Second Floor Renovation by Contract
-
Upload
caare-felix -
Category
Documents
-
view
219 -
download
0
Transcript of Second Floor Renovation by Contract
-
8/11/2019 Second Floor Renovation by Contract
1/78
Project : PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING
Location : Pilar Street, Zamboanga City
Scope of Work :A. NON ENGINEERING BASIC COST
I. PERMIT & FEES
II. CONSTRUCTION SAFETY & HEALTH PROGRAM
III. CONSTRUCTION OF ONE (1) UNIT TEMPORARY FACILITY
B. ENGINEERING BASIC COST
A. RENOVATION OF SECOND FLOOR
I. MOBILIZATION/DEMOBILIZATION
III. CONSTRUCTION OF TEMPORARY OFFICE
IV. MASONRY WORKS
IX. ELECTRICAL WORKS
X. PAINTING WORKS
XI. FIXTURES AND OFFICE EQUIPMENT
B. CONSTRUCTION OF COOP OFFICE/CANTEEN & STORAGE ROOM (FLOOR AREA = 65.87 SQ.M.)
I. MOBILIZATION
II. LAYOUTING WORKS
III. CONCRETING WORKS
IV. MASONRY WORKS
V. CARPENTRY WORKS
VI. ROOFING WORKS
VII. STEEL WORKS
VIII. ELECTRICAL WORKS
IX. PLUMBING WORKS
X. PAINTING WORKS
XI. DEMOBILIZATION
PROJECT COST :
Qty. Unit Unit
A. NON ENGINEERING BASIC COST
I. PERMIT & FEES
1. Building Permit 1 lot 15,0
DIRECT COST
II. CONSTRUCTION SAFETY & HEALTH PROGRAM
1. Public Safety & Health Program 1 lot 20,0
DIRECT COST
III. CONSTRUCTION OF ONE (1) UNIT TEMPORARY FACILITY
A. Material:
12 - pcs. 2" x 4" x 10' Coco Lumber 80 bd.ft.
14 - pcs. 2" x 3" x 10' Coco Lumber 70 bd.ft.
20 - pcs. 2" x 2" x 10' Coco Lumber 67 bd.ft.
Guage 26 x 1.20m x 2.40m Corrugated G.I. Roof Sheet 16 pcs. 2
Gauge 26 x 1.20m x 2.40m G.I. Plain Sheet 1 pc. 4
12mm Thick x 1.20m x 2.40m Ordinary Plywood 14 pcs. 7
2" C.W. Umbrella Roofing Nail 2 kgs. 6
3" C.W. Nail 2 kgs. 64" C.W. Nail 2 kgs. 6
3-1/2" Loose Pin Hinges 2 pcs. 21
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
VI. CARPENTRY WORKS
VII. PLUMBING WORKS
VIII. SPRINKLER SYSTEM
5,901,401.00Php
BILL OF MATERIALS & COST ESTIMATES
ITEM DESCRIPTION
-
8/11/2019 Second Floor Renovation by Contract
2/78
B. ENGINEERING BASIC COST
A. RENOVATION OF SECOND FLOOR
I. MOBILIZATION/DEMOBILIZATION 1 lot 40,0
DIRECT COST
II. DEMOLITION WORKS AND CLEARING
A. Labor:
4 - Skilled Worker 45 days 38 - Laborers 45 days 3
B. Equipment Rental/Fuel:
1 - Unit Dump Truck 25 days 5,0
Diesel/Fuel 250 liters
DIRECT COST
III. CONSTRUCTION OF TEMPORARY OFFICE
A. Materials:
Partition & Cubicle Work:
6mm thk x 1.20m x 2.40m Ordinary Plywood 52 shts. 3
220 pcs. - 2" x 3" x 8' Red Lauan Wood 880 bd.ft.
Concrete Nail 4" 6 kgs.
CW Nail 2-1/2" 4 kgs.
Electrical Work (58 Outlets):
48" Industrial Ceiling Fan (3-Blade, 80 Watts Power, 220V, Ceiling Type) 14 units 6,0
8 Branch Panel Board Box, Bolt-On Type 1 pc. 5,0
100 Ampere Circuit Breaker, Bolt-On, 230 Volts, 2P 1 pc. 1,4
20 Ampere Circuit Breaker, Bolt-On, 230 Volts, 2P 8 pcs. 5
22mm2THW Stranded Wire 22 mtrs. 2
3.5mm2TW Stranded Wire 6 rolls 6,3
14/2c Flat Cord 75 mtrs.
40 Watts Fluorescent Lamp, Box Type Assembly 24 pcs. 2
2-Gang Switch (Flush Type) w/ Plate 3 pcs. 1
3-Gang Convenience Outlet, Surface Type 30 pcs.
Duplex Convenience Outlet w/ Plate 15 pcs. 112mm Hook 30 pcs.
2"x4"x2" Utility Box 18 pcs.
4"x4" Junction Box 30 pcs.
4"x4" Junction Box Cover 30 pcs.
20mm FlexibleConduit 250 mtrs.
25mm x 3m Electrical Molding Conduit 38 pcs. 1
#14 G.I. Tie-wire 5 kgs.
12mm Insulated Staple 1 box
Rubber Tape 3 pcs.
Electrical Tape 1 pc.
Tarpaulin Canvass Lona, S200, 7mmthk x 1.83m x 50m/roll (Color White) 1 roll 7,7
19mm x 6.00m G.I. Pipe, Sch. 40 14 pcs. 6
4mm thk x 38mm x 6.00m Flat Bar 1 pc. 58mm x 25mm Ordinary Bolt, w/ Nut & Washer (Full Threaded) 28 pcs.
50mm x 6.00m G.I. Pipe, Sch. 40 16 pcs. 1,8
8mm Nylon Rope (600 ft./roll) 0.25 roll 18,4
B. Labor:
3 - Carpenters 15 days 3
1 - Electrician 15 days 3
4 - Laborers 15 days 3
DIRECT COST
IV. MASONRY WORKS
A. Materials:
Portland Cement 90 bags 2Washed Sand 3 cu.m. 1,0Fine Sand (For Plastering) 0.25 cu.m. 1,3100mm x 200mm x 400mm CHB 350 pcs.
-
8/11/2019 Second Floor Renovation by Contract
3/78
3 - Masons 10 days 3
3 - Laborers 10 days 3
DIRECT COST
V. TILE WORKS
A. Materials:
Tile Grout 15 packs 1
600mm x 600mm x Granite Tiles 1160 pcs. 2300mm x 300mm Ceramic Tiles 1280 pcs.
20mm thk. 0.60m x 2.13m Granite Slab 4 units 6,5
6mm Tile Trim 6 pcs. 2
B. Labor:
3 - Masons 25 days 3
3 - Laborers 25 days 3
DIRECT COST
VI. CARPENTRY WORKS
A. Materials:
1. CEILING WORKS3.50mm thk. 1.20m x 2.40m Hardiflex Lite Ceiling Board 140 pcs. 4
6mm thk x 1.20m x 2.40m Marine Plywood 12 shts. 419mm thk x 1.20m x 2.40m Marine Plyboard 24 shts. 1,11" x 2" x 8' Red Lauan Wood 16 bd.ft.
2" x 2" x 8' Red Lauan Wood 1800 bd.ft.4" Concrete Nail 10 kgs.3" CW Nail 27 kgs.
2' CW Nail 10 kgs.2" Finishing Nail 5 kgs.Hardi Nail 33 kgs. 11" x 5" x 8' Baseboard 60 pcs. 1
2. WALLING/PARTITION AND CUBICLE WORKS2" x 4" x 10' Red Lauan Wood 1068 bd.ft.6mm thk x 1.20m x 2.40m Ordinary Plywood 110 shts. 34" CW Nail 20 kgs.
3" CW Nail 15 kgs.2" CW Nail 10 kgs.1" Finishing Nail 7 kgs.
1" x 5" x 8' Baseboard 150 pcs. 1
3. FABRICATION OF OFFICE TABLES, CABINET & SHELVE
6mm thk x 1.20m x 2.40m Ordinary Plywood 15 shts. 3
20mm thk x 1.20m x 2.40m Plyboard 98 shts. 9400mm Length Roller Slide 139 setsDrawer Lock 139 sets 1
Drawer Handle 139 setsUpholstery Cloth 53 mtrs. 1Solvent (Rugby) 6 gals. 53" CW Nail 1 kg.
2" Finishing Nail 30 kgs.
1-1/2" Finishing Nail 20 kgs.1" Finishing Nail 7 kgs.
1" x 1" Wooden Nosing 30 bd.ft.1" x 2" Wooden Nosing 45 bd.ft.25mm x 6.00 Stainless Tubing 1 pcs. 910mm x 50mm Stainless Bolt w/ Nut & Washer 20 pcs.
2" x 4" x 10' Red Lauan Wood 30 bd.ft.
4. DOORS/WINDOWS & GLASS (Job Order)
D1 - 0.60m x 1.20m PVC Door, w/ PVC Door Jamb, and w/ Complete Hinges, w/out Door KnobD2 - 0.80m x 2.10m Panel Type Door, w/ 2" x 6" Jamb,
2" x 4" Door Frame, 6mm thk. Marine PlywoodD3 - Double Swing Door, 2" x 4" Alum. Frame/Jamb Analok Glass Aluminum Door Frame
Aluminum Analok Sliding Window, 6mm Thk. Bronze Glass 10 units 11,3
Fixed Glass/Aluminum Frame Analok , 6mm Thk. Bronze Glass 2 units 18,30.60m x 1.20m, 6mm Thk. Clear Glass 21 units 80.60m x 1.50m, 6mm Thk. Clear Glass 4 units 1,1
5 units 5,5
3 units 15,4
2 units 2,2
-
8/11/2019 Second Floor Renovation by Contract
4/78
B. Labor:
3 - Carpenters 90 days 36
3 - Laborers 90 days 31
C. Equipment Rental:
1 - Unit Welding Machine 15 days 2,16
DIRECT COST
VII. PLUMBING WORKS
A. Materials:Flush Type Water Closet w/ Complete Fittings and Accessories 6 sets 5,00Porcelain Lavatory w/ Complete Fittings and Acessories 4 sets 2,30Urinal w/ Complete Fittings and Acessories 2 sets 3,50Undermount Porcelain Lavatory w/ Complete Fittings And Accessories 2 sets 4,00Soap Holder 4 pcs. 15Tissue Holder 2 pcs. 25100mm x 100mm Stain. Floor Drain w/ Double Strainer 4 pcs. 20Solvent Cement 1 can 950mm x 3.0m PVC Pipe 6 pcs. 2550mm x 50mm PVC Elbow 8 pcs. 350mm PVC Coupling 6 pcs. 2Water Faucet 8 pcs. 12
B. Labor:
1 - Plumber 7 days 31
2 - Laborers 7 days 31
DIRECT COST
VIII. SPRINKLER SYSTEM
A. Materials & Labor:
SUPPLY, INSTALLATION, TESTING & COMMISSIONING OFONE (1) UNIT 10HP CENTRIFUGAL PUMP WITH MOTOR,MOTOR CONTROLS, CONTROL PANEL, 3 PHASEWITH PUMP OUTLET & INLET OF 4" DIAMETER WITH STEELBED PLATE
SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF
ONE (1) Lot Wet Fire Sprinkler System Complete with PipingPendent Type Sprinkler Head and Acessories
(Note: Actual Piping Lay out to refer on project site)
DIRECT COST
IX. ELECTRICAL WORKS
A. Materials:150AT/150AF, 230V, 3P, Three Phase, Common Trip Main Circuit Breaker 1 set 81
100 Amps. Molded Case Main Circuit Breaker, 3 Phase250 volts enclosed in Powder Coated Finished Panel Boardwith 7 Single Phase Branches of:
Lumpsum
1 unit 150,00
-
8/11/2019 Second Floor Renovation by Contract
5/78
1 sets - 20 Amps. Branch
6 sets - 15 Amps. Branch 1 set 7,
100 Amperes Main Circuit Breaker, 3 Phase,250 volts enclosed in Powder Coated Finished Panel Board
with 12 Single Phase Branches of:
3 sets - 60 Amps. Branch
2 sets - 30 Amps. Branch
6 sets - 20 Amps. Branch 1 sets - 15 Amps. Branch 1 set 8,
100 Amperes Main Circuit Breaker, 3 Phase,
250 volts enclosed in Powder Coated Finished Panel Board
with 4 Single Phase Branches of:
5 sets - 50 Amps. Branch 1 sets - 30 Amps. Branch 1 set 7,
30 Amperes, 2P, Safety Breaker 2 pc.60 Amperes, 2P, Safety Breaker 5 pc.
11 Watts, 2U, Compact Fluorescent Lamp, Cool Daylight 6 pcs.
13 Watts, 2U, Compact Fluorescent Lamp, Cool Daylight 18 pcs.
15 Watts, 2U, Compact Fluorescent Lamp, Cool Daylight 35 pcs.18 Watts, 3U, Compact Fluorescent Lamp, Cool Daylight 69 pcs.
23 Watts, 3U, Compact Fluorescent Lamp, Cool Daylight 2 pcs.
20 Watts Box Type Fluorescent Lamp 2 pcs.40 Watts Box Type Fluorescent Lamp 2 pcs.Recessed Type Downlights w/o Cover, E27 124 pcs.
Emergency lamp 8 pcs.
40 Watts Fluorescent Lamp, Cool Daylight, Recessed Type,
Mirrorized Fluorescent Louminaires, 2x40watts Assembly
Exaust Fan, Wall Mounted 2 pcs. 1
Duplex Convenience Outlet w/ plate (flush type) 52 pcs.
Aircon Outlet 1 Gang 5 pcs.
Ceiling Socket with screw 8 pcs.
Toggle Switch 1-Gang w/ plate (flush type) 6 pcs.
Toggle Switch 2-Gang w/ plate (flush type) 9 pcs.
Toggle Switch 3-Gang w/ plate (flush type) 13 pcs.
3-Way Switch w/ plate (flush type) 4 pcs.
38.0mm2THW Stranded Wire 75 mtrs.
22.0mm2THW Stranded Wire 30 mtrs.
5.5mm2THW Stranded Wire 3 rolls 9
3.5mm2THW Stranded Wire 150 mtrs.
3.5mm2TW Stranded Wire 8 rolls 4
2.0mm2TW Stranded Wire 10 rolls 3
40mm x 3m RSC Electrical Conduit 5 pcs.
40mmx 90 RSC Electrical Conduit Elbow Long Sweep 2 pcs.
40mm RSC Coupling 5 pcs.
40mm RSC Locknut 2 pcs.
40mm RSC Condulet 1 pcs.
40mm Conduit Clamp 20 pcs.
40mm G.I. Flexible Conduit, Corrugated Pipe 2 mtrs.
40mm Conduit Straight Connector 2 mtrs.32mm x 3.00m PVC Electrical Conduit 4 pcs.
32mm PVC Male Adaptor 8 pcs.
32mm PVC Lock Nut (Zinc Coated) 8 pcs.
25mm PVC Flexible Electrical Conduit 6 mtrs.
25mm x 3.00m PVC Electrical Conduit 19 pcs.
25mm x 90 PVC Electrical Conduit Elbow Long Sweep 10 pcs.
25mm PVC Electrical Coupling Connectors 18 pcs.
25mm PVC Male Adaptor 12 pcs.
25mm PVC Lock Nut (Zinc Coated) 12 pcs.
20mm PVC Flexible Electrical Conduit 2 roll
20mm x 3.00m PVC Electrical Conduit 750 pcs.
20mm x 90 PVC Electrical Conduit Elbow Long Sweep 50 pcs.
20
mm
PVC Electrical Coupling Connectors 250 pcs.20mm PVC Male Adaptor 150 pcs.
20mm PVC Lock Nut (Zinc Coated) 150 pcs.
2" 4" 2" PVC Utilit B ( H D ) 77
17 pcs. 2
-
8/11/2019 Second Floor Renovation by Contract
6/78
1/2" Camridge / Mica Tube 6 mtrs. 2
3/4" Polytype Electrical Tape 10 pcs. 3
3/4" Rubber Tape 5 pcs. 10
B. Labor:2 - Electrician 36 days 362 - Laborers 36 days 31
DIRECT COST
X. PAINTING WORKS
Conrete Neutralizer 2 gals. 48Penetrating Sealant 20 gals. 51Solvent-Based Acrylic Primer 90 gals. 66Putty Filler Cast 60 gals. 43Solvent-Based Acrylic Primer Top Coat (White) 120 gals. 78
Acrylic Based Reduction Thinning 40 gals. 36Tinting Color for Solvent-Based Acrylic Paint:
-
8/11/2019 Second Floor Renovation by Contract
7/78
Lamp Black 170 pint 10Raw Sienna 400 pint 10
Toloudine Red 30 pint 10Putty Filler w/ Hardener 40 qrts. 17
Patching Compound 10 kgs. 1
Lacquer Thinner 20 gals. 42Lacquer Flow 10 gals. 58
Sanding Sealer 25 gals. 540Paint Thinner 10 gals. 341
Baby Roller Cotton w/ Tray 8 pcs. 337" Roller Brush w/ Tray 8 pcs. 33
2" Paint Brush 8 pcs. 10
4" Paint Brush 8 pcs. 45Rust Converter 3 gals. 475
Zinc Chromate 4 gals. 86# 150 Sand Paper 10 doz. 10
# 120 Sand Paper 10 doz. 10
B. Labor:4 - Painters 60 days 31
4 - Laborers 60 days 31
DIRECT COST
XI. FIXTURES AND OFFICE EQUIPMENT
Executive Chair Executive Chair w/ Black Leatherette back and seat molded foam cushion,
lockable tilting mechanism, polyurethane or polypropylene armrest, five legged and black
leatherette back and nylon twin caster pneumatic height adjustment. 16 units 4,20
Office Chair w/ Low back and seat molded foam cushion, lockable tilting mechanism,
polyurethane or polypropylene armrest, five legged and black leatherette back
and nylon twin caster pneumatic height adjustment. 25 units 2,30
Visitors Chair w/ four legged, back and sit molded foam cushion, polypropylene armrest,
shiny chromed chair frame 11 units 1,60
Sala Set 2 sets 14,00
Packaged Supply,Installation & Testing of Two (2) Units Ceiling Mounted Split Type, Cassette Air Conditioner
Specs:
Cooling Capacity - 58,000 Btu/hr
Capacity - 5 TRPower - 3P/220 V/60 Hz
- LCD remote Type w/ Auto timer on/off, Sleep Mode,Dry Mode, Auto Fan Speed, Night Timer,Real Time Clock
- With inverter, Heating & Cooling
- High efficiency
- Eco Friendly
- Automatic Drain Pump
- Two thermistor control function
- Alarm function for filter cleaning 2 units 108,00
Labor (Lump Sum) 1 lot 10,00
Packaged Supply & Intallation of Ceiling Mounted Projector & Projector Screen 1 unit 59,180
Specs:
240VAC, 60Hz, 300W projector with 0.80-7.5 meters diagonally projection size, full color,ceiling mounted ready installation,moulded plastic, 307mm x 69mm x 210mm dimension,
approx. 2.3 kgs, 0o-40
oC temperature, 20%-80% humidity, with 2 meters power cord,
power cord secure lock, wireless remote control, VGA cable, carrying bag and application
software (CD-ROM). With metal ceiling mount projector bracket.
And with 1.7m wide - 78" diagonal projector screen, matt white surface with 3cm black border
and weighted bottom bar. Housed in a white case with mounting brackets on either end.
Can be operated with in-line control switch or a wirless remote control. Ceiling and wall
mounting compatible, low noise electric motor, 240 VAC input, 60 Hz. Remote control
distance of 20m.
