

    4. DOORS/WINDOWS & GLASS (Job Order)

    D1 - 0.60m x 1.20m PVC Door, w/ PVC Door Jamb, and w/ Complete Hinges, w/out Door KnobD2 - 0.80m x 2.10m Panel Type Door, w/ 2" x 6" Jamb,

    2" x 4" Door Frame, 6mm thk. Marine PlywoodD3 - Double Swing Door, 2" x 4" Alum. Frame/Jamb Analok Glass Aluminum Door Frame

    Aluminum Analok Sliding Window, 6mm Thk. Bronze Glass 10 units 11,3

    Fixed Glass/Aluminum Frame Analok , 6mm Thk. Bronze Glass 2 units 18,30.60m x 1.20m, 6mm Thk. Clear Glass 21 units 80.60m x 1.50m, 6mm Thk. Clear Glass 4 units 1,1

    5 units 5,5

    3 units 15,4

    2 units 2,2

  • 8/11/2019 Second Floor Renovation by Contract

    4/78

    B. Labor:

    3 - Carpenters 90 days 36

    3 - Laborers 90 days 31

    C. Equipment Rental:

    1 - Unit Welding Machine 15 days 2,16

    DIRECT COST

    VII. PLUMBING WORKS

    A. Materials:Flush Type Water Closet w/ Complete Fittings and Accessories 6 sets 5,00Porcelain Lavatory w/ Complete Fittings and Acessories 4 sets 2,30Urinal w/ Complete Fittings and Acessories 2 sets 3,50Undermount Porcelain Lavatory w/ Complete Fittings And Accessories 2 sets 4,00Soap Holder 4 pcs. 15Tissue Holder 2 pcs. 25100mm x 100mm Stain. Floor Drain w/ Double Strainer 4 pcs. 20Solvent Cement 1 can 950mm x 3.0m PVC Pipe 6 pcs. 2550mm x 50mm PVC Elbow 8 pcs. 350mm PVC Coupling 6 pcs. 2Water Faucet 8 pcs. 12

    B. Labor:

    1 - Plumber 7 days 31

    2 - Laborers 7 days 31

    DIRECT COST

    VIII. SPRINKLER SYSTEM

    A. Materials & Labor:

    SUPPLY, INSTALLATION, TESTING & COMMISSIONING OFONE (1) UNIT 10HP CENTRIFUGAL PUMP WITH MOTOR,MOTOR CONTROLS, CONTROL PANEL, 3 PHASEWITH PUMP OUTLET & INLET OF 4" DIAMETER WITH STEELBED PLATE

    SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF

    ONE (1) Lot Wet Fire Sprinkler System Complete with PipingPendent Type Sprinkler Head and Acessories

    (Note: Actual Piping Lay out to refer on project site)

    DIRECT COST

    IX. ELECTRICAL WORKS

    A. Materials:150AT/150AF, 230V, 3P, Three Phase, Common Trip Main Circuit Breaker 1 set 81

    100 Amps. Molded Case Main Circuit Breaker, 3 Phase250 volts enclosed in Powder Coated Finished Panel Boardwith 7 Single Phase Branches of:

    Lumpsum

    1 unit 150,00

  • 8/11/2019 Second Floor Renovation by Contract

    5/78

    1 sets - 20 Amps. Branch

    6 sets - 15 Amps. Branch 1 set 7,

    100 Amperes Main Circuit Breaker, 3 Phase,250 volts enclosed in Powder Coated Finished Panel Board

    with 12 Single Phase Branches of:

    3 sets - 60 Amps. Branch

    2 sets - 30 Amps. Branch

    6 sets - 20 Amps. Branch 1 sets - 15 Amps. Branch 1 set 8,

    100 Amperes Main Circuit Breaker, 3 Phase,

    250 volts enclosed in Powder Coated Finished Panel Board

    with 4 Single Phase Branches of:

    5 sets - 50 Amps. Branch 1 sets - 30 Amps. Branch 1 set 7,

    30 Amperes, 2P, Safety Breaker 2 pc.60 Amperes, 2P, Safety Breaker 5 pc.

    11 Watts, 2U, Compact Fluorescent Lamp, Cool Daylight 6 pcs.

    13 Watts, 2U, Compact Fluorescent Lamp, Cool Daylight 18 pcs.

    15 Watts, 2U, Compact Fluorescent Lamp, Cool Daylight 35 pcs.18 Watts, 3U, Compact Fluorescent Lamp, Cool Daylight 69 pcs.

    23 Watts, 3U, Compact Fluorescent Lamp, Cool Daylight 2 pcs.

    20 Watts Box Type Fluorescent Lamp 2 pcs.40 Watts Box Type Fluorescent Lamp 2 pcs.Recessed Type Downlights w/o Cover, E27 124 pcs.

    Emergency lamp 8 pcs.

    40 Watts Fluorescent Lamp, Cool Daylight, Recessed Type,

    Mirrorized Fluorescent Louminaires, 2x40watts Assembly

    Exaust Fan, Wall Mounted 2 pcs. 1

    Duplex Convenience Outlet w/ plate (flush type) 52 pcs.

    Aircon Outlet 1 Gang 5 pcs.

    Ceiling Socket with screw 8 pcs.

    Toggle Switch 1-Gang w/ plate (flush type) 6 pcs.

    Toggle Switch 2-Gang w/ plate (flush type) 9 pcs.

    Toggle Switch 3-Gang w/ plate (flush type) 13 pcs.

    3-Way Switch w/ plate (flush type) 4 pcs.

    38.0mm2THW Stranded Wire 75 mtrs.

    22.0mm2THW Stranded Wire 30 mtrs.

    5.5mm2THW Stranded Wire 3 rolls 9

    3.5mm2THW Stranded Wire 150 mtrs.

    3.5mm2TW Stranded Wire 8 rolls 4

    2.0mm2TW Stranded Wire 10 rolls 3

    40mm x 3m RSC Electrical Conduit 5 pcs.

    40mmx 90 RSC Electrical Conduit Elbow Long Sweep 2 pcs.

    40mm RSC Coupling 5 pcs.

    40mm RSC Locknut 2 pcs.

    40mm RSC Condulet 1 pcs.

    40mm Conduit Clamp 20 pcs.

    40mm G.I. Flexible Conduit, Corrugated Pipe 2 mtrs.

    40mm Conduit Straight Connector 2 mtrs.32mm x 3.00m PVC Electrical Conduit 4 pcs.

    32mm PVC Male Adaptor 8 pcs.

    32mm PVC Lock Nut (Zinc Coated) 8 pcs.

    25mm PVC Flexible Electrical Conduit 6 mtrs.

    25mm x 3.00m PVC Electrical Conduit 19 pcs.

    25mm x 90 PVC Electrical Conduit Elbow Long Sweep 10 pcs.

    25mm PVC Electrical Coupling Connectors 18 pcs.

    25mm PVC Male Adaptor 12 pcs.

    25mm PVC Lock Nut (Zinc Coated) 12 pcs.

    20mm PVC Flexible Electrical Conduit 2 roll

    20mm x 3.00m PVC Electrical Conduit 750 pcs.

    20mm x 90 PVC Electrical Conduit Elbow Long Sweep 50 pcs.

    20

    mm

    PVC Electrical Coupling Connectors 250 pcs.20mm PVC Male Adaptor 150 pcs.

    20mm PVC Lock Nut (Zinc Coated) 150 pcs.

    2" 4" 2" PVC Utilit B ( H D ) 77

    17 pcs. 2

  • 8/11/2019 Second Floor Renovation by Contract

    6/78

    1/2" Camridge / Mica Tube 6 mtrs. 2

    3/4" Polytype Electrical Tape 10 pcs. 3

    3/4" Rubber Tape 5 pcs. 10

    B. Labor:2 - Electrician 36 days 362 - Laborers 36 days 31

    DIRECT COST

    X. PAINTING WORKS

    Conrete Neutralizer 2 gals. 48Penetrating Sealant 20 gals. 51Solvent-Based Acrylic Primer 90 gals. 66Putty Filler Cast 60 gals. 43Solvent-Based Acrylic Primer Top Coat (White) 120 gals. 78

    Acrylic Based Reduction Thinning 40 gals. 36Tinting Color for Solvent-Based Acrylic Paint:

  • 8/11/2019 Second Floor Renovation by Contract

    7/78

    Lamp Black 170 pint 10Raw Sienna 400 pint 10

    Toloudine Red 30 pint 10Putty Filler w/ Hardener 40 qrts. 17

    Patching Compound 10 kgs. 1

    Lacquer Thinner 20 gals. 42Lacquer Flow 10 gals. 58

    Sanding Sealer 25 gals. 540Paint Thinner 10 gals. 341

    Baby Roller Cotton w/ Tray 8 pcs. 337" Roller Brush w/ Tray 8 pcs. 33

    2" Paint Brush 8 pcs. 10

    4" Paint Brush 8 pcs. 45Rust Converter 3 gals. 475

    Zinc Chromate 4 gals. 86# 150 Sand Paper 10 doz. 10

    # 120 Sand Paper 10 doz. 10

    B. Labor:4 - Painters 60 days 31

    4 - Laborers 60 days 31

    DIRECT COST

    XI. FIXTURES AND OFFICE EQUIPMENT

    Executive Chair Executive Chair w/ Black Leatherette back and seat molded foam cushion,

    lockable tilting mechanism, polyurethane or polypropylene armrest, five legged and black

    leatherette back and nylon twin caster pneumatic height adjustment. 16 units 4,20

    Office Chair w/ Low back and seat molded foam cushion, lockable tilting mechanism,

    polyurethane or polypropylene armrest, five legged and black leatherette back

    and nylon twin caster pneumatic height adjustment. 25 units 2,30

    Visitors Chair w/ four legged, back and sit molded foam cushion, polypropylene armrest,

    shiny chromed chair frame 11 units 1,60

    Sala Set 2 sets 14,00

    Packaged Supply,Installation & Testing of Two (2) Units Ceiling Mounted Split Type, Cassette Air Conditioner

    Specs:

    Cooling Capacity - 58,000 Btu/hr

    Capacity - 5 TRPower - 3P/220 V/60 Hz

    - LCD remote Type w/ Auto timer on/off, Sleep Mode,Dry Mode, Auto Fan Speed, Night Timer,Real Time Clock

    - With inverter, Heating & Cooling

    - High efficiency

    - Eco Friendly

    - Automatic Drain Pump

    - Two thermistor control function

    - Alarm function for filter cleaning 2 units 108,00

    Labor (Lump Sum) 1 lot 10,00

    Packaged Supply & Intallation of Ceiling Mounted Projector & Projector Screen 1 unit 59,180

    Specs:

    240VAC, 60Hz, 300W projector with 0.80-7.5 meters diagonally projection size, full color,ceiling mounted ready installation,moulded plastic, 307mm x 69mm x 210mm dimension,

    approx. 2.3 kgs, 0o-40

    oC temperature, 20%-80% humidity, with 2 meters power cord,

    power cord secure lock, wireless remote control, VGA cable, carrying bag and application

    software (CD-ROM). With metal ceiling mount projector bracket.

