SAPPHIRE SUPPRESSION SYSTEMS - ansul.com SAPPHIRE...2011-03; 4; CONTENTS; ... reportRefer to NFPA...
Click here to load reader
Transcript of SAPPHIRE SUPPRESSION SYSTEMS - ansul.com SAPPHIRE...2011-03; 4; CONTENTS; ... reportRefer to NFPA...
SAPPHIRE SUPPRESSION SYSTEMSDesign, Installation, Recharge and Maintenance Manual
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-02
ENGINEERED SYSTEMDESIGN AND INSTALLATION MANUAL
(INDIA - UL VERSION)
SAPPHIRE TOTAL FLOOD FIRE SUPPRESSION SYSTEMS
Copyright © 2011 Tyco Fire Protection Products. All rights reserved.
SAPPHIRE (UL)570805002011-03
2
REVISION RECORD
Date Page Revision
Indicates revised information.
Date Page Revision
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
3
CONTENTS
SECTION 1 - INTRODUCTION
About this Manual 5
Definitions 5
Contacts 5
Introduction 5
Approvals and Standards 5Novec™ 1230 Agent 6Manufactured Systems 6
Health and Safety 6First Aid 7
Novec™ 1230 Agent Characteristics 7Agent Physical Properties 8Table 1: Novec™ 1230 Physical Properties 8Table 2: Nitrogen Physical Properties 8Table 3: Novec™ 1230 Toxicology/
Environmental Properties 8
SECTION 2 - SYSTEM COMPONENTS
System Components 9SAPPHIRE Container & Valve Assembly 9Table 4: Container & Valve AssemblyDetails 10Table 5: Container - Valve Equivalent Lengths 10Container Label 11Valve Assembly 12Principle of Operation 12Burst Disc 13Low Pressure Switch (Transfer On Fall - Option
#1) 14Low Pressure Switch (Transfer On Fall - Option
#2) 14 PressureSwitch - DPST 15Fixing Brackets 15Manual Actuator 16Pneumatic Actuator 16Removable Electrical Actuator (Bridge Rectifier)
17AUTOPULSE Control System 18ANSUL AUTOMAN II-C Releasing Device 1850 mm (2 in) Flexible Discharge Hose 19Manifold Check Valve 19Manifolds 20Table 6: Manifold Details 20Actuation Hose 21Female Pilot Hose 21Male Actuation Connector 22Male Adaptor 22Male Actuation Tee 23Male Actuation Elbow 23Discharge Nozzle 24
Table 7: Discharge Nozzles 25ANSUL AUTOMAN Pressure Trip 26Safety Relief Valve 26Warning Signs 27Typical Manifold System 28
SECTION 3 - SYSTEM DESIGN
System Design 29Hazard Analysis 29Hazard Structure 30Hazard Volume 30Ventilation 31Hazard Temperature 31Hazard Fuels 31Personnel Safety 31Agent Quantities 31Agent Storage 31Manifolds 32Agent Distribution 32
Agent Flow Characteristics 33Nitrogen Superpressurisation 33Flow in Pipe 33Initial Vapour Discharge 33Trailing Vapour Pressure 33Nozzle Selection and Location 33Maximum Limits (Elevation) in Pipe Work 34Nozzle Discharge Radius 35Example: Nozzle Selection 35
System Design Procedure 35Example: Tee Split Designs 36
Design Example - Calculations 37Example: 37
Piping Practices 39
SECTION 4 - FLOW CALCULATIONS
Introduction 40Table 8: Novec™ 1230 Weight Calculations
Metric 40Table 9: Novec™ 1230 Weight Calculations
Imperial 41Table 10: Altitude Correction Factor 41
Novec™ 1230 Equation Calculations 42
Engineered Systems 42Program Parameters 42Table 11 : Max & Min Flow Rates 42Table 12 : Equivalent Length for Pipe Fittings 43Table 13 : Equivalent Length for Other System
Components 43
SAPPHIRE (UL)570805002011-03
4
CONTENTS
SECTION 5 - INSTALLATION
General Information 44
Container Installation 44
Single Container Installation 45Table 14: Bracket Fixing Heights 46
Multiple Container Installation 47Manifold Bracket Installation 47Table 15: Manifold Bracket Fixing Heights 48
Pipe Installation 49Table 16: US Steel Pipe Requirements 49Table 17: US Fittings 49Pipe Hangers 50Table 18: Hanger Spacing 50
Earthing and Electrical Clearance 51
Nozzles 51
Actuation Installation 52Single Container Actuation 52Multiple Container Actuation 54Table 19: ANSUL AUTOMAN II-C Piping
Lengths 57
Ancillary Equipment 58Discharge Pressure Switch 58Discharge Pressure Switch (Continued) 59Low Pressure Switch 59
Accessories 59Door Notices 59
Completion Procedures 60Pre-checks and Visual Inspections 60Final Connections 61
Hand-over Procedures 61
SECTION 6 - INTEGRITY TESTING
Introduction 62
Principle 62
Equivalent Leakage Area (ELA) 62
Below Ceiling Leakage Area (BCLA) 62
Predicting Retention Time 62
Slab to Slab Walls 62
Coordination and Planning 62Integrity Test Procedure 63Enclosure Evaluation 63
Calculation 64
Leakage Location 64
SECTION 7 - SYSTEM OPERATION
General Comments 65
System Detection and Actuation 65General 65Manual System 65Fully Automatic System 65Fully Automatic System with Manual Inter-
vention 66
Conditions During a Fire 66Novec™ 1230 Concentration 66Novec™ 1230 Decomposition 66Novec™ 1230 Discharge Conditions 66
Actions Following a Fire 67General 67Actions Immediately Following a Fire 67
SECTION 8 - MAINTENANCE
Introduction 68
User’s Programme of Inspection 68
Contract Service and Maintenance 69
Mechanical Servicing Procedure 71
Specialised Maintenance Duties 71Final Inspection 71
SECTION 9 - RECHARGING PROCEDURE
Recharging (OEM Only) 72Valve Refurbishment (OEM Only) 72Testing (OEM Only) 74Replacing Valve Assembly to container 74Filling 75Table 20 :Fill Tolerance Table 76Table 21: Temperature Correction Chart 77Container / Valve Assembly leakage Test 78Container Leak Test 78
SECTION 10 - APPENDICES APPENDIX A - Temperature Correction Chart
80APPENDIX B - Hughes Program Printout 81APPENDIX C - Novec™ 1230 Material Safety
Data Sheet (MSDS) 91
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
About this ManualThis manual is a comprehensive guide that contains all the information necessary to design, install and maintain the SAPPHIRE Engineered Extinguishing system However the manual does not address information relating to fire detection
Users of this manual are assumed to be competent fire engineers with a basic knowledge of such systems The contents are arranged in a logical order describing the various procedures in turn, alternatively specific sections can be referred to as required Users who are not familiar with the equipment should first read the complete manual
Definitions
Novec™ 1230 Novec™ 1230 is a registered trade mark of the 3M™
System In this manual ‘system’ refers to the extinguishing equipment and does not include any detection system which may initiate an agent release
Engineered Hydraulic flow program used to predict the two phase flow of Novec™ 1230 through a pipe network
ContactsShould any part of this manual not be understood, or there are any queries concerning a system, please contact:
Tyco Fire Protection ProductsOne Stanton StreetMarinette Wisconsin54143United States of America
Tel (+1) 715-735-7411Fax (+1) 715-732-3634
IntroductionNovec™ 1230 is a clean, safe fire fighting agent for use in total flooding automatic extinguishing systems It is intended as a long term replacement for Halon 1301 and, whilst maintaining the excellent fire suppression properties of Halon, has none of the environmental problems Storage and distribution requirements are similar to Halon and the majority of system components are identical However, Novec™ 1230 is not a direct replacement for existing Halon 1301 installations due to the difference in agent quantity and discharge characteristics The minimum Novec™ 1230 design concentration for Class A hazards is 42% for UL Listed systems For Class B hazards it is at least 585%
The US Environmental Protection Agency (EPA) accepts use in normally occupied areas where the concentration doesn't exceed 10% The safe use criteria has further been confirmed by the Halon Alternative Group (HAG) report Refer to NFPA 2001, 2008 edition “Clean Agent Fire Extinguishing Systems,” Section 1-5 “Safety,” for additional exposure requirements
The systems described in this manual are ‘engineered’ Engineered systems for example, may consist of several SAPPHIRE containers, modularised or manifolded together and connected via a pipe network to a number of discharge nozzles
Systems may be activated mechanically or electrically Mechanical manual actuation is via a manual actuator attached to the container valve Electrical actuation is via a removable side mounted solenoid or a top mounted electrical actuator Actuation can occur automatically via a signal from a detection and alarm control panel
Users of this manual should find that sufficient information is provided to plan, design, purchase components, install, operate and maintain the system However, in the event that part of the document is not understood, or if there is any concern as to the suitability of the protection, do not hesitate to contact one of our specialist engineers for the matter to be quickly resolved
Approvals and StandardsThe SAPPHIRE manufactured equipment and the Novec™ 1230 agent, manufactured by 3M™, have comprehensive approvals and listings providing further support to the overall product