Labor (Lump Sum) 1 lot 5,00
DIRECT COST
B. CONSTRUCTION OF COOP OFFICE/CANTEEN & STORAGE ROOM (FLOOR AREA = 65.87 SQ.M.)
I. MOBILIZATION 1 lot 10,00
-
8/11/2019 Second Floor Renovation by Contract
8/78
4" C.W. Nail 1 kg. 654" Concrete Nail 1 kg. 71
B. Labor:2 - Carpenters 1 day 366
DIRECT COST
III. CONCRETING WORKSA. Materials:
FlooringPortland Cement 39 bags 230
Washed Sand 2 cu.m. 1,000Gravel (G-1) 4 cu.m. 1,00010pcs. - 2" x 4" x 10' Coco Lumber 67 bd.ft. 20
4" Concrete Nail 1 kg. 142
-
8/11/2019 Second Floor Renovation by Contract
9/78
B. Labor:2 - Masons 2 days 362 - Carpenters 2 days 361 - Steelman 2 days 366 - Laborers 2 days 31
DIRECT COST
IV. MASONRY WORKS
A. Materials:
1. Floor Tiles0.40m x 0.40m Granite Tiles (White) 266 pcs. 12Portland Cement 12 bags 23Fine Sand (for plastering) 1 cu.m. 1,20Tile Grout (cement joint filler) 10 packs 4
B. Labor:
2 - Masons 8 days 36
4 - Laborers 8 days 31
C. Equipment Rental:1 - Unit Angular Grinder 8 days 30
2. Kitchen CounterPortland Cement 5 bags 23Washed Sand 0.25 cu.m. 1,00Gravel (G-1) 0.10 cu.m. 1,00Fine Sand (for plastering) 0.10 cu.m. 1,2010mm x 6.00m Deformed Reinforcing Steel Bars 4 pcs. 16#16 G.I. Tie-wire 1 kg. 612mm thk x 1.20m x 2.40m Ordinary Plywood 1 sht. 756pcs. - 2" x 3" x 10' Coco Lumber 30 bd.ft. 24" C.W. Nail 1 kg. 64" CHB (NBL) 53 pcs. 10.20m x 0.20m Granite Tiles (White) 90 pcs. 6PVC Tile Trim 2 pcs. 5Tile Grout (cement joint filler) 4 packs 4
B. Labor:
2 - Masons 4 days 36
1 - Laborer 4 days 31
C. Equipment Rental:
1 - Unit Angular Grinder 4 days 30
DIRECT COST
V. CARPENTRY WORKS
A. Materials:
1. Ceiling Works56pcs. - 2" x 4" x 10' S4s Lauan Wood 373 bd.ft. 456pcs. - 2" x 2" x 10' S4s Lauan Wood 186 bd.ft. 412mm thk x 1.20m x 2.40m Marine Plywood 6 shts. 635mm thk x 1.20m x 2.40m Marine Plywood 14 shts. 33
4" C.W. Nail 6 kgs. 63" C.W. Nail 4 kgs. 62" C.W. Nail 5 kgs. 6
B. Labor:
2 - Carpenters 10 days 362 - Laborers 10 days 31
A. Materials:
2. Wall/Wall Partition1pc. - 4" x 4" x 10' S4s Lauan 14 bd.ft. 4
94pcs. - 2" x 4" x 10' S4s Lauan Wood 627 bd.ft. 45mm thk x 1.20m x 2.40m Marine Plywood 44 shts. 384" C.W. Nail 10 kgs. 62" C.W. Nail 11 kgs. 6
B. Labor:
2 - Carpenters 5 days 36
4 Laborers 5 days 31
-
8/11/2019 Second Floor Renovation by Contract
10/78
1 1/2" C.W. Nail 2 kgs. 6
B. Labor:
2 - Carpenters 2 days 36
2 - Laborers 2 days 31
A. Materials:4. Counter Top
19mm thk x 1.20m x 2.40m Marine Plywood 10 shts. 1,025mm thk x 1.20m x 2.40m Marine Plywood 2 shts. 38Wood Glue 3 liters 112" C.W. Nail 3 kgs. 61.20m x 2.40m Plastic Formica 2 shts. 30Rubber Cement Solvent 4 btls. 82" x 2" Cabinet Hinges 44 pcs. 138mm Wooden Cabinet Handle 22 pcs. 1
B. Labor:
2 - Carpenters 4 days 36
2 - Laborers 4 days 31
A. Materials:5. Door and Window Jambs (Job Order)
0.90m x 2.10m x 0.05m x 0.15m Yakal/Hardwood Door Jambs 2 sets 1,501.40m x 1.20m x 0.05m x 0.15m Yakal/Hardwood Window Jambs 1 set 1,20
A. Materials:6. Doors & Window (Job Order)
0.90m x 2.10m Flush Door w/ 5mm thk Marine Plywood, Double 2 sets 3,500 Walling on 50mm x 100mm Door Frame, Door Knob5mm thk, 13 Blades Smoke Glass Jalousie Window w/ Standard 2 sets 680 Alum. Frame Holder (0.70m x 1.20m)
A. Materials:7. Ventillation (Job Order) 2 units 7025mm thk x 250mm x 1.20m Pre-fabrication Wooden Ventillation
DIRECT COST
VI. ROOFING WORKSA. Materials:
12mm thk x 1.20m x 2.40 Marine Plywood 22 shts. 63018pcs. - 2" x 2" x 10' S4s Lauan Wood 60 bd.ft. 3614pcs. - 2" x 3" x 10' S4s Lauan Wood 67 bd.ft. 3624pcs. - 2" x 3" x 8' S4s Lauan Wood 96 bd.ft. 3616pcs. - 2" x 2" x 8' S4s Lauan Wood 43 bd.ft. 364" C.W. Nail 4 kgs. 652" C.W. Nail 6 kgs. 65
B. Labor:
2 - Carpenters 5 days 36
4 - Laborers 5 days 31
DIRECT COST
VII. STEEL WORKSA. Materials:
50mm x 6.00m G.I. Pipe, Sch. 40 2 pcs. 2,2312mm x 6.00m Aluminum Tube 2 pcs. 653mm x 25mm x 25mm x 3.00m Alum. Angle Bar 4 pcs. 154mm x 25mm x 25mm x 6.00m Angle Bar 3 pcs. 614mm x 38mm x 6.00m Flat Bar 3 pcs. 3510mm x 10mm x 6.00m Square Bars 6 pcs. 185mm thk x 25mm x 6.00m Flat Bar 2 pcs. 19
B. Labor:
1 - Steelman 3 days 36
1 - Welder 3 days 36
2 - Laborers 3 days 31
C. Equipment Rental:
1 - Unit Welding Machine 2 days 2,20
DIRECT COST
-
8/11/2019 Second Floor Renovation by Contract
11/78
4 sets - 20 Amps. Branch
1 sets - 15 Amps. Branch 1 unit 52
8.0mm2THW Stranded Wire 16 mtrs.
3.5mm2THW Stranded Wire 2 rolls 41
16" Orbit Fan, Standard 2 sets 1512" exhaust fan 2 sets 12
3U Electronic CFL with Capsule, Daylight, 23W Assembly 5 sets 3Ceiling Socket with screw 13 sets
Reccessed Fluorescent illuminaire,1x40 Watts assemblyin Powder Coated Steel Plate; IP20 Assembly 4 sets 2
Duplex Convenience Outlet w/ plate (flush type) 7 sets 2Toggle Switch 3-Gang w/ plate (flush type) 2 sets 1
Toggle Switch 1-Gang w/ plate (flush type) 1 set
25mm (3/4") PVC Flexible Electrical Conduit 15 pcs. 2
25mm(3/4") x 90 PVC Electrical Conduit Elbow Long Sweep 5 pcs.
25mm (3/4")PVC Electrical Coupling Connectors 14 pcs.
25mm (3/4") PVC Male Adaptor 2 pcs.
25mm (3/4") PVC Lock Nut (Zinc Coated) 2 pcs.
25mm (3/4") PVC clamps w/ concrete nails 1 box 1
20mm (1/2") PVC Flexible Electrical Conduit 25 mtrs.
20mm (1/2") x 3.00m PVC Electrical Conduit 20 pcs. 2
20mm (1/2") x 90 PVC Electrical Conduit Elbow Long Sweep 3 pcs.
20mm
(1/2") x 90 PVC Electrical Conduit Short Elbow 5 pcs.20mm(1/2") PVC Electrical Coupling Connectors 8 pcs.
20mm (1/2") PVC Male Adaptor 4 pcs.
20mm (1/2") PVC Lock Nut (Zinc Coated) 4 pcs.
20mm (1/2") PVC clamps w/ concrete nails 3 boxes 1
2" x 4" x 2" PVC Utility Box ( H.D.) 15 pcs.4" x 4" x 2" PVC Junction Box ( H.D.) w/ Cover 20 pcs.
#16 G.I. Tie Wire 2 kgs.6" x 6" x 4" Gal. Pull Box 2 pcs. 5
PVC Solvent Cement 1 qrt. 31/2" Camridge / Mica Tube 6 pcs.
3/4" Polytype Electrical Tape 3 pcs.3/4" Rubber Tape 1 pc. 1
B. Labor:
1 - Skilled Electrician 5 days 3
2 - Laborers 5 days 3
DIRECT COST
IX. PLUMBING WORKS
A. Materials:50mm x 3.00m Sanitary PVC Pipe, Series-1000 12 pcs. 2
50mm x 900Sanitary PVC Elbow, Series-1000 6 pcs.