    And with 1.7m wide - 78" diagonal projector screen, matt white surface with 3cm black border

    and weighted bottom bar. Housed in a white case with mounting brackets on either end.

    Can be operated with in-line control switch or a wirless remote control. Ceiling and wall

    mounting compatible, low noise electric motor, 240 VAC input, 60 Hz. Remote control

    distance of 20m.

    Labor (Lump Sum) 1 lot 5,00

    DIRECT COST

    B. CONSTRUCTION OF COOP OFFICE/CANTEEN & STORAGE ROOM (FLOOR AREA = 65.87 SQ.M.)

    I. MOBILIZATION 1 lot 10,00

  • 8/11/2019 Second Floor Renovation by Contract

    8/78

    4" C.W. Nail 1 kg. 654" Concrete Nail 1 kg. 71

    B. Labor:2 - Carpenters 1 day 366

    DIRECT COST

    III. CONCRETING WORKSA. Materials:

    FlooringPortland Cement 39 bags 230

    Washed Sand 2 cu.m. 1,000Gravel (G-1) 4 cu.m. 1,00010pcs. - 2" x 4" x 10' Coco Lumber 67 bd.ft. 20

    4" Concrete Nail 1 kg. 142

  • 8/11/2019 Second Floor Renovation by Contract

    9/78

    B. Labor:2 - Masons 2 days 362 - Carpenters 2 days 361 - Steelman 2 days 366 - Laborers 2 days 31

    DIRECT COST

    IV. MASONRY WORKS

    A. Materials:

    1. Floor Tiles0.40m x 0.40m Granite Tiles (White) 266 pcs. 12Portland Cement 12 bags 23Fine Sand (for plastering) 1 cu.m. 1,20Tile Grout (cement joint filler) 10 packs 4

    B. Labor:

    2 - Masons 8 days 36

    4 - Laborers 8 days 31

    C. Equipment Rental:1 - Unit Angular Grinder 8 days 30

    2. Kitchen CounterPortland Cement 5 bags 23Washed Sand 0.25 cu.m. 1,00Gravel (G-1) 0.10 cu.m. 1,00Fine Sand (for plastering) 0.10 cu.m. 1,2010mm x 6.00m Deformed Reinforcing Steel Bars 4 pcs. 16#16 G.I. Tie-wire 1 kg. 612mm thk x 1.20m x 2.40m Ordinary Plywood 1 sht. 756pcs. - 2" x 3" x 10' Coco Lumber 30 bd.ft. 24" C.W. Nail 1 kg. 64" CHB (NBL) 53 pcs. 10.20m x 0.20m Granite Tiles (White) 90 pcs. 6PVC Tile Trim 2 pcs. 5Tile Grout (cement joint filler) 4 packs 4

    B. Labor:

    2 - Masons 4 days 36

    1 - Laborer 4 days 31

    C. Equipment Rental:

    1 - Unit Angular Grinder 4 days 30

    DIRECT COST

    V. CARPENTRY WORKS

    A. Materials:

    1. Ceiling Works56pcs. - 2" x 4" x 10' S4s Lauan Wood 373 bd.ft. 456pcs. - 2" x 2" x 10' S4s Lauan Wood 186 bd.ft. 412mm thk x 1.20m x 2.40m Marine Plywood 6 shts. 635mm thk x 1.20m x 2.40m Marine Plywood 14 shts. 33

    4" C.W. Nail 6 kgs. 63" C.W. Nail 4 kgs. 62" C.W. Nail 5 kgs. 6

    B. Labor:

    2 - Carpenters 10 days 362 - Laborers 10 days 31

    A. Materials:

    2. Wall/Wall Partition1pc. - 4" x 4" x 10' S4s Lauan 14 bd.ft. 4

    94pcs. - 2" x 4" x 10' S4s Lauan Wood 627 bd.ft. 45mm thk x 1.20m x 2.40m Marine Plywood 44 shts. 384" C.W. Nail 10 kgs. 62" C.W. Nail 11 kgs. 6

    B. Labor:

    2 - Carpenters 5 days 36

    4 Laborers 5 days 31

  • 8/11/2019 Second Floor Renovation by Contract

    10/78

    1 1/2" C.W. Nail 2 kgs. 6

    B. Labor:

    2 - Carpenters 2 days 36

    2 - Laborers 2 days 31

    A. Materials:4. Counter Top

    19mm thk x 1.20m x 2.40m Marine Plywood 10 shts. 1,025mm thk x 1.20m x 2.40m Marine Plywood 2 shts. 38Wood Glue 3 liters 112" C.W. Nail 3 kgs. 61.20m x 2.40m Plastic Formica 2 shts. 30Rubber Cement Solvent 4 btls. 82" x 2" Cabinet Hinges 44 pcs. 138mm Wooden Cabinet Handle 22 pcs. 1

    B. Labor:

    2 - Carpenters 4 days 36

    2 - Laborers 4 days 31

    A. Materials:5. Door and Window Jambs (Job Order)

    0.90m x 2.10m x 0.05m x 0.15m Yakal/Hardwood Door Jambs 2 sets 1,501.40m x 1.20m x 0.05m x 0.15m Yakal/Hardwood Window Jambs 1 set 1,20

    A. Materials:6. Doors & Window (Job Order)

    0.90m x 2.10m Flush Door w/ 5mm thk Marine Plywood, Double 2 sets 3,500 Walling on 50mm x 100mm Door Frame, Door Knob5mm thk, 13 Blades Smoke Glass Jalousie Window w/ Standard 2 sets 680 Alum. Frame Holder (0.70m x 1.20m)

    A. Materials:7. Ventillation (Job Order) 2 units 7025mm thk x 250mm x 1.20m Pre-fabrication Wooden Ventillation

    DIRECT COST

    VI. ROOFING WORKSA. Materials:

    12mm thk x 1.20m x 2.40 Marine Plywood 22 shts. 63018pcs. - 2" x 2" x 10' S4s Lauan Wood 60 bd.ft. 3614pcs. - 2" x 3" x 10' S4s Lauan Wood 67 bd.ft. 3624pcs. - 2" x 3" x 8' S4s Lauan Wood 96 bd.ft. 3616pcs. - 2" x 2" x 8' S4s Lauan Wood 43 bd.ft. 364" C.W. Nail 4 kgs. 652" C.W. Nail 6 kgs. 65

    B. Labor:

    2 - Carpenters 5 days 36

    4 - Laborers 5 days 31

    DIRECT COST

    VII. STEEL WORKSA. Materials:

    50mm x 6.00m G.I. Pipe, Sch. 40 2 pcs. 2,2312mm x 6.00m Aluminum Tube 2 pcs. 653mm x 25mm x 25mm x 3.00m Alum. Angle Bar 4 pcs. 154mm x 25mm x 25mm x 6.00m Angle Bar 3 pcs. 614mm x 38mm x 6.00m Flat Bar 3 pcs. 3510mm x 10mm x 6.00m Square Bars 6 pcs. 185mm thk x 25mm x 6.00m Flat Bar 2 pcs. 19

    B. Labor:

    1 - Steelman 3 days 36

    1 - Welder 3 days 36

    2 - Laborers 3 days 31

    C. Equipment Rental:

    1 - Unit Welding Machine 2 days 2,20

    DIRECT COST

  • 8/11/2019 Second Floor Renovation by Contract

    11/78

    4 sets - 20 Amps. Branch

    1 sets - 15 Amps. Branch 1 unit 52

    8.0mm2THW Stranded Wire 16 mtrs.

    3.5mm2THW Stranded Wire 2 rolls 41

    16" Orbit Fan, Standard 2 sets 1512" exhaust fan 2 sets 12

    3U Electronic CFL with Capsule, Daylight, 23W Assembly 5 sets 3Ceiling Socket with screw 13 sets

    Reccessed Fluorescent illuminaire,1x40 Watts assemblyin Powder Coated Steel Plate; IP20 Assembly 4 sets 2

    Duplex Convenience Outlet w/ plate (flush type) 7 sets 2Toggle Switch 3-Gang w/ plate (flush type) 2 sets 1

    Toggle Switch 1-Gang w/ plate (flush type) 1 set

    25mm (3/4") PVC Flexible Electrical Conduit 15 pcs. 2

    25mm(3/4") x 90 PVC Electrical Conduit Elbow Long Sweep 5 pcs.

    25mm (3/4")PVC Electrical Coupling Connectors 14 pcs.

    25mm (3/4") PVC Male Adaptor 2 pcs.

    25mm (3/4") PVC Lock Nut (Zinc Coated) 2 pcs.

    25mm (3/4") PVC clamps w/ concrete nails 1 box 1

    20mm (1/2") PVC Flexible Electrical Conduit 25 mtrs.

    20mm (1/2") x 3.00m PVC Electrical Conduit 20 pcs. 2

    20mm (1/2") x 90 PVC Electrical Conduit Elbow Long Sweep 3 pcs.

    20mm

    (1/2") x 90 PVC Electrical Conduit Short Elbow 5 pcs.20mm(1/2") PVC Electrical Coupling Connectors 8 pcs.

    20mm (1/2") PVC Male Adaptor 4 pcs.

    20mm (1/2") PVC Lock Nut (Zinc Coated) 4 pcs.

    20mm (1/2") PVC clamps w/ concrete nails 3 boxes 1

    2" x 4" x 2" PVC Utility Box ( H.D.) 15 pcs.4" x 4" x 2" PVC Junction Box ( H.D.) w/ Cover 20 pcs.

    #16 G.I. Tie Wire 2 kgs.6" x 6" x 4" Gal. Pull Box 2 pcs. 5

    PVC Solvent Cement 1 qrt. 31/2" Camridge / Mica Tube 6 pcs.