5
SECTION 1 - INTRODUCTION
SAPPHIRE (UL)570805002011-03
Novec™ 1230 AgentApprovals include, but are not limited to:• Underwriters Laboratories Inc (UL) Recognised
Component
• NFPA 2001 Clean Agent Fire Extinguishing Systems (Listed Alternative)
• US EPA SNAP Rpt (Unrestricted Listed Alternative)
• Australian Industrial Chemicals Notification (Approved)
• German Institute for Environmental Hygiene and Medicine (Approved)
Manufactured Systems• Underwriters Laboratories Inc
SAPPHIRE systems are manufactured in strict accordance with the internationally recognised Quality assurance Standard, BS EN IS0 9000 and approved to ISO 9001SAPPHIRE Extinguishing System units are to be designed, installed, inspected, maintained, tested and recharged by qualified, trained personnel in accordance with The Standard on Clean Agent Fire Extinguishing Systems, NFPA2001, 2008 edition and to be used in accordance with Environmental Protection Agency (EPA) Significant New Alternatives Program (SNAP) Where determined to be appropriate by the authority having jurisdiction, other applicable standards may additionally be utilised to specific system requirements for these purposes
Health and SafetyA properly designed and installed extinguishing system should not present any significant health or safety problems, however, there are basic precautions to be taken to avoid accidents, and aspects of the system operation that should be understood End-users often require reassurance regarding the safety of personnel, and this can only be given if a thorough understanding of the properties of the agent and its effects in different situations are known Best practice should be observed
Novec™ 1230 extinguishes primarily through heat absorption, and does not sufficiently deplete oxygen levels
Therefore, exposure to Novec™ 1230 at the design concentration of 42%, and up to 100%, is not hazardous to health Exposure to higher concentrations is permissible for limited periods Refer to NFPA 2001, 2008 edition Section 1-5 “Safety,” for exposure requirements As with halons, the US EPA and the National Fire Protection Association (NFPA) recommend that unnecessary exposure to any agent be avoided and that personnel evacuate protected areas as quickly as possible to avoid the decomposition products of the fire
Novec™ 1230 will decompose at high temperatures to form halogen acids If so, their presence is readily detected as a sharp, pungent odour long before hazardous maximum exposure levels are reached Fire toxicity studies conclude that generally decomposition products from the fire itself, especially carbon monoxide, smoke, heat, and oxygen depletion, create a greater hazard
The noise created by the Novec™ 1230 agent discharging can be loud enough to startle people in the vicinity, but is unlikely to cause any permanent injury Turbulence caused by the high velocity discharge can dislodge substantial objects directly in its path, and cause enough general turbulence within the protected area to move paper and light objects
Direct contact with the vaporising liquid discharged from an Novec™ 1230 nozzle may have a chilling effect on objects and in extreme cases may cause frostbite to the skin The liquid phase vaporises rapidly when mixed with air and therefore limits the risk to the immediate vicinity of the nozzle Minor reduction in visibility may occur for a brief period due to the condensation of water vapour
HMIS: 0-0-1/dodecafluoro-2-methylpentan-3-one/contents under pressure 0-0-0/nitrogen expellant gas/very cold, contents under pressure Consult 3M, 3M Center, St Paul, MN 55144-1000 Emergency phone number 1-800-364-3577
6
SECTION 1 - INTRODUCTION
! WARNING
The discharge of clean agent systems to extinguish a fire can result in a potential hazard to personnel from the natural form of the clean agent or from the products of combustion that results from exposure of the agent to the fire or hot surfaces Unnecessary exposure of personnel either to the natural agent or to the products of decomposition shall be avoided
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
First Aid
Refer to the Novec™ 1230 Material Safety Data Sheet within Appendix C
Novec™ 1230 Agent CharacteristicsNovec™ 1230 is a clean agent containing no particles or oily residues It is produced under ISO 9002 guidelines to strict manufacturing specifications ensuring product purity Novec™ 1230 leaves no residue or oily deposits on delicate electronic equipment, and can be removed from the protected space by ventilation
Novec™ 1230 is thermally and chemically stable, but without the extremely long atmospheric lifetimes associated with some other clean agents The atmospheric lifetime of Novec™ 1230 has been determined to be 5 days (Reference 3M™) The US EPA SNAP does not consider Novec™ 1230 to be a long lived substance when discharged, and as such has placed no restrictions on its use (Environmental Protection Agency’s Significant New Alternatives Program)
Typical areas that may be protected by a SAPPHIRE system are detailed below; the list is by no means exhaustive:
Bank VaultsLibrariesRare Book StoresElectronic Data ProcessingTelephone ExchangesStudiosCommunication CentresTransformer and SwitchroomsControl RoomsTest LaboratoriesFlammable Liquid Stores
The present understanding of the functioning of Novec™ 1230 is that its fire fighting effectiveness is achieved through heat absorption Complete suppression using Novec™ 1230 has the following advantages:
• Less visual obscurity and minimal risk to personnel
• Low toxicity
• Most effective when used with automatic detection to introduce Novec™ 1230 with a 10 second discharge
• The ability to prevent re-ignition providing concentration levels are maintained
Novec™ 1230 is stored as a liquid in approved IS 7285 (Part2): 2004 containers and is super-pressurised with dry nitrogen to 25 bar @ 21 °C (360 psi @ 70 °F)
7
SECTION 1 - INTRODUCTION
! WARNING
Novec™ 1230 shall not be used on fires involving the following materials unless they have been tested to the satisfaction of the authority having jurisdiction:
• Certain chemicals or mixtures of chemicals, such as cellulose nitrate and gunpowder, that are capable of rapid oxidation in the absence of air
• Reactive metals such as lithium, sodium, potassium, magnesium, titanium, zirconium, uranium and plutonium
• Metal hydrides
• Chemicals capable of undergoing autothermal decomposition, such as certain organic peroxidase and hydrazine
SAPPHIRE (UL)570805002011-03
8
SECTION 1 - INTRODUCTION
Agent Physical Properties
Table 1: Novec™ 1230 Physical Properties
Agent Physical Properties FK-5-1-12
Chemical structure CF3CF2C(O)CF(CF3)2
Chemical name Dodecafluoro-2-methylpentan-3-one
Molecular weight 316.04Boiling point 49.0 °C (120.2 °F)Freezing point -108.0 °C (-162.4 °F)Critical temperature 168.7 °C (335.6 °F)Critical pressure 18.7 bar (270.4 psi)
Critical volume 494.5 cc/mole(0.0251 ft³/lbm)
Critical density 639.1 kg/m³ (39.91 lb/ft³)(Reference: NFPA 2001, 2008 edition)
Table 2: Nitrogen Physical Properties
Agent Physical Properties
Chemical structure N2Chemical name Nitrogen
Molecular weight 28.0Boiling point -195.80 °C (-320.4 °F)Freezing point -210.00 °C (-346 °F)Critical temperature -146.90 °C (-232.4 °F)Critical pressure 34.0 bar (492.9 psi)
Table 3: Novec™ 1230 Toxicology/Environmental Properties
Novec™ 1230Environmental
Ozone Depletion (ODP) 0
Atmospheric Lifetime (yrs) 0.014
Toxicology
Acute Exposure LC50 >10.0%
Cardiac SensitizationNo Observed Adverse Effect Level (NOAEL) ≤10.0%
Lowest Observed Adverse Effect Level (LOAEL) >10.0%(Reference: NFPA 2001, 2008 edition)
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
System ComponentsThis section describes the individual components that comprise a complete system Some items are optional depending on the application, and are indicated as such
SAPPHIRE Container & Valve AssemblyThe container assembly consists of a container fitted with a valve and internal syphon tube, factory filled with Novec™ 1230, and super-pressurised with dry nitrogen to 25 bar @ 21 °C (360 psi @ 70 °F) Containers sharing the same manifold shall be equal in size and fill density Containers are finished in red and are available in various sizes A nameplate is fixed to the container displaying the agent weight, tare weight, gross weight, fill density, charge date and fill location
Container Technical Information
The 80 and 120 litre containers are manufactured in accordance with IS:7285 (Pt 2) under BIS with CCOE approval.
