Scope of Work Camden Power Station Title: Motor ... Motors... · 59 Perform El-cid test on stator 3...
Transcript of Scope of Work Camden Power Station Title: Motor ... Motors... · 59 Perform El-cid test on stator 3...
1
Title: Motor maintenance and repair contract: Unique identifier 240-125802178
: Alternative Ref No
:Area of applicability E
: Documentation Type Scope of work
: Revision 0
: Total pages 83
: Next review Oct 2020
: Disclosure classification Controlled
Disclosure
---------------------------------------------------------------------------------------------------------------------------
Compiled by Approved by Authorized by
------------------------------------ ---------------------------------- ---------------------------
M.C Xaba Banele Mthethwa Gerhard Botma
Contract Supervisor Motor Engineer (Act) EMD Manager (Act)
Date _________________ Date _________________ Date ___________
---------------------------------------------------------------------------------------------------------------------------
Reviewed by Received by
------------------------------------ ---------------------------------
Steyn Drotsky Name:
Elect Engineering Manager Procurement Manager
Date __________________ Date _________________
---------------------------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------------------------
Scope of Work Camden Power
Station
2
Contents
1 The motor price list: SECTION A .......................................................................................................... 4
2 LV Motors, 380V AC, 3 phase ............................................................................................................... 25
3 LV Motors, 220V DC .............................................................................................................................. 46
4 Manpower price list: SECTION B ........................................................................................................ 52
5 Description of the service .................................................................................................................... 53
5.1 Executive overview ...................................................................................... 53
5.2 Employer’s requirements for the service .................................................. 53
5.2.1 Site Maintenance Services ......................................................................................................... 59
6 Management strategy and start up. ..................................................................................................... 64
6.1 The Contractor’s plan for the service ........................................................ 64
6.2 Management meetings ................................................................................ 64
6.3 Contractor’s supervision and key people ................................................. 64
6.4 Provision of bonds and guarantees ........................................................... 64
6.5 Documentation control ................................................................................ 64
6.6 Invoicing and payment ................................................................................ 65
6.7 Contract change management ................................................................... 65
6.8 Records of Defined Cost to be kept by the Contractor ............................ 65
6.9 Insurance provided by the Employer ......................................................... 65
6.10 Training workshops and technology transfer ........................................... 65
6.11 Design and supply of Equipment ............................................................... 65
6.12 Things provided at the end of the service period for the Employer’s use 65
6.12.1 Equipment ................................................................................................................................. 65
6.12.2 Information and other things .................................................................................................. 65
6.13 Management of work done by Task Order ................................................ 66
7 Health and safety, the environment and quality assurance ............................................................. 66
7.1 Health and safety risk management .......................................................... 66
7.2 Environmental constraints and management ........................................... 66
7.3 Quality assurance requirements ................................................................ 66
3.3.3 Test reports .................................................................................................................................... 67
8 Procurement .......................................................................................................................................... 67
8.1 People ........................................................................................................... 67
8.1.1 Minimum requirements of people employed ......................................................................... 67
8.1.2 BBBEE and preference scheme.............................................................................................. 68
8.1.3 Accelerated Shared Growth Initiative – South Africa (ASGI-SA) ........................................ 68
8.2 Subcontracting ............................................................................................. 69
8.3 Plant and Materials ...................................................................................... 69
8.3.1 Specifications ........................................................................................................................... 69
8.3.2 Correction of latent defects ..................................................................................................... 71
3
8.3.3 Contractor’s procurement of Plant and Materials ................................................................. 71
Where a contractor buys an item from another supplier there should be a warranty/ guaranty that will be transferred to the employer. ................................................................................................... 71
8.3.4 Tests and inspections after stripping and before delivery .................................................. 71
8.3.5 Plant & Materials provided “free issue” by the Employer ................................................... 71
9 Working on the Affected Property ....................................................................................................... 71
9.1 Employer’s site entry and security control, permits, and site regulations 72
9.2 People restrictions, hours of work, conduct and records ....................... 72
9.3 Health and safety facilities on the Affected Property............................... 73
9.4 Environmental controls, fauna & flora ....................................................... 73
9.5 Cooperating with and obtaining acceptance of others ............................ 74
9.6 Records of Contractor’s Equipment .......................................................... 74
9.7 Equipment provided by the Employer ....................................................... 74
9.1 Site services and facilities .............................................................................. 83
9.1.1 PROVIDED BY THE Employer ................................................................................................. 83
EMOLOYER’S SITE INFORMATION ............................................................................................... 83
Refuse Disposal ...................................................................................................................................... 84
9.1.2 Office and Toilet Facilities ....................................................................................................... 85
9.1.3 Accommodation and catering ................................................................................................. 85
9.1.4 Provided by the Contractor ..................................................................................................... 85
9.2 Control of noise, dust, water and waste .................................................... 85
9.3 Hook ups to existing works ........................................................................ 85
9.4 Tests and inspections ................................................................................. 85
9.4.1 Description of tests and inspections ..................................................................................... 85
9.4.2 Materials facilities and samples for tests and inspections .................................................. 85
10 List of drawings ..................................................................................................................................... 86
10.1 Drawings issued by the Employer ............................................................. 86
4
1 The motor price list: SECTION A
HV Motors, 6.6kV AC, 3 phase THIS IS RATE BASE CONTRACT: UNIT IS EACH AND THE QUANTITY IS 1 FOR ALL THE LINES ON THE PRICELIST
BELOW
1. EFP Motor, Stock No 0230905, 2465 kW
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden power station 10
2 Deliver motor to Camden power station 10
3 Open motor, clean and complete assessment report (HV assessment form) 10
4 Assemble motor 10
5 Treat and paint motor with anti-rust paint 10
TERMINAL BOX AND LEADS
6 Replace terminal box and gaskets(Seals) 6
7 Replace porcelain glasses and nuts 6
8 Replace terminal copper connectors 6
COOLER
9 Clean cooler 6
10 Overhaul the cooler 6
11 Pressure test the cooler 6
SPACE HEATERS and PT 100
12 Test heaters 10
13 Replace heaters and wire to auxiliary box 10
14 Test PT 100 10
15 Replace PT 100 and wire to Auxiliary box 10
STATOR HOUSING
16 Clean and dry stator 10
17 Polish stator foot mounting 10
18 Check the concentricity of the stator 10
19 correct the stator concentricity 10
20 Weld crack on the stator/ end shields 6
STATOR WINDINGS AND LAMINATIONS
21 Winding patch 3
22 Complete Stator rewind 8
23 Treat and paint stator with vanish 10
24 Conduct IR and PI test 10
25 Repair stator bars 10
26 Drift stator core to avoid hot sports 6
27 Check concentricity of the stator 10
28 Correct the stator concentricity 10
5
ROTOR
29 Remove and clean rotor bars 8
30 Re-bar the rotor 8
31 Repair end rings 8
32 Treat and paint rotor with anti rust paint 10
33 Balance rotor at operating speed with fan and half key inserted 10
34 Polish the journals (NDE) 10
35 Polish the journals (DE) 10
36 Polish seal landings (NDE) 10
37 Polish seal landings (DE) 10
38 Polish Fan landing (DE) 10
39 Polish Fan landing (NDE) 10
40 Check shaft run out / concentricity 10
41 Rectify or correct the rotor concentricity 10
42 Micro weld rotor shaft/Journal (DE) 10
43 Micro weld rotor shaft/Journal (NDE) 10
DRIVE-END SHIELD/ NON DRIVE-END SHIELD
44 Replace fixing bolts 8
DE END BEARING/HOUSING AND NON-DE
BEARING/HOUSING
45 Re-metal white metal DE bearing according to shaft size and fit
10
46 Clean and polish DE bearing 10
47 Re-metal white metal NON-DE bearing according to shaft size and fit
10
48 Clean and polish NON-DE bearing 10
49 Clean DE bearing housing 10
50 Clean NON-DE bearing housing 10
51 Overhaul DE seal, oil ring, oil scoop 10
52 Replace DE seal, oil ring, oil scoop 10
53 Overhaul NON-DE seal, oil ring, oil scoop 10
54 Replace NON-DE seal, oil ring, oil scoop 10
55 Replace site glass and clean the ports, DE 10
56 Replace site glass and clean the ports, NON-DE 10
57 Bearing insulation test point inspect 8
58 Bearing insulation test point repair 8
ROUTINE TESTS AND AS AND WHEN
REQUIRED TESTS
59 Perform El-cid test on stator 6
60 Perform El-cid test on rotor 6
61 Perform Rotor bar to bar test 6
6
62 Tan Delta test the stator 10
63 Ultrasonic testing on white metal bearing surface 10
64 NDT on fan impellers or runners (Whole impeller) 8
65 NDT on the rotor shaft 8
66 Copper material analysis test / check 6
67 Test run the motor and check the bearing temperatures, vibration, winding temps 10
67.1 Load testing
SPECIAL CHARGES
68 Emergency repair charge 6
2. ID Motor, Stock No 0230816, 2000kW
Item Description Rate Price
GENERAL
1 Collect motor from Camden power station 3
2 Deliver motor to Camden power station 3
3 Open motor, clean and complete assessment report (HV assessment form) 3
4 Assemble motor 3
5 Treat and paint motor with anti-rust paint 3
TERMINAL BOX AND LEADS
6 Replace terminal box and gaskets(Seals) 3
7 Replace porcelain glasses and nuts 3
8 Replace terminal copper connectors 3
COOLER
9 Clean cooler 3
10 Overhaul the cooler 3
11 Pressure test the cooler 3
SPACE HEATERS and PT 100
12 Test heaters 3
13 Replace heaters and wire to auxiliary box 3
14 Test PT 100 3
15 Replace PT 100 and wire to Auxiliary box 3
STATOR HOUSING
16 Clean and dry stator 3
17 Polish stator foot mounting 3
18 Check the concentricity of the stator 3
19 correct the stator concentricity 3
20 Weld crack on the stator/ end shields 3
STATOR WINDINGS AND LAMINATIONS
21 Winding patch 2
7
22 Complete Stator rewind 3
23 Treat and paint stator with vanish 3
24 Conduct IR and PI test 3
25 Repair stator bars 3
26 Drift stator core to avoid hot sports 3
27 Check concentricity of the stator 3
28 Correct the stator concentricity 3
ROTOR
29 Remove and clean rotor bars 3
30 Re-bar the rotor 2
31 Repair end rings 2
32 Treat and paint rotor with anti rust paint 2
33 Balance rotor at operating speed with fan and half key inserted 2
34 Polish the journals (NDE) 3
35 Polish the journals (DE) 3
36 Polish seal landings (NDE) 3
37 Polish seal landings (DE) 3
38 Polish Fan landing (DE) 3
39 Polish Fan landing (NDE) 3
40 Check shaft run out / concentricity 3
41 Rectify or correct the rotor concentricity 3
42 Micro weld rotor shaft/Journal (DE) 2
43 Micro weld rotor shaft/Journal (NDE) 2
DRIVE-END SHIELD/ NON DRIVE-END SHIELD
44 Replace fixing bolts 2
DE END BEARING/HOUSING AND NON-DE
BEARING/HOUSING
45 Re-metal white metal DE bearing according to shaft size and fit 3
46 Clean and polish DE bearing 3
47 Re-metal white metal NON-DE bearing according to shaft size and fit
3
48 Clean and polish NON-DE bearing 3
49 Clean DE bearing housing 3
50 Clean NON-DE bearing housing 3
51 Overhaul DE seal, oil ring, oil scoop 3
52 Replace DE seal, oil ring, oil scoop 3
53 Overhaul NON-DE seal, oil ring, oil scoop 3
54 Replace NON-DE seal, oil ring, oil scoop 3
55 Replace site glass and clean the ports, DE 3
56 Replace site glass and clean the ports, NON-DE 3
57 Bearing insulation test point inspect 3
58 Bearing insulation test point repair 3
8
ROUTINE TESTS AND AS AND WHEN
REQUIRED TESTS
59 Perform El-cid test on stator 3
60 Perform El-cid test on rotor 3
61 Perform Rotor bar to bar test 3
62 Tan Delta test the stator 3
63 Ultrasonic testing on white metal bearing surface 3
64 NDT on fan impellers or runners (Whole impeller) 3
65 NDT on the rotor shaft 3
66 Copper material analysis test / check 3
67 Test run the motor and check the bearing temperatures, vibration, winding temps 3
67.1 Load testing 1
SPECIAL CHARGES
68 Emergency repair charge 1
3. FD Motor, Stock No 0230910, 860kW
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden power station 8
2 Deliver motor to Camden power station 8
3 Open motor, clean and complete assessment report (HV assessment form) 8
4 Assemble motor 8
5 Treat and paint motor with anti-rust paint 8
TERMINAL BOX AND LEADS
6 Replace terminal box and gaskets(Seals) 8
7 Replace porcelain glasses and nuts 8
8 Replace terminal copper connectors 8
COOLER
9 Clean cooler/ cooling tubes 8
10 Overhaul the cooler/ cooling tubes 8
11 Pressure test the cooler/ cooling tubes 8
SPACE HEATERS and PT 100
12 Test heaters 8
13 Replace heaters and wire to auxiliary box 8