    3/4" Polytype Electrical Tape 3 pcs.3/4" Rubber Tape 1 pc. 1

    B. Labor:

    1 - Skilled Electrician 5 days 3

    2 - Laborers 5 days 3

    DIRECT COST

    IX. PLUMBING WORKS

    A. Materials:50mm x 3.00m Sanitary PVC Pipe, Series-1000 12 pcs. 2

    50mm x 900Sanitary PVC Elbow, Series-1000 6 pcs.

    50mm x 450Sanitary PVC Elbow, Series-1000 2 pcs.PVC Cement Solvent 2 qrts. 2

    12mm x 900G.I. Elbow, Sch. 40 10 pcs.12mm x 6.00m G.I. Pipe, Sch. 40 5 pcs. 5

    Teflon Tape 10 rollsStainless Kitchen Sink, w/ Strainer drain assembly 1 set 1,9

    w/ Plug & complete water supply fitting

    B. Labor:

    1 - Plumber 3 days 3

    2 - Laborers 3 days 3DIRECT COST

    X. PAINTING WORKS

    A. Materials:Liquid Tile Primer 13 gals. 6Liquid Tile Putty Filler 18 gals. 4

    Liquid Tile Reducer 8 gals. 3Liquid Tile Top Coat (Glossy White) 14 gals. 7

    Lamp Black Tinting Color 2 pints 1Raw Sienna Tinting Color 2 pints 1

    Thalo Blue Tinting Color 2 pints 1Venetian Red Tinting Color 2 pints 1

    Burnt Umber Tinting Color 2 pints 1

    l

  • 8/11/2019 Second Floor Renovation by Contract

    12/78

    # 120 Sand Paper 2 dozs. 105.0

    B. Labor:

    1 - Painter 10 days 366.0

    4 - Laborers 10 days 317.0

    DIRECT COST

    XI. DEMOBILIZATION 1 lot 10,000.0

    TOTAL DIRECT COST

  • 8/11/2019 Second Floor Renovation by Contract

    13/78

  • 8/11/2019 Second Floor Renovation by Contract

    14/78

    Total Cost

    15,000.00

    15,000.00

    20,000.00

    20,000.00

    19,760.00

  • 8/11/2019 Second Floor Renovation by Contract

    15/78

    40,000.00

    40,000.00

    180,000.00

    137,250.00

    317,250.00

    207,594.00

    50,993.00

    40,980.00

    299,567.00

  • 8/11/2019 Second Floor Renovation by Contract

    16/78

    20,490.00

    53,485.00

    335,130.00

    51,225.00

    386,355.00

    156,635.00

    97,094.00

    150,860.00

  • 8/11/2019 Second Floor Renovation by Contract

    17/78

    184,410.00

    32,400.00

    909,159.00

    59,096.00

    6,657.00

    65,753.00

    560,149.00

    560,149.00

  • 8/11/2019 Second Floor Renovation by Contract

    18/78

  • 8/11/2019 Second Floor Renovation by Contract

    19/78

    306,954.00

    49,176.00356,130.00

  • 8/11/2019 Second Floor Renovation by Contract

    20/78

    311,903.00

    152,160.00464,063.00

    170,300.00

    226,000.00

    64,180.00

    460,480.00

    10,000.00

  • 8/11/2019 Second Floor Renovation by Contract

    21/78

    1,368.00

    732.002,100.00

    16,381.00

  • 8/11/2019 Second Floor Renovation by Contract

    22/78

    7,464.0023,845.00

    38,764.00

    16,000.00

    2,400.0057,164.00

    10,498.00

    4,196.00

    1,200.0015,894.00

    73,058.00

    31,735.00

    13,660.00

    45,395.00

    43,165.00

    10,000.00

    53 165 00

  • 8/11/2019 Second Floor Renovation by Contract

    23/78

    8,550.00

    2,732.00

    11,282.00

    13,599.00

    5,464.00

    19,063.00

    4,200.00

    4,200.00

    8,360.00

    8,360.00

    1,400.00

    1,400.00

    142,865.00

    24,086.00

    10,000.00

    34,086.00

    10,766.00

    4,098.00

    4,400.00

    19,264.00

  • 8/11/2019 Second Floor Renovation by Contract

    24/78

    37,219.00

    5,000.0042,219.00

    8,772.00

    3,000.00

    11,772.00

  • 8/11/2019 Second Floor Renovation by Contract

    25/78

    36,224.00

    16,340.00

    52,564.00

    10,000.00

    421,773.00

  • 8/11/2019 Second Floor Renovation by Contract

    26/78

    nt

  • 8/11/2019 Second Floor Renovation by Contract

    27/78

    G A N T T C H A R T

    : PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING

    : Pilar Street, Zamboanga City

    : 5,901,401.00

    : 120 CALENDAR DAYS: 34 MANPOWER

    A. NON ENGINEERING BASIC COST

    I. PERMIT & FEES

    II. CONSTRUCTION SAFETY & HEALTH PROGRAM

    III. CONSTRUCTION OF ONE (1) UNIT TEMPORARY FACILITY

    B. ENGINEERING BASIC COST

    A. RENOVATION OF SECOND FLOOR

    I. MOBILIZATION/DEMOBILIZATION April 29, 1900

    II. DEMOLITION WORKS AND CLEARING

    III. CONSTRUCTION OF TEMPORARY OFFICE January 16, 1900IV. MASONRY WORKS January 30, 1900

    V. TILE WORKS

    VI. CARPENTRY WORKS March 30, 1900

    VII. PLUMBING WORKS January 06, 1900

    VIII. SPRINKLER SYSTEM January 30, 1900

    IX. ELECTRICAL WORKS February 05, 1900

    X. PAINTING WORKS February 29, 1900

    XI. FIXTURES AND OFFICE EQUIPMENT

    B. CONST. OF COOP OFFICE/CANTEEN & STORAGE ROOM

    I. MOBILIZATION

    II. LAYOUTING WORKS

    III. CONCRETING WORKS

    IV. MASONRY WORKS =

    V. CARPENTRY WORKSVI. ROOFING WORKS

    VII. STEEL WORKS

    VIII. ELECTRICAL WORKS

    IX. PLUMBING WORKS

    X. PAINTING WORKS

    XI. DEMOBILIZATION

    SUB-TOTAL

    Total Direct Cost

    OCM

    VAT (12%)

    TOTAL PROJECT COST

    CASH OUTLAY REQUIREMENT

    TARGETED COMPLETION THIS PERIOD

    COMMULATIVE COMPLETION TO DATE

    Prepared by: Checked & Reviewed by: Submitted by:

    MARLI ACOST

    Officer-I

    Planning &

    142,865.0034,086.00

    42,219.00

    11,772.00

    52,564.00

    10,000.00

    10,000.00

    2,100.00

    23,845.00

    73,058.00

    5,901,401.00Php

    632,293.00 84,23

    Planning & Development Section

    Sr. Water Res. Fac. Optr. B Officer-In-Charge

    786,229.02

    13.32%

    MURPIN K. PALULLA MARIE CLAIRE C. BONGO

    13.32%

    58,49

    439,092.00 58,49

    356,130.00

    464,063.00

    4,390,924.00

    460,480.00

    439,092.00

    August 25, 350

    560,149.00

    19,264.00

    65,753.00

    909,159.00

    317,250.00

    299,567.0053,485.00

    386,355.00

    21,760.00

    20,000.00

    15,000.00

    40,000.00

    ( Php ) 15

    PROJECT DURATIONMANPOWER REQUIREMENTS

    WORK ITEMAMOUNT

    PROJECT

    LOCATION

    PROJECT COST

  • 8/11/2019 Second Floor Renovation by Contract

    28/78

    Project Title: PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING

    Approved Budget Cost:

    P.R. No.

    A. NON ENGINEERING BASIC COST

    I. PERMIT & FEES

    II. CONSTRUCTION SAFETY & HEALTH PROGRAM

    III. CONSTRUCTION OF ONE (1) UNIT TEMPORARY FACILITY

    B. ENGINEERING BASIC COST

    A. CONSTRUCTION OF TEMPORARY OFFICE

    I. Mobilization/Demobilization

    II. Installation of Walling/Partition and Cubicle Works

    III.

    IV.

    V.

    VI.

    VII.

    VIII.

    IX. Supply and Installation of Tarpaulin Canvass/Lona w/ Complete Accessories

    B. RENOVATION OF SECOND FLOOR

    I. Mobilization/Demobilization/Hauling

    II. Demolition and Clearing Works

    Wood Wall Partition

    Concrete Wall Partition

    Ceiling

    Floor/Wall TilesIII. Masonry Works

    IV. Tile Works

    Granite Tile Works with grouting (see plans for sizes and details)

    Granite Countertop with grouting (see plans for sizes and details)

    Ceramic Tile Works with grouting & tile trims (see plans for sizes and details)

    V. Carpentry Works

    Ceiling Works

    Walling/Partition and Cubicle Works

    Fabrication of Office Tables, Cabinets and Shelves

    VI Doors/Windows and Glass:

    D1 - 0.60m x 1.20m PVC Door, w/ PVC Door Jamb,

    and w/ Complete Hinges, w/out Door Knob

    D2 - 0.80m x 2.10m Panel Type Door, w/ 2" x 6" Jamb,

    2" x 4" Door Frame, 6mm thk. Marine Plywood

    D3 - Double Swing Door, 2" x 4" Alum. Frame/JambAnalok Glass Aluminum Door Frame

    Aluminum Analok Sliding Window, 6mm Thk. Bronze Glass

    Fixed Glass/Aluminum Frame Analok , 6mm Thk. Bronze Glass

    VII. Plumbing Works

    Flush Type Water Closet w/ Complete Fittings and Accessories

    Undermount Porcelain Lavatory w/ Complete Fittings and Acessories

    Wall Mounted Porcelain Lavatory w/ Complete Fittings and Acessories

    Urinal w/ Complete Fittings and Acessories

    Sanitary Pipes & Fittings

    Cold Water Pipes & Fittings

    VIII. Supply, Installation, Testing and Commissioning of Fire Sprinkler System

    Supply, Installation, Testing and Commissioning of One (1) Lot Wet Fire Sprinkler System Complete w/

    Piping, Pendent Type Sprinkler Head and Acessories, w/ One (1) Unit 10HP Centrifugal Pump

    Motor, Motor Controls, Control Panel, 3 Phase w/ Pump Outlet & Inlet of 4" Diameter w/ Steel Bed Plate

    IX. Electrical Works

    Single Phase Electrical Line

    150AT/150AF, 230V, 3P, Three Phase, Common Trip Main Circuit Breaker

    For Lighting Load

    Transfer of Wires & Cables (LAN, Internet & Telephone) from 2nd floor to Roofdeck

    Transfer of tables, chairs, computers, filing cabinet and other office equipment from 2nd floor to Roofdeck

    5,901,401.00Php

    Republic of the Philippines

    ZAMBOANGA CITY WATER DISTRICT

    Pilar Street, Zamboanga City

    BILL OF QUANTITIES

    ESTIMA

    QUANWORK ITEM/DESCRIPTION

    Supply and Installation of 100 Amp. Main Circuit Breaker, Three Phase, 3P, 220 volts enclosed in Powder Coated Finished Panel

    Board w/ 6 Single Phase Branches of 20Amp.Single Phase Electrical Line

    Lighting Fixtures

    Supply and Installation of T5 Flourescent Lighting Fixture w/ PC cover, 28W, 1200mm, 220V, cool daylight

    Supply & Installation of 48-Inches Industrial Ceiling Fan, 3 Blade, 220V

  • 8/11/2019 Second Floor Renovation by Contract

    29/78

    Project Title: PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING

    Approved Budget Cost:

    P.R. No.