Material: Carbon Steel
80L ContainerHydraulic Test Pressure:Working Pressure:
250 bar (3625.9 psi)150 bar (2175.6 psi)
120L ContainerHydraulic Test Pressure:Working Pressure:
334 bar (4844.3 psi)200 bar (2900.8 psi)
Paint Specification: Epoxy primerRed urethane top coat
Figure 1 - SAPPHIRE Container & Valve Assembly
Container & Valve Assembly Technical Information
Nominal Working Pressure: 25.0 bar (360 psi) at 21 °C (70 °F)
Max. Working Pressure: 29.2 bar (423.5 psi)
9
SECTION 2 - SYSTEM COMPONENTS
SAPPHIRE (UL)570805002011-03
Table 4: Container & Valve Assembly Details
Table 5: Container - Valve Equivalent Lengths
Part No. Nominal Volume
Nominal Tank Size
Minimum and Maximum Fills
Valve Size
Height from floor to outlet
(nominal)Diameter
Nominal Tare
Weightkg (lb) mm (in.) mm (in.) mm (in.) kg (lb)
570839 80 litre 210 lb 40 to 96 (88 to 211) 50 (2) 1794 (70.6) 267 (10.5) 85.7 (189)570840 120 litre 320 lb 60 to 144 (132 to 317) 50 (2) 1595 (62.8) 356 (14) 135.2 (298)
Part No. Nominal Volume
Nominal Tank Size
Equivalent Lengths
m (ft)570839 80 litre 210 lb 10.668 (35)570840 120 litre 320 lb 10.668 (35)
10
SECTION 2 - SYSTEM COMPONENTS
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Container LabelThe container label details the weight of Novec™ 1230
contained, empty weight, fill density and charge date Once the label is applied to the container surface, and to avoid possible tampering it can not be removed intact
Figure 2 - Container Label (Part No. 570804)
Technical Information
Material: Aluminum
Adhesive: Pre-applied 3M adhesive 9485
Certification: UL Recognised
Overall Size: 241.3 mm x 165.1 mm (15 in. x 6.5 in.)
Weight: 0.0416 kg (0.092 lb)
11
SECTION 2 - SYSTEM COMPONENTS
SAPPHIRE (UL)570805002011-03
Figure 3 - Valve Assembly
Valve AssemblyThe container valve is the result of extensive research and development and incorporates many unique safety features The valve assembly is factory-fitted to the container and is supplied pre-assembled with a low pressure switch (to be ordered seperately), pressure gauge and burst disc
Technical Information
50 mm (2 in.) ValveBody Material: Brass CZ 121Outlet Anti-Recoil Cap Material: CZ122Max. Working Pressure: 34 bar (493 psi)Outlet: 50 mm (2 in. BSPP)Low Pressure Switch Port: 1/8 in. NPTGauge Port: 1/8 in. NPTPilot Pressure Port: 1/4 in. BSPPSolenoid Adaptor Port: 1/8 in. NPTOverall Size: 173 mm (L) x 100 mm (Dia)
(6.12 in. (L) x 3.94 in. (Dia))Weight: 9.18 kg (20.238 lb)Equivalent Length: 10.668 m (35 ft)
Principle of OperationThe SAPPHIRE valve is a high-flow-rate device specially designed for use in fire systems Operation is by means of a pressure-differential piston Container pressure is used within the valve to create a positive force on the piston, sealing the valve closed Operation of the valve occurs when the upper chamber is vented faster than the ‘make up device’ in the shuttle can replace the pressure Thereby allowing, the shuttle to be forced up, and free flow of Novec™ 1230 from the valve Upper chamber pressure is released by the electrical, mechanical or pneumatic actuator
The valve incorporates the following features:• A pressure operated safety release device (burst disc)
• Main outlet, fitted with anti-recoil cap
• A connection for a pneumatic, mechanical or electrical actuator, fitted with safety cap
• A connection for an electrical solenoid
• A connection for the pneumatic actuation port
50 mm (2 in.) Valve Assembly Part No. 570536
12
SECTION 2 - SYSTEM COMPONENTS
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Figure 4 - Burst Disc
Burst DiscA burst disc is factory fitted to every valve assembly It is designed to rupture when the container becomes over pressurised when subjected to temperatures above the designed storage temperature of the container
Burst Disc for 50 mm (2 in.) Valve Part No. 570793
Technical Information
50 mm (2 in.) Valve
Body: Brass CZ 121Rating: 53.4 bar (775 psi) @ 50 °C (122 °F)Thread: M18 x 1.00Hole Orientation: 90° to BodyTorque: 35 Nm (25.8 ft lb) Overall Size : 20 mm (L) x 18 mm (Dia)
(0.79 in. (L) x 0.71 in. (Dia))Weight: 0.028 kg (0.062 lb)
13
SECTION 2 - SYSTEM COMPONENTS
SAPPHIRE (UL)570805002011-03
Low Pressure Switch (Transfer On Fall - Option #1)A low pressure warning switch can be fitted to every container and must be ordered seperately The device continuously monitors the container pressure and in the event of the pressure dropping below 203 bar (294 psi) the switch operates to enable the condition to be signalled to a control unitThis low pressure switch is the primary supply, (option #1), of a dual source component used in order to maintain the supply chain and ensure that adequate stock levels are available to fully support customers and installers
Low Pressure Switch (Transfer On Fall - Option #2)A low pressure warning switch can be fitted to every container and must be ordered seperately The device continuously monitors the container pressure and in the event of the pressure dropping below 20 bar (290 psi) the switch operates to enable the condition to be signalled to a control unitThis low pressure switch is the secondary supply, (option #2), of a dual source component used in order to maintain the supply chain and ensure that adequate stock levels are available to fully support customers and installers
Figure 5 - Alternate Low Pressure Switch (Part No. 570585) Option #1
Figure 6 - Alternate Low Pressure Switch (Part No. 570585) Option #2
Technical Information
Body: Zinc Plated Steel and KaptonSwitch Type: Single Pole, Double Throw (SPDT)Switch Point: Transfers on Fall at 20.3 bar (294 psi)
Resets on Rise at 24.1 bar (350 psi)Tolerance: +/-0.7 bar (± 10 psi)Proof Pressure: 206.8 bar (3000 psi)Contact Reset Method: Auto Resetting ContactsConnection: 1/8 in. NPT MaleElectrical Rating: 5 A at 24 v dc (Resistive)Electrical Connection: DIN 43650A Connector with
1/2 in. NPT Female Conduit Connection
Pin 1: Common at Atmospheric PressurePin 2: Normally Closed at Atmospheric
PressurePin 3: Normally Open at Atmospheric
PressureCertification: UL RecognisedIP Rating: IP65Overall Size: 104 mm (L) x 28 mm (Dia)
(4.10 in. (L) x 1.12 in. (Dia))Weight: 0.16 kg (0.35 lb)
Technical Information
Body: Brass and Anodised AluminiumSwitch Type: Single Pole, Double Throw (SPDT)Switch Point: Transfers on Fall at 20 bar (290 psi)
Resets on Rise at 22.8 bar (330 psi)Tolerance: +/-1.0 bar (± 15 psi)Proof Pressure: 413.7 bar (6000 psi)Contact Reset Method: Auto Resetting ContactsConnection: 1/8 in. NPT MaleElectrical Rating: 5 A at 24 v dc (Resistive)Electrical Connection: DIN 43650A Connector with
1/2 in. NPT Female Conduit Connection
Pin 1: Common at Atmospheric PressurePin 2: Normally Closed at Atmospheric
PressurePin 3: Normally Open at Atmospheric
PressureCertification: UL RecognisedIP Rating: IP65Overall Size: 104 mm (L) x 32 mm (Dia)
(4.40 in. (L) x 1.25 in. (Dia))Weight: 0.21 kg (0.46 lb)
14
SECTION 2 - SYSTEM COMPONENTS
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Pressure Switch – DPST
The pressure switch can be used to open or close electrical circuits to either shut down equipment or turn on lights and alarms The double pole, single throw (DPST) pressure switch is constructed with a gasketed, water-tight housing The housing is constructed of malleable iron A 1/4 in NPT pressure inlet is used to connect the pressure switch to the 1/4 in actuation piping between the ANSUL AUTOMAN II-C release and the pneumatic actuator on the master SAPPHIRE tank valve
Minimum operating pressure is 35 bar (50 psi)
Technical Information
Switch Material: BAKELITEHousing Material: Malleable IronPiston Material: BrassCover Material: BrassConduit Inlet: 3/4 in. NPT FemalePressure Inlet: 1/4 in. NPT FemaleElectrical Rating: 2 HP – 240 VAC/480 VAC
2 HP – 250 VDC30 A – 250 V AC/DC
Overall Size: 116 mm (H) x 73 mm (W) x 92 mm (D)(4.57 in. (H) x 2.87 in. (W) x 3.62 in. (D)
Figure 7 - Pressure Switch - DPST (Part No. 46250)
Fixing BracketsThe bracket assembly consists of a nut, bolt, and two bracket straps (back channel must be supplied by others)Approved type of Unistrut Channel is series P1000T, 41 mm x 41 mm (16 in x 16 in) To securely hold the container in position during the system discharge, a single bracket assembly is required per container
Each strap is notched for insertion into the back channel allowing the container to be properly aligned The bracket assembly is designed to be mounted to a rigid vertical surface with the container assembly resting fully on the floor
Figure 8 - Fixing Bracket (Strap Style)
Technical Information
Material: Mild SteelCoating: Black Polyethylene powder-Plascoat LDPEMounting: Unistrut Channel (By others)Weight of Strap: 0.30 kg (0.66 lb) (Part No. 570086 - 80L)
0.51 kg (1.12 lb) (Part No. 570841 - 120L)
Weight of Assembly: 1.58 kg (3.48 lb) (Part No. 570085)2.43 kg (5.35 lb) (Part No. 570842)
Part Number Container Size Nominal Length of Back Channel
mm (in.)570085 80 litre
265 mm dia. (10.5 in.)400 (15.75)
570842 120 litre356 mm dia. (14 in.)