14 Test PT 100 8
15 Replace PT 100 and wire to Auxiliary box 8
9
STATOR HOUSING
16 Clean and dry stator 8
17 Polish stator foot mounting 8
18 Check the concentricity of the stator 8
19 correct the stator concentricity 8
20 Weld crack on the stator/ end shields 8
STATOR WINDINGS AND LAMINATIONS
21 Winding patch 4
22 Complete Stator rewind 6
23 Treat and paint stator with vanish 6
24 Conduct IR and PI test 6
25 Repair stator bars 6
26 Drift stator core to avoid hot sports 4
27 Check concentricity of the stator 6
28 Correct the stator concentricity 6
ROTOR
29 Remove and clean rotor bars 6
30 Re-bar the rotor 3
31 Repair end rings 3
32 Treat and paint rotor with anti rust paint 8
33 Balance rotor at operating speed with fan and half key inserted 8
34 Polish the journals (NDE) 8
35 Polish the journals (DE) 8
36 Polish seal landings (NDE) 8
37 Polish seal landings (DE) 8
38 Polish Fan landing (DE) 8
39 Polish Fan landing (NDE) 8
40 Check shaft run out / concentricity 8
41 Rectify or correct the rotor concentricity 8
42 Micro weld rotor shaft/Journal (DE) 8
43 Micro weld rotor shaft/Journal (NDE) 8
DRIVE-END SHIELD/ NON DRIVE-END SHIELD
44 Replace fixing bolts 6
DE END BEARING/HOUSING AND NON-DE
BEARING/HOUSING
45 Re-metal white metal DE bearing according to shaft size and fit 8
46 Clean and polish DE bearing 8
10
47 Re-metal white metal NON-DE bearing according to shaft size and fit
8
48 Clean and polish NON-DE bearing 8
49 Clean DE bearing housing 8
50 Clean NON-DE bearing housing 8
51 Overhaul DE seal, oil ring, oil scoop 8
52 Replace DE seal, oil ring, oil scoop 8
53 Overhaul NON-DE seal, oil ring, oil scoop 8
54 Replace NON-DE seal, oil ring, oil scoop 8
55 Replace site glass and clean the ports, DE 8
56 Replace site glass and clean the ports, NON-DE 8
57 Bearing insulation test point inspect 4
58 Bearing insulation test point repair 4
ROUTINE TESTS AND AS AND WHEN
REQUIRED TESTS
59 Perform El-cid test on stator 4
60 Perform El-cid test on rotor 4
61 Perform Rotor bar to bar test 4
62 Tan Delta test the stator 8
63 Ultrasonic testing on white metal bearing surface 8
64 NDT on fan impellers or runners (Whole impeller) 6
65 NDT on the rotor shaft 6
66 Copper material analysis test / check 4
67 Test run the motor and check the bearing temperatures, vibration, winding temps 8
67.1 Load testing
SPECIAL CHARGES
68 Emergency repair charge 3
4. CEP Motor, Stock No 0230907, 485 HP
Item Description Rate Price
GENERAL
1 Collect motor from Camden power station 8
2 Deliver motor to Camden power station 8
3 Open motor, clean and complete assessment report (HV assessment form) 8
4 Assemble motor 8
5 Treat and paint motor with anti-rust paint 8
TERMINAL BOX AND LEADS
6 Replace terminal box and gaskets(Seals) 6
7 Replace porcelain glasses and nuts 6
8 Replace terminal copper connectors 6
COOLER
11
9 Clean louvers 6
10 Overhaul the louvers 6
11 Replace the louvers 6
SPACE HEATERS and PT 100
12 Test heaters 8
13 Replace heaters and wire to auxiliary box 8
14 Test PT 100 8
15 Replace PT 100 and wire to Auxiliary box 8
STATOR HOUSING
16 Clean and dry stator 8
17 Polish stator foot mounting 8
18 Check the concentricity of the stator 8
19 correct the stator concentricity 8
20 Weld crack on the stator/ end shields 4
STATOR WINDINGS AND LAMINATIONS
21 Winding patch 4
22 Complete Stator rewind 6
23 Treat and paint stator with vanish 8
24 Conduct IR and PI test 8
25 Repair stator core 8
26 Drift stator core to avoid hot sports 8
27 Check concentricity of the stator 8
28 Correct the stator concentricity 8
ROTOR
29 Remove and clean rotor bars 4
30 Re-bar the rotor 4
31 Repair end rings 6
32 Treat and paint rotor with anti rust paint 8
33 Balance rotor at operating speed with fan and half key inserted 8
34 Polish the journals (NDE) 6
35 Polish the journals (DE) 6
36 Polish seal landings (NDE) 6
37 Polish seal landings (DE) 6
38 Polish Fan landing (DE) 6
39 Polish Fan landing (NDE) 6
40 Check shaft run out / concentricity 6
41 Rectify or correct the rotor concentricity 6
42 Micro weld rotor shaft/Journal (DE) 6
43 Micro weld rotor shaft/Journal (NDE) 6
44 Replace DE ball and roller bearing 6
45 Replace NDE ball and roller bearing 6
DRIVE-END SHIELD/ NON DRIVE-END SHIELD
46 Replace fixing bolts 4
12
DE END BEARING/HOUSING AND NON-DE
BEARING/HOUSING
47 Re-metal white metal DE bearing according to shaft size and fit 6
48 Clean and polish DE bearing 6
49 Re-metal white metal NON-DE bearing according to shaft size and fit 6
50 Clean and polish NON-DE bearing 6
51 Clean DE bearing housing 6
52 Clean NON-DE bearing housing 6
53 Overhaul DE seal, oil ring, oil scoop 6
54 Replace DE seal, oil ring, oil scoop 6
55 Overhaul NON-DE seal, oil ring, oil scoop 6
56 Replace NON-DE seal, oil ring, oil scoop 6
57 Replace site glass and clean the ports, DE 6
58 Replace site glass and clean the ports, NON-DE 6
59 Bearing insulation test point inspect 4
60 Bearing insulation test point repair 4
ROUTINE TESTS AND AS AND WHEN
REQUIRED TESTS
61 Perform El-cid test on stator 6
62 Perform El-cid test on rotor 6
63 Perform Rotor bar to bar test 4
64 Tan Delta test the stator 8
65 Ultrasonic testing on white metal bearing surface 8
66 NDT on fan impellers or runners (Whole impeller) 6
67 NDT on the rotor shaft 6
68 Copper material analysis test / check 4
69 Test run the motor and check the bearing temperatures, vibration, winding temps 8
69.1 Load testing 1
SPECIAL CHARGES
70 Emergency repair charge 3
5. Main CW Motor, Stock No 0230903, 2500HP
Item Description Rate Price
GENERAL
1 Collect motor from Camden power station 6
2 Deliver motor to Camden power station 6
3 Open motor, clean and complete assessment report (HV assessment form) 6
4 Assemble motor 6
5 Treat and paint motor with anti-rust paint 6
TERMINAL BOX AND LEADS
6 Replace terminal box and gaskets(Seals) 5
7 Replace porcelain glasses and nuts 5
8 Replace terminal copper connectors 5
13
COOLER
9 Clean louvers 5
10 Overhaul the louvers 5
11 Replace the louvers 5
SPACE HEATERS and PT 100
12 Test heaters 6
13 Replace heaters and wire to auxiliary box 6
14 Test PT 100 6
15 Replace PT 100 and wire to Auxiliary box 6
STATOR HOUSING
16 Clean and dry stator 6
17 Polish stator foot mounting 6
18 Check the concentricity of the stator 6
19 correct the stator concentricity 6
20 Weld crack on the stator/ end shields 6
STATOR WINDINGS AND LAMINATIONS
21 Winding patch 4
22 Complete Stator rewind 6
23 Treat and paint stator with vanish 6
24 Conduct IR and PI test 6
25 Repair stator bars 6
26 Drift stator core to avoid hot sports 6
27 Check concentricity of the stator 6
28 Correct the stator concentricity 6
ROTOR
29 Remove and clean rotor bars 5
30 Re-bar the rotor 4
31 Repair end rings 4
32 Treat and paint rotor with anti rust paint 5
33 Balance rotor at operating speed with fan and half key inserted 5
34 Polish the journals (NDE) 6
35 Polish the journals (DE) 6
36 Polish seal landings (NDE) 6
37 Polish seal landings (DE) 6
38 Polish Fan landing (DE) 6
39 Polish Fan landing (NDE) 6
40 Check shaft run out / concentricity 6
41 Rectify or correct the rotor concentricity 6
42 Micro weld rotor shaft/Journal (DE) 6
43 Micro weld rotor shaft/Journal (NDE) 6
DRIVE-END SHIELD/ NON DRIVE-END SHIELD
44 Replace fixing bolts 5
14
DE END BEARING/HOUSING AND NON-DE
BEARING/HOUSING
45 Re-metal white metal DE bearing according to shaft size and fit 6
46 Clean and polish DE bearing 6
47 Re-metal white metal NON-DE bearing according to shaft size and fit 6
48 Clean and polish NON-DE bearing 6
49 Clean DE bearing housing 6
50 Clean NON-DE bearing housing 6
51 Overhaul DE seal, oil ring, oil scoop 6
52 Replace DE seal, oil ring, oil scoop 6
53 Overhaul NON-DE seal, oil ring, oil scoop 6
54 Replace NON-DE seal, oil ring, oil scoop 6
55 Replace site glass and clean the ports, DE 6
56 Replace site glass and clean the ports, NON-DE 6
57 Bearing insulation test point inspect 3
58 Bearing insulation test point repair 3
ROUTINE TESTS AND AS AND WHEN
REQUIRED TESTS
59 Perform El-cid test on stator 4
60 Perform El-cid test on rotor 4
61 Perform Rotor bar to bar test 5
62 Tan Delta test the stator 6
63 Ultrasonic testing on white metal bearing surface 6
64 NDT on fan impellers or runners (Whole impeller) 5
65 NDT on the rotor shaft 5
66 Copper material analysis test / check 5
67 Test run the motor and check the bearing temperatures, vibration, winding temps 6
67.1 Load testing 1
SPECIAL CHARGES
68 Emergency repair charge 3
6. Mill Motor, Stock No 0230908, 235kW
Item Description Rate Price
GENERAL
1 Collect motor from Camden power station 15
2 Deliver motor to Camden power station 15
3 Open motor, clean and complete assessment report (HV assessment form) 15
4 Assemble motor 15
5 Treat and paint motor with anti-rust paint 15
TERMINAL BOX AND LEADS
6 Replace terminal box and gaskets(Seals) 10
7 Replace porcelain glasses and nuts 10
8 Replace terminal copper connectors 10
15
COOLER
9 Clean cooling tubes 15
10 Overhaul the cooling tubes 15
11 Pressure test the cooling tubes 15
SPACE HEATERS and PT 100
12 Test heaters 15
13 Replace heaters and wire to auxiliary box 15
14 Test PT 100 15
15 Replace PT 100 and wire to Auxiliary box 15
STATOR HOUSING
16 Clean and dry stator 15
17 Polish stator foot mounting 15
18 Check the concentricity of the stator 15
19 correct the stator concentricity 15
20 Weld crack on the stator/ end shields 10
STATOR WINDINGS AND LAMINATIONS
21 Winding patch 8
22 Complete Stator rewind 15
23 Treat and paint stator with vanish 15
24 Conduct IR and PI test 15
25 Repair stator bars 15
26 Drift stator core to avoid hot sports 15
27 Check concentricity of the stator 15
28 Correct the stator concentricity 15
ROTOR
29 Remove and clean rotor bars 10
30 Re-bar the rotor 8
31 Repair end rings 8
32 Treat and paint rotor with anti rust paint 10
33 Balance rotor at operating speed with fan and half key inserted 10
34 Polish the journals (NDE) 10
35 Polish the journals (DE) 10
36 Polish seal landings (NDE) 10
37 Polish seal landings (DE) 10
38 Polish Fan landing (DE) 10
39 Polish Fan landing (NDE) 10
40 Check shaft run out / concentricity 10
41 Rectify or correct the rotor concentricity 10
42 Micro weld rotor shaft/Journal (DE) 10
43 Micro weld rotor shaft/Journal (NDE) 10
44 Replace DE ball and roller bearing 10
45 Replace NDE ball and roller bearing 10
DRIVE-END SHIELD/ NON DRIVE-END SHIELD
46 Replace fixing bolts 8
DE END BEARING/HOUSING AND NON-DE BEARING/HOUSING
16
47 Repair worn-out DE shaft and housing to correct shaft size 10
48 Repair worn-out NDE shaft and housing to correct shaft size 10
ROUTINE TESTS AND AS AND WHEN REQUIRED TESTS
49 Perform El-cid test on stator 3
50 Perform El-cid test on rotor 3
51 Perform Rotor bar to bar test 8
52 Tan Delta test the stator 10
53 NDT on fan impellers or runners (Whole impeller) 8
54 NDT on the rotor shaft 8
55 Copper material analysis test / check 6
56 Test run the motor and check the bearing temperatures, vibration, winding temps 10
57 Load testing
SPECIAL CHARGES
58 Emergency repair charge 6
7. PA Motor, Stock No 0230909, 335kW
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden power station 15
2 Deliver motor to Camden power station 15
3 Open motor, clean and complete assessment report (HV assessment form) 15
4 Assemble motor 15
5 Treat and paint motor with anti-rust paint 15
TERMINAL BOX AND LEADS
Item Description Unit Rate Price
6 Replace terminal box and gaskets(Seals) 10
7 Replace porcelain glasses and nuts 10
8 Replace terminal copper connectors 10
COOLER
9 Clean cooling tubes 15
10 Overhaul the cooling tubes 15
11 Pressure test the cooling tubes 15
SPACE HEATERS and PT 100
12 Test heaters 15
13 Replace heaters and wire to auxiliary box 15
14 Test PT 100 15
15 Replace PT 100 and wire to Auxiliary box 15
17
STATOR HOUSING
16 Clean and dry stator 10
17 Polish stator foot mounting 10
18 Check the concentricity of the stator 10
19 correct the stator concentricity 10
20 Weld crack on the stator/ end shields 10
STATOR WINDINGS AND LAMINATIONS
21 Winding patch 8
22 Complete Stator rewind 12
23 Treat and paint stator with vanish 15
24 Conduct IR and PI test 15
25 Repair stator core 10
26 Drift stator core to avoid hot sports 10
27 Check concentricity of the stator 10
28 Correct the stator concentricity 10
ROTOR
29 Remove and clean rotor bars 10
30 Re-bar the rotor 8
31 Repair end rings 8
32 Treat and paint rotor with anti rust paint 15
33 Balance rotor at operating speed with fan and half key inserted 15
34 Polish the journals (NDE) 15
35 Polish the journals (DE) 15
36 Polish seal landings (NDE) 15
37 Polish seal landings (DE) 15
38 Polish Fan landing (DE) 15
39 Polish Fan landing (NDE) 15
40 Check shaft run out / concentricity 15
41 Rectify or correct the rotor concentricity 15
42 Micro weld rotor shaft/Journal (DE) 12
43 Micro weld rotor shaft/Journal (NDE) 12
44 Replace DE ball and roller bearing 12
45 Replace NDE ball and roller bearing 12
DRIVE-END SHIELD/ NON DRIVE-END SHIELD
46 Replace fixing bolts 10
DE END BEARING/HOUSING AND NON-DE BEARING/HOUSING
47 Repair worn-out DE shaft and housing to correct shaft size 15
48 Repair worn-out NDE shaft and housing to correct shaft size 15
49 Clean DE bearing housing 15
50 Clean NON-DE bearing housing 15
51 Overhaul DE seal, oil ring, oil scoop 15
52 Replace DE seal, oil ring, oil scoop 15
53 Overhaul NON-DE seal, oil ring, oil scoop 15
54 Replace NON-DE seal, oil ring, oil scoop 15
18
55 Replace grease nipple, pipes and thermocouple port DE 15
56 Replace grease nipple, pipes and thermocouple port DE 15
ROUTINE TESTS AND AS AND WHEN REQUIRED TESTS
61 Perform El-cid test on stator 10
62 Perform El-cid test on rotor 10
63 Perform Rotor bar to bar test 10
64 Tan Delta test the stator 15
65 NDT on fan impellers or runners (Whole impeller) 15
66 NDT on the rotor shaft 15
67 Copper material analysis test / check 15
68 Test run the motor and check the bearing temperatures, vibration, winding temps 15
68.1 Load testing 2
SPECIAL CHARGES
69 Emergency repair charge 10
8. Sluice Motor, Stock No 0230904, 440HP
Item Description Rate Price
GENERAL
1 Collect motor from Camden power station 6
2 Deliver motor to Camden power station 6
3 Open motor, clean and complete assessment report (HV assessment form) 6
4 Assemble motor 6
5 Treat and paint motor with anti-rust paint 6
TERMINAL BOX AND LEADS
6 Replace terminal box and gaskets(Seals) 6
7 Replace porcelain glasses and nuts 6
8 Replace terminal copper connectors 6
COOLER
9 Clean cooler/ cooling tubes 6
10 Overhaul the cooler/ cooling tubes 6
11 Pressure test the cooler/ cooling tubes 6
SPACE HEATERS and PT 100
12 Test heaters 6
13 Replace heaters and wire to auxiliary box 6
14 Test PT 100 6
19
15 Replace PT 100 and wire to Auxiliary box 6
STATOR HOUSING
16 Clean and dry stator 6
17 Polish stator foot mounting 6
18 Check the concentricity of the stator 6
19 correct the stator concentricity 6
20 Weld crack on the stator/ end shields 6
STATOR WINDINGS AND LAMINATIONS
21 Winding patch 3
22 Complete Stator rewind 6
23 Treat and paint stator with vanish 6
24 Conduct IR and PI test 6
25 Repair stator core 4
26 Drift stator core to avoid hot sports 4
ROTOR
29 Remove and clean rotor bars 4
30 Re-bar the rotor 3
31 Repair end rings 3
32 Treat and paint rotor with anti rust paint 6
33 Balance rotor at operating speed with fan and half key inserted 6
34 Polish the journals (NDE) 6
35 Polish the journals (DE) 6
36 Polish seal landings (NDE) 6
37 Polish seal landings (DE) 6
38 Polish Fan landing (DE) 6
39 Polish Fan landing (NDE) 6
40 Check shaft run out / concentricity 6
41 Rectify or correct the rotor concentricity 6
42 Micro weld rotor shaft/Journal (DE) 6
43 Micro weld rotor shaft/Journal (NDE) 6
44 Replace DE ball and roller bearing 6
45 Replace NDE ball and roller bearing 6
DRIVE-END SHIELD/ NON DRIVE-END SHIELD
46 Replace fixing bolts
ROUTINE TESTS AND AS AND WHEN REQUIRED TESTS
47 Perform El-cid test on stator 4