    5,901,401.00Php

    Republic of the Philippines

    ZAMBOANGA CITY WATER DISTRICT

    Pilar Street, Zamboanga City

    BILL OF QUANTITIES

    ESTIM

    QUAWORK ITEM/DESCRIPTION

    Recessed Type Downlights w/o Glass Cover, E27, 185mmH x 150mm w/ 15Watts CFL, Cool Daylight, 220V

    Recessed Type Downlights w/o Glass Cover, E27, 185mmH x 150mm w/ 33Watts CFL, Cool Daylight, 220V

    Recessed Type Reflectorized/Mirrorized Fluorescent Luminaire w/ 2-40Watts Fluorescent Lamp

    Recessed Type Reflectorized/Mirrorized Fluorescent Luminaire w/ 2-20Watts Fluorescent Lamp

    Six Down Lighting Chandelier, w/ Six Bulbs Fluorescent type, 230 Volts

    T5 Flourescent Lighting Fixture w/ PC cover, 28W, 1200mm, 220V, cool daylight

    Single Phase Electrical Lline Outlets

    X. Painting Works

    XI. Fixtures, Office Furnitures and Office Equipment

    Table 1 (See plans for details)

    Table 2 (See plans for details)

    Table 3 (See plans for details)

    Table 4 (See plans for details)

    Table 5 (See plans for details)

    Patients Bed (See plans for details)

    Executive Chair Executive Chair w/ Black Leatherette back and seat molded foam cushion,

    lockable tilting mechanism, polyurethane or polypropylene armrest, five legged and black

    leatherette back and nylon twin caster pneumatic height adjustment.

    Office Chair w/ Low back and seat molded foam cushion, lockable tilting mechanism,

    polyurethane or polypropylene armrest, five legged and black leatherette back

    and nylon twin caster pneumatic height adjustment.

    Visitors Chair w/ four legged, back and sit molded foam cushion, polypropylene armrest,

    shiny chromed chair frame

    Sala Set w/ Glass Top Center Table 9See TOR for Specs)

    Supply & Installation of Ceiling Mounted Aircon

    Specs:Cooling Capacity - 58,000 Btu/hr

    Capacity - 5 TR

    Power - 3P/220 V/60 Hz

    - LCD remote Type w/ Auto t imer on/off, Sleep Mode,Dry Mode, Auto Fan Speed,

    Night Timer,Real Time Clock

    - With inverter, Heating & Cooling

    - High efficiency

    - Eco Friendly

    - Automatic Drain Pump

    - Two thermistor control function

    - Alarm function for filter cleaning

    Supply & Installation of Ceiling Mounted Projector

    Specs:

    240VAC, 60Hz, 300W projector with 0.80-7.5 meters diagonally projection size, full color,

    ceiling mounted ready installation,moulded plastic, 307mm x 69mm x 210mm dimension,approx. 2.3 kgs, 0

    o-40

    oC temperature, 20%-80% humidity, with 2 meters power cord,

    power cord secure lock, wireless remote control, VGA cable, carrying bag and application

    software (CD-ROM). With metal ceiling mount projector bracket

    And with 1.7m wide - 78" diagonal projector screen, matt white surface with 3cm black

    border and weighted bottom bar. Housed in a white case with mounting brackets on

    either end. Can be operated with in-line control switch or a wirless remote control.

    Ceiling and wall mounting compatible, low noise electric motor, 240 VAC input, 60 Hz.

    Remote Control

    XII. Transfer and reinstallation of Existing Split-type ACU, 230V, 1, 60hz, 186Watts

    C. CONSTRUCTION OF COOP OFFICE/CANTEEN & STORAGE ROOM (FLOOR AREA = 65.87 SQ.M.)

    I. MOBILIZATION

    II. LAYOUTING WORKS

    III. CONCRETING WORKS

    IV. MASONRY WORKS

    1. Floor Tiles2. Kitchen Counter

    V. CARPENTRY WORKS

    1 Ceiling Works

  • 8/11/2019 Second Floor Renovation by Contract

    30/78

    Project Title: PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING

    Approved Budget Cost:

    P.R. No.

    5,901,401.00Php

    Republic of the Philippines

    ZAMBOANGA CITY WATER DISTRICT

    Pilar Street, Zamboanga City

    BILL OF QUANTITIES

    ESTIMAT

    QUANTIWORK ITEM/DESCRIPTION

    IX. PLUMBING WORKS

    Sanitary Pipes and Fittings

    Cold Water Pipes and Fittings

    Stainless Kitchen Sink, w/ Strainer drain assembly w/ Plug & complete water supply fitting

    X. PAINTING WORKS

    XI. Demobilization

    Prepared by: Reviewed & Checked by:

    EDITO M. BAUTISTA, JR. MARIE CLAIRE C. BONGO

    J.O.-Senior Engineer A (C.E.) Officer-In-Charge

    Planning & Development Section

    ARIANN D. GODINEZ

    J.O.- Senior Engineer A (E.E.)

    MARK BENEDICT C. REYES

    J.O.- Senior Engineer A (M.E.)

    Recommending Project Implementation: Approved

    ARNULFO A. ALFONSO LEONARDO

    Department Manager C, Maintenance General M

  • 8/11/2019 Second Floor Renovation by Contract

    31/78

    Project Title: PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING

    Approved Budget Cost:

    P.R. No.

    A. NON ENGINEERING BASIC COST

    I. PERMIT & FEES 1 lot

    II. CONSTRUCTION SAFETY & HEALTH PROGRAM 1 lot

    III. CONSTRUCTION OF ONE (1) UNIT TEMPORARY FACILITY 1 lot

    B. ENGINEERING BASIC COST

    A. CONSTRUCTION OF TEMPORARY OFFICE

    I. Mobilization/Demobilization

    II. Installation of Walling/Partition and Cubicle Works 1 lot

    III.1 assy.

    IV. 83 outlets

    V.

    28 units

    VI. 14 units

    VII. 1 lot

    VIII. 1 lot

    IX. Supply and Installation of Tarpaulin Canvass/Lona w/ Complete Accessories 1 lot

    B. RENOVATION OF SECOND FLOOR

    I. Mobilization/Demobilization/Hauling 1 lot

    II. Demolition and Clearing Works

    Wood Wall Partition 238 sq.mtr.

    Concrete Wall Partition 55 sq.mtr.

    Ceiling 459 sq.mtr.

    Floor/Wall Tiles 540 sq.mtr.

    III. Masonry Works 30 sq.mtr.

    IV. Tile Works

    Granite Tile Works with grouting (see plans for sizes and details) 375 sq.mtr.

    Granite Countertop with grouting (see plans for sizes and details) 5.112 sq.mtr.

    Ceramic Tile Works with grouting & tile trims (see plans for sizes and details) 113 sq.mtr.

    V. Carpentry Works

    Ceiling Works 459 sq. mtr.

    Walling/Partition and Cubicle Works 145 sq. mtr.

    Fabrication of Office Tables, Cabinets and Shelves 1 lot

    VI Doors/Windows and Glass:

    D1 - 0.60m x 1.20m PVC Door, w/ PVC Door Jamb, 3 units

    and w/ Complete Hinges, w/out Door Knob

    D2 - 0.80m x 2.10m Panel Type Door, w/ 2" x 6" Jamb, 5 units

    2" x 4" Door Frame, 6mm thk. Marine Plywood

    D3 - Double Swing Door, 2" x 4" Alum. Frame/Jamb 3 units

    Analok Glass Aluminum Door FrameAluminum Analok Sliding Window, 6mm Thk. Bronze Glass 10 units

    Fixed Glass/Aluminum Frame Analok , 6mm Thk. Bronze Glass 2 units

    VII. Plumbing Works 1 lot

    Flush Type Water Closet w/ Complete Fittings and Accessories 7 sets

    Undermount Porcelain Lavatory w/ Complete Fittings and Acessories 3 sets

    Wall Mounted Porcelain Lavatory w/ Complete Fittings and Acessories 3 sets

    Urinal w/ Complete Fittings and Acessories 3 sets

    Sanitary Pipes & Fittings 1 lot

    Cold Water Pipes & Fittings 1 lot

    VIII. Supply, Installation, Testing and Commissioning of Fire Sprinkler System

    Supply, Installation, Testing and Commissioning of One (1) Lot Wet Fire Sprinkler System Complete w/ 1 lot

    Piping, Pendent Type Sprinkler Head and Acessories, w/ One (1) Unit 10HP Centrifugal Pump

    Motor, Motor Controls, Control Panel, 3 Phase w/ Pump Outlet & Inlet of 4" Diameter w/ Steel Bed Plate

    IX. Electrical Works

    Single Phase Electrical Line 208 outlets150AT/150AF, 230V, 3P, Three Phase, Common Trip Main Circuit Breaker 1 unit

    For Lighting Load

    100 Amperes Main Circuit Breaker Three Phase 3P

    Republic of the Philippines

    ZAMBOANGA CITY WATER DISTRICT

    Pilar Street, Zamboanga City

    BILL OF QUANTITIES

    5,901,401.00Php

    WORK ITEM/DESCRIPTIONESTIMATED

    QUANTITYUNIT

    Supply and Installation of 100 Amp. Main Circuit Breaker, Three Phase, 3P, 220 volts enclosed in Powder Coated

    Finished Panel Board w/ 6 Single Phase Branches of 20Amp.