600 (23.6)
15
SECTION 2 - SYSTEM COMPONENTS
SAPPHIRE (UL)570805002011-03
Technical Information
Body: Brass CZ121Actuation Pin: Stainless SteelPiston Rod: Brass CZ 121Pipe connection: 1/4 in. NPT FemaleMin. Actuation Pressure: 4 bar (58 psi)Max. Working Pressure: 75 bar (58 psi)Overall Size: 48 mm (L) x 41.5 mm (Dia)
(1.89 in. (L) x 1.63 in. (Dia))
Weight: 0.228 kg (0.503 lb)
Figure 10 - Pneumatic Actuator (Part No. 570550)
Pneumatic ActuatorThe pneumatic actuator is used to pneumatically operate the system at the container position and is fitted to the top of the valve assembly or removable electrical actuator Pressure from a ‘master’ container or the ANSUL AUTOMAN II-C Releasing Device is used to actuate the valve, via small bore piping or a flexible hose
Technical Information
Body: Brass CZ 121Knob: Red PVCSafety Pin: Stainless Steel 303Piston Rod: Brass CZ 121Min. Actuation Force: 25.5 N (5.73 Ibf)Overall Size: 52 mm (L) x 41.5 mm (Dia)
(2.05 in. (L) x 1.63 in. (Dia))
Weight: 0.265 kg (0.584 lb)
Manual ActuatorThe manual actuator is used to mechanically operate the system at the container position and is fitted to the top of the valve assembly or removable electrical actuator Inadvertent operation is prevented by a safety clip which has to be removed before activation
Figure 9 - Manual Actuator (Part No. 570549)
16
SECTION 2 - SYSTEM COMPONENTS
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Figure 11 - Electrical Actuator - Bridge Rectifier (Part No. 570537)
Removable Electrical Actuator (Bridge Rectifier)The removable electrical actuator locates to the top of the container valve 24 v dc is required for solenoid operation Provision is made for the connection of a manual actuator to the top of the actuator assembly Due to the design of the bridge rectifier it will operate regardless of how it is wired up; the positive supply from control panel can be connected to either terminal 1 or 2 with the reverse for the negative supply The removable electrical actuator has a life span of 10 years from manufacture, which is indicated on the label
Technical Information
Body: Mild Steel & Dull NickelSwivel nut: Brass CZ121Actuation Pin: Stainless SteelActuation Type: LatchingReset Requirement: Manually via Reset Tool
suppliedConnection: 1 in. BSPP BrassNominal Voltage: 24 v dcNominal Current: 0.25 AMax. Monitoring Current: 25 mAManual Actuation Force: 50 N (11.24 Ibf)Nominal Pin Travel: 4.4 mm (0.17 in.)Electrical connection: 3-pin plug connectorBack EMF Protection: Bridge RectifierCertification: UL RecognisedOverall Size: 104 mm (L) x 44 mm (Dia)
(4.09 in. (L) x 1.73 in. (Dia))Weight: 0.95 kg (2.09 lb)
17
SECTION 2 - SYSTEM COMPONENTS
SAPPHIRE (UL)570805002011-03
AUTOPULSE Control SystemThe AUTOPULSE Control System is designed to monitor fixed fire hazards The control system can automatically actuate the fire suppression system after receiving an input signal from one or more initiating devices, ie, manual pull station or detector The control system incorporates an internal power supply, on-line emergency batteries, and solid state electronics Refer to Detection and Control manual for additional information
Figure 12 - The AUTOPULSE Group of Equipment
ANSUL AUTOMAN II-C Releasing DeviceThe ANSUL AUTOMAN II-C Releasing Device consists of a metal enclosure which contains a spring-loaded puncture pin release mechanism, an actuation cartridge, electrical circuitry, and an input/output terminal strip for making electrical connections The ANSUL AUTOMAN II-C releasing device provides automatic pneumatic actuation of the SAPPHIRE System When wired to an AUTOPULSE Control system, it will provide supervised electric detection and release It also provides manual actuation using the strike button on the release When an AUTOPULSE Control System is used, manual actuation is accomplished using an electric manual pull station
The ANSUL AUTOMAN II-C releasing device requires an LT-30-R nitrogen cartridge for system actuation Cartridge must be ordered separately
ANSUL AUTOMAN II-C Releasing Device Part No. 17728
LT-30-R Nitrogen Cartridge (Ordered Seperately) Part No. 5373
Cocking Lever (Ordered Seperately)Part No. 26310
Figure 13 - ANSUL AUTOMAN II-C Releasing Device
18
SECTION 2 - SYSTEM COMPONENTS
Technical Information
50 mm (2 in.) HoseHose Construction: Twin steel wire braided oil resistant
seamless synthetic rubber core to DIN EN 853 2SN
Connection: Zinc Passivated Mild Steel50 mm (2 in. NPT) Straight Fixed Male50 mm (2 in. BSPP) 90° Female Swivel Union
Max. Bend Angle: 15° @ 0 °C (32 °F)Max. Working Pressure: 80 bar (1160 psi)Overall Size: 520 mm (L) x 125 mm (W)
(20.47 in. (L) x 4.92 in. (W))Weight: 3.90 kg (8.60 lb)Equivalent Length: 5.36 m (17.6 ft)
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
50 mm (2 in.) Flexible Discharge HoseSAPPHIRE container installations may be connected to the system by means of a flexible discharge hose This enables containers to be disconnected for maintenance or recharge without dismantling other container mountings, manifold connections and pipework, etc The flexible discharge hose is provided with a swivel fitting at the inlet
Figure 14 - Flexible Discharge Hose
50 mm (2 in.) Hose Part No. 570538
Manifold Check ValveManifold check valves are of mushroom pattern type and lift into the manifold as discharge occurs The function of the check valve is to prevent loss of extinguishing agent during discharge from an outlet, should a container have been removed Manifolds are constructed of standard Schedule 40 pipe and 300 lb fittings The check valves assemble directly into the fittings
Figure 15 - Manifold Check Valve
Technical Information
Body: Brass CZ122Stem: Stainless SteelSpring: Stainless SteelBottom Plate: Brass CZ122Top Plate: Stainless SteelSeal Material: NitrileInlet Connection Thread: 50 mm (2 in. NPT) FemaleOutlet Connection Thread: 65 mm (2½ in. NPT) MaleOverall Size: 73 mm (L) x 83 mm (W)
(2.87 in. (L) x 3.25 in. (W))Weight: 1.60 kg (3.53 lb)Equivalent Length: 6.66 m (21.8 ft)
50 mm (2 in.) Check Valve AssemblyPart No. 570568
19
SECTION 2 - SYSTEM COMPONENTS
SAPPHIRE (UL)570805002011-03
ManifoldsManifolds are fabricated sections of steel pipework They enable multiple containers to be connected to a common pipe network They may also be used in systems where main / reserve containers arrangements are required
Manifolding requirements are:• Use Schedule 40 black iron, galvanized, chrome-
plated, or stainless steel pipe conforming to ASTM A53, or A106 All fittings must be a minimum Class 300, malleable or ductile iron
• After welding, make certain all inlet holes in the pipe are clean of any weld spatter and are completely open
• Pipe unions are acceptable
• Reducing bushings and reducing fittings are allowed when reducing pipe size
• Cast iron pipe and fittings are not acceptable
• PTFE (Teflon) tape is the only acceptable pipe sealant and must be applied to male threads only Do not allow tape to overlap the pipe opening, as this could cause possible blockage of the agent Thread sealant or compound must not be used
• Before assembling the pipe and fittings, make certain all ends are carefully reamed and blown clear of chips, debris and scale The inside of pipe and fittings must be free of oil and dirt
Figure 16 - Typical Manifold Assembly
Inlet to End Cap Distance
Inlet to Inlet
Distance
Container Size
mm (in.) mm (in.)150 (6) 350 (14) 80L150 (6) 460 (18) 120L
Table 6: Manifold Details
20
SECTION 2 - SYSTEM COMPONENTS
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Female Actuation HoseThe 1/4 in stainless steel, female actuation hose is used toconnect the actuation line compression tees between eachagent tank The hose has the same thread, 7/16-20, as thecompression tees
Figure 18 - Female actuation hose (Part No. 32336)
Technical Information
Length: 610 mm (24 in. )