48 Perform El-cid test on rotor 4
49 Perform Rotor bar to bar test 4
50 Tan Delta test the stator 5
51 NDT on fan impellers or runners (Whole impeller) 6
52 NDT on the rotor shaft 6
53 Copper material analysis test / check 4
54 Test run the motor and check the bearing 6
20
temperatures, vibration, winding temps
55 Load testing
SPECIAL CHARGES
56 Emergency repair charge 4
9. Ash Motor, Stock No 0226186, 500kW
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden power station 16
2 Deliver motor to Camden power station 16
3 Open motor, clean and complete assessment report (HV assessment form) 16
4 Assemble motor 16
5 Treat and paint motor with anti-rust paint 16
TERMINAL BOX AND LEADS
6 Replace terminal box and gaskets(Seals) 10
7 Replace porcelain glasses and nuts 10
8 Replace terminal copper connectors 10
SPACE HEATERS and PT 100
12 Test heaters 16
13 Replace heaters and wire to auxiliary box 16
14 Test PT 100 16
15 Replace PT 100 and wire to Auxiliary box 16
STATOR HOUSING
16 Clean and dry stator 16
17 Polish stator foot mounting 16
18 Correct the stator concentricity 16
19 Weld crack on the stator/ end shields 8
STATOR WINDINGS AND LAMINATIONS
20 Winding patch 4
21 Complete Stator rewind 8
22 Treat and paint stator with vanish 16
23 Conduct IR and PI test 16
24 Repair stator core 6
25 Drift stator core to avoid hot sports 6
ROTOR
26 Treat and paint rotor with anti rust paint 16
27 Balance rotor at operating speed with fan and half key inserted 16
28 Polish the journals (NDE) 16
29 Polish the journals (DE) 16
21
30 Polish seal landings (NDE) 16
31 Polish seal landings (DE) 16
32 Polish Fan landing (NDE) 10
33 Micro weld rotor shaft/Journal (DE) 16
34 Micro weld rotor shaft/Journal (NDE) 16
35 Replace DE ball and roller bearing 16
46 Replace NDE ball and roller bearing 16
DRIVE-END SHIELD/ NON DRIVE-END SHIELD
37 Replace DE and NDE shields 8
ROUTINE TESTS AND AS AND WHEN REQUIRED TESTS
38 Perform El-cid test on stator 8
39 Perform El-cid test on rotor 8
40 Tan Delta test the stator 12
41 NDT on the rotor shaft 12
42 Copper material analysis test / check 10
43 Test run the motor and check the bearing temperatures, vibration, winding temps 16
44 Load testing
SPECIAL CHARGES
45 Emergency repair charge 14
10. Main CW booster Motor, Stock No 0230906, 385HP
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden power station 1
2 Deliver motor to Camden power station 1
3 Open motor, clean and complete assessment report (HV assessment form) 1
4 Assemble motor 1
5 Treat and paint motor with anti-rust paint
TERMINAL BOX AND LEADS
6 Replace terminal box and gaskets(Seals) 1
7 Replace porcelain glasses and nuts 1
8 Replace terminal copper connectors 1
COOLER
9 Clean louvers 1
10 Overhaul the louvers 1
11 Replace the louvers 1
1
SPACE HEATERS and PT 100
12 Test heaters 1
22
13 Replace heaters and wire to auxiliary box 1
14 Test PT 100 1
15 Replace PT 100 and wire to Auxiliary box 1
STATOR HOUSING
16 Clean and dry stator 1
17 Polish stator foot mounting 1
18 Check the concentricity of the stator 1
19 correct the stator concentricity 1
20 Weld crack on the stator/ end shields 1
STATOR WINDINGS AND LAMINATIONS
21 Winding patch 1
22 Complete Stator rewind 1
23 Treat and paint stator with vanish 1
24 Conduct IR and PI test 1
25 Repair stator core 1
26 Drift stator core to avoid hot sports 1
27 Check concentricity of the stator 1
28 Correct the stator concentricity 1
ROTOR
29 Remove and clean rotor bars 1
30 Re-bar the rotor 1
31 Repair end rings 1
32 Treat and paint rotor with anti rust paint 1
33 Balance rotor at operating speed with fan and half key inserted 1
34 Polish the journals (NDE) 1
35 Polish the journals (DE) 1
36 Polish seal landings (NDE) 1
37 Polish seal landings (DE) 1
39 Polish Fan landing (NDE) 1
40 Check shaft run out / concentricity 1
41 Rectify or correct the rotor concentricity 1
42 Micro welding rotor shaft (DE) 1
43 Micro welding rotor shaft (NDE) 1
DRIVE-END SHIELD/ NON DRIVE-END SHIELD
44 Replace fixing bolts 1
DE END BEARING/HOUSING AND NON-DE BEARING/HOUSING
45 Re-metal white metal DE bearing according to shaft size 1
46 Clean and polish DE bearing 1
47 Re-metal white metal NON-DE bearing according to shaft size 1
48 Clean and polish NON-DE bearing 1
49 Clean DE bearing housing 1
23
50 Clean NON-DE bearing housing 1
51 Overhaul DE seal, oil ring 1
52 Replace DE seal, oil ring 1
53 Overhaul NON-DE seal, oil ring 1
54 Replace NON-DE seal, oil ring 1
55 Replace site glass and clean the ports, DE 1
56 Replace site glass and clean the ports, NON-DE 1
58 Bearing insulation test point repair 1
ROUTINE TESTS AND AS AND WHEN REQUIRED TESTS
59 Perform El-cid test on stator 1
60 Perform El-cid test on rotor 1
61 Perform Rotor bar to bar test 1
62 Tan Delta test the stator 1
63 Ultrasonic testing on white metal bearing surface 1
64 NDT on fan impellers or runners (Whole impeller) 1
65 NDT on the rotor shaft 1
66 Copper material analysis test / check 1
67 Test run the motor and check the bearing temperatures, vibration, winding temps 1
67 Load testing 1
SPECIAL CHARGES
68 Emergency repair charge 1
11. Incline Conveyor Motor, Stock no. 6023344, 85Kw
Item Description Rate Price
GENERAL
1 Collect motor from Camden power station 4
2 Deliver motor to Camden power station 4
3 Open motor, clean and complete assessment report (HV assessment form) 4
4 Assemble motor 4
5 Treat and paint motor with anti-rust paint 4
TERMINAL BOX AND LEADS
6 Replace terminal box and gaskets(Seals) 4
7 Replace porcelain glasses and nuts 4
8 Replace terminal copper connectors 4
COOLER
9 Clean cooling tubes 4
10 Overhaul the cooling tubes 1
11 Pressure test the cooling tubes 1
SPACE HEATERS and PT 100
24
12 Test heaters 4
13 Replace heaters and wire to auxiliary box 4
14 Test PT 100 4
15 Replace PT 100 and wire to Auxiliary box 4
STATOR HOUSING
16 Clean and dry stator 4
17 Polish stator foot mounting 4
18 Check the concentricity of the stator 4
19 correct the stator concentricity 4
20 Weld crack on the stator/ end shields 4
STATOR WINDINGS AND LAMINATIONS
21 Winding patch 1
22 Complete Stator rewind 4
23 Treat and paint stator with vanish 4
24 Conduct IR and PI test 4
25 Repair stator bars 3
26 Drift stator core to avoid hot sports 3
27 Check concentricity of the stator 4
28 Correct the stator concentricity 4
ROTOR
29 Remove and clean rotor bars 1
30 Re-bar the rotor 1
31 Repair end rings 4
32 Treat and paint rotor with anti rust paint 4
33 Balance rotor at operating speed with fan and half key inserted 4
34 Polish the journals (NDE) 4
35 Polish the journals (DE) 4
36 Polish seal landings (NDE) 4
37 Polish seal landings (DE) 4
38 Polish Fan landing (DE) 4
39 Polish Fan landing (NDE) 4
40 Check shaft run out / concentricity 4
41 Rectify or correct the rotor concentricity 4
42 Micro weld rotor shaft/Journal (DE) 4
43 Micro weld rotor shaft/Journal (NDE) 4
44 Replace DE ball and roller bearing 4
45 Replace NDE ball and roller bearing 4
DRIVE-END SHIELD/ NON DRIVE-END SHIELD
46 Replace fixing bolts 4
DE END BEARING/HOUSING AND NON-DE BEARING/HOUSING
47 Repair worn-out DE shaft and housing to correct shaft size 4
48 Repair worn-out NDE shaft and housing to correct shaft size 4
ROUTINE TESTS AND AS AND WHEN REQUIRED TESTS
49 Perform El-cid test on stator 2
50 Perform El-cid test on rotor 2
51 Perform Rotor bar to bar test 2
25
52 Tan Delta test the stator 4
53 NDT on fan impellers or runners (Whole impeller) 4
54 NDT on the rotor shaft 4
55 Copper material analysis test / check 2
56 Test run the motor and check the bearing temperatures, vibration, winding temps 4
57 Load testing 1
SPECIAL CHARGES
58 Emergency repair charge 1
2 LV Motors, 380V AC, 3 phase
1. LV Motors, 0.55kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 2
2 Deliver motor to Camden Power Station 2
3 Open motor, clean and complete assessment report. 2
4 Assemble motor 2
5 Treat and paint motor with anti-rust paint 2
TERMINAL BOX
6 Replace terminal box cover 2
7 Replace terminal block and connect windings 2
COOLING FAN
8 Replace cooling fan 2
DE AND NDE END SHIELD
9 Replace DE shield 2
10 Replace NDE shield 2
26
ROTOR
11 Replace rotor shaft 2
12 Replace Mechanical O' rings DE 2
13 Replace Mechanical O' rings NDE 2
14 Replace DE bearing 2
15 Replace NDE bearing 2
STATOR
16 Stator rewind 2
17 Treat and paint stator with vanish 2
18 Conduct IR, winding balance test 2
19 Test run for vibrations and current balance test 2
SPECIAL CHARGES
20 Emergency repair charge 1
2. LV Motors, 0.75kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 2
2 Deliver motor to Camden Power Station 2
3 Open motor, clean and complete assessment report 2
4 Assemble motor 2
5 Treat and paint motor with anti-rust paint 2
TERMINAL BOX
6 Replace terminal box cover 2
7 Replace terminal block and connect windings 2
COOLING FAN
8 Replace cooling fan 2
DE AND NDE END SHIELD
9 Replace DE shield 2
10 Replace NDE shield 2
ROTOR
11 Replace rotor shaft 2
12 Replace Mechanical O' rings DE 2
13 Replace Mechanical O' rings NDE 2
14 Replace DE bearing 2
15 Replace NDE bearing 2
STATOR
16 Stator rewind 2
17 Treat and paint stator with vanish 2
18 Conduct IR, winding balance test 2
27
19 Test run for vibrations and current balance test 2
SPECIAL CHARGES
20 Emergency repair charge 2
3. LV Motors, 1.1kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 2
2 Deliver motor to Camden Power Station 2
3 Open motor, clean and complete assessment report 2
4 Assemble motor 2
5 Treat and paint motor with anti-rust paint 2
TERMINAL BOX
6 Replace terminal box 2
7 Replace terminal box cover 2
8 Replace terminal block and connect windings 2
COOLING FAN
9 Replace cooling fan 2
2
DE AND NDE END SHIELD
10 Micro-weld and polish DE bearing housing 2
11 Micro-weld and polish NDE bearing housing 2
12 Replace DE shield 2
13 Replace NDE shield 2
ROTOR
14 Replace rotor shaft 2
15 Micro welding rotor shaft (DE) 2
16 Micro welding rotor shaft (NDE) 2
17 Replace Mechanical O' rings DE 2
18 Replace Mechanical O' rings NDE 2
19 Replace DE bearing 2
20 Replace NDE bearing 2
STATOR
21 Stator rewind 2
22 Treat and paint stator with vanish 2
23 Conduct IR, winding balance test 2
24 Test run for vibrations and current balance test 2
SPECIAL CHARGES
25 Emergency repair charge 2
28
4. LV Motors, 1.5kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 2
2 Deliver motor to Camden Power Station 2
3 Open motor, clean and complete assessment report 2
4 Assemble motor 2
5 Treat and paint motor with anti-rust paint 2
TERMINAL BOX
6 Replace terminal box 2
7 Replace terminal box cover 2
8 Replace terminal block and connect windings 2
COOLING FAN
9 Replace cooling fan 2
10 Replace cooling fan key 2
DE AND NDE END SHIELD
11 Micro-weld and polish DE bearing housing 2
12 Micro-weld and polish NDE bearing housing 2
13 Replace DE shield 2
14 Replace NDE shield 2
ROTOR 2
15 Replace rotor shaft 2
16 Micro welding rotor shaft (DE) 2
17 Micro welding rotor shaft (NDE) 2
18 Balance the rotor with a cooling fan 2
19 Replace Mechanical O' rings DE 2
20 Replace Mechanical O' rings NDE 2
21 Replace DE bearing 2
22 Replace NDE bearing 2
STATOR
23 Stator rewind 2
24 Treat and paint stator with vanish 2
25 Conduct IR, winding balance test 2
26 Test run for vibrations and current balance test 2
SPECIAL CHARGES
27 Emergency repair charge 2
5. LV Motors, 2.2kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
29
1 Collect motor from Camden Power station 2
2 Deliver motor to Camden Power Station 2
3 Open motor, clean and complete assessment report 2
4 Assemble motor 2
5 Treat and paint motor with anti-rust paint 2
TERMINAL BOX
6 Replace terminal box 2
7 Replace terminal box cover 2
8 Replace terminal block and connect windings 2
COOLING FAN
9 Replace cooling fan 2
10 Replace cooling fan key 2
DE AND NDE END SHIELD
11 Micro-weld and polish DE bearing housing 2
12 Micro-weld and polish NDE bearing housing 2
13 Replace DE shield 2
14 Replace NDE shield 2
15 Fit DE and NDE grease nipples 2
ROTOR
16 Replace rotor shaft 2
17 Micro welding rotor shaft (DE) 2
18 Micro welding rotor shaft (NDE) 2
19 Balance the rotor with a cooling fan 2
20 Replace Mechanical O' rings DE 2
21 Replace Mechanical O' rings NDE 2
22 Replace DE bearing 2
23 Replace NDE bearing 2
STATOR
24 Stator rewind 2
25 Treat and paint stator with vanish 2
26 Conduct IR, winding balance test 2
27 Test run for vibrations and current balance test 2
SPECIAL CHARGES
28 Emergency repair charge 2
6. LV Motors, 3kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 1
2 Deliver motor to Camden Power Station 1
30
3 Open motor, clean and complete assessment report (see Attachment 1) 1
4 Assemble motor 1
5 Treat and paint motor with anti-rust paint 1
TERMINAL BOX
6 Replace terminal box 1
7 Replace terminal box cover 1
8 Replace terminal block and connect windings 1
COOLING FAN
9 Replace cooling fan 1
10 Replace cooling fan key 1
DE AND NDE END SHIELD
11 Micro-weld and polish DE bearing housing 1
12 Micro-weld and polish NDE bearing housing 1
13 Replace DE shield 1
14 Replace NDE shield 1
15 Fit DE and NDE grease nipples 1
ROTOR
16 Replace rotor shaft 1
17 Micro welding rotor shaft (DE) 1
18 Micro welding rotor shaft (NDE) 1
19 Balance the rotor with a cooling fan 1
20 Replace Mechanical O' rings DE 1
21 Replace Mechanical O' rings NDE 1
22 Replace DE bearing 1
23 Replace NDE bearing 1
STATOR
24 Stator rewind 1
25 Treat and paint stator with vanish 1
26 Conduct IR, winding balance test 1
27 Test run for vibrations and current balance test 1
SPECIAL CHARGES
28 Emergency repair charge 1
7. LV Motors, 4kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 3
2 Deliver motor to Camden Power Station 3
3 Open motor, clean and complete assessment report (see Attachment 1) 3
4 Assemble motor 3
5 Treat and paint motor with anti-rust paint 3
31
TERMINAL BOX
6 Replace terminal box 3
7 Replace terminal box cover 3
8 Replace terminal block and connect windings 3
COOLING FAN
9 Replace cooling fan 3
10 Replace cooling fan key 3
DE AND NDE END SHIELD
11 Micro-weld and polish DE bearing housing 3
12 Micro-weld and polish NDE bearing housing 3
13 Replace DE shield 3
14 Replace NDE shield 3
15 Fit DE and NDE grease nipples 3
ROTOR
16 Replace rotor shaft 3
17 Micro welding rotor shaft (DE) 3
18 Micro welding rotor shaft (NDE) 3
19 Balance the rotor with a cooling fan 3
20 Replace Mechanical O' rings DE 3
21 Replace Mechanical O' rings NDE 3
22 Replace DE bearing 3
23 Replace NDE bearing 3
STATOR
24 Stator rewind 3
25 Treat and paint stator with vanish 3
26 Conduct IR, winding balance test 3
27 Test run for vibrations and current balance test 3
SPECIAL CHARGES
28 Emergency repair charge 3
8. LV Motors, 5.5kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 3
2 Deliver motor to Camden Power Station 3
3 Open motor, clean and complete assessment report 3
4 Assemble motor 3
5 Treat and paint motor with anti-rust paint 3
TERMINAL BOX
6 Replace terminal box 3
32
7 Replace terminal box cover 3
8 Replace terminal block and connect windings 3
COOLING FAN
9 Replace cooling fan 3
10 Replace cooling fan key 3
DE AND NDE END SHIELD
11 Micro-weld and polish DE bearing housing 3
12 Micro-weld and polish NDE bearing housing 3
13 Replace DE shield 3
14 Replace NDE shield 3
15 Fit DE and NDE grease nipples 3
ROTOR
16 Replace the rotor 3
17 Replace rotor shaft 3
18 Micro welding rotor shaft (DE) 3
19 Micro welding rotor shaft (NDE) 3
20 Balance the rotor with a cooling fan 3
21 Replace Mechanical O' rings DE 3
22 Replace Mechanical O' rings NDE 3
23 Replace DE bearing 3
24 Replace NDE bearing 3
STATOR
25 Stator rewind 3
26 Replace stator laminations/core 3
27 Restack stator laminations/core 3
28 Treat and paint stator with vanish 3
29 Conduct IR, winding balance test 3
30 Test run for vibrations and current balance test 3
SPECIAL CHARGES
31 Emergency repair charge 3
9. LV Motors, 7.5kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 3