    Single Phase Electrical Line

    Lighting Fixtures

    Supply and Installation of T5 Flourescent Lighting Fixture w/ PC cover, 28W, 1200mm, 220V, cool daylight

    Supply & Installation of 48-Inches Industrial Ceiling Fan, 3 Blade, 220V

    Transfer of Wires & Cables (LAN, Internet & Telephone) from 2nd floor to Roofdeck

    Transfer of tables, chairs, computers, filing cabinet and other office equipment from 2nd floor to Roofdeck

  • 8/11/2019 Second Floor Renovation by Contract

    32/78

    Project Title: PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING

    Approved Budget Cost:

    P.R. No.

    Republic of the Philippines

    ZAMBOANGA CITY WATER DISTRICTPilar Street, Zamboanga City

    BILL OF QUANTITIES

    5,901,401.00Php

    WORK ITEM/DESCRIPTIONESTIMATED

    QUANTITYUNIT

    For Power Load

    100 Amperes Main Circuit Breaker, 3 Pole, 3 Phase, 250 volts in Combined Panel Board complete

    with Ground Bus Bar/Terminal Blocks, enclosed in Powder Coated Finished Panel Board,

    with 7 Single Phase Branches of:

    1 sets - 30 Amps., Single Pole Breaker

    6 sets - 20 Amps., Single Pole Breaker 1 assy.

    For ACU Load

    150 Amperes Main Circuit Breaker, 2 Pole, 250 volts in Combined Panel Board complete

    with Ground Bus Bar/Terminal Blocks, enclosed in Powder Coated Finished Panel Board,

    with 6 Single Phase Branches of:

    5 sets - 60 Amps., Single Pole Breaker

    1 sets - 30 Amps., Single Pole Breaker 1 assy.30 Amperes, 2P, Safety Breaker (for ACU) 1 pc.

    60 Amperes, 2P, Safety Breaker (for ACU) 5 pcs.

    Lighting Fixtures

    Recessed Type Downlights w/o Glass Cover, E27, 185mmH x 150mm w/ 13Watts CFL, Cool Daylight, 220V 23 sets

    Recessed Type Downlights w/o Glass Cover, E27, 185mmH x 150mm w/ 15Watts CFL, Cool Daylight, 220V 91 sets

    Recessed Type Downlights w/o Glass Cover, E27, 185mmH x 150mm w/ 33Watts CFL, Cool Daylight, 220V 15 sets

    Recessed Type Reflectorized/Mirrorized Fluorescent Luminaire w/ 2-40Watts Fluorescent Lamp 15 sets

    Recessed Type Reflectorized/Mirrorized Fluorescent Luminaire w/ 2-20Watts Fluorescent Lamp 1 set

    Six Down Lighting Chandelier, w/ Six Bulbs Fluorescent type, 230 Volts 1 set

    T5 Flourescent Lighting Fixture w/ PC cover, 28W, 1200mm, 220V, cool daylight 2 sets

    Centralized Grounding System 1 lot

    Single Phase Electrical Lline Outlets 208 outlets

    X. Painting Works 1,800 sq. mtr.

    XI. Fixtures, Office Furnitures and Office Equipment

    Table 1 (See plans for details) 22 units

    Table 2 (See plans for details) 3 units

    Table 3 (See plans for details) 1 unit

    Table 4 (See plans for details) 12 units

    Table 5 (See plans for details) 1 unit

    Patients Bed (See plans for details) 1 unit

    Executive Chair Executive Chair w/ Black Leatherette back and seat molded foam cushion, 16 units

    lockable tilting mechanism, polyurethane or polypropylene armrest, five legged and black

    leatherette back and nylon twin caster pneumatic height adjustment.

    Office Chair w/ Low back and seat molded foam cushion, lockable tilting mechanism, 24 units

    polyurethane or polypropylene armrest, five legged and black leatherette back

    and nylon twin caster pneumatic height adjustment.

    Visitors Chair w/ four legged, back and sit molded foam cushion, polypropylene armrest, 12 units

    shiny chromed chair frame

    Sala Set w/ Glass Top Center Table 9See TOR for Specs) 2 sets

    Supply & Installation of Ceiling Mounted Aircon 2 unitsSpecs:

    Cooling Capacity - 58,000 Btu/hr

    Capacity - 5 TR

    Power - 3P/220 V/60 Hz

    - LCD remote Type w/ Auto timer on/off, Sleep Mode,Dry Mode, Auto Fan Speed,

    Night Timer,Real Time Clock

    - With inverter, Heating & Cooling

    - High efficiency

    - Eco Friendly

    - Automatic Drain Pump

    - Two thermistor control function

    - Alarm function for filter cleaning

    Supply & Installation of Ceiling Mounted Projector 1 unit

    Specs:

    240VAC, 60Hz, 300W projector with 0.80-7.5 meters diagonally projection size, full color,ceiling mounted ready installation,moulded plastic, 307mm x 69mm x 210mm dimension,

    approx. 2.3 kgs, 0o-40

    oC temperature, 20%-80% humidity, with 2 meters power cord,

  • 8/11/2019 Second Floor Renovation by Contract

    33/78

    Project Title: PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING

    Approved Budget Cost:

    P.R. No.

    Republic of the Philippines

    ZAMBOANGA CITY WATER DISTRICT

    Pilar Street, Zamboanga City

    BILL OF QUANTITIES

    5,901,401.00Php

    WORK ITEM/DESCRIPTIONESTIMATED

    QUANTITYUNIT

    Ceiling and wall mounting compatible, low noise electric motor, 240 VAC input, 60 Hz.

    Remote Control

    XII. Transfer and reinstallation of Existing Split-type ACU, 230V, 1, 60hz, 186Watts 4 units

    C. CONSTRUCTION OF COOP OFFICE/CANTEEN & STORAGE ROOM (FLOOR AREA = 65.87 SQ.M.)

    I. MOBILIZATION 1 lot

    II. LAYOUTING WORKS 65.87 sq. mtr.

    III. CONCRETING WORKS 53.17 sq. mtr.

    IV. MASONRY WORKS

    1. Floor Tiles 46.16 sq. mtr.

    2. Kitchen Counter 3.60 sq. mtr.

    V. CARPENTRY WORKS

    1. Ceiling Works 57.6 sq. mtr.2. Wall/Wall Partition 126.72 sq. mtr.

    3. Shelves 23.04 sq. mtr.

    4. Counter Top 40.32 sq. mtr.

    5. Door and Window Jambs

    0.90m x 2.10m x 0.05m x 0.15m Yakal/Hardwood Door Jambs 2 sets

    1.40m x 1.20m x 0.05m x 0.15m Yakal/Hardwood Window Jambs 1 set

    6. Door and Window

    0.90m x 2.10m Flush Door w/ 5mm thk Marine Plywood, Double 2 sets

    5mm thk, 13 Blades Smoke Glass Jalousie Window w/ Standard 2 sets

    7. Wooden Ventillation

    25mm thk x 250mm x 1.20m Pre-fabrication Wooden Ventillation 2 units

    VI. ROOFING WORKS 63.36 sq. mtr.

    VII. STEEL WORKS 147.56 kgs.

    VIII. ELECTRICAL WORKS

    1 set

    Single Phase Electrical Lline Outlets 18 outlets

    Supply and Installation of T5 Flourescent Lighting Fixture w/ PC cover, 28W, 1200mm, 220V cool daylight 4 sets

    Recessed Type Downlights w/o Glass Cover, E27, 185mmH x 150mm w/ 18Watts CFL, Cool Daylight, 220V 5 sets

    16" Ceiling Orbit Fan, industrial type 2 units

    12" Exhaust Fan 2 units

    IX. PLUMBING WORKS

    Sanitary Pipes and Fittings 1 lot

    Cold Water Pipes and Fittings 1 lot

    Stainless Kitchen Sink, w/ Strainer drain assembly w/ Plug & complete water supply fitting 1 set

    X. PAINTING WORKS 144 sq. mtr.

    XI. Demobilization 1 lot

    Prepared by: Reviewed & Checked by: Approved

    EDITO M. BAUTISTA, JR. MARIE CLAIRE C. BONGO MARLI AC

    J.O.-Senior Engineer A (C.E.) Officer-In-Charge Officer-In-

    Planning & Development Section Planning &

    ARIANN D. GODINEZ

    J.O.- Senior Engineer A (E.E.)

    MARK BENEDICT C. REYES

    J.O.- Senior Engineer A (M.E.)

    Recommending Project Implementation: Approved for Project Imp

    ARNULFO A. ALFONSO LEONARDO REY D. VASQU

    Supply and Installation of 60 Amp. Main Circuit Breaker, Three Phase, 3P, 220 volts enclosed in Powder CoatedFinished Panel Board w/ 5 Single Phase Branches of 4sets-20Amps, 1set-15Amps

  • 8/11/2019 Second Floor Renovation by Contract

    34/78

    Project Title: PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING

    Approved Budget Cost:

    P.R. No.