Actuation HoseThe 1/4 in stainless steel actuation hose is used to connectthe 1/4 in actuation line to the pneumatic actuator locatedon the container discharge valve The hose can be used when the actuation line is rigid 1/4 in pipe and fittings or from the pilot pressure port on the master container to the pneumatic actuators on the slave containers The hose has a 1/4 in NPT male thread on one end and a 7/16-20 female thread on the other end A male adaptor, (either Part No 32338 or 570342), is required with this hose Three lengths of hoses are available
406 mm (16 in.) Actuation hosePart No. 73597
813 mm (32 in.) Actuation hosePart No. 415142
1067 mm (42 in.) Actuation hosePart No. 430815
Figure 17 - 1/4 in. Actuation hose
21
SECTION 2 - SYSTEM COMPONENTS
SAPPHIRE (UL)570805002011-03
Figure 19 - Male Actuation Connector (Part No. 32338)
Technical Information
Connection: 1/4 in. NPT x 7/16-20
Technical Information
Connection: 1/4 in. NPT x 1/4 in. BSP
Male AdaptorThe male adaptor is required to attach the 1/4 in actuationhose to the master tank pilot port When using the maleadaptor on the master container pilot port, a 1/4 in pipe coupling must be used between the adaptor and the male hose thread
Figure 20 - Male Adaptor (Part No. 570342)
Male Actuation ConnectorThe male connector is used to connect the 1/4 in femaleactuation hose to rigid 1/4 in actuation fittings and also the pneumatic actuator The connector has a 7/16-20 thread for connecting to the actuation hose and a 1/4 in NPT thread for connecting to the actuation piping and pneumatic actuator
22
SECTION 2 - SYSTEM COMPONENTS
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Male Actuation TeeThe male actuation tee is used to connect multiple actuation hoses together The actuation tee has a 7/16-20 thread for connecting to the female actuation hose and a NPT thread for connecting to the pneumatic actuator on the container discharge valve
Figure 21 - Male Tee (Part No. 31811)
Technical Information
Connection: 7/16-20 x 7/16-20 x 1/4 in. NPT
Figure 22 - Male Elbow (Part No. 31810)
Technical Information
Connection: 7/16-20 x 1/4 in. NPT
Male Actuation ElbowThe male actuation elbow is used to connect the actuationhose to a single or last container in a multiple container system The elbow connects between the hose and the pneumatic actuator on the valve The elbow has a 7/16-20 thread for connecting to the hose and a 1/4 in NPT thread for connecting to the pneumatic actuator on the container discharge valve
23
SECTION 2 - SYSTEM COMPONENTS
SAPPHIRE (UL)570805002011-03
Discharge NozzleNovec™ 1230 is distributed within the protected area by the discharge nozzle which is sized to ensure the correct flow of agent for the risk Nozzles are available with seven or sixteen ports to allow for 360° or 180° horizontal discharge patterns Ports are drilled in 01 mm (0004 in) increments to the specified system design Nozzles are supplied as standard in Brass as NPT with Stainless Steel as an option
Technical Information
Material: Brass / Stainless SteelThread Type: NPTDrill Incrementation: 0.1 mmNozzle Type: 16 Port 360° / 7 Port 180°Max. Distance from Ceiling: 300 mmOrientation: Pendant / Upright
Figure 23 - 16 & 7 Port Nozzle Brass Configuration
180° Nozzle Pattern (7 Ports)360° Nozzle Pattern (16 Ports)
24
SECTION 2 - SYSTEM COMPONENTS
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Table 7: Discharge Nozzles
Nozzle Overall Sizes
Nozzle Size Length Diameter15 mm (1/2 in.) 41 mm (1.61 in. ) 47.6 mm (1.87 in. )20 mm (3/4 in.) 47 mm (1.85 in. ) 53.1 mm (2.09 in. )25 mm (1 in.) 52 mm (2.05 in. ) 58.9 mm (2.32 in. )32 mm (1¼ in.) 63.1 mm (2.48 in. ) 66.5 mm (2.62 in. )40 mm (1½ in.) 68 mm (2.68 in. ) 72.9 mm (2.87 in. )50 mm (2 in.) 89 mm (3.50 in. ) 88.9 mm (3.50 in. )
Nozzle Weights
Nozzle Size Brass Stainless Steel15 mm (1/2 in.) 0.16 kg (0.35 lb) 0.15 kg (0.33 lb)20 mm (3/4 in.) 0.22kg (0.49 lb) 0.21 kg (0.46 lb)25 mm (1 in.) 0.28 kg (0.62 lb) 0.26 kg (0.57 lb)32 mm (1¼ in.) 0.42 kg (0.93 lb) 0.39 kg (0.86 lb)40 mm (1½ in.) 0.47 kg (1.04 lb) 0.44 kg (0.97 lb)50 mm (2 in.) 0.84kg (1.85 lb) 0.79 kg (1.74 lb)
25
SECTION 2 - SYSTEM COMPONENTS
Part Nozzle Nozzle Nozzle Thread Number Size Type Material Type570515 15 mm (1/2 in.) 7 Port 180° Brass NPT
570602 15 mm (1/2 in.) 16 Port 360° Brass NPT
570516 20 mm (3/4 in.) 7 Port 180° Brass NPT
570603 20 mm (3/4 in.) 16 Port 360° Brass NPT
570517 25 mm (1 in.) 7 Port 180° Brass NPT
570604 25 mm (1 in.) 16 Port 360° Brass NPT
570518 32 mm (1¼ in.) 7 Port 180° Brass NPT
570605 32 mm (1¼ in.) 16 Port 360° Brass NPT
570519 40 mm (1½ in.) 7 Port 180° Brass NPT
570606 40 mm (1½ in.) 16 Port 360° Brass NPT
570520 50 mm (2 in.) 7 Port 180° Brass NPT570607 50 mm (2 in.) 16 Port 360° Brass NPT
Part Nozzle Nozzle Nozzle Thread Number Size Type Material Type577627 15 mm (1/2 in.) 7 Port 180° Stainless NPT
577628 15 mm (1/2 in.) 16 Port 360° Stainless NPT
577629 20 mm (3/4 in.) 7 Port 180° Stainless NPT
577630 20 mm (3/4 in.) 16 Port 360° Stainless NPT
577631 25 mm (1 in.) 7 Port 180° Stainless NPT
577632 25 mm (1 in.) 16 Port 360° Stainless NPT
577633 32 mm (1¼ in.) 7 Port 180° Stainless NPT
577634 32 mm (1¼ in.) 16 Port 360° Stainless NPT
577635 40 mm (1½ in.) 7 Port 180° Stainless NPT
577636 40 mm (1½ in.) 16 Port 360° Stainless NPT
577637 50 mm (2 in.) 7 Port 180° Stainless NPT577638 50 mm (2 in.) 16 Port 360° Stainless NPT
SAPPHIRE (UL)570805002011-03
ANSUL AUTOMAN Pressure TripThe pressure trip is connected to the 1/4 in actuation piping from the ANSUL AUTOMAN II-C release By either pneumatic or manual actuation, the pressure trip can release spring or weight powered devices to close doors and windows, open fuel dump valves, close fire dampers or close fuel line valves The pressure trip is constructed of brass with two 1/4 in NPT fittings for connection to actuation piping The link on the pressure switch is released either pneumatically, by nitrogen pressure from the cartridge in the ANSUL AUTOMAN II-C, or manually, by use of the pull ring The link then releases the device which performs the auxiliary functions Operating pressure must be a minimum of 52 bar (75 psi) with a maximum load of 318 kg (70 lb) Note: Pressure trip must not be installed in agent discharge piping
Figure 24 - Pressure Trip (Part No. 5156)
Safety Relief ValveThe safety relief valve is used to relieve the nitrogen pressure in the actuation line after the system has been actuated by an ANSUL AUTOMAN II-C release After agent discharge, pulling the ring on the relief valve can relieve the pressure in the line
Figure 25 - Safety Relief Valve (Part No. 15677)
Technical Information
Body: BrassSpring: Stainless SteelPull Ring: Stainless SteelInlet: 1/4 in. MaleSet Point: 18.3 bar (265 psi)Max. Installation Torque: 27 Nm (20 ft lb)Overall Size: 50.8 mm (L) x 17.5 mm (W)
(2 in. (L) x 0.69 in. (W))
Technical Information
Body: BrassSpring: Stainless SteelPull Ring: Stainless SteelPressure Ports: 1/4 in. NPTMounting Holes: 7.1 mm (0.281 in.) DiameterMin. Operating Pressure: 5.2 bar (75 psi)Max Load at 5.2bar (75psi): 31.75 kg (70 lb)Overall Size: 95 mm (L) x 76 mm (W)
(3.75 in. (L) x 3 in. (W))
26
SECTION 2 - SYSTEM COMPONENTS
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Figure 26 - Warning Sign (Part No. 570580)
Warning SignsTwo warning signs are available for warning personnel that the space is protected by a SAPPHIRE system and no one should enter after a discharge without being properly protected Each sign is made of aluminum and contains four mounting holes for ease of installation
Figure 27 - Agent Discharge Warning Sign (Part No. 570581)
LABEL NO. 570581
WHEN ALARM SOUNDSVACATE AT ONCE3M™ NOVEC™ 1230 FIREPROTECTION FLUIDBEING RELEASED
LABEL NO. 570580
WARNINGTHIS SPACE IS PROTECTED BY A SAPPHIRE™
FIRE SUPPRESSION SYSTEM
WHEN SYSTEM IS DISCHARGED AS A RESULTOF FIRE, CAUTION MUST BE TAKEN TO AVOIDEXPOSURE TO PRODUCTS OF COMBUSTION.