2 Deliver motor to Camden Power Station 3
3 Open motor, clean and complete assessment report 3
4 Assemble motor 3
5 Treat and paint motor with anti-rust paint 3
TERMINAL BOX
6 Replace terminal box 3
33
7 Replace terminal box cover 3
8 Replace terminal block and connect windings 3
COOLING FAN
9 Replace cooling fan 3
10 Replace cooling fan key 3
DE AND NDE END SHIELD
11 Micro-weld and polish DE bearing housing 3
12 Micro-weld and polish NDE bearing housing 3
13 Replace DE shield 3
14 Replace NDE shield 3
15 Fit DE and NDE grease nipples 3
ROTOR
16 Replace the rotor 3
17 Replace rotor shaft 3
18 Micro welding rotor shaft (DE) 3
19 Micro welding rotor shaft (NDE) 3
20 Balance the rotor with a cooling fan 3
21 Replace Mechanical O' rings DE 3
22 Replace Mechanical O' rings NDE 3
23 Replace DE bearing 3
24 Replace NDE bearing 3
STATOR
25 Stator rewind 3
26 Replace stator laminations/core 3
27 Treat and paint stator with vanish 3
28 Conduct IR, winding balance test 3
29 Test run for vibrations and current balance test 3
SPECIAL CHARGES
30 Emergency repair charge 3
10. LV Motors, 9.2kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 2
2 Deliver motor to Camden Power Station 2
3 Open motor, clean and complete assessment report (see Attachment 1) 2
4 Assemble motor 2
5 Treat and paint motor with anti-rust paint 2
TERMINAL BOX
6 Replace terminal box 2
7 Replace terminal box cover 2
34
8 Replace terminal block and connect windings 2
COOLING FAN
9 Replace cooling fan 2
10 Replace cooling fan key 2
DE AND NDE END SHIELD
11 Micro-weld and polish DE bearing housing 2
12 Micro-weld and polish NDE bearing housing 2
13 Replace DE shield 2
14 Replace NDE shield 2
15 Fit DE and NDE grease nipples 2
ROTOR
16 Replace the rotor 2
17 Replace rotor shaft 2
18 Micro welding rotor shaft (DE) 2
19 Micro welding rotor shaft (NDE) 2
20 Balance the rotor with a cooling fan 2
21 Replace Mechanical O' rings DE 2
22 Replace Mechanical O' rings NDE 2
23 Replace DE bearing 2
24 Replace NDE bearing 2
STATOR
25 Stator rewind 2
26 Replace stator laminations/core 2
27 Treat and paint stator with vanish 2
28 Conduct IR, winding balance test 2
29 Test run for vibrations and current balance test 2
SPECIAL CHARGES
30 Emergency repair charge 2
11. LV Motors, 11kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 2
2 Deliver motor to Camden Power Station 2
3 Open motor, clean and complete assessment report 2
4 Assemble motor 2
5 Treat and paint motor with anti-rust paint 2
TERMINAL BOX
6 Replace terminal box 2
7 Replace terminal box cover 2
8 Replace terminal block and connect windings 2
35
COOLING FAN
9 Replace cooling fan 2
10 Replace cooling fan key 2
DE AND NDE END SHIELD
11 Micro-weld and polish DE bearing housing 2
12 Micro-weld and polish NDE bearing housing 2
13 Replace DE shield 2
14 Replace NDE shield 2
15 Fit DE and NDE grease nipples 2
ROTOR
16 Replace the rotor 2
17 Replace rotor shaft 2
18 Micro welding rotor shaft (DE) 2
19 Micro welding rotor shaft (NDE) 2
20 Balance the rotor with a cooling fan 2
21 Replace Mechanical O' rings DE 2
22 Replace Mechanical O' rings NDE 2
23 Replace DE bearing 2
24 Replace NDE bearing 2
STATOR
25 Stator rewind 2
26 Replace stator laminations/core 2
27 Treat and paint stator with vanish 2
28 Conduct IR, winding balance test 2
29 Test run for vibrations and current balance test 2
SPECIAL CHARGES
30 Emergency repair charge 2
12. LV Motors, 15kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 8
2 Deliver motor to Camden Power Station 8
3 Open motor, clean and complete assessment report 8
4 Assemble motor 8
5 Treat and paint motor with anti-rust paint 8
TERMINAL BOX
6 Replace terminal box 8
7 Replace terminal box cover 8
8 Replace terminal block and connect windings 8
COOLING FAN
36
9 Replace cooling fan 8
10 Replace cooling fan key 8
DE AND NDE END SHIELD
11 Micro-weld and polish DE bearing housing 8
12 Micro-weld and polish NDE bearing housing 8
13 Replace DE shield 8
14 Replace NDE shield 8
15 Fit DE and NDE grease nipples 8
ROTOR
16 Replace the rotor 8
17 Replace rotor shaft 8
18 Micro welding rotor shaft (DE) 8
19 Micro welding rotor shaft (NDE) 8
20 Balance the rotor with a cooling fan 8
21 Replace Mechanical O' rings DE 8
22 Replace Mechanical O' rings NDE 8
23 Replace DE bearing 8
24 Replace NDE bearing 8
STATOR
25 Stator rewind 8
26 Replace stator laminations/core 8
27 Treat and paint stator with vanish 8
28 Conduct IR, winding balance test 8
29 Test run for vibrations and current balance test 8
SPECIAL CHARGES
30 Emergency repair charge 5
13. LV Motors, 18.5kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 6
2 Deliver motor to Camden Power Station 6
3 Open motor, clean and complete assessment report (see Attachment 1) 6
4 Assemble motor 6
5 Treat and paint motor with anti-rust paint 6
TERMINAL BOX
6 Replace terminal box 6
7 Replace terminal box cover 6
8 Replace terminal block and connect windings 6
COOLING FAN
9 Replace cooling fan 6
37
10 Replace cooling fan key 6
DE AND NDE END SHIELD
11 Micro-weld and polish DE bearing housing 6
12 Micro-weld and polish NDE bearing housing 6
13 Replace DE shield 6
14 Replace NDE shield 6
15 Fit DE and NDE grease nipples 6
ROTOR
16 Replace the rotor 6
17 Replace rotor shaft 6
18 Micro welding rotor shaft (DE) 6
19 Micro welding rotor shaft (NDE) 6
20 Balance the rotor with a cooling fan 6
21 Replace Mechanical O' rings DE 6
22 Replace Mechanical O' rings NDE 6
23 Replace DE bearing 6
24 Replace NDE bearing 6
STATOR
25 Stator rewind 6
26 Replace stator laminations/core 6
27 Treat and paint stator with vanish 6
28 Conduct IR, winding balance test 6
29 Test run for vibrations and current balance test 6
SPECIAL CHARGES
30 Emergency repair charge 4
14. LV Motors, 22kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 3
2 Deliver motor to Camden Power Station 3
3 Open motor, clean and complete assessment report 3
4 Assemble motor 3
5 Treat and paint motor with anti-rust paint 3
TERMINAL BOX
6 Replace terminal box 3
7 Replace terminal box cover 3
8 Replace terminal block and connect windings 3
COOLING FAN
9 Replace cooling fan 3
10 Replace cooling fan key 3
38
DE AND NDE END SHIELD
11 Micro-weld and polish DE bearing housing 3
12 Micro-weld and polish NDE bearing housing 3
13 Replace DE shield 3
14 Replace NDE shield 3
15 Fit DE and NDE grease nipples 3
ROTOR
16 Replace the rotor 3
17 Replace rotor shaft 3
18 Micro welding rotor shaft (DE) 3
19 Micro welding rotor shaft (NDE) 3
20 Balance the rotor with a cooling fan 3
21 Replace Mechanical O' rings DE 3
22 Replace Mechanical O' rings NDE 3
23 Replace DE bearing 3
24 Replace NDE bearing 3
STATOR
25 Stator rewind 3
26 Replace stator laminations/core 3
27 Treat and paint stator with vanish 3
28 Conduct IR, winding balance test 3
29 Test run for vibrations and current balance test 3
SPECIAL CHARGES
30 Emergency repair charge 3
15. LV Motors, 30kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 15
2 Deliver motor to Camden Power Station 15
3 Open motor, clean and complete assessment report (see Attachment 1) 15
4 Assemble motor 15
5 Treat and paint motor with anti-rust paint 15
TERMINAL BOX
6 Replace terminal box 15
7 Replace terminal box cover 15
8 Replace terminal block and connect windings 15
COOLING FAN
9 Replace cooling fan 15
10 Replace cooling fan key 15
DE AND NDE END SHIELD
11 Micro-weld and polish DE bearing housing 15
39
12 Micro-weld and polish NDE bearing housing 15
13 Replace DE shield 15
14 Replace NDE shield 15
15 Fit DE and NDE grease nipples 15
ROTOR
16 Replace the rotor 15
17 Replace rotor shaft 15
18 Micro welding rotor shaft (DE) 15
19 Micro welding rotor shaft (NDE) 15
20 Balance the rotor with a cooling fan 15
21 Replace Mechanical O' rings DE 15
22 Replace Mechanical O' rings NDE 15
23 Replace DE bearing 15
24 Replace NDE bearing 15
STATOR
25 Stator rewind 15
26 Replace stator laminations/core 15
27 Treat and paint stator with vanish 15
28 Conduct IR, winding balance test 15
29 Test run for vibrations and current balance test 15
SPECIAL CHARGES
30 Emergency repair charge 15
16. LV Motors, 37kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 2
2 Deliver motor to Camden Power Station 2
3 Open motor, clean and complete assessment report (see Attachment 1) 2
4 Assemble motor 2
5 Treat and paint motor with anti-rust paint 2
TERMINAL BOX
6 Replace terminal box 2
7 Replace terminal box cover 2
8 Replace terminal block and connect windings 2
COOLING FAN
9 Replace cooling fan 2
10 Replace cooling fan key 2
DE AND NDE END SHIELD
11 Micro-weld and polish DE bearing housing 2
40
12 Micro-weld and polish NDE bearing housing 2
13 Replace DE shield 2
14 Replace NDE shield 2
15 Fit DE and NDE grease nipples 2
ROTOR
16 Replace the rotor 2
17 Replace rotor shaft 2
18 Micro welding rotor shaft (DE) 2
19 Micro welding rotor shaft (NDE) 2
20 Balance the rotor with a cooling fan 2
21 Replace Mechanical O' rings DE 2
22 Replace Mechanical O' rings NDE 2
23 Replace DE bearing 2
24 Replace NDE bearing 2
STATOR
25 Stator rewind 2
26 Replace stator laminations/core 2
27 Treat and paint stator with vanish 2
28 Conduct IR, winding balance test 2
29 Test run for vibrations and current balance test 2
SPECIAL CHARGES
30 Emergency repair charge 2
17. LV Motors, 45kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 3
2 Deliver motor to Camden Power Station 3
3 Open motor, clean and complete assessment report 3
4 Assemble motor 3
5 Treat and paint motor with anti-rust paint 3
TERMINAL BOX
6 Replace terminal box 3
7 Replace terminal box cover 3
8 Replace terminal block and connect windings 3
COOLING FAN
9 Replace cooling fan 3
10 Replace cooling fan key 3
DE AND NDE END SHIELD
11 Micro-weld and polish DE bearing housing 3
41
12 Micro-weld and polish NDE bearing housing 3
13 Replace DE shield 3
14 Replace NDE shield 3
15 Fit DE and NDE grease nipples 3
ROTOR
16 Replace the rotor 3
17 Replace rotor shaft 3
18 Micro welding rotor shaft (DE) 3
19 Micro welding rotor shaft (NDE) 3
20 Balance the rotor with a cooling fan 3
21 Replace Mechanical O' rings DE 3
22 Replace Mechanical O' rings NDE 3
23 Replace DE bearing 3
24 Replace NDE bearing 3
STATOR
25 Stator rewind 3
26 Replace stator laminations/core 3
27 Treat and paint stator with vanish 3
28 Conduct IR, winding balance test 3
29 Test run for vibrations and current balance test 3
SPECIAL CHARGES
30 Emergency repair charge 3
18. LV Motors, 55kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 6
2 Deliver motor to Camden Power Station 6
3 Open motor, clean and complete assessment report 6
4 Assemble motor 6
5 Treat and paint motor with anti-rust paint 6
TERMINAL BOX
6 Replace terminal box 6
7 Replace terminal box cover 6
8 Replace terminal block and connect windings 6
COOLING FAN
9 Replace cooling fan 6
10 Replace cooling fan key 6
DE AND NDE END SHIELD
42
11 Micro-weld and polish DE bearing housing 6
12 Micro-weld and polish NDE bearing housing 6
13 Replace DE shield 6
14 Replace NDE shield 6
15 Fit DE and NDE grease nipples 6
ROTOR
16 Replace the rotor 6
17 Replace rotor shaft 6
18 Micro welding rotor shaft (DE) 6
19 Micro welding rotor shaft (NDE) 6
20 Balance the rotor with a cooling fan 6
21 Replace Mechanical O' rings DE 6
22 Replace Mechanical O' rings NDE 6
23 Replace DE bearing 6
24 Replace NDE bearing 6
STATOR
25 Stator rewind 6
26 Replace stator laminations/core 6
27 Treat and paint stator with vanish 6
28 Conduct IR, winding balance test 6
29 Test run for vibrations and current balance test 6
SPECIAL CHARGES
30 Emergency repair charge 2
19. LV Motors, 75kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 2
2 Deliver motor to Camden Power Station 2
3 Open motor, clean and complete assessment report (see Attachment 1) 2
4 Assemble motor 2
5 Treat and paint motor with anti-rust paint 2
TERMINAL BOX
6 Replace terminal box 2
7 Replace terminal box cover 2
8 Replace terminal block and connect windings 2
COOLING FAN
9 Replace cooling fan 2
10 Replace cooling fan key 2
43
DE AND NDE END SHIELD
11 Micro-weld and polish DE bearing housing 2
12 Micro-weld and polish NDE bearing housing 2
13 Replace DE shield 2
14 Replace NDE shield 2
15 Fit DE and NDE grease nipples 2
ROTOR
16 Replace the rotor 2
17 Replace rotor shaft 2
18 Micro welding rotor shaft (DE) 2
19 Micro welding rotor shaft (NDE) 2
20 Balance the rotor with a cooling fan 2
21 Replace Mechanical O' rings DE 2
22 Replace Mechanical O' rings NDE 2
23 Replace DE bearing 2
24 Replace NDE bearing 2
STATOR
25 Stator rewind 2
26 Replace stator laminations/core 2
27 Treat and paint stator with vanish 2
28 Conduct IR, winding balance test 2
29 Test run for vibrations and current balance test 2
SPECIAL CHARGES
30 Emergency repair charge 2
20. LV Motors, 90kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 7
2 Deliver motor to Camden Power Station 7
3 Open motor, clean and complete assessment report (see Attachment 1) 7
4 Assemble motor 7
5 Treat and paint motor with anti-rust paint 7
TERMINAL BOX
6 Repair terminal box 7
7 Replace terminal box 7
8 Replace terminal box cover 7
9 Replace terminal block and connect windings 7
COOLING FAN
10 Replace cooling fan 7
11 Replace cooling fan key 7
44
DE AND NDE END SHIELD
12 Micro-weld and polish DE bearing housing 7
13 Micro-weld and polish NDE bearing housing 7
14 Replace DE shield 7
15 Replace NDE shield 7
16 Fit DE and NDE grease nipples 7
ROTOR
17 Replace the rotor 7
18 Replace rotor shaft 7
19 Micro welding rotor shaft (DE) 7
20 Micro welding rotor shaft (NDE) 7
21 Balance the rotor with a cooling fan 7
22 Replace Mechanical O' rings DE 7
23 Replace Mechanical O' rings NDE 7
24 Replace DE bearing 7
25 Replace NDE bearing 7
STATOR
26 Stator rewind 7
27 Replace stator laminations/core 7
28 Treat and paint stator with vanish 7
29 Conduct IR, winding balance test 7
30 Test run for vibrations and current balance test 7
SPECIAL CHARGES
31 Emergency repair charge 7
21. LV Motors, 110kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 9
2 Deliver motor to Camden Power Station 9
3 Open motor, clean and complete assessment report 9
4 Assemble motor 9
5 Treat and paint motor with anti-rust paint 9
TERMINAL BOX
6 Repair terminal box 9
7 Replace terminal box 9
8 Replace terminal box cover 9
9 Replace terminal block and connect windings 9
COOLING FAN
10 Replace cooling fan 9
11 Replace cooling fan key 9
45
DE AND NDE END SHIELD
12 Micro-weld and polish DE bearing housing 9
13 Micro-weld and polish NDE bearing housing 9
14 Replace DE shield 9
15 Replace NDE shield 9
16 Fit DE and NDE grease nipples 9
ROTOR
17 Replace the rotor 9
18 Replace rotor shaft 9
19 Micro welding rotor shaft (DE) 9
20 Micro welding rotor shaft (NDE) 9
21 Balance the rotor with a cooling fan 9
22 Replace Mechanical O' rings DE 9
23 Replace Mechanical O' rings NDE 9
24 Replace DE bearing 9
25 Replace NDE bearing 9
STATOR
26 Stator rewind 9
27 Replace stator laminations/core 9
28 Treat and paint stator with vanish 9
29 Conduct IR, winding balance test 9
30 Test run for vibrations and current balance test 9
SPECIAL CHARGES
31 Emergency repair charge 3
22. LV Motors, 132kW, 380V AC 3PH
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 2
2 Deliver motor to Camden Power Station 2
3 Open motor, clean and complete assessment report 2
4 Assemble motor 2
5 Treat and paint motor with anti-rust paint 2
TERMINAL BOX
6 Repair terminal box 2
7 Replace terminal box 2
8 Replace terminal box cover 2
9 Replace terminal block and connect windings 2
COOLING FAN
10 Replace cooling fan 2
11 Replace cooling fan key 2
46
DE AND NDE END SHIELD
12 Micro-weld and polish DE bearing housing 2
13 Micro-weld and polish NDE bearing housing 2
14 Replace DE shield 2
15 Replace NDE shield 2
16 Fit DE and NDE grease nipples 2
ROTOR
17 Replace the rotor 2
18 Replace rotor shaft 2
19 Micro welding rotor shaft (DE) 2
20 Micro welding rotor shaft (NDE) 2
21 Balance the rotor with a cooling fan 2
22 Replace Mechanical O' rings DE 2