    QTY UNIT AVAILABLE S.N./H.P./PLATE NO

    1 Service Vehicle 1.00 unit

    2 Boom Truck (2 tonner. min. capacity) 2.00 units

    3 Dump Truck (6cu.m. min. capacity) 2.00 units

    4 Air Compressor 1.00 unit

    5 Welding Machine w/ Cutting Outfit 1.00 unit

    6 Angular Grinder 1.00 unit

    7 Electric Hand Drill 1.00 unit

    8 Portable Demolition Hammer (min. of 1800Watts) 1.00 unit

    9 Electric Planer 1.00 unit

    10 Generator Set 1.00 unit

    Project Manager 1

    Safety Engineer 1

    Materials Engineer 1

    Project Engineer 1

    Foreman 1

    Timekeeper/Warehouse Man 1

    Purchasing Manager 1

    Prepared by: Reviewed & Checked by: Approved by:

    EDITO M. BAUTISTA, JR. MARIE CLAIRE C. BONGO MARLI ACOSTA-DE FIESTAJ.O.-Senior Engineer A (C.E.) Officer-In-Charge Officer-In-Charge

    Planning & Development Section Planning & Design Division

    Recommending Project Implementation: Approved for Project Implementation:

    ARNULFO A. ALFONSO LEONARDO REY D. VASQUEZ

    Department Manager C, Maintenance General Manager

    PARTICULARS

    MANPOWER REQUIREMENTS

    EQUIPMENT REQUIREMENTS

    Republic of the Philippines

    ZAMBOANGA CITY WATER DISTRICT

    Pilar Street, Zamboanga City

    5,901,401.00Php

    Equipment Page 34 of 78 246371728.xls.ms_

  • 8/11/2019 Second Floor Renovation by Contract

    35/78

    Department: Engineering Department/Planning & Design Div. PR No.: Date:

    Section: Planning & Development Section SAI No.: Date:

    Approved Budget Cost:

    1 LOT

    NON ENGINEERING BASIC COSTI. PERMIT & FEES

    II. CONSTRUCTION SAFETY & HEALTH PROGRAM

    III. CONSTRUCTION OF ONE (1) UNIT TEMPORARY FACILITY

    ENGINEERING BASIC COSTA. CONSTRUCTION OF TEMPORARY OFFICE AT ROOF DECK

    B. RENOVATION OF SECOND FLOOR

    I. Mobilization/Demobilization/HaulingII. Demolition and Clearing Works

    III. Masonry Works

    IV. Tile Works

    V. Carpentry Works

    VI. Doors/Windows and Glass:

    VII. Plumbing Works

    VIII. Supply, Installation, Testing and Commissioning of Fire Sprinkler System

    IX. Electrical Works

    X. Painting Works

    XI. Fixtures, Office Furnitures and Office Equipment

    XII. Transfer and reinstallation of Existing Split-type ACU, 230V, 1, 60hz, 186Watts

    I. MobilizationII. Layouting Works

    III. Concreting Works

    IV. Masonry Works

    V. Carpentry Works

    VI. Roofing Works

    VII. Steel Works

    VIII. Electrical Works

    IX. Plumbing Works

    X. Painting Works

    XI. DemobilizationxxxxxxxxxxxxxxxxNOTHING FOLLOWSxxxxxxxxxxxxxxxxxxxxxxxxxxxxx

    Purpose / Remarks: For theProposed Renovation of Second Floor ZCWD Main Building.

    5,901,401.00Php

    Republic of the Philippines

    ZAMBOANGA CITY WATER DISTRICT

    Pilar Street, Zamboanga City

    PURCHASE REQUEST

    ACCOUNTNUMBER

    P.O.No.

    ITEM DESCRIPTION QTY. UNITUNITCOST

    AVAIL.STOCK

    C. CONSTRUCTION OF COOP OFFICE/CANTEEN & STORAGE ROOM (FLOOR AREA = 65.87 SQ.M.)

    PROP. RENOVATION OF SECOND FLOOR, ZCWD MAINBUILDING

  • 8/11/2019 Second Floor Renovation by Contract

    36/78

    Signature:

    Printed Name:

    Designation:

    Date:

    Requested by: Funds Certified Available: Recommending Approval: Approve

    MARLI P. ACOSTA-DE FIESTA LUIS A. WEE ARNULFO A. ALFONSO LEONARDO REYOIC-Planning & Design Division Depaartment Manager, ATD Department Manager C, Maintenance General M

  • 8/11/2019 Second Floor Renovation by Contract

    37/78

    DATENEEDED

  • 8/11/2019 Second Floor Renovation by Contract

    38/78

    EZ

  • 8/11/2019 Second Floor Renovation by Contract

    39/78

    Department/Division ENGINEERING DEPARTMENT Responsibility Center No. _________Office PLANNING & DESIGN DIVISION Code __________

    STOCK NO. Unit Quantity Status of Stock

    1.00 LOT

    xxxxxxxxxxxxxxxxNOTHING FOLLOWSxxxxxxxxxxxxxxxxxxxxxxxxxxxxx

    PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING

    Republic of the Philipines

    ZAMBOANGA CITY WATER DISTRICT

    Pilar Street, Zamboanga City

    SUPPLIES AVAILABILITY INQUIRY (SAI)

    ITEM DESCRIPTION

    NON ENGINEERING BASIC COST

    I. PERMIT & FEES

    II. CONSTRUCTION SAFETY & HEALTH PROGRAM

    III. CONSTRUCTION OF ONE (1) UNIT TEMPORARY FACILITY

    ENGINEERING BASIC COST

    B. RENOVATION OF SECOND FLOOR

    A. CONSTRUCTION OF TEMPORARY OFFICE AT ROOF DECK

    I. Mobilization/Demobilization/Hauling

    II. Demolition and Clearing Works

    III. Masonry Works

    IV. Tile Works

    V. Carpentry Works

    VI. Doors/Windows and Glass:

    VII. Plumbing Works

    VIII. Supply, Installation, Testing and Commissioning of Fire

    Sprinkler System

    IX. Electrical Works

    C. CONSTRUCTION OF COOP OFFICE/CANTEEN & STORAGE

    ROOM (FLOOR AREA = 65.87 SQ.M.)

    I. Mobilization

    II. Layouting Works

    X. Painting Works

    XI. Fixtures, Office Furnitures and Office Equipment

    XII. Transfer and reinstallation of Existing Split-type ACU, 230V, 1,

    60hz, 186Watts

    IX. Plumbing Works

    X. Painting Works

    XI. Demobilization

    III. Concreting Works

    IV. Masonry Works

    V. Carpentry WorksVI. Roofing Works

    VII. Steel Works

    VIII. Electrical Works

  • 8/11/2019 Second Floor Renovation by Contract

    40/78

    Purpose / Remarks: For theProposed Renovation of Second Floor ZCWD Main Building.

    Inqui red by: Status prov ided by Acco unt ing and Treasury Department :

    Signature Signature

    Name Name

    Designatio Designation

    Date Date

    This form should be prepared in 3 copies. Copy 1 - Accounting Section; Copy 2 - Property Section; Copy 3 - End Users.

    MARLI P. ACOSTA-DE FIESTA LUIS A. WEE

    OIC, Planning & Design Division Department Manager

  • 8/11/2019 Second Floor Renovation by Contract

    41/78

    Pre-Procurement

    Conference

    Public Bidding P 5,901,401.00 10/8/12 10/10/12 - 10/

    xxxxxxxxxxxxxxxxNOTHING FOLLOWSxxxxxxxxxxxxxxxxxxxxxxxxxx

    P 5,901,401.00

    Requisitioned by: Recommending A

    MARIE CLAIRE C. BONGO MARLI P. ACOSTA-DE FIESTA ARNULFO A. ALFOfficer-In-Charge Officer-In-Charge Department Mana

    Planning & Development Section Planning and Design Division

    ABCAdvertisement

    Republic of the Philipines

    ZAMBOANGA CITY WATER DISTRICT

    Pilar Street, Zamboanga City

    PROJECT PROCUREMENT MANAGEMENT PLANENGINEERING DEPARTMENT

    PLANNING AND DESIGN DIVISION

    PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING

    TOTAL BUDGET AMOUNT

    Prepared by:

    Ref.[1] Contract Package (Description)Procurement

    Method

  • 8/11/2019 Second Floor Renovation by Contract

    42/78

    Project : PROPOSED COOP OFFICE/CAN

    Location : Roof Deck, Main Office, Pilar St., Z

    Scope of Work :

    I. MOBILIZATION

    II. LAYOUTING WORKS

    III. CONCRETING WORKSIV. MASONRY WORKS

    V. CARPENTRY WORKSVI. ROOFING WORKS

    VII. STEEL WORKSVIII. ELECTRICAL WORKS

    IX. PLUMBING WORKS

    X. PAINTING WORKS

    XI. DEMOBILIZATION

    Cost of Project :

    I. MOBILIZATION

    II. LAYOUTING WORKSa. Materials:

    10pcs. - 2" x 3" x 10' Coco Lumber

    4pcs. - 2" x 3" x 8' Coco Lumber

    #100 Nylon Chord (1kg./roll)

    4" C.W. Nail

    4" Concrete Nail

    b. Labor:

    2 - Carpenters

    TOTAL DIRECT COST

    OVERHEAD EXPENSES

    PHYSICAL CONTINGENCIES

    MISCELLANEOUS EXPENSESTOTAL COST OF ITEM II

    III. CONCRETING WORKS

    Flooring

    a. Materials:

    Portland Cement

    Washed Sand

    Gravel (G-1)

    10pcs. - 2" x 4" x 10' Coco Lumber

    Republic of the Phil

    ZAMBOANGA CITY WAT

    Pilar Street, Zamboa

    511,965.00Php

    BILL OF MATERIALS & C

    Item Description

  • 8/11/2019 Second Floor Renovation by Contract

    43/78

    4" Concrete Nail

    b. Labor:

    2 - Masons

    2 - Carpenters

    1 - Steelman

    6 - Laborers

    TOTAL DIRECT COST

    OVERHEAD EXPENSES

    PHYSICAL CONTINGENCIES

    MISCELLANEOUS EXPENSES

    TOTAL COST OF ITEM III

    IV. MASONRY WORKS

    1. Floor Tilesa. Materials:

    0.40m x 0.40m Granite Tiles (White)

    Portland Cement

    Fine Sand (for plastering)

    Tile Grout (cement joint filler)

    b. Labor:

    2 - Masons

    4 - Laborers

    c. Equipment Rental:

    1 - Unit Angular Grinder

    2. Kitchen Counter

    a. Materials:

    Portland Cement

    Washed Sand

    Gravel (G-1)Fine Sand (for plastering)

    10mm x 6.00m Deformed Reinforcing Steel Bars

    #16 G.I. Tie-wire

    12mm thk x 1.20m x 2.40m Ordinary Plywood

    6pcs. - 2" x 3" x 10' Coco Lumber

    4" C.W. Nail

    4" CHB (NBL)

    0.20m x 0.20m Granite Tiles (White)

    PVC Tile Trim

    Tile Grout (cement joint filler)

    b. Labor:2 - Masons

    1 - Laborer

    c. Equipment Rental:

    1 - Unit Angular Grinder

    TOTAL DIRECT COST

    OVERHEAD EXPENSES

  • 8/11/2019 Second Floor Renovation by Contract

    44/78

    PHYSICAL CONTINGENCIES

    MISCELLANEOUS EXPENSES

    TOTAL COST OF ITEM IV

    V. CARPENTRY WORKS

    1. Ceiling Worksa. Materials:

    56pcs. - 2" x 4" x 10' S4s Lauan Wood

    56pcs. - 2" x 2" x 10' S4s Lauan Wood

    12mm thk x 1.20m x 2.40m Marine Plywood

    5mm thk x 1.20m x 2.40m Marine Plywood

    4" C.W. Nail

    3" C.W. Nail

    2" C.W. Nail

    b. Labor:

    2 - Carpenters

    2 - Laborers

    2. Wall/Wall Partition

    a. Materials:

    1pc. - 4" x 4" x 10' S4s Lauan

    94pcs. - 2" x 4" x 10' S4s Lauan Wood

    5mm thk x 1.20m x 2.40m Marine Plywood

    4" C.W. Nail

    2" C.W. Nail

    b. Labor:

    2 - Carpenters

    4 - Laborers

    3. Shelves

    a. Materials:

    19mm thk x 1.20m x 2.40m Marine Plywood

    Wood Glue

    1 1/2" C.W. Nail

    b. Labor:

    2 - Carpenters

    2 - Laborers

    4. Counter Topa. Materials:

    19mm thk x 1.20m x 2.40m Marine Plywood

    5mm thk x 1.20m x 2.40m Marine Plywood

    Wood Glue

    2" C.W. Nail

    1.20m x 2.40m Plastic Formica

    Rubber Cement Solvent

    2" x 2" Cabinet Hinges

    38mm Wooden Cabinet Handle

  • 8/11/2019 Second Floor Renovation by Contract

    45/78

    b. Labor:

    2 - Carpenters

    2 - Laborers

    5. Door and Window Jambs (Job Order)

    a. Materials:0.90m x 2.10m x 0.05m x 0.15m Yakal/Hardwood Door Jambs

    1.40m x 1.20m x 0.05m x 0.15m Yakal/Hardwood Window Jambs

    6. Doors & Window (Job Order)

    a. Materials:

    0.90m x 2.10m Flush Door w/ 5mm thk Marine Plywood, Double

    Walling on 50mm x 100mm Door Frame, Door Knob

    5mm thk, 13 Blades Smoke Glass Jalousie Window w/ Standard

    Alum. Frame Holder (0.70m x 1.20m)

    7. Ventillation (Job Order)

    a. Materials:25mm thk x 250mm x 1.20m Pre-fabrication Wooden Ventillation

    TOTAL DIRECT COST

    OVERHEAD EXPENSES

    PHYSICAL CONTINGENCIES

    MISCELLANEOUS EXPENSES

    TOTAL COST OF ITEM V

    VI. ROOFING WORKSa. Materials:

    12mm thk x 1.20m x 2.40 Marine Plywood

    18pcs. - 2" x 2" x 10' S4s Lauan Wood

    14pcs. - 2" x 3" x 10' S4s Lauan Wood

    24pcs. - 2" x 3" x 8' S4s Lauan Wood

    16pcs. - 2" x 2" x 8' S4s Lauan Wood

    4" C.W. Nail

    2" C.W. Nail

    b. Labor:

    2 - Carpenters

    4 - Laborers

    TOTAL DIRECT COST

    OVERHEAD EXPENSES

    PHYSICAL CONTINGENCIES

    MISCELLANEOUS EXPENSES

    TOTAL COST OF ITEM VI

    VII. STEEL WORKS

    a. Materials:

    50mm x 6.00m G.I. Pipe, Sch. 40

    12mm x 6.00m Aluminum Tube

    3mm x 25mm x 25mm x 3.00m Alum. Angle Bar

    4mm x 25mm x 25mm x 6.00m Angle Bar

    4mm x 38mm x 6.00m Flat Bar

  • 8/11/2019 Second Floor Renovation by Contract

    46/78

    10mm x 10mm x 6.00m Square Bars

    5mm thk x 25mm x 6.00m Flat Bar

    b. Labor:

    1 - Steelman

    1 - Welder

    2 - Laborers

    c. Equipment Rental:

    1 - Unit Welding Machine

    TOTAL DIRECT COST

    OVERHEAD EXPENSES

    PHYSICAL CONTINGENCIES

    MISCELLANEOUS EXPENSES

    TOTAL COST OF ITEM VI

    VIII. ELECTRICAL WORKSa. Materials:

    50 Amperes Main Circuit Breaker, Single Phase,

    220 volts enclosed in Powder Coated Finished Panel Board

    with 5 Single Phase Branches of:

    4 sets - 20 Amps. Branch

    1 sets - 15 Amps. Branch

    8.0mm2THW Stranded Wire

    3.5mm2THW Stranded Wire

    16" Orbit Fan, Standard

    12" exhaust fan

    3U Electronic CFL with Capsule, Daylight, 23W Assembly

    Ceiling Socket with screw

    Reccessed Fluorescent illuminaire,1x40 Watts assembly

    in Powder Coated Steel Plate; IP20 Assembly

    Duplex Convenience Outlet w/ plate (flush type)

    Toggle Switch 3-Gang w/ plate (f lush type)

    Toggle Switch 1-Gang w/ plate (f lush type)

    25mm (3/4") PVC Flexible Electrical Conduit

    25mm(3/4") x 90 PVC Electrical Conduit Elbow Long Sweep

    25mm (3/4")PVC Electrical Coupling Connectors

    25mm (3/4") PVC Male Adaptor

    25mm (3/4") PVC Lock Nut (Zinc Coated)

    25mm (3/4") PVC clamps w/ concrete nails

    20mm (1/2") PVC Flexible Electrical Conduit

    20mm (1/2") x 3.00m PVC Electrical Conduit

    20mm (1/2") x 90 PVC Electrical Conduit Elbow Long Sweep

    20mm (1/2") x 90 PVC Electrical Conduit Short Elbow

    20mm(1/2") PVC Electrical Coupling Connectors

    20mm (1/2") PVC Male Adaptor

    20mm (1/2") PVC Lock Nut (Zinc Coated)

    20mm (1/2") PVC clamps w/ concrete nails

    2" x 4" x 2" PVC Utility Box ( H.D.)

    4" x 4" x 2" PVC Junction Box ( H.D.) w/ Cover

    #16 G.I. Tie Wire

    6" x 6" x 4" Gal. Pull Box

    PVC Solvent Cement

  • 8/11/2019 Second Floor Renovation by Contract

    47/78

    1/2" Camridge / Mica Tube

    3/4" Polytype Electrical Tape

    3/4" Rubber Tape

    b. Labor:

    1 - Skilled Electrician

    2 - Contractual Laborers

    TOTAL DIRECT COST

    OVERHEAD EXPENSES

    PHYSICAL CONTINGENCIES

    MISCELLANEOUS EXPENSES

    TOTAL COST OF ITEM VIII

    IX. PLUMBING WORKS

    a. Materials:

    50mm x 3.00m Sanitary PVC Pipe, Series-1000

    50mm x 900Sanitary PVC Elbow, Series-1000

    50mm x 450Sanitary PVC Elbow, Series-1000PVC Cement Solvent

    12mm x 900G.I. Elbow, Sch. 40

    12mm x 6.00m G.I. Pipe, Sch. 40

    Teflon Tape

    Stainless Kitchen Sink, w/ Strainer drain assembly

    w/ Plug & complete water supply fitting

    b. Labor:

    1 - Plumber

    2 - Laborers

    TOTAL DIRECT COST

    OVERHEAD EXPENSES

    PHYSICAL CONTINGENCIES

    MISCELLANEOUS EXPENSES

    TOTAL COST OF ITEM IX

    X. PAINTING WORKSa. Materials:

    Liquid Tile Primer

    Liquid Tile Putty Filler

    Liquid Tile Reducer

    Liquid Tile Top Coat (Glossy White)

    Lamp Black Tinting Color

    Raw Sienna Tinting ColorThalo Blue Tinting Color

    Venetian Red Tinting Color

    Burnt Umber Tinting Color

    Rust Remover

    Acrylic Base Paint

    Metal Primer Paint

    Paint Thinner

    2" Paint Brush

    Paint Roller Tray

  • 8/11/2019 Second Floor Renovation by Contract

    48/78

    # 150 Sand Paper

    # 120 Sand Paper

    b. Labor:

    1 - Painter

    4 - Laborers

    TOTAL DIRECT COST

    OVERHEAD EXPENSESPHYSICAL CONTINGENCIES

    MISCELLANEOUS EXPENSES

    TOTAL COST OF ITEM IX

    XI. DEMOBILIZATION

    I. MOBILIZATION

    II. LAYOUTING WORKS

    III. CONCRETING WORKS

    IV. MASONRY WORKS

    V. CARPENTRY WORKS

    VI. ROOFING WORKS

    VII. STEEL WORKS

    VIII. ELECTRICAL WORKS

    IX. PLUMBING WORKS

    X. PAINTING WORKS

    XI. DEMOBILIZATION

    PROJECT COST

    VAT (12%)

    Prepared by: Checked &

    FELIXBERTO R. CAARE, JR. MARIE CL

    Reseacher/Analyst A (J.O.) Officer-In-C

    Planning & Development Section Planning &

    Approved by: Certified as

    CARLOS L. PEREZ, SR. LUIS A. W

    Officer-In-Charge Division Ma

    Engineering Department Treasury a

    Approved f

    General Ma

    S U M M A R

    LEONARD

  • 8/11/2019 Second Floor Renovation by Contract

    49/78

    TEEN & STORAGE ROOM (Floor Area = 65.87 sq.m.)