50mm x 450Sanitary PVC Elbow, Series-1000 2 pcs.PVC Cement Solvent 2 qrts. 2
12mm x 900G.I. Elbow, Sch. 40 10 pcs.12mm x 6.00m G.I. Pipe, Sch. 40 5 pcs. 5
Teflon Tape 10 rollsStainless Kitchen Sink, w/ Strainer drain assembly 1 set 1,9
w/ Plug & complete water supply fitting
B. Labor:
1 - Plumber 3 days 3
2 - Laborers 3 days 3DIRECT COST
X. PAINTING WORKS
A. Materials:Liquid Tile Primer 13 gals. 6Liquid Tile Putty Filler 18 gals. 4
Liquid Tile Reducer 8 gals. 3Liquid Tile Top Coat (Glossy White) 14 gals. 7
Lamp Black Tinting Color 2 pints 1Raw Sienna Tinting Color 2 pints 1
Thalo Blue Tinting Color 2 pints 1Venetian Red Tinting Color 2 pints 1
Burnt Umber Tinting Color 2 pints 1
l
-
8/11/2019 Second Floor Renovation by Contract
12/78
# 120 Sand Paper 2 dozs. 105.0
B. Labor:
1 - Painter 10 days 366.0
4 - Laborers 10 days 317.0
DIRECT COST
XI. DEMOBILIZATION 1 lot 10,000.0
TOTAL DIRECT COST
-
8/11/2019 Second Floor Renovation by Contract
13/78
-
8/11/2019 Second Floor Renovation by Contract
14/78
Total Cost
15,000.00
15,000.00
20,000.00
20,000.00
19,760.00
-
8/11/2019 Second Floor Renovation by Contract
15/78
40,000.00
40,000.00
180,000.00
137,250.00
317,250.00
207,594.00
50,993.00
40,980.00
299,567.00
-
8/11/2019 Second Floor Renovation by Contract
16/78
20,490.00
53,485.00
335,130.00
51,225.00
386,355.00
156,635.00
97,094.00
150,860.00
-
8/11/2019 Second Floor Renovation by Contract
17/78
184,410.00
32,400.00
909,159.00
59,096.00
6,657.00
65,753.00
560,149.00
560,149.00
-
8/11/2019 Second Floor Renovation by Contract
18/78
-
8/11/2019 Second Floor Renovation by Contract
19/78
306,954.00
49,176.00356,130.00
-
8/11/2019 Second Floor Renovation by Contract
20/78
311,903.00
152,160.00464,063.00
170,300.00
226,000.00
64,180.00
460,480.00
10,000.00
-
8/11/2019 Second Floor Renovation by Contract
21/78
1,368.00
732.002,100.00
16,381.00
-
8/11/2019 Second Floor Renovation by Contract
22/78
7,464.0023,845.00
38,764.00
16,000.00
2,400.0057,164.00
10,498.00
4,196.00
1,200.0015,894.00
73,058.00
31,735.00
13,660.00
45,395.00
43,165.00
10,000.00
53 165 00
-
8/11/2019 Second Floor Renovation by Contract
23/78
8,550.00
2,732.00
11,282.00
13,599.00
5,464.00
19,063.00
4,200.00
4,200.00
8,360.00
8,360.00
1,400.00
1,400.00
142,865.00
24,086.00
10,000.00
34,086.00
10,766.00
4,098.00
4,400.00
19,264.00
-
8/11/2019 Second Floor Renovation by Contract
24/78
37,219.00
5,000.0042,219.00
8,772.00
3,000.00
11,772.00
-
8/11/2019 Second Floor Renovation by Contract
25/78
36,224.00
16,340.00
52,564.00
10,000.00
421,773.00
-
8/11/2019 Second Floor Renovation by Contract
26/78
nt
-
8/11/2019 Second Floor Renovation by Contract
27/78
G A N T T C H A R T
: PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING
: Pilar Street, Zamboanga City
: 5,901,401.00
: 120 CALENDAR DAYS: 34 MANPOWER
A. NON ENGINEERING BASIC COST
I. PERMIT & FEES
II. CONSTRUCTION SAFETY & HEALTH PROGRAM
III. CONSTRUCTION OF ONE (1) UNIT TEMPORARY FACILITY
B. ENGINEERING BASIC COST
A. RENOVATION OF SECOND FLOOR
I. MOBILIZATION/DEMOBILIZATION April 29, 1900
II. DEMOLITION WORKS AND CLEARING
III. CONSTRUCTION OF TEMPORARY OFFICE January 16, 1900IV. MASONRY WORKS January 30, 1900
V. TILE WORKS
VI. CARPENTRY WORKS March 30, 1900
VII. PLUMBING WORKS January 06, 1900
VIII. SPRINKLER SYSTEM January 30, 1900
IX. ELECTRICAL WORKS February 05, 1900
X. PAINTING WORKS February 29, 1900
XI. FIXTURES AND OFFICE EQUIPMENT
B. CONST. OF COOP OFFICE/CANTEEN & STORAGE ROOM
I. MOBILIZATION
II. LAYOUTING WORKS
III. CONCRETING WORKS
IV. MASONRY WORKS =
V. CARPENTRY WORKSVI. ROOFING WORKS
VII. STEEL WORKS
VIII. ELECTRICAL WORKS
IX. PLUMBING WORKS
X. PAINTING WORKS
XI. DEMOBILIZATION
SUB-TOTAL
Total Direct Cost
OCM
VAT (12%)
TOTAL PROJECT COST
CASH OUTLAY REQUIREMENT
TARGETED COMPLETION THIS PERIOD
COMMULATIVE COMPLETION TO DATE
Prepared by: Checked & Reviewed by: Submitted by:
MARLI ACOST
Officer-I
Planning &
142,865.0034,086.00
42,219.00
11,772.00
52,564.00
10,000.00
10,000.00
2,100.00
23,845.00
73,058.00
5,901,401.00Php
632,293.00 84,23
Planning & Development Section
Sr. Water Res. Fac. Optr. B Officer-In-Charge
786,229.02
13.32%
MURPIN K. PALULLA MARIE CLAIRE C. BONGO
13.32%
58,49
439,092.00 58,49
356,130.00
464,063.00
4,390,924.00
460,480.00
439,092.00
August 25, 350
560,149.00
19,264.00
65,753.00
909,159.00
317,250.00
299,567.0053,485.00
386,355.00
21,760.00
20,000.00
15,000.00
40,000.00
( Php ) 15
PROJECT DURATIONMANPOWER REQUIREMENTS
WORK ITEMAMOUNT
PROJECT
LOCATION
PROJECT COST
-
8/11/2019 Second Floor Renovation by Contract
28/78
Project Title: PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING
Approved Budget Cost:
P.R. No.
A. NON ENGINEERING BASIC COST
I. PERMIT & FEES
II. CONSTRUCTION SAFETY & HEALTH PROGRAM
III. CONSTRUCTION OF ONE (1) UNIT TEMPORARY FACILITY
B. ENGINEERING BASIC COST
A. CONSTRUCTION OF TEMPORARY OFFICE
I. Mobilization/Demobilization
II. Installation of Walling/Partition and Cubicle Works
III.
IV.
V.
VI.
VII.
VIII.
IX. Supply and Installation of Tarpaulin Canvass/Lona w/ Complete Accessories
B. RENOVATION OF SECOND FLOOR
I. Mobilization/Demobilization/Hauling
II. Demolition and Clearing Works
Wood Wall Partition
Concrete Wall Partition
Ceiling
Floor/Wall TilesIII. Masonry Works
IV. Tile Works
Granite Tile Works with grouting (see plans for sizes and details)
Granite Countertop with grouting (see plans for sizes and details)
Ceramic Tile Works with grouting & tile trims (see plans for sizes and details)
V. Carpentry Works
Ceiling Works
Walling/Partition and Cubicle Works
Fabrication of Office Tables, Cabinets and Shelves
VI Doors/Windows and Glass:
D1 - 0.60m x 1.20m PVC Door, w/ PVC Door Jamb,
and w/ Complete Hinges, w/out Door Knob
D2 - 0.80m x 2.10m Panel Type Door, w/ 2" x 6" Jamb,
2" x 4" Door Frame, 6mm thk. Marine Plywood
D3 - Double Swing Door, 2" x 4" Alum. Frame/JambAnalok Glass Aluminum Door Frame
Aluminum Analok Sliding Window, 6mm Thk. Bronze Glass
Fixed Glass/Aluminum Frame Analok , 6mm Thk. Bronze Glass
VII. Plumbing Works
Flush Type Water Closet w/ Complete Fittings and Accessories
Undermount Porcelain Lavatory w/ Complete Fittings and Acessories
Wall Mounted Porcelain Lavatory w/ Complete Fittings and Acessories
Urinal w/ Complete Fittings and Acessories
Sanitary Pipes & Fittings
Cold Water Pipes & Fittings
VIII. Supply, Installation, Testing and Commissioning of Fire Sprinkler System
Supply, Installation, Testing and Commissioning of One (1) Lot Wet Fire Sprinkler System Complete w/
Piping, Pendent Type Sprinkler Head and Acessories, w/ One (1) Unit 10HP Centrifugal Pump
Motor, Motor Controls, Control Panel, 3 Phase w/ Pump Outlet & Inlet of 4" Diameter w/ Steel Bed Plate
IX. Electrical Works
Single Phase Electrical Line
150AT/150AF, 230V, 3P, Three Phase, Common Trip Main Circuit Breaker
For Lighting Load
Transfer of Wires & Cables (LAN, Internet & Telephone) from 2nd floor to Roofdeck
Transfer of tables, chairs, computers, filing cabinet and other office equipment from 2nd floor to Roofdeck
5,901,401.00Php
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
BILL OF QUANTITIES
ESTIMA
QUANWORK ITEM/DESCRIPTION
Supply and Installation of 100 Amp. Main Circuit Breaker, Three Phase, 3P, 220 volts enclosed in Powder Coated Finished Panel
Board w/ 6 Single Phase Branches of 20Amp.Single Phase Electrical Line
Lighting Fixtures
Supply and Installation of T5 Flourescent Lighting Fixture w/ PC cover, 28W, 1200mm, 220V, cool daylight
Supply & Installation of 48-Inches Industrial Ceiling Fan, 3 Blade, 220V
-
8/11/2019 Second Floor Renovation by Contract
29/78
Project Title: PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING
Approved Budget Cost:
P.R. No.
5,901,401.00Php
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
BILL OF QUANTITIES
ESTIM
QUAWORK ITEM/DESCRIPTION
Recessed Type Downlights w/o Glass Cover, E27, 185mmH x 150mm w/ 15Watts CFL, Cool Daylight, 220V
Recessed Type Downlights w/o Glass Cover, E27, 185mmH x 150mm w/ 33Watts CFL, Cool Daylight, 220V
Recessed Type Reflectorized/Mirrorized Fluorescent Luminaire w/ 2-40Watts Fluorescent Lamp
Recessed Type Reflectorized/Mirrorized Fluorescent Luminaire w/ 2-20Watts Fluorescent Lamp
Six Down Lighting Chandelier, w/ Six Bulbs Fluorescent type, 230 Volts
T5 Flourescent Lighting Fixture w/ PC cover, 28W, 1200mm, 220V, cool daylight
Single Phase Electrical Lline Outlets
X. Painting Works
XI. Fixtures, Office Furnitures and Office Equipment
Table 1 (See plans for details)
Table 2 (See plans for details)
Table 3 (See plans for details)
Table 4 (See plans for details)
Table 5 (See plans for details)
Patients Bed (See plans for details)
Executive Chair Executive Chair w/ Black Leatherette back and seat molded foam cushion,
lockable tilting mechanism, polyurethane or polypropylene armrest, five legged and black
leatherette back and nylon twin caster pneumatic height adjustment.
Office Chair w/ Low back and seat molded foam cushion, lockable tilting mechanism,
polyurethane or polypropylene armrest, five legged and black leatherette back
and nylon twin caster pneumatic height adjustment.
Visitors Chair w/ four legged, back and sit molded foam cushion, polypropylene armrest,
shiny chromed chair frame
Sala Set w/ Glass Top Center Table 9See TOR for Specs)
Supply & Installation of Ceiling Mounted Aircon
Specs:Cooling Capacity - 58,000 Btu/hr
Capacity - 5 TR
Power - 3P/220 V/60 Hz
- LCD remote Type w/ Auto t imer on/off, Sleep Mode,Dry Mode, Auto Fan Speed,
Night Timer,Real Time Clock
- With inverter, Heating & Cooling
- High efficiency
- Eco Friendly
- Automatic Drain Pump
- Two thermistor control function
- Alarm function for filter cleaning
Supply & Installation of Ceiling Mounted Projector
Specs:
240VAC, 60Hz, 300W projector with 0.80-7.5 meters diagonally projection size, full color,
ceiling mounted ready installation,moulded plastic, 307mm x 69mm x 210mm dimension,approx. 2.3 kgs, 0
o-40
oC temperature, 20%-80% humidity, with 2 meters power cord,
power cord secure lock, wireless remote control, VGA cable, carrying bag and application
software (CD-ROM). With metal ceiling mount projector bracket
And with 1.7m wide - 78" diagonal projector screen, matt white surface with 3cm black
border and weighted bottom bar. Housed in a white case with mounting brackets on
either end. Can be operated with in-line control switch or a wirless remote control.
Ceiling and wall mounting compatible, low noise electric motor, 240 VAC input, 60 Hz.
Remote Control
XII. Transfer and reinstallation of Existing Split-type ACU, 230V, 1, 60hz, 186Watts
C. CONSTRUCTION OF COOP OFFICE/CANTEEN & STORAGE ROOM (FLOOR AREA = 65.87 SQ.M.)
I. MOBILIZATION
II. LAYOUTING WORKS
III. CONCRETING WORKS
IV. MASONRY WORKS
1. Floor Tiles2. Kitchen Counter
V. CARPENTRY WORKS
1 Ceiling Works
-
8/11/2019 Second Floor Renovation by Contract
30/78
Project Title: PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING
Approved Budget Cost:
P.R. No.