23 Replace Mechanical O' rings NDE 2
24 Replace DE bearing 2
25 Replace NDE bearing 2
STATOR
26 Stator rewind 2
27 Replace stator laminations/core 2
28 Treat and paint stator with vanish 2
29 Conduct IR, winding balance test 2
30 Test run for vibrations and current balance test 2
SPECIAL CHARGES
31 Emergency repair charge 1
3 LV Motors, 220V DC
1. 2 HP, 230V DC- DC Stator Coolant Motor
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 6
2 Deliver motor to Camden Power Station 6
3 Open motor, clean and complete assessment report. 6
4 Assemble motor 6
5 Treat and paint motor with anti-rust paint 6
TERMINAL BOX and BRUSHES
6 Repair terminal box 6
7 Replace terminal box 6
8 Replace terminal block 6
47
9 Repair brush holder and spring 6
10 Replace brush holder and spring 6
11 Replace brushes 6
COOLING FAN
12 Replace cooling fan 6
13 Repair cooling fan 6
14 Replace/ repair cooling fan key and key way 6
DE AND NDE END SHIELD
15 Micro-weld and polish DE bearing housing 6
16 Micro-weld and polish NDE bearing housing 6
17 Fit DE and NDE grease nipples 6
ROTOR/ ARMATURE
18 Replace the rotor 6
19 Replace rotor shaft 6
20 Replace/ repair armature core 6
21 Rewind armature and repair slots 6
22 Replace/ repair commutator 6
23 Replace/ repair laminations 6
24 Micro welding rotor shaft journal and polish (DE) 6
25 Micro welding rotor shaft journal and polish(NDE) 6
26 Balance the rotor with a cooling fan 6
27 Replace Mechanical O' rings DE 6
28 Replace Mechanical O' rings NDE 6
29 Replace DE bearing 6
30 Replace NDE bearing 6
STATOR
31 Rewind Field 6
32 Replace/ repair permanent magnets 6
33 Replace/ repair pole shoe 6
34 Replace/ repair iron core 6
35 Treat and paint field with vanish 6
36 Conduct IR, winding balance test 6
37 Test run for vibrations and current balance test 6
SPECIAL CHARGES
38 Emergency repair charge 3
2. 3 HP, 230V DC- SFPT DC loop oil pump Motor
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 6
2 Deliver motor to Camden Power Station 6
48
3 Open motor, clean and complete assessment report. 6
4 Assemble motor 6
5 Treat and paint motor with anti-rust paint 6
TERMINAL BOX and BRUSHES
6 Repair terminal box 6
7 Replace terminal box 6
8 Replace terminal block 6
9 Repair brush holder and spring 6
10 Replace brush holder and spring 6
11 Replace brushes 6
COOLING FAN
12 Replace cooling fan 6
13 Repair cooling fan 6
14 Replace/ repair cooling fan key and key way 6
DE AND NDE END SHIELD
15 Micro-weld and polish DE bearing housing 6
16 Micro-weld and polish NDE bearing housing 6
17 Fit DE and NDE grease nipples 6
ROTOR/ ARMATURE
18 Replace the rotor 6
19 Replace rotor shaft 6
20 Replace/ repair armature core 6
21 Rewind armature and repair slots 6
22 Replace/ repair commutator 6
23 Replace/ repair laminations 6
24 Micro welding rotor shaft journal and polish (DE) 6
25 Micro welding rotor shaft journal and polish(NDE) 6
26 Balance the rotor with a cooling fan 6
27 Replace Mechanical O' rings DE 6
28 Replace Mechanical O' rings NDE 6
29 Replace DE bearing 6
30 Replace NDE bearing 6
STATOR
31 Rewind Field 6
32 Replace/ repair permanent magnets 6
33 Replace/ repair pole shoe 6
34 Replace/ repair iron core 6
35 Treat and paint field with vanish 6
36 Conduct IR, winding balance test 6
37 Test run for vibrations and current balance test 6
SPECIAL CHARGES
38 Emergency repair charge 3
49
3. 3.7 kW, 230V DC- DC jacking oil pump Motor
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 6
2 Deliver motor to Camden Power Station 6
3 Open motor, clean and complete assessment report. 6
4 Assemble motor 6
5 Treat and paint motor with anti-rust paint 6
TERMINAL BOX and BRUSHES
6 Repair terminal box 6
7 Replace terminal box 6
8 Replace terminal block 6
9 Repair brush holder and spring 6
10 Replace brush holder and spring 6
11 Replace brushes 6
COOLING FAN
12 Replace cooling fan 6
13 Repair cooling fan 6
14 Replace/ repair cooling fan key and key way 6
DE AND NDE END SHIELD
15 Micro-weld and polish DE bearing housing 6
16 Micro-weld and polish NDE bearing housing 6
17 Fit DE and NDE grease nipples 6
ROTOR/ ARMATURE
18 Replace the rotor 6
19 Replace rotor shaft 6
20 Replace/ repair armature core 6
21 Rewind armature and repair slots 6
22 Replace/ repair commutator 6
23 Replace/ repair laminations 6
24 Micro welding rotor shaft journal and polish (DE) 6
25 Micro welding rotor shaft journal and polish(NDE) 6
26 Balance the rotor with a cooling fan 6
27 Replace Mechanical O' rings DE 6
28 Replace Mechanical O' rings NDE 6
29 Replace DE bearing 6
30 Replace NDE bearing 6
STATOR
31 Rewind Field 6
32 Replace/ repair permanent magnets 6
33 Replace/ repair pole shoe 6
50
34 Replace/ repair iron core 6
35 Treat and paint field with vanish 6
36 Conduct IR, winding balance test 6
37 Test run for vibrations and current balance test 6
SPECIAL CHARGES
38 Emergency repair charge 6
4. 15 HP, 230V DC- DC bearing oil pump Motor
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 6
2 Deliver motor to Camden Power Station 6
3 Open motor, clean and complete assessment report. 6
4 Assemble motor 6
5 Treat and paint motor with anti-rust paint 6
TERMINAL BOX and BRUSHES
6 Repair terminal box 6
7 Replace terminal box 6
8 Replace terminal block 6
9 Repair brush holder and spring 6
10 Replace brush holder and spring 6
11 Replace brushes 6
COOLING FAN
12 Replace cooling fan 6
13 Repair cooling fan 6
14 Replace/ repair cooling fan key and key way 6
DE AND NDE END SHIELD
15 Micro-weld and polish DE bearing housing 6
16 Micro-weld and polish NDE bearing housing 6
17 Fit DE and NDE grease nipples 6
ROTOR/ ARMATURE
18 Replace the rotor 6
19 Replace rotor shaft 6
20 Replace/ repair armature core 6
21 Rewind armature and repair slots 6
22 Replace/ repair commutator 6
23 Replace/ repair laminations 6
24 Micro welding rotor shaft journal and polish (DE) 6
25 Micro welding rotor shaft journal and polish(NDE) 6
26 Balance the rotor with a cooling fan 6
27 Replace Mechanical O' rings DE 6
51
28 Replace Mechanical O' rings NDE 6
29 Replace DE bearing 6
30 Replace NDE bearing 6
STATOR
31 Rewind Field 6
32 Replace/ repair permanent magnets 6
33 Replace/ repair pole shoe 6
34 Replace/ repair iron core 6
35 Treat and paint field with vanish 6
36 Conduct IR, winding balance test 6
37 Test run for vibrations and current balance test 6
SPECIAL CHARGES
38 Emergency repair charge 6
5. 20 HP, 230V DC- Turbine DC seal oil pump
Motor
Item Description Unit Rate Price
GENERAL
1 Collect motor from Camden Power station 8
2 Deliver motor to Camden Power Station 8
3 Open motor, clean and complete assessment report. 8
4 Assemble motor 8
5 Treat and paint motor with anti-rust paint 8
TERMINAL BOX and BRUSHES
6 Repair terminal box 8
7 Replace terminal box 8
8 Replace terminal block 8
9 Repair brush holder and spring 8
10 Replace brush holder and spring 8
11 Replace brushes 8
COOLING FAN
12 Replace cooling fan 8
13 Repair cooling fan 8
14 Replace/ repair cooling fan key and key way 8
DE AND NDE END SHIELD
15 Micro-weld and polish DE bearing housing 8
16 Micro-weld and polish NDE bearing housing 8
17 Fit DE and NDE grease nipples 8
ROTOR/ ARMATURE
18 Replace the rotor 8
52
19 Replace rotor shaft 8
20 Replace/ repair armature core 8
21 Rewind armature and repair slots 8
22 Replace/ repair commutator 8
23 Replace/ repair laminations 8
24 Micro welding rotor shaft journal and polish (DE) 8
25 Micro welding rotor shaft journal and polish(NDE) 8
26 Balance the rotor with a cooling fan 8
27 Replace Mechanical O' rings DE 8
28 Replace Mechanical O' rings NDE 8
29 Replace DE bearing 8
30 Replace NDE bearing 8
STATOR
31 Rewind Field 8
32 Replace/ repair permanent magnets 8
33 Replace/ repair pole shoe 8
34 Replace/ repair iron core 8
35 Treat and paint field with vanish 8
36 Conduct IR, winding balance test 8
37 Test run for vibrations and current balance test 8
SPECIAL CHARGES
38 Emergency repair charge 8
NB: Single phase motors and Motors that are not identified in these lists will be discussed and negotiated with the Eskom Contract Manager.
4 Manpower price list: SECTION B
MAINTENANCE TEAM RATES ON SITE
No Labour/ Skills Unit Quantities / No of hours
Rate per Hour
Total prices
1. Supervisor x 1 person hrs 5760 Overtime after hours (1.5) hrs 800 Overtime (2) hrs 600
2. Fitter x 2 employees hrs 11520 Overtime(1.5) hrs 9640 Overtime(2) hrs 6040
3. Semi-Skilled x 2 employees
hrs 11520
Overtime(1.5) hrs 9640 Overtime(2) hrs 6040
4. Trade Assistant x 2 employees
hrs 11520
53
Overtime(1.5) hrs 7200 Overtime(2) hrs 5040
5. Standby allowance (Fitter & Semi-skilled) per month
Month 36
6.1 Travelling per kilometre (standard car)
km 36000
6.2 Travelling per kilometre (LDV-bakkie)
km 50868
7. Non-stock LV Motor repairs/m each ---------------------------------------------------------------------------------------------------------------- ----------------------- Notes:
Only Fitter and semi-skilled personnel allowed to work stand-by.
1st call-out made/emergency call out, four hours will be a time to be booked even if the work done during call-out is less than four hours. Second, third call, actual hours shall be booked as they are.
If the work exceeded four hours of the first call, the actual hours worked will be booked.
Hours worked under emergency will be paid only if there is emergency call out form sign by EOD
Time sheet will be used to monitor the time worked and it’s the supervisor responsibility to ensure that they are submitted to the contract Manager every week for approval. It will be used for monthly assessment.
Transport rate will be based on maximum of 44 km return trip (Ermelo to Camden Power Station).
The above quantities are based on estimated requirements.
5 Description of the service
5.1 Executive overview
The Works covers Maintenance, transportation to and from Camden Power station, stripping, assessment, refurbishment, testing, supply of test certificates and other related Documents for refurbished HV and LV Stock and Non-stock Motors. The works shall be accomplished with minimum sub-contracting to reduce make-up pricing and extended warranty delays. Camden P/S will shut-down as instructed by the Executive because of life time, it shall be communicated in advanced and this agreement/ partnership will stop.
5.2 Employer’s requirements for the service
The Works covers Maintenance, transportation to and from Camden Power station, stripping, assessment, refurbishment, testing, supply of test certificates and other related Documents for refurbished HV and LV Stock and Non-stock Motors. The works shall be accomplished with minimum sub-contracting to reduce make-up pricing and extended warranty delays.
The Employer has limited design information on the old type motors. The Contractor shall obtain all the design and manufacturing details required for the Works. On completion of the Works, motors shall be delivered to and off-loaded at Camden Power Station Main stores (or venue preferred by the employer).
1.1. The preliminary scope of work covered by this contract is as follows:
1.1.1. Transportation of motors from Camden Power station to the contractor’s works and back to site at Camden Power Station after completion of works. The Supplier accepts full
54
responsibility for the motor/s when the motor/s is handed over to the Supplier on site to be transported from Camden site for refurbishment. Any additional damage during transport or during the stripping, testing, assessment, refurbishment and re-assemble will be for the Supplier’s account and could include the cost for a new motor in the worst case scenario.
1.1.2. Strip the motor and mark all parts with unique relevant job number 1.1.3. Do a full assess of the motor condition, and complete the assessment sheet, ensuring
that any evidence of failure or deterioration is kept for review by the employer, if not present during assessment.
1.1.4. The complete Assessment report will determine the detailed scope of work for refurbishment; refer to HV Motor Assessment Form.
1.1.5. Execute the scope of work on each individual motor as approved by the Employer, including the relevant Engineering work as defined in paragraph 1.6. Ensure that quality management is incorporated in refurbishment process as defined in approved Process Quality Plans (PQP’s) between the Contractor and Eskom.
1.1.6. Should the motor be found to be beyond repair, and the employer concurs with the finding, the contractor will be informed to re-assemble the motor and return the motor to Camden Power station accompanied by a full breakdown report on the findings and motivation for the beyond repairs status.
1.1.7. Where additional tests or work not covered by the contract is required from the motor assessment, a quotation must be submitted to Camden Power station before any commencement of such tests or activities for approval.
1.1.8. The employer reserves the right to do price matching of any additional work specified in the assessment report, with the intent to ensure that the pricing is market related.
1.2 The motors covered by this contract are as indicated on the Motor price lists
The works are to be carried out at the contractor’s workshop and on-site by maintenance team at
Camden on all HV Motors AND LV Motors, stock and Non-stock. The Motor price list has been given for the purpose of quoting.
2. CONTRACT REQUIREMENTS & SPECIFICATION 2.1 Dismantling
Dismantling of the motor should not commence until the required checks and test have been physically carried out by the repairer and accepted by the Eskom representative as per assessment form.
2.2 Testing, Tools
All tests, inspections, repairs and measurements must be done by qualified, competent persons and must have sound years of experience. All testing equipment, tools and other respective accessories must be calibrated according to SANS, SANS, IEC and ISO standards and have valid calibration certificates. The Contractor will be informed by the Contract Manager on an “as and when” required basis to assist with Motor investigations on site.
2.3 Invoicing
Quotation with full SOW must be accepted and signed by the employer before commencing with the repairs.
Failure report Data pack must be submitted to the employer upon delivery of the motors. Invoices to be paid on the month must be submitted to Contract Manager before the 20
th of
each month.
55
A WARRANTY will be repaired at NO cost to Camden Power Station.
A GUARANTEE will be repaired at NO cost to Camden Power Station
2.2.1 Tests to be performed at the repair workshop before disassembly and after assembly.
The high voltage tests will only be performed after the stator has passed the polarization index test. (High voltage tests are subjected to employer’s request or approval as indicated on Motor price list “as and when required tests”) Tests to be performed after repairs.
STATOR TESTS
Stator winding insulation resistance
Stator winding polarization index
El-Cid
Tan delta
PT100 insulation resistance
Space heater insulation resistance ROTOR TEST
Bar to bar continuity test
El-Cid test
HEAT RUN TEST AND MEASUREMENTS
Bearing insulation test
Bearing heat run test
No load test run
Current balance between phases
Power at no load
Bearing vibration tests and vibration acceptance testing.
Bearing temperatures
Power factor at no load (duty point)
Start up and run down time (Motor uncoupled) 2.2.2 Vibration testing and analysis scope of work: The following services and specifications must be adhered to and be provided by the motor repairer and motor supplier: ACCEPTANCE TESTING PROCEDURE AND REQUIREMENTS:
With every vibration test, a test certificate and a report containing complete analysis and recommendations must be completed, signed by repairer’s QC before handing to the employer. The motor must be tested at a correct rotational direction when loaded at Camden.
All tests and measurements must be done by a qualified, competent person and must have sound years of experience.