    mboanga City

    Qty. Unit Unit Cost Amount Total Cost

    1 lot 10,000.00 10,000.00 10,000.00

    50 bd.ft. 17.00 850.00

    16 bd.ft. 17.00 272.00

    1 roll 110.00 110.00

    1 kg. 65.00 65.00

    1 kg. 71.00 71.00 1,368.00

    1 day 366.00 732.00 732.00

    2,100.00

    105.00

    84.00

    21.00 210.002,310.00

    39 bags 230.00 8,970.00

    2 cu.m. 1,000.00 2,000.00

    4 cu.m. 1,000.00 4,000.00

    67 bd.ft. 20.00 1,340.00

    ippines

    ER DISTRICT

    nga City

    ST ESTIMATES

  • 8/11/2019 Second Floor Renovation by Contract

    50/78

    0.50 kg. 142.00 71.00 16,381.00

    2 days 366.00 1,464.00 7,464.00

    2 days 366.00 1,464.00

    2 days 366.00 732.00

    2 days 317.00 3,804.00 7,464.00

    23,845.00

    1,192.00

    954.00

    238.00 2,384.00

    26,229.00

    266 pcs. 129.00 34,314.00

    12 bags 230.00 2,760.00

    1 cu.m. 1,200.00 1,200.00

    10 packs 49.00 490.00 38,764.00

    8 days 366.00 5,856.00

    8 days 317.00 10,144.00 16,000.00

    8 days 300.00 2,400.00 2,400.00

    57,164.00

    5 bags 230.00 1,150.00

    0.25 cu.m. 1,000.00 250.00

    0.10 cu.m. 1,000.00 100.000.10 cu.m. 1,200.00 120.00

    4 pcs. 165.00 660.00

    0.50 kg. 65.00 33.00

    1 sht. 750.00 750.00

    30 bd.ft. 20.00 600.00

    0.50 kg. 65.00 33.00

    53 pcs. 14.00 742.00

    90 pcs. 64.00 5,760.00

    2 pcs. 52.00 104.00

    4 packs 49.00 196.00 10,498.00

    4 days 366.00 2,928.00

    4 days 317.00 1,268.00 4,196.00

    4 days 300.00 1,200.00 1,200.00

    15,894.00

    73,058.003,653.00

  • 8/11/2019 Second Floor Renovation by Contract

    51/78

    2,922.00

    731.00 7,306.00

    80,364.00

    373 bd.ft. 40.00 14,920.00

    186 bd.ft. 40.00 7,440.00

    6 shts. 630.00 3,780.00

    14 shts. 330.00 4,620.00

    6 kgs. 65.00 390.00

    4 kgs. 65.00 260.00

    5 kgs. 65.00 325.00 31,735.00

    10 days 366.00 7,320.00

    10 days 317.00 6,340.00 13,660.00

    45,395.00

    14 bd.ft. 40.00 560.00

    627 bd.ft. 40.00 25,080.00

    44 shts. 380.00 16,720.00

    10 kgs. 65.00 650.00

    11 kgs. 65.00 715.00 43,165.00

    5 days 366.00 3,660.00

    5 days 317.00 6,340.00 10,000.00

    53,165.00

    8 shts. 1,025.00 8,200.00

    2 liters 110.00 220.00

    2 kgs. 65.00 130.00 8,550.00

    2 days 366.00 1,464.00

    2 days 317.00 1,268.00 2,732.00

    11,282.00

    10 shts. 1,025.00 10,250.00

    2 shts. 380.00 760.00

    3 liters 110.00 330.00

    3 kgs. 65.00 195.00

    2 shts. 300.00 600.00

    4 btls. 80.00 320.00

    44 pcs. 18.00 792.00

    22 pcs. 16.00 352.00 13,599.00

  • 8/11/2019 Second Floor Renovation by Contract

    52/78

    4 days 366.00 2,928.00

    4 days 317.00 2,536.00 5,464.00

    19,063.00

    2 sets 1,500.00 3,000.00

    1 set 1,200.00 1,200.00 4,200.00

    4,200.00

    2 sets 3,500.00 7,000.00

    2 sets 680.00 1,360.00

    8,360.00

    8,360.00

    2 units 700.00 1,400.00 1,400.00

    1,400.00

    142,865.007,143.00

    5,715.00

    1,429.00 14,287.00

    157,152.00

    22 shts. 630.00 13,860.00

    60 bd.ft. 36.00 2,160.00

    67 bd.ft. 36.00 2,412.00

    96 bd.ft. 36.00 3,456.00

    43 bd.ft. 36.00 1,548.00

    4 kgs. 65.00 260.00

    6 kgs. 65.00 390.00 24,086.00

    5 days 366.00 3,660.00

    5 days 317.00 6,340.00 10,000.00

    34,086.00

    1,704.00

    1,363.00

    341.00 3,408.00

    37,494.00

    2 pcs. 2,238.00 4,476.00

    2 pcs. 652.00 1,304.00

    4 pcs. 150.00 600.00

    3 pcs. 612.00 1,836.00

    3 pcs. 356.00 1,068.00

  • 8/11/2019 Second Floor Renovation by Contract

    53/78

    6 pcs. 182.00 1,092.00

    2 pcs. 195.00 390.00 10,766.00

    3 days 366.00 1,098.00

    3 days 366.00 1,098.00

    3 days 317.00 1,902.00 4,098.00

    2 days 2,200.00 4,400.00 4,400.00

    14,864.00743.00

    595.00

    149.00 1,487.00

    16,351.00

    1 unit 5,250.00 5,250.00

    16 mtrs. 95.00 1,520.00

    2 rolls 4,183.00 8,366.00

    2 sets 1,518.00 3,036.00

    2 sets 1,221.00 2,442.00

    5 sets 310.00 1,550.00

    13 sets 25.00 325.00

    4 sets 286.00 1,144.00

    7 sets 253.00 1,771.00

    2 sets 114.00 228.00

    1 set 81.00 81.00

    15 pcs. 253.00 3,795.00

    5 pcs. 18.00 90.00

    14 pcs. 7.00 98.00

    2 pcs. 9.00 18.00

    2 pcs. 4.00 8.00

    1 box 138.00 138.00

    25 mtrs. 6.00 150.00

    20 pcs. 201.00 4,020.00

    3 pcs. 13.00 39.00

    5 pcs. 13.00 65.00

    8 pcs. 6.00 48.00

    4 pcs. 8.00 32.00

    4 pcs. 3.00 12.00

    3 boxes 110.00 330.00

    15 pcs. 17.00 255.00

    20 pcs. 22.00 440.00

    2 kgs. 65.00 130.00

    2 pcs. 554.00 1,108.00

    1 qrt. 370.00 370.00

  • 8/11/2019 Second Floor Renovation by Contract

    54/78

    6 pcs. 30.00 180.00

    3 pcs. 25.00 75.00

    1 pc. 105.00 105.00 37,219.00

    5 days 366.00 1,830.00

    5 days 317.00 3,170.00 5,000.00

    42,219.00

    42,219.00

    2,111.00

    1,689.00

    422.00 4,222.00

    46,441.00

    12 pcs. 250.00 3,000.00

    6 pcs. 28.00 168.00

    2 pcs. 22.00 44.002 qrts. 285.00 570.00

    10 pcs. 12.00 120.00

    5 pcs. 550.00 2,750.00

    10 rolls 22.00 220.00

    1 set 1,900.00 1,900.00

    8,772.00

    3 days 366.00 1,098.00

    3 days 317.00 1,902.00 3,000.00

    11,772.00

    589.00

    471.00

    118.00 1,178.00

    12,950.00

    13 gals. 660.00 8,580.00

    18 gals. 470.00 8,460.00

    8 gals. 369.00 2,860.00

    14 gals. 787.00 11,018.00

    2 pints 100.00 200.00

    2 pints 100.00 200.002 pints 100.00 200.00

    2 pints 100.00 200.00

    2 pints 100.00 200.00

    1 gals. 510.00 510.00

    2 gals. 900.00 1,800.00

    2 gals. 398.00 796.00

    2 gals. 325.00 650.00

    4 pcs. 10.00 40.00

    2 pcs. 45.00 90.00

  • 8/11/2019 Second Floor Renovation by Contract

    55/78

    2 dozs. 105.00 210.00

    2 dozs. 105.00 210.00 36,224.00

    10 days 366.00 3,660.00

    10 days 317.00 12,680.00 16,340.00

    52,564.00

    2,628.002,103.00

    526.00 5,257.00

    57,821.00

    1 lot 10,000.00 10,000.00 10,000.00

    Reviewed by: Submitted by:

    IRE C. BONGO MARLI ACOSTA-DE FIESTA

    harge

    Development Section

    to Availability of Funds: Recommending Project Implementation:

    EE ALEJO S. ROJAS, JR.

    nager C Assistant General Manager for Operations

    d Finance Department

    r Project Implementation:

    nager

    Y

    10,000.00Php

    2,310.00Php

    80,364.00Php

    157,152.00Php

    26,229.00Php

    37,494.00Php

    16,351.00Php

    46,441.00Php

    12,950.00Php

    57,821.00Php

    10,000.00Php

    457,112.00Php

    Planning & Design Division

    REY D. VASQUEZ

    54,853.00Php

    511,965.00Php

    Officer-In-Charge

  • 8/11/2019 Second Floor Renovation by Contract

    56/78

    12.7 SQ.M.

    6.58 m.

    8.08 m.

    53.17 sq.m.

    65.87

    ok

  • 8/11/2019 Second Floor Renovation by Contract

    57/78

    ok

  • 8/11/2019 Second Floor Renovation by Contract

    58/78

    ok

  • 8/11/2019 Second Floor Renovation by Contract

    59/78

  • 8/11/2019 Second Floor Renovation by Contract

    60/78

    1 welder #REF! kg/6m

    7.58 lbs./ft. #REF! days

    170503.8

    2544.833

    4009.333

    10 Matting/day

  • 8/11/2019 Second Floor Renovation by Contract

    61/78

    0 days

    20 kg./hr. 559817.90 kg./m.

    #####

  • 8/11/2019 Second Floor Renovation by Contract

    62/78

    0.12

  • 8/11/2019 Second Floor Renovation by Contract

    63/78

  • 8/11/2019 Second Floor Renovation by Contract

    64/78

  • 8/11/2019 Second Floor Renovation by Contract

    65/78

  • 8/11/2019 Second Floor Renovation by Contract

    66/78

  • 8/11/2019 Second Floor Renovation by Contract

    67/78

  • 8/11/2019 Second Floor Renovation by Contract

    68/78

  • 8/11/2019 Second Floor Renovation by Contract

    69/78

  • 8/11/2019 Second Floor Renovation by Contract

    70/78

  • 8/11/2019 Second Floor Renovation by Contract

    71/78

  • 8/11/2019 Second Floor Renovation by Contract

    72/78

  • 8/11/2019 Second Floor Renovation by Contract

    73/78

  • 8/11/2019 Second Floor Renovation by Contract

    74/78

  • 8/11/2019 Second Floor Renovation by Contract

    75/78

  • 8/11/2019 Second Floor Renovation by Contract

    76/78

  • 8/11/2019 Second Floor Renovation by Contract

    77/78

  • 8/11/2019 Second Floor Renovation by Contract

    78/78

    #REF! #REF! #REF! #REF!

    filling item 201 item 200

    #REF! #REF! #REF!

    item 104

    0.23 thk