5,901,401.00Php
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
BILL OF QUANTITIES
ESTIMAT
QUANTIWORK ITEM/DESCRIPTION
IX. PLUMBING WORKS
Sanitary Pipes and Fittings
Cold Water Pipes and Fittings
Stainless Kitchen Sink, w/ Strainer drain assembly w/ Plug & complete water supply fitting
X. PAINTING WORKS
XI. Demobilization
Prepared by: Reviewed & Checked by:
EDITO M. BAUTISTA, JR. MARIE CLAIRE C. BONGO
J.O.-Senior Engineer A (C.E.) Officer-In-Charge
Planning & Development Section
ARIANN D. GODINEZ
J.O.- Senior Engineer A (E.E.)
MARK BENEDICT C. REYES
J.O.- Senior Engineer A (M.E.)
Recommending Project Implementation: Approved
ARNULFO A. ALFONSO LEONARDO
Department Manager C, Maintenance General M
-
8/11/2019 Second Floor Renovation by Contract
31/78
Project Title: PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING
Approved Budget Cost:
P.R. No.
A. NON ENGINEERING BASIC COST
I. PERMIT & FEES 1 lot
II. CONSTRUCTION SAFETY & HEALTH PROGRAM 1 lot
III. CONSTRUCTION OF ONE (1) UNIT TEMPORARY FACILITY 1 lot
B. ENGINEERING BASIC COST
A. CONSTRUCTION OF TEMPORARY OFFICE
I. Mobilization/Demobilization
II. Installation of Walling/Partition and Cubicle Works 1 lot
III.1 assy.
IV. 83 outlets
V.
28 units
VI. 14 units
VII. 1 lot
VIII. 1 lot
IX. Supply and Installation of Tarpaulin Canvass/Lona w/ Complete Accessories 1 lot
B. RENOVATION OF SECOND FLOOR
I. Mobilization/Demobilization/Hauling 1 lot
II. Demolition and Clearing Works
Wood Wall Partition 238 sq.mtr.
Concrete Wall Partition 55 sq.mtr.
Ceiling 459 sq.mtr.
Floor/Wall Tiles 540 sq.mtr.
III. Masonry Works 30 sq.mtr.
IV. Tile Works
Granite Tile Works with grouting (see plans for sizes and details) 375 sq.mtr.
Granite Countertop with grouting (see plans for sizes and details) 5.112 sq.mtr.
Ceramic Tile Works with grouting & tile trims (see plans for sizes and details) 113 sq.mtr.
V. Carpentry Works
Ceiling Works 459 sq. mtr.
Walling/Partition and Cubicle Works 145 sq. mtr.
Fabrication of Office Tables, Cabinets and Shelves 1 lot
VI Doors/Windows and Glass:
D1 - 0.60m x 1.20m PVC Door, w/ PVC Door Jamb, 3 units
and w/ Complete Hinges, w/out Door Knob
D2 - 0.80m x 2.10m Panel Type Door, w/ 2" x 6" Jamb, 5 units
2" x 4" Door Frame, 6mm thk. Marine Plywood
D3 - Double Swing Door, 2" x 4" Alum. Frame/Jamb 3 units
Analok Glass Aluminum Door FrameAluminum Analok Sliding Window, 6mm Thk. Bronze Glass 10 units
Fixed Glass/Aluminum Frame Analok , 6mm Thk. Bronze Glass 2 units
VII. Plumbing Works 1 lot
Flush Type Water Closet w/ Complete Fittings and Accessories 7 sets
Undermount Porcelain Lavatory w/ Complete Fittings and Acessories 3 sets
Wall Mounted Porcelain Lavatory w/ Complete Fittings and Acessories 3 sets
Urinal w/ Complete Fittings and Acessories 3 sets
Sanitary Pipes & Fittings 1 lot
Cold Water Pipes & Fittings 1 lot
VIII. Supply, Installation, Testing and Commissioning of Fire Sprinkler System
Supply, Installation, Testing and Commissioning of One (1) Lot Wet Fire Sprinkler System Complete w/ 1 lot
Piping, Pendent Type Sprinkler Head and Acessories, w/ One (1) Unit 10HP Centrifugal Pump
Motor, Motor Controls, Control Panel, 3 Phase w/ Pump Outlet & Inlet of 4" Diameter w/ Steel Bed Plate
IX. Electrical Works
Single Phase Electrical Line 208 outlets150AT/150AF, 230V, 3P, Three Phase, Common Trip Main Circuit Breaker 1 unit
For Lighting Load
100 Amperes Main Circuit Breaker Three Phase 3P
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
BILL OF QUANTITIES
5,901,401.00Php
WORK ITEM/DESCRIPTIONESTIMATED
QUANTITYUNIT
Supply and Installation of 100 Amp. Main Circuit Breaker, Three Phase, 3P, 220 volts enclosed in Powder Coated
Finished Panel Board w/ 6 Single Phase Branches of 20Amp.
Single Phase Electrical Line
Lighting Fixtures
Supply and Installation of T5 Flourescent Lighting Fixture w/ PC cover, 28W, 1200mm, 220V, cool daylight
Supply & Installation of 48-Inches Industrial Ceiling Fan, 3 Blade, 220V
Transfer of Wires & Cables (LAN, Internet & Telephone) from 2nd floor to Roofdeck
Transfer of tables, chairs, computers, filing cabinet and other office equipment from 2nd floor to Roofdeck
-
8/11/2019 Second Floor Renovation by Contract
32/78
Project Title: PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING
Approved Budget Cost:
P.R. No.
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICTPilar Street, Zamboanga City
BILL OF QUANTITIES
5,901,401.00Php
WORK ITEM/DESCRIPTIONESTIMATED
QUANTITYUNIT
For Power Load
100 Amperes Main Circuit Breaker, 3 Pole, 3 Phase, 250 volts in Combined Panel Board complete
with Ground Bus Bar/Terminal Blocks, enclosed in Powder Coated Finished Panel Board,
with 7 Single Phase Branches of:
1 sets - 30 Amps., Single Pole Breaker
6 sets - 20 Amps., Single Pole Breaker 1 assy.
For ACU Load
150 Amperes Main Circuit Breaker, 2 Pole, 250 volts in Combined Panel Board complete
with Ground Bus Bar/Terminal Blocks, enclosed in Powder Coated Finished Panel Board,
with 6 Single Phase Branches of:
5 sets - 60 Amps., Single Pole Breaker
1 sets - 30 Amps., Single Pole Breaker 1 assy.30 Amperes, 2P, Safety Breaker (for ACU) 1 pc.
60 Amperes, 2P, Safety Breaker (for ACU) 5 pcs.
Lighting Fixtures
Recessed Type Downlights w/o Glass Cover, E27, 185mmH x 150mm w/ 13Watts CFL, Cool Daylight, 220V 23 sets
Recessed Type Downlights w/o Glass Cover, E27, 185mmH x 150mm w/ 15Watts CFL, Cool Daylight, 220V 91 sets
Recessed Type Downlights w/o Glass Cover, E27, 185mmH x 150mm w/ 33Watts CFL, Cool Daylight, 220V 15 sets
Recessed Type Reflectorized/Mirrorized Fluorescent Luminaire w/ 2-40Watts Fluorescent Lamp 15 sets
Recessed Type Reflectorized/Mirrorized Fluorescent Luminaire w/ 2-20Watts Fluorescent Lamp 1 set
Six Down Lighting Chandelier, w/ Six Bulbs Fluorescent type, 230 Volts 1 set
T5 Flourescent Lighting Fixture w/ PC cover, 28W, 1200mm, 220V, cool daylight 2 sets
Centralized Grounding System 1 lot
Single Phase Electrical Lline Outlets 208 outlets
X. Painting Works 1,800 sq. mtr.
XI. Fixtures, Office Furnitures and Office Equipment
Table 1 (See plans for details) 22 units
Table 2 (See plans for details) 3 units
Table 3 (See plans for details) 1 unit
Table 4 (See plans for details) 12 units
Table 5 (See plans for details) 1 unit
Patients Bed (See plans for details) 1 unit
Executive Chair Executive Chair w/ Black Leatherette back and seat molded foam cushion, 16 units
lockable tilting mechanism, polyurethane or polypropylene armrest, five legged and black
leatherette back and nylon twin caster pneumatic height adjustment.
Office Chair w/ Low back and seat molded foam cushion, lockable tilting mechanism, 24 units
polyurethane or polypropylene armrest, five legged and black leatherette back
and nylon twin caster pneumatic height adjustment.
Visitors Chair w/ four legged, back and sit molded foam cushion, polypropylene armrest, 12 units
shiny chromed chair frame
Sala Set w/ Glass Top Center Table 9See TOR for Specs) 2 sets
Supply & Installation of Ceiling Mounted Aircon 2 unitsSpecs:
Cooling Capacity - 58,000 Btu/hr
Capacity - 5 TR
Power - 3P/220 V/60 Hz
- LCD remote Type w/ Auto timer on/off, Sleep Mode,Dry Mode, Auto Fan Speed,
Night Timer,Real Time Clock
- With inverter, Heating & Cooling
- High efficiency
- Eco Friendly
- Automatic Drain Pump
- Two thermistor control function
- Alarm function for filter cleaning
Supply & Installation of Ceiling Mounted Projector 1 unit
Specs:
240VAC, 60Hz, 300W projector with 0.80-7.5 meters diagonally projection size, full color,ceiling mounted ready installation,moulded plastic, 307mm x 69mm x 210mm dimension,
approx. 2.3 kgs, 0o-40
oC temperature, 20%-80% humidity, with 2 meters power cord,
-
8/11/2019 Second Floor Renovation by Contract
33/78
Project Title: PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING
Approved Budget Cost:
P.R. No.
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
BILL OF QUANTITIES
5,901,401.00Php
WORK ITEM/DESCRIPTIONESTIMATED
QUANTITYUNIT
Ceiling and wall mounting compatible, low noise electric motor, 240 VAC input, 60 Hz.