Vibration phase analysis (Phase relationship testing) must be conducted during acceptance testing. The result must also reflect on the test report and certificate.
Overall magnitude of vibrations generated (all directions i.e. vertical, horizontal and axial movement) within the motor when running on their own shall not exceed the values specified below:
56
6 pole and 8 pole – 1mm/sec 4 pole – 1.5 mm/sec 2 pole – 2 mm/sec
With every vibration test certificate, a schematic or sketch of the machine or equipment must be supplied. The following will be indicated:
- Measurement locations. - The measurement locations shall be numbered
With every vibration test certificate, a machinery data sheet must be completed, signed and supplied.
The data sheet must have the following parameters:
- RPM minimum. - RPM maximum. - Manufacturer. - Serial number. - Frame size. - AC or DC. - Voltage. - Phase. - Amperage - Kilowatt or Horsepower. - Number of rotor bars. - Number of motor fan blades. - Number of drive end bearings. - Drive end bearing model. (If it is a sleeve bearing indicate by writing “Sleeve”) - Drive end bearing manufacturer. - Number of non - drive end bearings. - Non drive end bearing model. (If it is a sleeve bearing indicate by writing “Sleeve”) - Non drive end bearing manufacturer. - Type mounts the unit are on.
Obtain or calculate the major component forcing frequencies i.e. bearing defect frequencies, blade/vane pass frequencies, pole passing frequencies and rotor bar frequencies.
Prior the final acceptance testing is performed, the following must be done:
- Use the correct instrumentation, vibration transducer, mounting method and cabling. - List the machine details, measurement point information, location and orientation on
the vibration test report - The vibration analyser and data collector should have a minimum frequency resolution
of 3.75 CPM/Line (.0625 Hz/Line) and minimum dynamic range of 72 dB.
- While vibration testing is being conducted and on the test reports and certificates 30,000 CPM (500Hz) must be used for the spectrum.
- Refer to the specifications and recommendations of the vibration transducer OEM for
the correct frequency response range. - Cables and their individual connectors must be in a good condition.
57
- Cables and their respective connectors must not introduce distortion on the pick-up signal.
- Make sure that the transducer is securely mounted.
- The contact surfaces of both the motor and the vibration transducer must be free of
foreign materials.
- The vibration analyser’s sampling time setting for the time waveforms must be 10 revolutions of the shaft of the specific motor.
- Vibration data for machine certification and acceptance in the following measurement
units as shown in Frequency (Hz), Rotational speed (RPM), Velocity (RMS) mm/sec.
- The motor to be tested for vibration must be mounted on a T-slotted steel block. The T-slotted steel block must be isolated from the floor and other nearby equipment that is operating must be switched off during testing to avoid interference. Other equipment’s vibration must not interfere with the machine being tested.
- The motor must run until it attains its stabilised speed and operating temperature.
- Load test the motors as per Contract Manager Instructions. AC induction motors must
be loaded 70% of full load or higher, except if it is stated otherwise by the Contract Manager.
- The following specific frequencies’ vibration results must be supplied via spectrums
and values (mm/sec) and recommendations thereafter.
i) AC Motors:
For AC induction motors under a minimum of 70% of full load, the Pole Pass Frequency Sidebands.
Two times line frequency.
Rotor bar passing frequency. ii) DC Motors:
SCR firing frequency.
Line frequency harmonics.
- The contractor must analyse vibration test results and give simplified recommendation
2.2.3 Bearing temperature acceptance criteria
1. - The acceptance criteria for bearing temperature rise when thermal equilibrium has been
reached are;
2. A.1 Ball and Roller Bearings;
3. A.1.1 35°C on motors with 4 or more poles
4. A.2 Sleeve and Tilting Pad/ white metal Bearings;
5. A.2.1 35C for vertical motors when measured on thrust pads,
6. A.2.2 30C for motors with shaft diameter less than 70 mm,
58
7. A.2.3 40C for 2 and 4-pole motors with shaft diameter between 70 and 100 mm,
8. A.2.4 30C for 6-pole and 8-pole motors with shaft diameter between 70 and 100 mm,
9. A.2.5 45C for 2 and 4-pole motors with shaft diameter between above 100 mm,
10. A.2.6 35C for 6-pole and 8-pole motors with shaft diameter above 100 mm,
11. Magnetic centre of the sleeve bearing type must be clearly marked and have a solid pointer. Magnetic centre mark shall be at the centre of both DE and NDE thrust marked on the shaft( 50%-50% / 60%-40%).
12. During solo run the bearing temperature differences shall be less than 10C
2.4 Engineering Services as Required by Eskom Generation Standard
The contractor is responsible for engineering services, material and labour as follows:
2.3.1. Verify the performance matching requirements of the power supply and driven machine. 2.3.2. Inspection and testing of the motor prior to and after repairs, recording, reporting and
making recommendations and providing the necessary information where applicable.
2.3.3. The contractor is required to provide detailed breakdown report for each motor stating clearly the contributory and root causes of motor failure.
2.3.4. Evaluate all parts for possible re-use. 2.3.5. Select, design and procurement of new components, ensuring that replacement
insulation system and other material are compatible with the existing materials. If the replacements parts are not exactly as the originals, the contractor demonstrate that the replacement meets or exceeds the capability of the original in all essential requirements.
2.3.6. The contractor must ensure that the employer and others required are present during dismantling, testing and assessment to inspect any evidence of failure or aspects of defective design or workmanship uncovered. Ensure that correct photographic records and history of each Motor as per Serial No’s are made and be available when requested by the employer.
2.3.7. Establish the suitability of the motor for rewinding to achieve the life extension required
by the Employer. Perform all tests, investigation and calculation required for these purpose.
2.3.8. Shall eliminate weaknesses. Submitting a written report recording the defects, and
detailing the extent of repair and work required to achieve the life extension specified by the Employer. Obtaining the Employer’s prior agreement in writing for the extent of repair and work to be done.
2.3.9. Design replacement stator windings when necessary or specified, with the required
wedging and coil end-winding support systems, including means of tightening if looseness develops. The means of tightening is agreed with the Employer.
2.3.10. The test facility shall comply for stator temperature monitoring, on-line partial discharge
monitoring, 2.3.11. Where changes to the design or rating are necessary, carrying out design review and
validation of the rating and suitability of the motor for the applicable environment and
59
cooling arrangements. Where changes are introduced, carrying out design calculations of motor capability and appropriate settings for over current protection, repeated start protection, stall protection, voltage unbalance protection, and other protection applied or required. Submission of design results and proposed protection settings to the Employer for agreement.
2.3.12. Where changes to the design are made, producing details of the design, working
drawings, repair and rewinding instructions and procedures, as well as all necessary amendments to operating and maintenance manuals; producing agreed procedures for works inspection and tests, and site commissioning and testing, all with details of acceptance criteria to be attained. Producing reports or test certificates detailing actual results attained. Producing quality plans for the activities concerned before commencing work. Producing progress reports on a Micro-soft project as required periodically by the Employer.
2.3.13. Submit details of the redesign and all drawings and documentation in quadruplicate to
the Employer for agreement. 2.3.14. Produce a consolidated report on all aspects of the work, incorporating all reports, data,
acceptance criteria, and quality assurance records. 2.3.15. White Metal bearing Manufacturing Company used must be competent, registered and
have a good track record. A bearing test Certificate to be provided for every manufactured white metal bearing.
2.3.16. Provide complete vibration analysis for factory acceptance testing.
2.3.17. The repairer must keep record of each motor Serial No repaired and shall be requested by the Employer at any time.
5.2.1 Site Maintenance Services
2.4.1 Purpose/Activities • Inspection, all maintenance activities and repair of all motors. 2.4.2 PSR Authorization • The contractor must be authorized within three months of the contract in terms of PSR (LV) to be
able to perform the following activities covered in a scope of work. If all employees of the contractor are not authorized in terms of PSR a deduction of 10% from the monthly maintenance invoice shall apply thereafter.
2.4.3 Daily Inspection and Maintenance • Inspect and repair bearings, breathers for oil leaks – record current readings • Take Temperatures and keep records. – Record and/or report excessive noise. • Keep correct oil levels, repair oil leaks and fill up where necessary, The Daily inspection sheet
must be completed, analysed by the Supervisor and filed for record purposes • Record winding temperatures (RTD’s). • Attend day to day notification created against, close and give them to relevant planner for
processing. • Do daily plant walk before knock-off time and load defects where necessary. • Attend all daily meeting necessary. • Adhere and attend all standby duties, call-outs during and after hours. • Assist in Collection and repair LV and HV motors under emergency / normal conditions
60
• Take LV motor to and from the base plate. Clean dust from all motors to enhance air circulation. • Maintain and repair LV and HV motors bearing when required. 2.4.4 Weekly maintenance • Record all defects and compile SOW for weekend outage and other opportunities to be corrected. • Monitor bearing temperature trend and correct the problem, keep records of what was done. • Monitor winding temperature trend, vacuum stator and check air suction. • Adhere to weekly maintenance program, PM’s, plan for Lockdown and close lockdown work and
defects on time. 2.4.5 Monthly maintenance • Ensure that all bolts are tightened i.e. Motor hold down, bearing housing where possible • Adhere to Monthly maintenance program • Dust proofing of motors • Visual inspection and recording of any defects on LV and MV motors • Record casing and bearing temperatures by the use of Laser thermometers if possible/ needed. • Check that covers are intact and suction air is free from obstruction. • Check that the earths are intact and repair if necessary. • Attend all monthly PM’s, close and give them to relevant planner • Attend the monthly greasing program & shaft rotation program • Check and plan in the meeting for the Unit that needs to be flushed in that month • Clean LV and HV motors 2.4.6 Pre-planned maintenance (Pre-outage Inspection for SOW) • Inspected and record outage related defects and must form part of an outage scope of work • Plan for the resources needed for outage prior to outage. • Compile outage SOW and execute as planned 2.4.7 Planned maintenance (Outage scope) • Do repairs on all the defective motors • Correct all problems identified before and during the outage for the unit to synchronize on time • Open all white metal bearings and clean them, repair bearings when needed • Inspect bearing clearances, journals for any damages and for any changes in sizes • Drain, clean and refill bearing with new oil • Do Bearing resistance tests and record when possible. • Clean heat exchanger pipe work and dust out of the motor stator • Tighten fixing bolts, coupling guards, cooling water pipe on the motor. • Assist in mounting and dismounting Terminal boxes, Re-install Porcelain glasses. • Inspect motors for corrosion. • Check resistors for burning on DC Motors and repair where it is due. • Check and replace the brushes on DC motors where necessary. • Clean carbon dust on DC motors with compressed air. 2.4.8 Post-planned outage • Compile a report for all the activities done in an outage and keep record (filed). ITP must be available and approved first for all critical jobs to be done. • Keep test Certificates available on request.
2.4.9 LV Motor and HV Motor repair delivery duration. 2.4.9.1 i. The LV Motor sent under emergency repairs must be delivered back within 24 Hrs/ 36 Hrs
the latest to clear the load loss earlier.
61
ii. The LV motor sent under normal repairs should be delivered back within 5 days. iii. If the Motor is unrepairable, the Eskom motor replacement flowchart must be followed and a full assessment must be done, agreed and signed. The un-repairable Motor should be delivered back to Camden together with the replacement Motor. See below flowchart.
ESKOM MOTOR REPAIR VS REPLACEMENT FLOWCHART
62
NOTE: IF THE ESKOM MOTOR REPAIR VS REPLACEMENT FLOWCHART WAS USED TO ESTABLISH WHETHER A
MOTOR MUST BE REPLACED OR NOT, AND IT IS ESTABLISHED THAT THE MOTOR MUST BE REPLACED, THE
DECISION TO SOURCE OR NOT TO SOURCE A MOTOR FROM THIS CONTRACT WILL REST WITH THE CONTRACT
MANAGER. I.E. TO BE REPLACED FROM THE CONTRACT OR FROM A SEPARATE ORDER NUMBER. 2.4.9.2 i. The HV motor should be stripped immediately when reaching the contractors site (Camden
Motors shall take precedence from other repairs)
63
ii. Delivery of an HV motor should be within 7 weeks after instruction to commence major
repair work (Rotor Re-bar, Stator Rewind) from Employer (Order Number given – Normal Repair Request).
iii. Delivery of an HV motor should be within 6 weeks after instruction to commence major
repair work (Rotor Re-bar, Stator Rewind) from Employer (Order Number given – Emergency Repair Request).
iv. Delivery of an HV motor should be within 2 week after instruction to commence minor
repair work (Low PI, bearings, ash removal from windings) from Employer (Order Number given – Normal Repair Request).
v. Delivery of an HV motor should be within 2 days after instruction to commence minor
repair work (Low PI, bearings, ash removal from windings) from Employer (Order Number given – Emergency Repair Request).
2.4.1. Test Certificate
• Complete motor tests and Certificates must be submitted with the LV motor upon delivery.
. Complete motor tests and Certificates must be submitted with Data pack of the HV motor upon delivery
• Delivery Notes must be signed by the relevant Eskom personnel. 2.4.11 House keeping • All work places must be kept clean at all times not Interface with other contractors
2.4.12 Training • All relevant courses must be attended as required on contractor’s account. • The Employer shall only be responsible for PSR Regulation on site 2.4.13 Safety Risk management • Risk assessment must be done prior to performing any task • Barricading and demarcation must be maintained when safety related work is to be performed
2.4.14 Completion Communication • Completed task must be communicated to Contract Manager and to Operating when needed. 2.4.15 Meetings • All relevant meetings must be attended by contract Manager.
2.4.16 Tools • Contractor must provide sound original tools to the Maintenance team. • All tools that need certificates must have valid certificate to comply with safety.
2.4.17 PROGRAM 3.1 A detailed program should be provided preferably in the form of Micro-soft project with bar-chart
or any software that will specify the plan and progress of HV motor repairs. 3.2 A program detailing up to the delivery date must be drafted after an Assessment has been done
and agreed upon with the Client.
64
6 Management strategy and start up.
6.1 The Contractor’s plan for the service
THE CONTRACTOR SHALL BE AUTHORIZED WITHIN THREE MONTHS IN TERMS OF PSR TO WORK
INDEPENDENTLY OTHERWISE 10% WILL BE DEDUCTED FROM MONTHLY GROSS MAINTENANCE INVOICE.
6.2 Management meetings
Monthly meetings shall be attended monthly as per NEC where contract related issues shall be discussed in details with due dates agreed. This meeting shall take place before the 25
th of each
month, assessment should also be signed. Minutes of the meeting shall be compiled by the contractor and submitted to the Contract Manager within five days of the meeting for verification and adoption. Actions shall be adhere to as per due dates specified. All meetings shall be recorded and minutes circulated such minutes shall not be used for issuing instructions under the contract.
6.3 Contractor’s supervision and key people
All tests, inspections, repairs and measurements must be done by qualified, competent persons and must have sound years of experience or at least more than three years doing that work physically. Supervisor and Fitters for site maintenance as a minimum must have a Trade test with experience of more than two years working with Motors as a requirement. Technical Competence Certificate will be required by the employer for any skill provided to execute the given scope of work and this includes proof of courses attended. The employer may verify the qualification when feels needed. Semi-skills must have two years and above working with Motors.
All relevant courses must be attended as required and special PPE such as Arc-flash suit will be on contractor’s account. The Employer shall only be responsible for PSR Regulation on site.
6.4 Provision of bonds and guarantees
Where Guarantees and Warrantees are applicable, it must be stipulated clearly in writing.
6.5 Documentation control
All documents linked to a failure shall reflect a Document unique number in each page where there is a change, a revision number shall also reflect. A contractor shall keep the hard copy and an electronic copy be available on request. All critical communication shall be formal. The following minimum documents must be supplied to the Employer for each motor that is sent for repairs
2.5.1 Electrical and mechanical assessment performed before repairs. 2.5.2 Detailed report for each motor 2.5.3 Certificates and tests results 2.5.4 Signed Quality Control Plan/ ITP’s etc
Also the Employer may wish to exercise constraints or include witness and hold points during manufacture, assembly, test run until to the delivery of such Equipment. Eskom representative shall be available for hold and witness points OR it should be authorised in writing before the contractor can continue.
65
6.6 Invoicing and payment
Once the item is delivered after the repairs the Contractor shall provide the Employer with a tax invoice showing the amount due for payment equal to that stated in the Contract Manager’s assessment form for payment certificate. This shall be provided on monthly meetings. The Contractor shall address the Copy tax invoice to Eskom Holdings SOC Ltd Camden Power Station Private bag X 1002 NUCAM 2355 Name and address of the Contractor and the Service Manager; The contract number and title; Contractor’s VAT registration number; The Employer’s VAT registration number 4740101508; Description of service provided for each item invoiced based on the Price List; Total amount invoiced excluding VAT, the VAT and the invoiced amount including VAT; (add other details as required by Finance department) The invoice must be submitted in a form of an original hard copy to Eskom Finance department and as a copy to the contract Manager.