DO NOT ENTER WITHOUT APPROVED SELF-CONTAINED BREATHING APPARATUS ORUNTIL AREA IS PROPERLY VENTILATED.
27
SECTION 2 - SYSTEM COMPONENTS
SAPPHIRE (UL)570805002011-03
Typical Manifold SystemFigure 28 indicates a typical two container system complete with electrical actuation, manual actuator, pressure switch, low pressure switches, flexible connections, distribution pipework and nozzles
Figure 28 - Typical Manifold System
28
SECTION 2 - SYSTEM COMPONENTS
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
System DesignThere are two main elements of system design The first is the risk assessment; determining the type of protection required, considerations such as ventilation, openings and restrictions; equipment location etc The second is calculating the quantity of Novec™ 1230 required, including floor and/or ceiling voids, positioning of nozzles, electrical requirements, etc
All systems are designed in accordance with NFPA 2001
Hazard AnalysisThe first, and one of the most important, exercises in planning a SAPPHIRE extinguishing system is the hazard survey The information derived from the survey should include risk assessment, environmental conditions, personnel considerations, system operation both in normal conditions and after a discharge, access and construction limitations, dimensions, volumes, and any special requirements
SAPPHIRE systems are suitable for use in normal commercial and industrial environments The minimum design concentration for Class A & C fires is 42% but differs for Class B fires To determine other recommended design concentrations for Class B flammable liquids, refer to the technical support centre All design concentration calculations are based on extinguishing concentrations plus 20% safety factor for Class A & C and 30% safety factor for Class B
All agent quantities are calculated at minimum design temperature to determine agent quantity Maximum achieved concentration should be calculated at the maximum anticipated enclosure temperature, and compared to NOAEL / LOAEL values, see Table 3
The Novec™ 1230 cupburner value* is 45% for commercial grade Heptane, and an extinguishing concentration of 35% for Class A materials
Calculations to determine minimum design concentration:
Cupburner or fire test concentration x safety factor
Safety factor: Class A = 12Class B = 13Class C = Class A
For Class A (Determined by fire test) -35 x 12 = 42%
For Class B (Commercial grade Heptane)-45% x 13 = 585%
For Class B (Other class B fuels)-cupburner x 13 = design concentration
For Class C -Use at least design concentration for Class A surfaces fires (42%)
For systems with only manual actuation -cupburner x 13 = design concentration but not less than 585%
Rugged environments, and those requiring intrinsically safe or flameproof equipment, require special consideration and should be discussed fully with the technical support centre before finalising a system design Novec™ 1230 is suitable for use with the following materials:
Class A Fires involving solid materials usually of an organic nature, in which combustion normally takes place with the formation of glowing embers
Class B Fires involving flammable liquids or liquefiable solids and flammable gases
Class C Fires involving energized electrical equipment where the electrical nonconductivity of the extinguishing media is of importance
* Cupburner and Cupburner value as defined in NFPA 2001
29
SECTION 3 - SYSTEM DESIGN
SAPPHIRE (UL)570805002011-03
Note: Certain materials in this group may require increased concentrations to achieve satisfactory extinguishment Consult the technical support centre for details of specific risk
Hazard VolumeIn total flooding applications the risk area must comprise an enclosed space with no significant openings so that the design concentration can be achieved and maintained Generally, the calculation is based on an empty area; the subsequent furniture and fittings having little effect on the actual concentration Similarly, large equipment cabinets and control panels should not be considered in the calculation as it is assumed that the internal area is required to be filled with agent
Each enclosed space is considered as a risk area and requires at least one nozzle A floor void, ceiling void, cable duct, etc, is treated as a separate adjacent area and requires simultaneous discharge to occur
Ceiling obstructions such as beams that are less than 300 mm (12 in) below the slab need not be considered Obstructions greater than 300 mm (12 in) can affect the distribution of agent and may require additional nozzles Consult the technical support centre if in doubt
To determine the volume refer to the site drawings, ensuring that the scale is accurate and that heights are denoted, or make a sketch of the area adding dimensions and any relevant details Calculate the volume of each area
Hazard StructureThe protected enclosure shall be bounded by rigid elements of building construction The ceiling should be not less than 03 m (1 ft) above the hazard
During agent discharge, the hazard enclosure will experience a pressure change Consideration should be given to mitigating these pressure changes
30
SECTION 3 - SYSTEM DESIGN
! CAUTION
Novec™ 1230 is not effective on the following: -
• Class A Deep seated fires
• Class D Combustible metals
• Chemicals capable of auto-thermal recomposition
• Chemicals capable of rapid oxidation
• Enclosures with hot surfaces (>400 °C) (752 °F)
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
VentilationIf the hazard enclosure has no means of adequate venting after discharge, consideration should be given to installing a normally closed means of ventilation with extraction arrangements which will discharge directly to atmosphere
Air conditioning and/or forced ventilation can affect the system performance and the quantity of agent required
(i) Self-contained air conditioning unit
A self-contained unit conditions the air within the enclosure and does not rely on a fresh air supply, or draw air from other parts of the building
If the hazard has a self-contained unit and it is located within the area without an outside air supply, no additional agent is required It is not necessary to shut down the unit prior to a discharge as the mixing effect is beneficial
(ii) Central air conditioning unit
A central air conditioning unit relies on air from outside and is often linked by ducts to other parts of the building, therefore, prior to a discharge, the unit should be shut down and/or dampers operated to close the ducts Sufficient time must be allowed for the plant to stop, or dampers to close, before discharge occurs
Dampers should be installed in both supply and return air ducts, as close as possible to the area The duct volume between the hazard and the damper must be added to the overall volume
Hazard TemperatureDetermine as accurately as possible the anticipated minimum and maximum temperatures likely to be experienced within the protected area Minimum agent quantity requirements are based on minimum temperature At maximum temperature, hazard concentration must not exceed the NOAEL/LOAEL values for normally occupied spaces, reference NFPA 2001, “Safety” section
Agent QuantitiesNormally the agent quantity is the weight required to produce the desired concentration at the lowest temperature within the hazard enclosure
Agent StorageNovec™ 1230 is stored as a liquid in appropriate containers to meet IS 7285 (Part 2): 2004 requirements Nitrogen in the container maintains a superpressurisation of 25 bar at 21 °C (360 psi at 70 °F) The chosen location should provide protection from severe weather, mechanical, chemical, or other types of damage
Once assembled, filled and pressurised the SAPPHIRE extinguishing system should not be exposed to temperatures outside the storage/operating temperature range of 0 to 55 °C (32 °F to 130 °F) This also includes while being in storage or transported
Hydraulic calculations assume an agent temperature of 21 °C (70 °F) When the storage temperature varies by 55 °C (10 °F), there is a risk that the system will not supply the designed quantity of extinguishing agent
Hazard FuelsAll fuels in the hazard must be identified and the corresponding agent concentration requirements assessed The design concentration (percent by volume) required for the hazard will be the highest concentration required by any one of the fuels present in the hazard
Personnel Safety
Symptoms of overexposure to concentrations greater than 100% may include dizziness, impaired coordination, reduced mental acuity, cardiac effects or unconsciousnessIn the event of overexposure, remove to fresh air immediately and summon medical assistance
31
SECTION 3 - SYSTEM DESIGN
! WARNING
Direct skin contact with Novec™ 1230 in the immediate area of discharge may cause frostbite
! CAUTION
To avoid possible injury, avoid any exposure to Novec™ 1230 in volume concentrations greater than 10% unless using self contained breathing apparatus Limit exposure times as in NFPA 2001, “Safety” section
SAPPHIRE (UL)570805002011-03
ManifoldsIt may be necessary to manifold agent containers to provide the required amount of agent for a hazard, or to make available the proper increments of agent weight for the protection of multiple hazards
Whenever containers are manifolded, the following rules must be observed
1 All containers connected to the same manifold or pipe must be the same size and filled with the same agent weight, pressure and fill density
2 Agent containers must be located in a single row and spaced according to section
3 A connected reserve may be employed in some circumstances providing a secondary supply of agent
4 Flexible discharge hoses and check valves must be used at each inlet
Agent DistributionDistribution piping will be installed only with approved piping as indicated in Section 5
Pipe size reductions may be made by using reducing tees or reducing bushings or reducing couplings
32
SECTION 3 - SYSTEM DESIGN
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Agent Flow Characteristics
Nitrogen SuperpressurisationNitrogen is added to the SAPPHIRE containers This addition of nitrogen, known as superpressurisation, will cause a portion of the nitrogen to mix with the Novec™ 1230, the remaining portion of the nitrogen will remain in the vapour space above the liquid providing the increased propulsion necessary to discharge the Novec™ 1230 from the container