Remote Control
XII. Transfer and reinstallation of Existing Split-type ACU, 230V, 1, 60hz, 186Watts 4 units
C. CONSTRUCTION OF COOP OFFICE/CANTEEN & STORAGE ROOM (FLOOR AREA = 65.87 SQ.M.)
I. MOBILIZATION 1 lot
II. LAYOUTING WORKS 65.87 sq. mtr.
III. CONCRETING WORKS 53.17 sq. mtr.
IV. MASONRY WORKS
1. Floor Tiles 46.16 sq. mtr.
2. Kitchen Counter 3.60 sq. mtr.
V. CARPENTRY WORKS
1. Ceiling Works 57.6 sq. mtr.2. Wall/Wall Partition 126.72 sq. mtr.
3. Shelves 23.04 sq. mtr.
4. Counter Top 40.32 sq. mtr.
5. Door and Window Jambs
0.90m x 2.10m x 0.05m x 0.15m Yakal/Hardwood Door Jambs 2 sets
1.40m x 1.20m x 0.05m x 0.15m Yakal/Hardwood Window Jambs 1 set
6. Door and Window
0.90m x 2.10m Flush Door w/ 5mm thk Marine Plywood, Double 2 sets
5mm thk, 13 Blades Smoke Glass Jalousie Window w/ Standard 2 sets
7. Wooden Ventillation
25mm thk x 250mm x 1.20m Pre-fabrication Wooden Ventillation 2 units
VI. ROOFING WORKS 63.36 sq. mtr.
VII. STEEL WORKS 147.56 kgs.
VIII. ELECTRICAL WORKS
1 set
Single Phase Electrical Lline Outlets 18 outlets
Supply and Installation of T5 Flourescent Lighting Fixture w/ PC cover, 28W, 1200mm, 220V cool daylight 4 sets
Recessed Type Downlights w/o Glass Cover, E27, 185mmH x 150mm w/ 18Watts CFL, Cool Daylight, 220V 5 sets
16" Ceiling Orbit Fan, industrial type 2 units
12" Exhaust Fan 2 units
IX. PLUMBING WORKS
Sanitary Pipes and Fittings 1 lot
Cold Water Pipes and Fittings 1 lot
Stainless Kitchen Sink, w/ Strainer drain assembly w/ Plug & complete water supply fitting 1 set
X. PAINTING WORKS 144 sq. mtr.
XI. Demobilization 1 lot
Prepared by: Reviewed & Checked by: Approved
EDITO M. BAUTISTA, JR. MARIE CLAIRE C. BONGO MARLI AC
J.O.-Senior Engineer A (C.E.) Officer-In-Charge Officer-In-
Planning & Development Section Planning &
ARIANN D. GODINEZ
J.O.- Senior Engineer A (E.E.)
MARK BENEDICT C. REYES
J.O.- Senior Engineer A (M.E.)
Recommending Project Implementation: Approved for Project Imp
ARNULFO A. ALFONSO LEONARDO REY D. VASQU
Supply and Installation of 60 Amp. Main Circuit Breaker, Three Phase, 3P, 220 volts enclosed in Powder CoatedFinished Panel Board w/ 5 Single Phase Branches of 4sets-20Amps, 1set-15Amps
-
8/11/2019 Second Floor Renovation by Contract
34/78
Project Title: PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING
Approved Budget Cost:
P.R. No.
QTY UNIT AVAILABLE S.N./H.P./PLATE NO
1 Service Vehicle 1.00 unit
2 Boom Truck (2 tonner. min. capacity) 2.00 units
3 Dump Truck (6cu.m. min. capacity) 2.00 units
4 Air Compressor 1.00 unit
5 Welding Machine w/ Cutting Outfit 1.00 unit
6 Angular Grinder 1.00 unit
7 Electric Hand Drill 1.00 unit
8 Portable Demolition Hammer (min. of 1800Watts) 1.00 unit
9 Electric Planer 1.00 unit
10 Generator Set 1.00 unit
Project Manager 1
Safety Engineer 1
Materials Engineer 1
Project Engineer 1
Foreman 1
Timekeeper/Warehouse Man 1
Purchasing Manager 1
Prepared by: Reviewed & Checked by: Approved by:
EDITO M. BAUTISTA, JR. MARIE CLAIRE C. BONGO MARLI ACOSTA-DE FIESTAJ.O.-Senior Engineer A (C.E.) Officer-In-Charge Officer-In-Charge
Planning & Development Section Planning & Design Division
Recommending Project Implementation: Approved for Project Implementation:
ARNULFO A. ALFONSO LEONARDO REY D. VASQUEZ
Department Manager C, Maintenance General Manager
PARTICULARS
MANPOWER REQUIREMENTS
EQUIPMENT REQUIREMENTS
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
5,901,401.00Php
Equipment Page 34 of 78 246371728.xls.ms_
-
8/11/2019 Second Floor Renovation by Contract
35/78
Department: Engineering Department/Planning & Design Div. PR No.: Date:
Section: Planning & Development Section SAI No.: Date:
Approved Budget Cost:
1 LOT
NON ENGINEERING BASIC COSTI. PERMIT & FEES
II. CONSTRUCTION SAFETY & HEALTH PROGRAM
III. CONSTRUCTION OF ONE (1) UNIT TEMPORARY FACILITY
ENGINEERING BASIC COSTA. CONSTRUCTION OF TEMPORARY OFFICE AT ROOF DECK
B. RENOVATION OF SECOND FLOOR
I. Mobilization/Demobilization/HaulingII. Demolition and Clearing Works
III. Masonry Works
IV. Tile Works
V. Carpentry Works
VI. Doors/Windows and Glass:
VII. Plumbing Works
VIII. Supply, Installation, Testing and Commissioning of Fire Sprinkler System
IX. Electrical Works
X. Painting Works
XI. Fixtures, Office Furnitures and Office Equipment
XII. Transfer and reinstallation of Existing Split-type ACU, 230V, 1, 60hz, 186Watts
I. MobilizationII. Layouting Works
III. Concreting Works
IV. Masonry Works
V. Carpentry Works
VI. Roofing Works
VII. Steel Works
VIII. Electrical Works
IX. Plumbing Works
X. Painting Works
XI. DemobilizationxxxxxxxxxxxxxxxxNOTHING FOLLOWSxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
Purpose / Remarks: For theProposed Renovation of Second Floor ZCWD Main Building.
5,901,401.00Php
Republic of the Philippines
ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
PURCHASE REQUEST
ACCOUNTNUMBER
P.O.No.
ITEM DESCRIPTION QTY. UNITUNITCOST
AVAIL.STOCK
C. CONSTRUCTION OF COOP OFFICE/CANTEEN & STORAGE ROOM (FLOOR AREA = 65.87 SQ.M.)
PROP. RENOVATION OF SECOND FLOOR, ZCWD MAINBUILDING
-
8/11/2019 Second Floor Renovation by Contract
36/78
Signature:
Printed Name:
Designation:
Date:
Requested by: Funds Certified Available: Recommending Approval: Approve
MARLI P. ACOSTA-DE FIESTA LUIS A. WEE ARNULFO A. ALFONSO LEONARDO REYOIC-Planning & Design Division Depaartment Manager, ATD Department Manager C, Maintenance General M
-
8/11/2019 Second Floor Renovation by Contract
37/78
DATENEEDED
-
8/11/2019 Second Floor Renovation by Contract
38/78
EZ
-
8/11/2019 Second Floor Renovation by Contract
39/78
Department/Division ENGINEERING DEPARTMENT Responsibility Center No. _________Office PLANNING & DESIGN DIVISION Code __________
STOCK NO. Unit Quantity Status of Stock
1.00 LOT
xxxxxxxxxxxxxxxxNOTHING FOLLOWSxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING
Republic of the Philipines
ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
SUPPLIES AVAILABILITY INQUIRY (SAI)
ITEM DESCRIPTION
NON ENGINEERING BASIC COST
I. PERMIT & FEES
II. CONSTRUCTION SAFETY & HEALTH PROGRAM
III. CONSTRUCTION OF ONE (1) UNIT TEMPORARY FACILITY
ENGINEERING BASIC COST
B. RENOVATION OF SECOND FLOOR
A. CONSTRUCTION OF TEMPORARY OFFICE AT ROOF DECK
I. Mobilization/Demobilization/Hauling
II. Demolition and Clearing Works
III. Masonry Works
IV. Tile Works
V. Carpentry Works
VI. Doors/Windows and Glass:
VII. Plumbing Works
VIII. Supply, Installation, Testing and Commissioning of Fire
Sprinkler System
IX. Electrical Works
C. CONSTRUCTION OF COOP OFFICE/CANTEEN & STORAGE
ROOM (FLOOR AREA = 65.87 SQ.M.)
I. Mobilization
II. Layouting Works
X. Painting Works
XI. Fixtures, Office Furnitures and Office Equipment
XII. Transfer and reinstallation of Existing Split-type ACU, 230V, 1,
60hz, 186Watts
IX. Plumbing Works
X. Painting Works
XI. Demobilization
III. Concreting Works
IV. Masonry Works
V. Carpentry WorksVI. Roofing Works
VII. Steel Works
VIII. Electrical Works
-
8/11/2019 Second Floor Renovation by Contract
40/78
Purpose / Remarks: For theProposed Renovation of Second Floor ZCWD Main Building.
Inqui red by: Status prov ided by Acco unt ing and Treasury Department :
Signature Signature
Name Name
Designatio Designation
Date Date
This form should be prepared in 3 copies. Copy 1 - Accounting Section; Copy 2 - Property Section; Copy 3 - End Users.