6.7 Contract change management
N/A
6.8 Records of Defined Cost to be kept by the Contractor
N/A
6.9 Insurance provided by the Employer
N/A
6.10 Training workshops and technology transfer
The contractor will train student as requested by the employer
6.11 Design and supply of Equipment
As per paragraph 3.5 above
6.12 Things provided at the end of the service period for the Employer’s use
6.12.1 Equipment
All equipments unrepairable and equipments repaired are part of Eskom’s asset shall be return to Eskom before the end of the contract.
6.12.2 Information and other things
Failure data base or Failure history should be provided as and when required and at the end of the service period
66
6.13 Management of work done by Task Order
Maintenance Task Order Number shall be provided by the Employer in the beginning of each the month and it shall be closed with an assessment which will be signed by both parties before the end of the month. Any stock item motor failed will be collected when an Order No is issued by the Employer, the order will only be closed when the item is delivered back to Camden and Quality checked.
7 Health and safety, the environment and quality assurance
7.1 Health and safety risk management
Risk assessment must be done prior to performing any task Baseline risk assessment to be submitted as part of SHE profile for evaluation
7.2 Environmental constraints and management
The contractor to comply with the following requirements and legislation: -Occupational Health and Safety Act 85 of 1993 as amended and its regulations -Compensation for Occupational Injuries and Diseases Act 130 of 1993 as amended -National Environmental Management Act 107 of 1998 as amended -National Environmental Waste Act 59 of 2008 as amended -National Water Act 36 of 1998 as amended -Eskom procedures and safety requirements set out in safety, health and environmental
specifications 004 4830 - Eskom procedure 32-95 in regards with the management of safety, health and environmental incidents -Any other act or procedure deemed necessary or applicable
7.3 Quality assurance requirements
The Contractor shall implement and maintain a Quality Management System that, as a minimum meets the requirements of ISO 9001 series and the Business Excellence Quality Management Standard for Refurbishment, Engineering, Manufacturing & Maintenance Works for Camden Power Station (Doc No: 004/5602). 3.3.1. Contractor’s Quality Assurance and Quality Control
The Contractor compiles, in conjunction with the Employer and the Supervisor, a product
verification plan. This document shows at which stages during the contract involvement is required, and what types of inspection, testing, hold, witnessing etc. are carried out to ensure that the requirements of the specifications are met
3.3.2. Quality Control Plan
The Quality Control Plan, which should be based on an agreed Quality Control Plan between
Eskom and the Contractor. The Quality Control Plan consists of the following as a minimum and is accepted by the
Supervisor and the Contractor prior to commencement of the work. - A covering page which includes and makes provision for the following:
Document unique number. Revision number. Page number Provision to incorporate all inspection report numbers. System worked on
67
High level description of work execution Provision for review and approval signatures by the Contractor, the Employer
Representative and Relevant Engineers. Provision for final releases signatures by the Contractor, Employer
Representative and the Relevant Engineers. - A page which includes a logical sequence of work execution, but not detailed.
Abbreviations. Record numbers. Procedure numbers. Reference document numbers. Certificate numbers and references.
- The work execution logic and sequence for the fabrication and erection addition to this hold, witness points etc. are also detailed.
- A material summary list which includes: Material quantities and specifications. Material certificate numbers.
3.3.3 Test reports
Where tests were performed they are recorded and the positions of measurements are traceable
to the specific area of testing against the records. Factory Acceptance Testing certificates to be submitted upon delivery of motor to site.
8 Procurement
8.1 People
8.1.1 Minimum requirements of people employed
The Contractor applies for access permits (Contractor’s permit) at the Security gate on the start date of the contract. The Contractor personnel shall be required to be in possession of an access permit at all times. In order to assist Protection Services with the issuing of permits and the identification of personnel on site the successful contractor is to supply a list of all personnel that intends using on site, at least 72 hours prior to entry of the Security Area. This list must be delivered to Protection Services. The list, identified with the Contractor's name, is to contain the following minimum information:
Employee name
Employee ID Number
The Employer’s Safety Coordinator’s signature
Electrical Maintenance Manager signature
Copy of the ID book for every employee of the Contractor Access permits must be returned to protection services when the worker/s leave the site, either after completion of the services, or upon earlier termination of service of a worker during the contract period. To speed up the process of gaining access to the site, the Contractor must compile detailed lists of all tools and equipment (including serial numbers where applicable) to be taken on site before arriving at the Power Station Security gate. An authorised copy of this list must be retained by the contractor - to be used again when the tools and equipment are removed from site after the completion of the services. Any additional tools or equipment brought to site, or any tools or equipment removed during the contract period must be reported to protection services and all lists amended likewise. Gate release permits will not be issued for the removal of any tools or equipment not specified on the tool list.
68
The Contractor's visitors and all personnel shall conform at all times to the security arrangements in force at the site. Application forms for visitors must be filled in by the Contractor's Site Manager and approved by the Service Manager, one day before the visit and submitted to the Employer's Protection Services office. Visitors will not be allowed on site if the necessary forms are not in the possession of the security staff. The Chief of Protection Services may, with valid cause, remove any, of the Contractor's personnel from the site, either temporarily, or permanently. He may deny access to the site to any person whom, in the opinion of the said Chief of Protection Services, constitutes a security risk. No unauthorised vehicles will be allowed on site. Only Contractor's Vehicles with displayed Contract Vehicle Permits disks will be allowed on site. Contract Vehicle Applications should be directed to the Service Manager. The Contractor will be restricted to the working areas associated with his place of work. The Contractor is forbidden to enter any other areas, and must ensure that his employees abide by these regulations.
8.1.2 BBBEE and preference scheme
As stated in this contract
8.1.3 Accelerated Shared Growth Initiative – South Africa (ASGI-SA)
The Contractor complies with and fulfils the Contractor’s obligations in respect of the Accelerated and Shared Growth Initiative - South Africa in accordance with and as provided for in the Contractor’s ASGI-SA Compliance Schedule stated below
The following ASGISA requirements
Criterion Weight %
Target % Proposed Offer
Score
BWO (From Eskom Vendor list)
Local Content (Mpumalanga Province)
Skills development
Total
Notes: BWO - From Eskom Vendor list The supplier that will be counted as Black woman owned business should be registered with Eskom Vendor management. Local Content (Mpumalanga Province) The local content should be spent to any business in Mpumalanga preferable Ermelo and surrounding areas. Skills development The contractor should train at least two students or unskilled labours from previously disadvantage background within the contract period. At end of the contract the trained employee should have at least be fully qualified Artisans or Technicians.
69
For tender purposes the contractor should complete the ASGI-SA table above and submit their proposals on how they can achieve the proposed targets.
Should the contractor fails to comply to the requirements, the penalty of 2 % of the contract value will be deducted from the assessment made at completion of the contract period. The Contractor shall keep accurate records and provide the Service Manager with reports on the Contractor’s actual delivery against the above stated ASGI-SA criteria in the formatted to be stated by the employer. The Contractor’s failure to comply with his ASGI-SA obligations constitutes substantial failure on the part of the Contractor to comply with his obligations under this contract.
8.2 Subcontracting
Sub-contracting is minimum allowed but not on critical items because of warranty/ guaranty conclusion delays. Local suppliers must be considered for ASGI-SA purposes.
8.3 Plant and Materials
8.3.1 Specifications
Contractor must provide tools and PPE to the Maintenance team All tools that need certificates must have valid certificate to comply with safety NORMATIVE REFERENCES, STANDARDS, PROCEDURES, SPECIFICATIONS TO BE USED.
The following technical specifications, standards and procedures and their normative references are applicable to this contract. The following specifications, standards and procedures and their normative references are part of this Contract Works Information and are to be read in conjunction with this document. Only the latest revisions of the specifications, standards and procedures and their normative references to be used. The Contract Works Information is not limited by the following specifications, standards and procedures and their normative references. New or additional specifications, standards and procedures and their normative references may be added to the following list at any given time by the Contract Manager. Eskom related specifications, standards and procedures and their normative references are available on request from Eskom. All other technical specifications, standards and procedures are available from the original compiler i.e. IEC, IEEE, SANS etc. The cost of obtaining these specifications, standards and procedures and their normative references, except Eskom technical specifications, standards and procedures, are on the Contractor’s account. The requirements of the Eskom technical specifications, standards and procedures take precedence over the requirements of normative references and other specifications mentioned in this document. Note that where a conflict arises between any of the specifications, standards and procedures and their normative references, mentioned in this document, the IEC documentation has precedence, except over Eskom technical specifications, standards and procedures.
70
TITLE DOCUMENT NUMBER
Eskom Camden Motor Installation, Alignment and Magnetic Centre Determination Rev 0
229 -12158
Eskom Camden LV Motor Overhaul Rev 0 229 - 11683
Eskom Camden Maintenance of LV DC Motors Rev 0 229 - 11708
Eskom Refurbishment of Power Station Electric Motors GGS 0389
Eskom Power Station Electrical Motor Procurement GGS 0802
Eskom Storage of power station electric motors 36 - 396
Eskom Transportation of power station electrical motors 36 - 397
Rotating electrical machines Part 5: Degrees of protection provided by the integral design of rotating electrical machines (IP code) – Classification-IEC
IEC 60034-4:2008, IDT, ED. 3
Eskom Re-Metalling White Metal Bearings GGSS0526
White metal designated WM 90 SANS124
Guide for diagnostic field testing of electric Power apparatus- Electrical apparatus
IEEE STD 62.2
Rotating electrical machines. part 1, rotating and performance IEC 60034-1
IEEE Recommended Practice for Testing Insulation Resistance of Rotating Machinery
IEEE STD 43-2000
Requirements for Clean Condition & Access control during manufacturing, maintenance &repair of generators & large motors.
GGS 0393
71
8.3.2 Correction of latent defects
At least a twelve (12) month guarantee must be offered on workmanship and (18) months when stored properly. Guarantee and warrantee terms must be stated clearly in the quotation provided.
The contractor’s guarantee and warrantee starts the day when the item is delivere.
The contractor must state any guarantee limitations or other requirements from Camden P/S’s side that may influence the guarantees given.
A WARRANTY will be repaired at NO cost to Camden Power Station. A GUARANTEE will be repaired at NO cost to Camden Power Station.
8.3.3 Contractor’s procurement of Plant and Materials
Where a contractor buys an item from another supplier there should be a warranty/ guaranty that will be transferred to the employer.
8.3.4 Tests and inspections after stripping and before delivery
The repairer invites Camden personnel to inspect the motor and agree with the assessment report, the following should be ready. All motor components kept on one unique area at the repairer’s workshop. Any communication and arrangement for inspections at the Contractor’s premises to be
arranged through the Employers Representative or be copied on the e-mail. The motor should be fully assessed by the repairer before Camden personnel (Electrical
Engineering, Electrical Maintenance and Mechanical Engineer) are called out. Invite / notify Camden personnel at least 5 days before inspection. Pictures of all defective components to be taken and handed over to Camden on request The proposed repair scope of work should be ready and shall be finalized with Camden
personnel on the same day of assessment / inspection. The preliminary quotation to be ready on the day of inspection and should reflect the item
numbers and price as agreed on the contract (Camden personnel might/ might not agree with the quote).
All additional items that are not included on the contract (The contractor should advice to close gaps on the contract prices before it is signed) prices should be included on the price column of the quotation and indicated as such.
No quotations shall be blank. All quotation must be signed/ approved in writing before continuing with work. All quotations shall be verified by Electrical Engineering, Electrical Maintenance/ Mechanical
Engineer or anyone in a good position to do so. No work shall commence before approval or a go ahead from the Employer’s Representative
or the personnel acting on his behalf (Contract Manager). In an event of a WARRANTY the contractor shall carry all costs of repairs, tests,
transportation etc.
8.3.5 Plant & Materials provided “free issue” by the Employer
Consumables which are stock items shall be provided by the Employer and those non-stock the contractor will provide.
9 Working on the Affected Property
PSR regulation shall apply when work is to be done in the plant.
72
9.1 Employer’s site entry and security control, permits, and site regulations
The Contractor applies for access permits (Contractor’s permit) at the Security gate on the start date of the contract. The Contractor personnel shall be required to be in possession of an access permit at all times. In order to assist Protection Services with the issuing of permits and the identification of personnel on site the successful contractor is to supply a list of all personnel that he intends using on site, at least 72 hours prior to entry of the Security Area. This list must be delivered to Protection Services. The list, identified with the Contractor's name, is to contain the following information:
Employee name
Employee ID Number
The Employer’s Safety Coordinator’s signature
Electrical Maintenance Manager signature
Copy of the ID book for every employee of the Contractor Access permits must be returned to protection services when the worker/s leave the site, either after completion of the services, or upon earlier termination of service of a worker during the contract period. To speed up the process of gaining access to the site, the Contractor must compile detailed lists of all tools and equipment (including serial numbers where applicable) to be taken on site before arriving at the Power Station Security gate. An authorised copy of this list must be retained by the contractor - to be used again when the tools and equipment are removed from site after the completion of the services.
Any additional tools or equipment brought to site, or any tools or equipment removed during the contract period must be reported to protection services and all lists amended likewise. Gate release permits will not issued for the removal of any tools or equipment not specified on the tool list. The Contractor's visitors and all personnel shall conform at all times to the security arrangements in force at the site. Application forms for visitors must be filled in by the Contractor's Site Manager and approved by the Contract Manager, one day before the visit and submitted to the Employer's Protection Services office. Visitors will not be allowed on site if the necessary forms are not in the possession of the security staff. The Chief of Protection Services may, with valid cause, remove any, of the Contractor's personnel from the site, either temporarily, or permanently. He may deny access to the site to any person whom, in the opinion of the said Chief of Protection Services, constitutes a security risk. No unauthorised vehicles will be allowed on site. Only Contractor's Vehicles with displayed Contract Vehicle Permits disks will be allowed on site. Contract Vehicle Applications should be directed to the Service Manager. The Contractor will be restricted to the working areas associated with his place of work. The Contractor is forbidden to enter any other areas, and must ensure that his employees abide by these regulations.
9.2 People restrictions, hours of work, conduct and records
Lunch time is between 12:00 until 12:45, the Contractor’s personnel working at the plant is expected to be on site at 07h15, 12:00 then break for Lunch and back at 12:45 from lunch. Knock off time is 16:30 from Monday to Thursday and 12:15 on Friday.
73
The contractor should keep daily attendance register for each employee.
9.3 Health and safety facilities on the Affected Property
The Contractor provides a First Aid service to his employees and subcontractor. In the case where these prove to be inadequate, as in the event of a serious injury, the Employer's Medical Centre and facilities will be used. Outside the Employer's office hours, the Employer's First Aid Services will only be available for serious injuries and life threatening situations. BARRICATING
The Contractor will ensure that equipment and persons are not exposed to danger or to prevent access to dangerous areas.
NB: All welding, flame cutting and grinding work shall be properly screened to protect persons from any injury. A PTW must be applied and issued before working.
All gratings shall be covered with adequate protective screening when welding or flame cutting in the vicinity. SPEED LIMIT
All vehicles must be driven with due consideration for personnel and property. A maximum speed limit of 40 km/h will be adhered to on the premises and 20 km/h in the plant at all times. HEALTH AND SAFETY ARRANGEMENTS
The Contractor must ensure that all his personnel attend a Health and Safety Induction Course prior to starting with their work. The Induction Course can, on request, be provided by the Employer and will be valid for the duration of the services. Safety Risk Management has the right and authority to visit and inspect the Contractor's workplace or site establishment to ensure that tools, machinery and equipment comply with the minimum safety requirements. The Contract Manager shall be entitled to instruct the Contractor to stop work, where the Contractor's personnel fail to conform to safety standards or contravene health and safety regulations. The contract Manager is entitled to caLL the Contractor to discipline his employees and to submit disciplinary action, and submit a report to the Contract Manager. The Contractor shall implement additional health and safety precautions where necessary. The Contractor will provide all his personnel with the required personal protective equipment and tools. Employer shall only be responsible for PSR regulation on site. Risk Assessments, PTW, Pre-Job Briefs, Post – Job Briefs & Job Observations will be conducted for all jobs. All Construction Regulation - safety requirements should also be adhered to. - Safety Plan - Fall Protection Plan - 161 and 162 appointments
9.4 Environmental controls, fauna & flora
The contractor to comply with the following requirements and legislation:
74
-Occupational Health and Safety Act 85 of 1993 as amended and its regulations -Compensation for Occupational Injuries and Diseases Act 130 of 1993 as amended -National Environmental Management Act 107 of 1998 as amended -National Environmental Waste Act 59 of 2008 as amended -National Water Act 36 of 1998 as amended -Eskom procedures and safety requirements set out in safety, health and environmental
specifications 004 4830 - Eskom procedure 32-95 in regards with the management of safety, health and environmental incidents -Any other act or procedure deemed necessary or applicable If the work includes some toxic and hazardous substances during normal and routine maintenance activities. It this case the Contractor uses such hazardous substances in accordance with the applicable regulations and procedures are disposed off by the contractor in accordance with the applicable law
9.5 Cooperating with and obtaining acceptance of others
1) The Contractor may be required to share the Affected Plant equipment and/or space with Others. 2) Cooperating with statutory authorities or inspection agencies
9.6 Records of Contractor’s Equipment
Maintenance team must have a rigging skill and rigging equipment to rig motors when motors are out of plant sectional boundaries.