Flow in PipeIn a properly designed distribution piping network the flow of Novec™ 1230 will consist of a two phase mixture of liquid and vapour The properties of this mixture will vary with its composition; therefore, when the mixture contacts the pipeline walls, the friction decreases the density of the mixture resulting in a non-linear pressure drop and an increase in flow velocity
Another consequence of two-phase flow is the potential for separation of liquid and vapour In a properly designed pipe network, the velocity of the mixture will be high enough to maintain highly turbulent flow However, if the pipeline diameter is too large for the design flow rate, the two phases may separate, leading to alternate discharges of liquid and vapour (slugging) or layering of the two phases Therefore, the pipeline must be properly sized to keep the Novec™ 1230 flow turbulent enough to prevent phase separation
Initial Vapour DischargeAt the instant the discharge valve is opened, rapid expansion of the agent will cool the piping network
Trailing Vapour PressureDischarge time is defined as the average liquid discharge time through all nozzles in the system After the liquid portion of the discharge has been completed, there will be a short transition period followed by the delivery of the remaining Novec™ 1230 nitrogen mixture as a vapour This is due to flashing of the trailing edge of the fluid as it moves from the tank to the nozzles In some systems the transition period is relatively long; this can lead to confusion as to when the discharge is complete, possibly resulting in an inaccurate measurement of the discharge time
Nozzle Selection and LocationThe number of nozzles required is based on the hazard size and configuration and the coverage provided by the nozzle Nozzles are available in 7-port or 16-port versions to provide 180 or 360 degree discharge patterns respectively When considering the optimum nozzle location, the following factors should be taken into account
• Nozzle location is affected by the shape of the hazard area
• The maximum discharge radius is 91 m (30 ft) for a 360° nozzle and 150 m (4925 ft) for a 180° nozzle
• The maximum coverage area for either nozzle is 1672 m² (1800 ft²)
• Nozzle orifices must not be placed where they may discharge into nearby objects
• Nozzles must be installed a maximum of 300 mm (12 in) below the ceiling
• 43 m (14 ft) maximum protection height for a single row of 360° and 180° nozzle For ceiling heights over 43 m additional rows of nozzles may be added
• 180° nozzles must be mounted adjacent to a wall and must be located to cover the entire area
• 300 mm (12 in) minimum void height (ie Sub-floors and false ceilings)
• Sub-floor nozzles may be positioned either vertically down from the top of the sub-floor or vertically up from the bottom of the sub-floor
• Maximum distance 180° nozzles should be placed from a wall 300 mm (12 in), the minimum 50 mm (2 in) Measured from centre of the nozzle to the wall
• Nozzles located both above and below the container outlet, Maximum distance between them 91 m (30 ft)
• Nozzles located either above or below the container outlet, maximum distance between them 91 m (30 ft)
33
SECTION 3 - SYSTEM DESIGN
SECTION 3 - SYSTEM DESIGNHYGOOD
34 FM-200® Installation Guide/11100/02.08.05/Issue 3.3
Maximum Limits in Pipe Work.Figure 25a -
Figure 25b -
Figure 25c -
If nozzles are only located above thecontainer outlet, then the maximum elevation differencebetween the container outlet and the furthest horizontalpipe run or discharge nozzle (whichever is furthest) shallnot exceed 91m (30 ft) See figure 25a
If nozzles are only located below thecontainer outlet, then the maximum elevation differencebetween the container outlet and the furthest horizontalpipe run or discharge nozzle (whichever is furthest) shallnot exceed 91m (30 ft) See Figure 25b
If nozzles are located both above andbelow the container outlet, then the maximum distancebetween the furthest horizontal pipe runs, or dischargenozzles (whichever is further) shall not exceed 91m (30ft) See figure 25c
Note: If a system design violatesthese limits, contact Macron SafetySystems to determine what actionhas to be taken
Examples:
SECTION 3 - SYSTEM DESIGNHYGOOD
34 FM-200® Installation Guide/11100/02.08.05/Issue 3.3
Maximum Limits in Pipe Work.Figure 25a -
Figure 25b -
Figure 25c -
If nozzles are only located above thecontainer outlet, then the maximum elevation differencebetween the container outlet and the furthest horizontalpipe run or discharge nozzle (whichever is furthest) shallnot exceed 91m (30 ft) See figure 25a
If nozzles are only located below thecontainer outlet, then the maximum elevation differencebetween the container outlet and the furthest horizontalpipe run or discharge nozzle (whichever is furthest) shallnot exceed 91m (30 ft) See Figure 25b
If nozzles are located both above andbelow the container outlet, then the maximum distancebetween the furthest horizontal pipe runs, or dischargenozzles (whichever is further) shall not exceed 91m (30ft) See figure 25c
Note: If a system design violatesthese limits, contact Macron SafetySystems to determine what actionhas to be taken
Examples:
SECTION 3 - SYSTEM DESIGNHYGOOD
34 FM-200® Installation Guide/11100/02.08.05/Issue 3.3
Maximum Limits in Pipe Work.Figure 25a -
Figure 25b -
Figure 25c -
If nozzles are only located above thecontainer outlet, then the maximum elevation differencebetween the container outlet and the furthest horizontalpipe run or discharge nozzle (whichever is furthest) shallnot exceed 91m (30 ft) See figure 25a
If nozzles are only located below thecontainer outlet, then the maximum elevation differencebetween the container outlet and the furthest horizontalpipe run or discharge nozzle (whichever is furthest) shallnot exceed 91m (30 ft) See Figure 25b
If nozzles are located both above andbelow the container outlet, then the maximum distancebetween the furthest horizontal pipe runs, or dischargenozzles (whichever is further) shall not exceed 91m (30ft) See figure 25c
Note: If a system design violatesthese limits, contact Macron SafetySystems to determine what actionhas to be taken
Examples:
SAPPHIRE (UL)570805002011-03
Maximum Limits (Elevation) in Pipe WorkExamples:
If nozzles are only located above the container outlet, then the maximum elevation difference between the container outlet and the furthest horizontal pipe run or discharge nozzle (whichever is furthest) shall not exceed 91 m (30 ft) See Figure 29
If nozzles are only located below the container outlet, then the maximum elevation difference between the container outlet and the furthest horizontal pipe run or discharge nozzle (whichever is furthest) shall not exceed 91 m (30 ft) See Figure 30
If nozzles are located both above and below the container outlet, then the maximum distance between the furthest horizontal pipe runs, or discharge nozzles (whichever is further) shall not exceed 91 m (30 ft) See Figure 31
Figure 29 - Nozzles Located Above the Container Outlet
Figure 30 - Nozzles Located Below the Container Outlet
Figure 31 - Nozzles Located Above and Below the Container Outlet
9.1 m (30 ft) 9.1 m (30 ft)4.5 m (15 ft)
9.1 m (30 ft) 9.1 m (30 ft)4.5 m (15 ft)
9.1 m (30 ft)
Note: If a system design violates these limits, contact the technical support centre to determine what action has to be taken
34
SECTION 3 - SYSTEM DESIGN
HYGOODSECTION 3 - SYSTEM DESIGN
FM-200® Installation Guide/11100/02.08.05/Issue 3.3 35
Figure 26 - Nozzle Discharge Radius System Design ProcedureThe following procedure must be followed when design-ing FM-200® systems
• Determine hazard material and required designconcentration
• Identify individual enclosure volumes and deductany impermeable volumes where appropriate
• Determine hazard altitude and correction factor
• Calculate quantity of FM-200® per enclosure, atminimum design temperature
• Determine container size and fill density
• Select nozzle type and location
• Design pipe network
• Calculate quantity of FM-200® per nozzle
• Check percentage agent split at tee's
• Identify all pipe lengths, rises, falls and nozzlereference numbers
Note: The side tee splits shall be between 10-30%,bull tee splits will be between 30-70% All Tee out-lets must be in the same horizontal plane
See examples figure 27 a-f
Example: Nozzle Selection
Switch Room:
120.7m3 (4262.6ft3) 1 x 7 port nozzle
Computer Room:
543.3m3 (19237.1ft3) 4 x 8 port nozzles
Floor Void:
63.36m3 (2275.4ft3) 2 x 8 port nozzles
Nozzle placement and piping arrangements for the exam-ple are shown in Figure 28
(286ft)
(33ft)
87m
1005m
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Figure 32 - Nozzle Discharge Radius
Example: Nozzle Selection
Switch Room: 120.8 m³ (4264.2 ft³)
1 x 7 port nozzle
Computer Room: 537.6 m³ (18985.2 ft³)
4 x 16 port nozzles
Floor Void: 65.3 m³ (2305.3 ft³)
2 x 16 port nozzles
Nozzle placement and piping arrangements for the example are shown in Figure 39
System Design ProcedureThe following procedure must be followed when designing SAPPHIRE systems
• Determine hazard material and required design concentration
• Identify individual enclosure volumes and deduct any impermeable volumes where appropriate
• Determine hazard altitude and correction factor
• Calculate quantity of Novec™ 1230 per enclosure, at minimum design temperature
• Determine container size and fill density
• Select nozzle type and location
• Design pipe network
• Calculate quantity of Novec™ 1230 per nozzle
• Check percentage agent split at tee’s
• Identify all pipe lengths, rises, falls and nozzle reference numbers
Note: The side tee splits shall be between 10-35%, bull tee splits will be between 30-70% All Tee outlets must be in the same horizontal plane
See examples Figures 33 to 38
7 PORT
16 PORT
30.1 ft
49.2 ft
15.0 m
9.2 m
Nozzle Discharge Radius
The maximum discharge radius is 91 m (30 ft) for a 360° nozzle and 150 m (4925 ft) for a 180° nozzle
35
SECTION 3 - SYSTEM DESIGN
SAPPHIRE (UL)570805002011-03
Example: Tee Split Designs
Figure 33 - Side Tee Split limits.