MARLI P. ACOSTA-DE FIESTA LUIS A. WEE
OIC, Planning & Design Division Department Manager
-
8/11/2019 Second Floor Renovation by Contract
41/78
Pre-Procurement
Conference
Public Bidding P 5,901,401.00 10/8/12 10/10/12 - 10/
xxxxxxxxxxxxxxxxNOTHING FOLLOWSxxxxxxxxxxxxxxxxxxxxxxxxxx
P 5,901,401.00
Requisitioned by: Recommending A
MARIE CLAIRE C. BONGO MARLI P. ACOSTA-DE FIESTA ARNULFO A. ALFOfficer-In-Charge Officer-In-Charge Department Mana
Planning & Development Section Planning and Design Division
ABCAdvertisement
Republic of the Philipines
ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
PROJECT PROCUREMENT MANAGEMENT PLANENGINEERING DEPARTMENT
PLANNING AND DESIGN DIVISION
PROP. RENOVATION OF SECOND FLOOR, ZCWD MAIN BUILDING
TOTAL BUDGET AMOUNT
Prepared by:
Ref.[1] Contract Package (Description)Procurement
Method
-
8/11/2019 Second Floor Renovation by Contract
42/78
Project : PROPOSED COOP OFFICE/CAN
Location : Roof Deck, Main Office, Pilar St., Z
Scope of Work :
I. MOBILIZATION
II. LAYOUTING WORKS
III. CONCRETING WORKSIV. MASONRY WORKS
V. CARPENTRY WORKSVI. ROOFING WORKS
VII. STEEL WORKSVIII. ELECTRICAL WORKS
IX. PLUMBING WORKS
X. PAINTING WORKS
XI. DEMOBILIZATION
Cost of Project :
I. MOBILIZATION
II. LAYOUTING WORKSa. Materials:
10pcs. - 2" x 3" x 10' Coco Lumber
4pcs. - 2" x 3" x 8' Coco Lumber
#100 Nylon Chord (1kg./roll)
4" C.W. Nail
4" Concrete Nail
b. Labor:
2 - Carpenters
TOTAL DIRECT COST
OVERHEAD EXPENSES
PHYSICAL CONTINGENCIES
MISCELLANEOUS EXPENSESTOTAL COST OF ITEM II
III. CONCRETING WORKS
Flooring
a. Materials:
Portland Cement
Washed Sand
Gravel (G-1)
10pcs. - 2" x 4" x 10' Coco Lumber
Republic of the Phil
ZAMBOANGA CITY WAT
Pilar Street, Zamboa
511,965.00Php
BILL OF MATERIALS & C
Item Description
-
8/11/2019 Second Floor Renovation by Contract
43/78
4" Concrete Nail
b. Labor:
2 - Masons
2 - Carpenters
1 - Steelman
6 - Laborers
TOTAL DIRECT COST
OVERHEAD EXPENSES
PHYSICAL CONTINGENCIES
MISCELLANEOUS EXPENSES
TOTAL COST OF ITEM III
IV. MASONRY WORKS
1. Floor Tilesa. Materials:
0.40m x 0.40m Granite Tiles (White)
Portland Cement
Fine Sand (for plastering)
Tile Grout (cement joint filler)
b. Labor:
2 - Masons
4 - Laborers
c. Equipment Rental:
1 - Unit Angular Grinder
2. Kitchen Counter
a. Materials:
Portland Cement
Washed Sand
Gravel (G-1)Fine Sand (for plastering)
10mm x 6.00m Deformed Reinforcing Steel Bars
#16 G.I. Tie-wire
12mm thk x 1.20m x 2.40m Ordinary Plywood
6pcs. - 2" x 3" x 10' Coco Lumber
4" C.W. Nail
4" CHB (NBL)
0.20m x 0.20m Granite Tiles (White)
PVC Tile Trim
Tile Grout (cement joint filler)
b. Labor:2 - Masons
1 - Laborer
c. Equipment Rental:
1 - Unit Angular Grinder
TOTAL DIRECT COST
OVERHEAD EXPENSES
-
8/11/2019 Second Floor Renovation by Contract
44/78
PHYSICAL CONTINGENCIES
MISCELLANEOUS EXPENSES
TOTAL COST OF ITEM IV
V. CARPENTRY WORKS
1. Ceiling Worksa. Materials:
56pcs. - 2" x 4" x 10' S4s Lauan Wood
56pcs. - 2" x 2" x 10' S4s Lauan Wood
12mm thk x 1.20m x 2.40m Marine Plywood
5mm thk x 1.20m x 2.40m Marine Plywood
4" C.W. Nail
3" C.W. Nail
2" C.W. Nail
b. Labor:
2 - Carpenters
2 - Laborers
2. Wall/Wall Partition
a. Materials:
1pc. - 4" x 4" x 10' S4s Lauan
94pcs. - 2" x 4" x 10' S4s Lauan Wood
5mm thk x 1.20m x 2.40m Marine Plywood
4" C.W. Nail
2" C.W. Nail
b. Labor:
2 - Carpenters
4 - Laborers
3. Shelves
a. Materials:
19mm thk x 1.20m x 2.40m Marine Plywood
Wood Glue
1 1/2" C.W. Nail
b. Labor:
2 - Carpenters
2 - Laborers
4. Counter Topa. Materials:
19mm thk x 1.20m x 2.40m Marine Plywood
5mm thk x 1.20m x 2.40m Marine Plywood
Wood Glue
2" C.W. Nail
1.20m x 2.40m Plastic Formica
Rubber Cement Solvent
2" x 2" Cabinet Hinges
38mm Wooden Cabinet Handle
-
8/11/2019 Second Floor Renovation by Contract
45/78
b. Labor:
2 - Carpenters
2 - Laborers
5. Door and Window Jambs (Job Order)
a. Materials:0.90m x 2.10m x 0.05m x 0.15m Yakal/Hardwood Door Jambs
1.40m x 1.20m x 0.05m x 0.15m Yakal/Hardwood Window Jambs
6. Doors & Window (Job Order)
a. Materials:
0.90m x 2.10m Flush Door w/ 5mm thk Marine Plywood, Double
Walling on 50mm x 100mm Door Frame, Door Knob
5mm thk, 13 Blades Smoke Glass Jalousie Window w/ Standard
Alum. Frame Holder (0.70m x 1.20m)
7. Ventillation (Job Order)
a. Materials:25mm thk x 250mm x 1.20m Pre-fabrication Wooden Ventillation
TOTAL DIRECT COST
OVERHEAD EXPENSES
PHYSICAL CONTINGENCIES
MISCELLANEOUS EXPENSES
TOTAL COST OF ITEM V
VI. ROOFING WORKSa. Materials:
12mm thk x 1.20m x 2.40 Marine Plywood
18pcs. - 2" x 2" x 10' S4s Lauan Wood
14pcs. - 2" x 3" x 10' S4s Lauan Wood
24pcs. - 2" x 3" x 8' S4s Lauan Wood
16pcs. - 2" x 2" x 8' S4s Lauan Wood
4" C.W. Nail
2" C.W. Nail
b. Labor:
2 - Carpenters
4 - Laborers
TOTAL DIRECT COST
OVERHEAD EXPENSES
PHYSICAL CONTINGENCIES
MISCELLANEOUS EXPENSES
TOTAL COST OF ITEM VI
VII. STEEL WORKS
a. Materials:
50mm x 6.00m G.I. Pipe, Sch. 40
12mm x 6.00m Aluminum Tube
3mm x 25mm x 25mm x 3.00m Alum. Angle Bar
4mm x 25mm x 25mm x 6.00m Angle Bar
4mm x 38mm x 6.00m Flat Bar
-
8/11/2019 Second Floor Renovation by Contract
46/78
10mm x 10mm x 6.00m Square Bars
5mm thk x 25mm x 6.00m Flat Bar
b. Labor:
1 - Steelman
1 - Welder
2 - Laborers
c. Equipment Rental:
1 - Unit Welding Machine
TOTAL DIRECT COST
OVERHEAD EXPENSES
PHYSICAL CONTINGENCIES
MISCELLANEOUS EXPENSES
TOTAL COST OF ITEM VI
VIII. ELECTRICAL WORKSa. Materials:
50 Amperes Main Circuit Breaker, Single Phase,
220 volts enclosed in Powder Coated Finished Panel Board
with 5 Single Phase Branches of:
4 sets - 20 Amps. Branch
1 sets - 15 Amps. Branch
8.0mm2THW Stranded Wire
3.5mm2THW Stranded Wire
16" Orbit Fan, Standard
12" exhaust fan
3U Electronic CFL with Capsule, Daylight, 23W Assembly
Ceiling Socket with screw
Reccessed Fluorescent illuminaire,1x40 Watts assembly
in Powder Coated Steel Plate; IP20 Assembly
Duplex Convenience Outlet w/ plate (flush type)
Toggle Switch 3-Gang w/ plate (f lush type)
Toggle Switch 1-Gang w/ plate (f lush type)
25mm (3/4") PVC Flexible Electrical Conduit
25mm(3/4") x 90 PVC Electrical Conduit Elbow Long Sweep
25mm (3/4")PVC Electrical Coupling Connectors
25mm (3/4") PVC Male Adaptor
25mm (3/4") PVC Lock Nut (Zinc Coated)
25mm (3/4") PVC clamps w/ concrete nails
20mm (1/2") PVC Flexible Electrical Conduit
20mm (1/2") x 3.00m PVC Electrical Conduit
20mm (1/2") x 90 PVC Electrical Conduit Elbow Long Sweep
20mm (1/2") x 90 PVC Electrical Conduit Short Elbow
20mm(1/2") PVC Electrical Coupling Connectors
20mm (1/2") PVC Male Adaptor
20mm (1/2") PVC Lock Nut (Zinc Coated)
20mm (1/2") PVC clamps w/ concrete nails
2" x 4" x 2" PVC Utility Box ( H.D.)
4" x 4" x 2" PVC Junction Box ( H.D.) w/ Cover
#16 G.I. Tie Wire
6" x 6" x 4" Gal. Pull Box
PVC Solvent Cement
-
8/11/2019 Second Floor Renovation by Contract
47/78
1/2" Camridge / Mica Tube
3/4" Polytype Electrical Tape
3/4" Rubber Tape
b. Labor:
1 - Skilled Electrician
2 - Contractual Laborers
TOTAL DIRECT COST
OVERHEAD EXPENSES
PHYSICAL CONTINGENCIES
MISCELLANEOUS EXPENSES
TOTAL COST OF ITEM VIII
IX. PLUMBING WORKS
a. Materials:
50mm x 3.00m Sanitary PVC Pipe, Series-1000
50mm x 900Sanitary PVC Elbow, Series-1000
50mm x 450Sanitary PVC Elbow, Series-1000PVC Cement Solvent
12mm x 900G.I. Elbow, Sch. 40
12mm x 6.00m G.I. Pipe, Sch. 40
Teflon Tape
Stainless Kitchen Sink, w/ Strainer drain assembly
w/ Plug & complete water supply fitting
b. Labor:
1 - Plumber
2 - Laborers
TOTAL DIRECT COST
OVERHEAD EXPENSES
PHYSICAL CONTINGENCIES
MISCELLANEOUS EXPENSES
TOTAL COST OF ITEM IX
X. PAINTING WORKSa. Materials:
Liquid Tile Primer
Liquid Tile Putty Filler
Liquid Tile Reducer
Liquid Tile Top Coat (Glossy White)
Lamp Black Tinting Color
Raw Sienna Tinting ColorThalo Blue Tinting Color
Venetian Red Tinting Color
Burnt Umber Tinting Color
Rust Remover
Acrylic Base Paint
Metal Primer Paint
Paint Thinner
2" Paint Brush
Paint Roller Tray
-
8/11/2019 Second Floor Renovation by Contract
48/78
# 150 Sand Paper
# 120 Sand Paper
b. Labor:
1 - Painter
4 - Laborers
TOTAL DIRECT COST
OVERHEAD EXPENSESPHYSICAL CONTINGENCIES
MISCELLANEOUS EXPENSES
TOTAL COST OF ITEM IX
XI. DEMOBILIZATION
I. MOBILIZATION
II. LAYOUTING WORKS
III. CONCRETING WORKS
IV. MASONRY WORKS
V. CARPENTRY WORKS
VI. ROOFING WORKS
VII. STEEL WORKS
VIII. ELECTRICAL WORKS
IX. PLUMBING WORKS
X. PAINTING WORKS
XI. DEMOBILIZATION
PROJECT COST
VAT (12%)
Prepared by: Checked &
FELIXBERTO R. CAARE, JR. MARIE CL
Reseacher/Analyst A (J.O.) Officer-In-C
Planning & Development Section Planning &
Approved by: Certified as
CARLOS L. PEREZ, SR. LUIS A. W
Officer-In-Charge Division Ma
Engineering Department Treasury a
Approved f
General Ma
S U M M A R
LEONARD
-
8/11/2019 Second Floor Renovation by Contract
49/78
TEEN & STORAGE ROOM (Floor Area = 65.87 sq.m.)