9.7 Equipment provided by the Employer
Proper communication must be made then a crane shall be made available when needed.
The Contractor will use this Camden pre-assessment form if does not have their own approved form.
APPENDIX 1 : PRE ASSESSMENT REPORT FORM
CAMDEN POWER STATION HV MOTOR
75
PRE -ASSESSMENT FORM
MOTOR DETAIL
CONTRACTOR’S ASSESSOR _______________________ ESKOM ASSESSOR ____________________
LAST JOB NO. AND NAME OF CONTRACTOR WHO HAS DONE REPAIRS BEFORE: JOB NO.: ________________________ NAME OF CO: ________________________ NEW JOB NO:______________________ ORDER NO.: ______________________
QCP REF. NUMBER: __________________ FAULT FOUND: _______________________
MACHINE NAME PLATE DETAILS
MAKE SERIAL NO.
STATOR VOLTS KW/HP
STATOR AMPS FRAME SIZE
SPEED
MOTOR DISCRIPTION
PRE-CLEANING ASSESMENT
ITEM DESCRIPTION ACCEPTABLE
REMARKS AND MEASUREMENTS YES NO
STATOR
STATOR CORONA DISCHARGE / PARTIAL DISCHARGE
CLEANLINESS OF WINDING.(OIL, DUST MOISTURE)
SIGNS OF OVERHEATING
LOOK FOR FOREIGN OBJECTS IN HOUSING
VENT DUCTS BLOCKED
ROTOR
SIGNS OF OVERHEATING
VENT DUCTS BLOCKED
BEARINGS
MISALIGNMENT
76
LAY
EXTERNAL FANS
FAN LOOSE
FAN CRACK
TERMINAL CONNECTION BOX
TERMINALS CONDITION
TERMINAL-BOX - CONDITION
TERMINAL BOX CONNECTION AND INSULATORS
TERMINAL BOX CONDITION ``
INSULATION RESISTANCE AND PI
ITEM DESCRIPTION ACCEPTABLE
REMARKS AND MEASUREMENTS YES NO
STAR POINT BOX & AUX BOX:
STAR POINT BOX- CONDITION
STAR POINT AND NUTS - CONDITION
TERMINAL BOX RTD'S CONDITION
TERMINAL BOX HEATERS- CONDITION
CONDITION OF DESICCATORS AND INSULATORS
ASSESMENT AFTER CLEANING ALL COMPONENTS
ITEM DESCRIPTION ACCEPTABLE
REMARKS AND MEASUREMENTS YES NO
STATOR
HEAT EXCHANGER/ COOLER
HEAT EXCHANGER PHISICAL APPEARANCE
COOLING TUBES/ COOLER BLOCKAGE
CASING CRACK/ RUST
STATOR HOUSING
FOOT MOUNTING - CONDITION
END SHIELD MOUNTING SPIGOTS DE - ID MEASUREMENTS
A)
B)
C)
77
END SHIELD MOUNTING SPIGOTS NDE - ID MEASUREMENTS
A)
B)
C)
WINDING ANTI-CONDENSATION HEATERS - RATING
CHECK CONCENTRICITY
HOUSING OVERALL CONDITION
CORE AND WINDINGS
CORE - CONDITION
CORE - FLUX TEST RESULT (COMPULSORY) HOT SPOT AND WATTS
LOSS, EL CID (CONSULT REPRESENTATIVE)
WINDING - CONDITION
CONDITION OF WEDGES
RTD'S RESISTANCE
1 2
3 4
5 6
WINDING - INSULATION RESISTANCE TEST
INSULATION REASISTANCE TEST BETWEEN PHASES
INSULATION REASISTANCE TEST PHASE TO EARTH
POLARISATION INDEX TEST
TAN DELTA TEST (CONSULT ESKOM REPRESENTATIVE)
WITHSTAND VOLTAGE TEST (CONSULT ESKOM REPRESENTATIVE)
LAMINATION OUTER DIAMETER
CORE AND WINDINGS - SQUIRREL CAGE ROTOR
VISUAL INSPECTION - CONDITION (CRACKING)
CORE TEST (ELCID CONSULT ESKOM REPRESENTATIVE)
BAR TO BAR TEST (ELCID CONSULT ESKOM REPRESENTATIVE)
CRACKS / WELDING
IF DEFECTIVE, RECORD DATA BELOW
ROTOR CORE - DIAMETER
ROTOR CORE - LENGTH
ROTOR WINDINGS - SINGLE OR DOUBLE CAGE
ROTOR SLOTS - NUMBER OF
78
ROTOR BARS - NUMBER OF
ROTOR BARS - MATERIAL
ROTOR BARS - SECTIONAL DIMENSIONS (DRAWING)
ROTOR BARS - LENGTH
SHORT CIRCUIT RINGS - MATERIAL
SHORT CIRCUIT RINGS - NUMBER OF
SHORT CIRCUIT RINGS - OUTSIDE DIAMETER
SHORT CIRCUIT RINGS - INSIDE DIAMETER
SHORT CIRCUIT RINGS -WIDTH
AIR GAP
ROTOR OD (TAKE 3 OD MEASUREMENTS ON 3 PLACES MINIMUM, DEPENDING ON LENGTH OF CORE)
A1) A2) A3) A4)
B1) B2) B3) B4)
C1) C2) C3) C4)
STATOR ID (TAKE 3 ID MEASUREMENTS ON 3 PLACES MINIMUM, DEPENDING ON LENGTH OF CORE)
A1) A2) A3) A4)
B1) B2) B3) B4)
C1) C2) C3) C4)
AIR GAP (CALCULATED FROM ABOVE MEASUREMENTS
ROTOR OVAL / DEFORMED / MISALIGNMENT
STATOR
IF WINDING IS DEFECTIVE, RECORD WINDING DATA BELOW
STATOR CORE - DIAMETER
STATOR CORE - LENGTH
WINDING - TYPE
WINDING - CONNECTION
STATOR SLOT - NUMBER OF
STATOR COIL - NUMBER OF
STATOR COIL - PITCH
STATOR COIL - MEAN TURN LENGTH
STATOR COIL - TURNS
CONDUCTOR - BARE DIMENSION
CONDUCTOR - HOW MANY IN PARALLEL
STATOR SLOT - WIDTH
79
STATOR SLOT - DEPTH BELOW WEDGE
STATOR SLOT - DEPTH ABOVE WEDGE
WINDING PROJECTION - CONNECTION SIDE
WINDING PROJECTION - PLAIN SIDE
ITEM DESCRIPTION ACCEPTABLE
REMARKS AND MEASUREMENTS YES NO
ROTOR
SHAFT NDT TEST (CONSULT ESKOM REPRESENTATIVE – MPI (MAGNETIC PARTICLE
INSPECTION TEST) MEASURED GAUSS LEVEL IN BEARING AREA (AS A GUIDELINE IT
MUST BE LESS THA N 2G) MEASURED GAUSS LEVEL IN SHAFT AREA (AS A GUIDELINE IT
MUST BE LESS THA N 8G)
SHAFT EXTENSION - DIMENSION FAN SIDE
A)
B)
C)
SHAFT EXTENSION - DIMENSION NON FAN SIDE
A)
B)
C)
SHAFT EXTENSION - ACTUAL LENGTH NON FAN SIDE
SHAFT RUN OUT FAN SIDE
SHAFT RUN OUT NON FAN SIDE
ROTOR CORE RUN OUT
COMPLETE ROTOR RUN OUT (6 MEASUREMENTS) A) B) C)
D) E) F)
D/E BEARING JOURNAL - CONDITION
D/E BEARING JOURNAL -SPECIFIED DIMENSIONS MIN.) MAX.)
D/E BEARING JOURNAL - ACTUAL DIMENSIONS
A)
B)
C) D/E BEARING JOURNAL - ACTUAL LENGTH
D/E SEAL LANDINGS - CONDITION
80
D/E SEAL LANDINGS - ACTUAL DIMENSIONS
A)
B)
C)
D/E SEAL LANDINGS - ACTUAL LENGTH
ND/E BEARING JOURNAL - CONDITION
ND/E BEARING JOURNAL -SPECIFIED DIMENSIONS MIN.) MAX.)
ND/E BEARING JOURNAL - ACTUAL DIMENSIONS
A)
B)
C) ND/E BEARING JOURNAL - ACTUAL LENGTH
ND/E SEAL LANDINGS - CONDITION
ND/E SEAL LANDINGS - ACTUAL DIMENSIONS
A)
B)
C)
ND/E SEAL LANDINGS - ACTUAL LENGTH
D/E COOLING FAN INTERNAL - CONDITION (NDT TO BE DONE)(CONSULT REPRESENTATIVE)
ND/E COOLING FAN INTERNAL - CONDITION (NDT TO BE DONE)(CONSULT REPRESENTATIVE)
EXTERNAL COOLING FAN - CONDITION (NDT TO BE DONE)(CONSULT REPRESENTATIVE)
FAN COWL
DRIVE END - END SHIELD AND BEARING HOUSING
DRIVE END - END SHIELD
SPIGOT -OD MEASUREMENTS A)
B)
C) BEARINGS HOUSING SEAT - INSIDE DIAMETER A)
B)
C)
BEARING CAP - INNER
BEARING CAP - OUTER
CHECK CONCENTRICITY
DRIVE END END SHIELD FIXING BOLTS - CONDITION
DRIVE END END SHIELD FIXING BOLTS - NUMBER OF
81
DRIVE END BEARING HOUSING
WHITE METAL - SIDE GLASS & PORTS
WHITE METAL BEARING HOUSING CHECK PORTS AND ADDITION
ITEMS E.G. OIL PUMP
BEARING HOUSING - CONDITION
BEARING HOUSING FRONT // REAR COVER - CONDITION
A)
BEARING HOUSING SEAT - OUTSIDE DIAMETER B)
BEARING HOUSING SEAT - OUTSIDE DIAMETER C)
BEARING - CONDITION
BEARING - TYPE AND MAKE
BEARING - SIZE
BEARING HOUSING BORE -SPECIFIED DIMENSIONS MIN.) MAX.)
A)
BEARING HOUSING BORE - ACTUAL DIMENSIONS B)
C)
BEARING IR MEASUREMENTS
SLEEVE BEARING BORE -SPECIFIED DIMENSIONS MIN.) MAX.)
A)
SLEEVE BEARING BORE - ACTUAL DIMENSIONS B)
C)
SLEEVE BEARING OIL RING - CONDITION
SLEEVE BEARING OIL RING - NUMBER OF
SLEEVE BEARING OIL WIPER
BEARING OIL SCOOP CONDITION
BEARING GREASE SLINGER - CONDITION
BEARING - INSULATED
BEARING INSULATION - CONDITION
BEARING HOUSING FIXING BOLTS - CONDITION
BEARING HOUSING FIXING BOLTS - NUMBER OF
SEALS
TEMPERATURE DETECTOR CONDITION
OIL LEVEL INDICATOR PIPING CONDITION
ITEM DESCRIPTION ACCEPTABLE REMARKS AND MEASUREMENTS
YES NO
82
NON-DRIVE END - END SHIELD AND BEARING HOUSING
NON-DRIVE END - END SHIELD
SPIGOT -OD MEASUREMENTS A)
B)
C) BEARINGS HOUSING SEAT - INSIDE DIAMETER A)
B)
C)
BEARING CAP - INNER
BEARING CAP - OUTER
CHECK CONCENTRICITY
NON DRIVE END END SHIELD FIXING BOLTS - CONDITION
NON DRIVE END END SHIELD FIXING BOLTS - NUMBER OF
NON-DRIVE END BEARING HOUSING
WHITE METAL - SIDE GLASS & PORTS WHITE METAL BEARING HOUSING CHECK PORTS AND ADDITION
ITEMS E.G. OIL PUMP
BEARING HOUSING - CONDITION
BEARING HOUSING FRONT // REAR COVER - CONDITION
BEARING HOUSING SEAT - OUTSIDE DIAMETER A)
B)
C)
BEARING - CONDITION
BEARING - TYPE AND MAKE
BEARING - SIZE
BEARING HOUSING BORE -SPECIFIED DIMENSIONS MIN.) MAX.)
A)
BEARING HOUSING BORE - ACTUAL DIMENSIONS B)
C)
BEARING IR MEASUREMENTS
SLEEVE BEARING BORE -SPECIFIED DIMENSIONS MIN.) MAX.)
A)
SLEEVE BEARING BORE - ACTUAL DIMENSIONS B)
C)
SLEEVE BEARING OIL RING - CONDITION
83
SLEEVE BEARING OIL RING - NUMBER OF
SLEEVE BEARING OIL WIPER
BEARING OIL SCOOP CONDITION
BEARING GREASE SLINGER - CONDITION
BEARING - INSULATED
BEARING INSULATION - CONDITION
BEARING HOUSING FIXING BOLTS - CONDITION
BEARING HOUSING FIXING BOLTS - NUMBER OF
SEALS
TEMPERATURE DETECTOR CONDITION
OIL LEVEL INDICATOR PIPING CONDITION
9.1 Site services and facilities
9.1.1 PROVIDED BY THE Employer
EMOLOYER’S SITE INFORMATION
84
FIRE PRECAUTIONS
Any tampering with the Employer's fire equipment is strictly forbidden. All exit doors, fire escape routes, walkways, stairways, stair landings and access to electrical distribution boards must be kept free of obstruction, and not be used for work or storage at any time. Fire fighting equipment must remain accessible at all times. In case of a fire, report the location and extent of the fire to the Electrical Operating Desk at extension 3471. Take the necessary action to safe guard the area to prevent injury and spreading of the fire. REPORTING OF ACCIDENTS
The Employer follows an accident prevention policy that includes the investigation of all accidents involving personnel and property. This is done with the intention of introducing control measures to prevent a RE-OCCURRANCE of the same incidents. The Contractor is expected to fully co-operate to achieve this objective. The Contract Manager must be informed immediately of any incidents and any damage to property or equipment must be reported within 12 hours. NOTE! This report does not relieve the Contractor of his legal obligation to report certain incidents to the Department of Labour, or to keep records in terms of the Occupational Health and Safety Act, and Compensation for Occupational Injuries and Diseases Act.
Refuse Disposal
The Employer will provide and empty special colour coded bins for refuse disposal. The Contractor will be responsible for refuse bins for his own site. The Contractor ensures that all workers under his control strictly adhere to the correct use of refuse bins: For the full duration of the services, the Contractor is responsible to keep the work area clean of any rubble, and to place all refuse into the bins provided.
Portable Water The contractor may utilize water points on Site. Where no supply is available the contractor makes his own arrangements. Electrical Power Existing 3 Phase 380V and single phase 220V power on site may be utilised by the contractor. Where no supplies are available the contractor supplies his own source. The employer does not guarantee uninterrupted supply. Sanitary Facilities Permanent facilities to serve the Power Station terrace are provided randomly by the employer. Waste Removal Household waste removal to the bins, as provided on the Site by the employer, is the responsibility of the Contractor. The contractor complies with Employer’s policy for waste management on Site, policy. 004/4100. Telecommunication
85
Connections are available. The contractor applies via the Project Manager for a connection. Connection fees and calls are for the Contractor’s account.
9.1.2 Office and Toilet Facilities
The Employer will provide the Contractor access to office and toilet facilities.
9.1.3 Accommodation and catering
The Contractor will be responsibility for the provision of accommodation to his personnel – the Employer does not provide accommodation.
The Contractor or any of his employees or subcontractors will be allowed to use the Employer’s dining facilities.
The Contractor or any of his employees or subcontractors may also buy take away meals from the fast foods outlet on Site. Lunch time is from 12:00 to 12:45. Work starts at 07h15 until 16h30 from Monday to Thursday and Friday we knock off at 12h15 midday.
9.1.4 Provided by the Contractor
The contractor shall provide accommodation, vehicles, office equipment, PPE, special PPE like Arc-flash suit etc to execute the given SOW. The contractor shall only collect what belongs to the contractor upon completion of the contract.
9.2 Control of noise, dust, water and waste
Full PPE shall be worn at all times when entering the plant.
9.3 Hook ups to existing works
Eskom Cardinal Rules shall apply, contractor shall provide safety harnesses
9.4 Tests and inspections
9.4.1 Description of tests and inspections
Safety equipments shall be tested/ calibrated and inspected before use by the Contractor, a record/ certificates shall be kept by the contractor and available upon request.
9.4.2 Materials facilities and samples for tests and inspections
N/A
86
10 List of drawings
10.1 Drawings issued by the Employer
This is the list of drawings issued by the Employer at or before the Contract Date and which apply to this contract.
Drawing number Revision Title
N/A N/A N/A