mboanga City
Qty. Unit Unit Cost Amount Total Cost
1 lot 10,000.00 10,000.00 10,000.00
50 bd.ft. 17.00 850.00
16 bd.ft. 17.00 272.00
1 roll 110.00 110.00
1 kg. 65.00 65.00
1 kg. 71.00 71.00 1,368.00
1 day 366.00 732.00 732.00
2,100.00
105.00
84.00
21.00 210.002,310.00
39 bags 230.00 8,970.00
2 cu.m. 1,000.00 2,000.00
4 cu.m. 1,000.00 4,000.00
67 bd.ft. 20.00 1,340.00
ippines
ER DISTRICT
nga City
ST ESTIMATES
-
8/11/2019 Second Floor Renovation by Contract
50/78
0.50 kg. 142.00 71.00 16,381.00
2 days 366.00 1,464.00 7,464.00
2 days 366.00 1,464.00
2 days 366.00 732.00
2 days 317.00 3,804.00 7,464.00
23,845.00
1,192.00
954.00
238.00 2,384.00
26,229.00
266 pcs. 129.00 34,314.00
12 bags 230.00 2,760.00
1 cu.m. 1,200.00 1,200.00
10 packs 49.00 490.00 38,764.00
8 days 366.00 5,856.00
8 days 317.00 10,144.00 16,000.00
8 days 300.00 2,400.00 2,400.00
57,164.00
5 bags 230.00 1,150.00
0.25 cu.m. 1,000.00 250.00
0.10 cu.m. 1,000.00 100.000.10 cu.m. 1,200.00 120.00
4 pcs. 165.00 660.00
0.50 kg. 65.00 33.00
1 sht. 750.00 750.00
30 bd.ft. 20.00 600.00
0.50 kg. 65.00 33.00
53 pcs. 14.00 742.00
90 pcs. 64.00 5,760.00
2 pcs. 52.00 104.00
4 packs 49.00 196.00 10,498.00
4 days 366.00 2,928.00
4 days 317.00 1,268.00 4,196.00
4 days 300.00 1,200.00 1,200.00
15,894.00
73,058.003,653.00
-
8/11/2019 Second Floor Renovation by Contract
51/78
2,922.00
731.00 7,306.00
80,364.00
373 bd.ft. 40.00 14,920.00
186 bd.ft. 40.00 7,440.00
6 shts. 630.00 3,780.00
14 shts. 330.00 4,620.00
6 kgs. 65.00 390.00
4 kgs. 65.00 260.00
5 kgs. 65.00 325.00 31,735.00
10 days 366.00 7,320.00
10 days 317.00 6,340.00 13,660.00
45,395.00
14 bd.ft. 40.00 560.00
627 bd.ft. 40.00 25,080.00
44 shts. 380.00 16,720.00
10 kgs. 65.00 650.00
11 kgs. 65.00 715.00 43,165.00
5 days 366.00 3,660.00
5 days 317.00 6,340.00 10,000.00
53,165.00
8 shts. 1,025.00 8,200.00
2 liters 110.00 220.00
2 kgs. 65.00 130.00 8,550.00
2 days 366.00 1,464.00
2 days 317.00 1,268.00 2,732.00
11,282.00
10 shts. 1,025.00 10,250.00
2 shts. 380.00 760.00
3 liters 110.00 330.00
3 kgs. 65.00 195.00
2 shts. 300.00 600.00
4 btls. 80.00 320.00
44 pcs. 18.00 792.00
22 pcs. 16.00 352.00 13,599.00
-
8/11/2019 Second Floor Renovation by Contract
52/78
4 days 366.00 2,928.00
4 days 317.00 2,536.00 5,464.00
19,063.00
2 sets 1,500.00 3,000.00
1 set 1,200.00 1,200.00 4,200.00
4,200.00
2 sets 3,500.00 7,000.00
2 sets 680.00 1,360.00
8,360.00
8,360.00
2 units 700.00 1,400.00 1,400.00
1,400.00
142,865.007,143.00
5,715.00
1,429.00 14,287.00
157,152.00
22 shts. 630.00 13,860.00
60 bd.ft. 36.00 2,160.00
67 bd.ft. 36.00 2,412.00
96 bd.ft. 36.00 3,456.00
43 bd.ft. 36.00 1,548.00
4 kgs. 65.00 260.00
6 kgs. 65.00 390.00 24,086.00
5 days 366.00 3,660.00
5 days 317.00 6,340.00 10,000.00
34,086.00
1,704.00
1,363.00
341.00 3,408.00
37,494.00
2 pcs. 2,238.00 4,476.00
2 pcs. 652.00 1,304.00
4 pcs. 150.00 600.00
3 pcs. 612.00 1,836.00
3 pcs. 356.00 1,068.00
-
8/11/2019 Second Floor Renovation by Contract
53/78
6 pcs. 182.00 1,092.00
2 pcs. 195.00 390.00 10,766.00
3 days 366.00 1,098.00
3 days 366.00 1,098.00
3 days 317.00 1,902.00 4,098.00
2 days 2,200.00 4,400.00 4,400.00
14,864.00743.00
595.00
149.00 1,487.00
16,351.00
1 unit 5,250.00 5,250.00
16 mtrs. 95.00 1,520.00
2 rolls 4,183.00 8,366.00
2 sets 1,518.00 3,036.00
2 sets 1,221.00 2,442.00
5 sets 310.00 1,550.00
13 sets 25.00 325.00
4 sets 286.00 1,144.00
7 sets 253.00 1,771.00
2 sets 114.00 228.00
1 set 81.00 81.00
15 pcs. 253.00 3,795.00
5 pcs. 18.00 90.00
14 pcs. 7.00 98.00
2 pcs. 9.00 18.00
2 pcs. 4.00 8.00
1 box 138.00 138.00
25 mtrs. 6.00 150.00
20 pcs. 201.00 4,020.00
3 pcs. 13.00 39.00
5 pcs. 13.00 65.00
8 pcs. 6.00 48.00
4 pcs. 8.00 32.00
4 pcs. 3.00 12.00
3 boxes 110.00 330.00
15 pcs. 17.00 255.00
20 pcs. 22.00 440.00
2 kgs. 65.00 130.00
2 pcs. 554.00 1,108.00
1 qrt. 370.00 370.00
-
8/11/2019 Second Floor Renovation by Contract
54/78
6 pcs. 30.00 180.00
3 pcs. 25.00 75.00
1 pc. 105.00 105.00 37,219.00
5 days 366.00 1,830.00
5 days 317.00 3,170.00 5,000.00
42,219.00
42,219.00
2,111.00
1,689.00
422.00 4,222.00
46,441.00
12 pcs. 250.00 3,000.00
6 pcs. 28.00 168.00
2 pcs. 22.00 44.002 qrts. 285.00 570.00
10 pcs. 12.00 120.00
5 pcs. 550.00 2,750.00
10 rolls 22.00 220.00
1 set 1,900.00 1,900.00
8,772.00
3 days 366.00 1,098.00
3 days 317.00 1,902.00 3,000.00
11,772.00
589.00
471.00
118.00 1,178.00
12,950.00
13 gals. 660.00 8,580.00
18 gals. 470.00 8,460.00
8 gals. 369.00 2,860.00
14 gals. 787.00 11,018.00
2 pints 100.00 200.00
2 pints 100.00 200.002 pints 100.00 200.00
2 pints 100.00 200.00
2 pints 100.00 200.00
1 gals. 510.00 510.00
2 gals. 900.00 1,800.00
2 gals. 398.00 796.00
2 gals. 325.00 650.00
4 pcs. 10.00 40.00
2 pcs. 45.00 90.00
-
8/11/2019 Second Floor Renovation by Contract
55/78
2 dozs. 105.00 210.00
2 dozs. 105.00 210.00 36,224.00
10 days 366.00 3,660.00
10 days 317.00 12,680.00 16,340.00
52,564.00
2,628.002,103.00
526.00 5,257.00
57,821.00
1 lot 10,000.00 10,000.00 10,000.00
Reviewed by: Submitted by:
IRE C. BONGO MARLI ACOSTA-DE FIESTA
harge
Development Section
to Availability of Funds: Recommending Project Implementation:
EE ALEJO S. ROJAS, JR.
nager C Assistant General Manager for Operations
d Finance Department
r Project Implementation:
nager
Y
10,000.00Php
2,310.00Php
80,364.00Php
157,152.00Php
26,229.00Php
37,494.00Php
16,351.00Php
46,441.00Php
12,950.00Php
57,821.00Php
10,000.00Php
457,112.00Php
Planning & Design Division
REY D. VASQUEZ
54,853.00Php
511,965.00Php
Officer-In-Charge
-
8/11/2019 Second Floor Renovation by Contract
56/78
12.7 SQ.M.
6.58 m.
8.08 m.
53.17 sq.m.
65.87
ok
-
8/11/2019 Second Floor Renovation by Contract
57/78
ok
-
8/11/2019 Second Floor Renovation by Contract
58/78
ok
-
8/11/2019 Second Floor Renovation by Contract
59/78
-
8/11/2019 Second Floor Renovation by Contract
60/78
1 welder #REF! kg/6m
7.58 lbs./ft. #REF! days
170503.8
2544.833
4009.333
10 Matting/day
-
8/11/2019 Second Floor Renovation by Contract
61/78
0 days
20 kg./hr. 559817.90 kg./m.
#####
-
8/11/2019 Second Floor Renovation by Contract
62/78
0.12
-
8/11/2019 Second Floor Renovation by Contract
63/78
-
8/11/2019 Second Floor Renovation by Contract
64/78
-
8/11/2019 Second Floor Renovation by Contract
65/78
-
8/11/2019 Second Floor Renovation by Contract
66/78
-
8/11/2019 Second Floor Renovation by Contract
67/78
-
8/11/2019 Second Floor Renovation by Contract
68/78
-
8/11/2019 Second Floor Renovation by Contract
69/78
-
8/11/2019 Second Floor Renovation by Contract
70/78
-
8/11/2019 Second Floor Renovation by Contract
71/78
-
8/11/2019 Second Floor Renovation by Contract
72/78
-
8/11/2019 Second Floor Renovation by Contract
73/78
-
8/11/2019 Second Floor Renovation by Contract
74/78
-
8/11/2019 Second Floor Renovation by Contract
75/78
-
8/11/2019 Second Floor Renovation by Contract
76/78
-
8/11/2019 Second Floor Renovation by Contract
77/78
-
8/11/2019 Second Floor Renovation by Contract
78/78
#REF! #REF! #REF! #REF!
filling item 201 item 200
#REF! #REF! #REF!
item 104
0.23 thk