Figure 35 - Side tee orientation “correct”
Figure 37 - Bull tee orientation “correct”
Figure 34 - Bull Tee Split limits.
Figure 36 - Side tee orientation “incorrect”
Figure 38 - Bull tee orientation “incorrect”
Note: Incorrect orientation of side and bull tee could result in separation of the Novec™ 1230 from the Nitrogen (due to Novec™ 1230 greater density) The design would also be outside the parameters permitted by the calculation software See Figures 36 and 38
Incorrect Tee Splits
Correct Tee Splits
Minimum length of 10 x nominal pipe diameter
Minimum length of 10 x nominal pipe diameter
90-65%
10-35%
30-70%
70-30%
Correct Tee Splits
Incorrect Tee Splits
Minimum length of 10 x nominal pipe diameter
Flow
Flow
Flow
Flow
Flow
Flow
36
SECTION 3 - SYSTEM DESIGN
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Design Example - CalculationsMinimum Agent Quantity is based on the hazard volume at the minimum anticipated temperature and concentration required To determine the minimum agent quantity the following equation is used:
W = (V/S) (C/100-C)
W = Weight of agent required (kg)
V = Hazard volume (m³)
S = Specific Vapour Volume (m³/kg)
S = 00664 + 0000274t
t = Design Temperature in Hazard Area (°C)
C = Required Novec™ 1230 Design Concentration (% by
volume) at Design Temperature (t)
Example:Calculation for two rooms and floor void with the following dimensions:
Switch Room: 70 x 69 x 25 = 1208 m³
Computer Room: 160 x 120 x 28 = 5376 m³
Floor Void: 160 x 120 x 034 = 653 m³
t = 21 °C for calculation example
Switch Room: (520% required design concentration example only)
W = 1208 x 52 = 918 kg0072154 (100-52)
Computer Room: (52% required design concentration example only)
W = 5376 x 52 = 4087 kg0072154 (100-52)
Floor Void: (52% required design concentration example only)
W = 653 x 52 = 496 kg0072154 (100-52)
When the minimum quantity of Novec™ 1230 has been calculated the weight is compared to the available agent container size The container size must be equal to or greater then the weight of agent (see Table 4)
With the appropriate container selected, the previous equation can be rearranged to determine the concentration based on the actual weight as containers are filled to the nearest kilogram
C = 100 WS WS + V
To calculate the required agent for each hazard volume as a percentage of the total agent required;
% Hazard Agent = Individual hazard volumeSum of hazard volumes
Switch Room: 1208/7237 = 167% of agent
Computer Room: 5376/7237 = 743% of agent
Floor Void: 653/7237 = 90% of agent
It is determined from the above that both the Switch Room and the Computer Room can be fed by one manifolded system using 5 x 120 litre containers, each filled with 101 kg of agent The Floor Void would use 1 x 80 litre container filled with 50 kg as it requires less than 10% of the total agent and therefore equates as follows (Separate tank is required for floor voids If protected with nozzle from computer room system, the piping would be outside the tee split limits)
Switch Room: 1208/6584 = 183% of agent
Computer Room: 5376/6584 = 817% of agent
Floor Void: 653/653 = 100% of agent
Actual agent to Switch Room :
0183 x 5 x 101 = 924 kg
Agent to Computer Room :
(5 x 101) - 924 = 4126 kg
37
SECTION 3 - SYSTEM DESIGN
SECTION 3 - SYSTEM DESIGNHYGOOD
38 FM-200® Installation Guide/11100/02.08.05/Issue 3.3
After determining the minimum weight and concentra-tion, the maximumconcentration can be determined byrecalculating the equation based on the maximum tem-perature anticipated in each enclosure 270C (800F) maxi-mum design temperature This calculation is required todetermine if the maximum concentration is below theNOAEL limit for normally occupied areas
Switch Room: C = 100 x 1502 x 22538 = 736% (1502 x 2253) + 42626
Computer Room: C = 100 x 6778 x 22538 = 736% (6778 x 2253) + 192371
Floor Void: C = 100 x 80 x 22538 = 734% (80 x 2253) + 22754
The minimum enclosure concentrations can be calcu-lated based on the actual container fill (70oF minimumdesign temperature)
Switch Room: C = 100 x 1502 x2207 = 722% (1502x2207)+42626
Computer Room: C = 100 x 6778 x 2207 = 722% (6778 x 2207)+192371
Floor Void: C = 100 x 80 x 2207 = 72% (80 x 2207) + 22754
Figure 28 - Example Nozzle Location
Switch Room: 42626/234997 = 1814% of Agent
Computer Room: 192371/234997 = 819% of Agent
Floor Void: 22754/22754 = 100% of Agent
Actual agent to switch Room :
01814 x 3 x 276 = 1502 lbs
Agent to Computer room :
3 x 276 - 1502 = 6778
SAPPHIRE (UL)570805002011-03
The minimum enclosure concentrations can be calculated based on the actual container fill (21 °C minimum design temperature)
Switch C = 100 x 924 x 0072154 = 523%Room: (924 x 0072154) + 1208
Computer C = 100 x 4126 x 0072154 = 525%Room: (4126 x 0072154) + 5376
Floor Void: C = 100 x 496 x 0072154 = 520%(496 x 0072154) + 653
After determining the minimum weight and concentration, the maximum concentration can be determined by recalculating the equation based on the maximum temperature anticipated in each enclosure 27 °C maximum design temperature This calculation is required to determine if the maximum concentration is below the NOAEL limit for normally occupied areas
Switch C = 100 x 924 x 0073798 = 534%Room: (924 x 0073798) + 1208
Computer C = 100 x 4126 x 0073798 = 536%Room: (4126 x 0073798) + 5376
Floor Void: C = 100 x 496 x 0073798 = 531%(496 x 0073798) + 653
Figure 39 - Example Nozzle Location
38
SECTION 3 - SYSTEM DESIGN
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Piping PracticesDue to the two phase flow of Novec™ 1230, certain piping practices must be adhered to, mainly that the flow split must be on the horizontal plane There are two types of tee used in SAPPHIRE systems, a through/side tee and a bull tee Both have limitations on the minimum and maximum allowable flow splits which are detailed on page 36
It should also be noted that system designers shall allow a minimum of 10 times the nominal pipe diameter around tee splits before any change of direction
System designers should aim to design as far as possible balanced pipe networks, use minimum lengths of pipe, use minimum numbers of elbows, maximize pipe volume before the first tee and incorporate similar pipe run lengths to nozzles
39
SECTION 3 - SYSTEM DESIGN
SAPPHIRE (UL)570805002011-03
IntroductionIn determining the quantity of Novec™ 1230 required for a particular application, it is important to assess the hazard area correctly The following information will need to be determined as discussed in Section 3
1 Hazard Volume
2 Minimum Room Temperature
3 Hazard Type
4 Height above sea-level
The Hazard volume can be determined by calculating the room volume and deducting any impermeable volumes that may be contained within the area The anticipated temperature of the Hazard area will normally be advised by the client The agent concentration is dependant upon the type of hazard being protected and hazard altitude The quantity of Novec™ 1230 can be calculated by using the flooding factors (Table 8: Metric / Table 9: Imperial) or by using the formula (Novec™ 1230 Equation Calculations) and then multiplying by the altitude correction factor (Table 10)
Example:
Hazard Volume: 280 m³Room Temperature: 20 °CAgent Concentration: 42%Flooding Factor: 060992
Quantity of Novec™ 1230 required: 0.60992 x 280 = 170.8 kg
Note: Specific Vapour Volume data shown in Tables 8 and 9 are experimentally derived values and the specific vapour volume equation (S) has a correlation coefficient of 099 However the equation can be used to give a close approximation of required agent quantities
Table 8: Novec™ 1230 Weight Calculations Metric
40
SECTION 4 - FLOW CALCULATIONS
Temp Specific Vapor
Volume
Weight Requirements of Hazard Volume, W/V (kg/m3)Design Concentration (% per volume)
4.2 5.3 5.5 5.6 5.85 5.9 6 7 8
t (°C)
s (m3/kg)
0 0.0664 0.66026 0.84286 0.87652 0.89340 0.93577 0.94427 0.96129 1.13357 1.30959
5 0.0678 0.64691 0.82583 0.85880 0.87534 0.91685 0.92518 0.94186 1.11065 1.28311
10 0.0691 0.63410 0.80946 0.84179 0.85800 0.89868 0.90684 0.92320 1.08864 1.25769
15 0.0705 0.62177 0.79373 0.82543 0.84133 0.88122 0.88923 0.90526 1.06749 1.23325
20 0.0719 0.60992 0.77861 0.80970 0.82529 0.86443 0.87228 0.88800 1.04715 1.20975
25 0.0733 0.59852 0.76404 0.79455 0.80986 0.84826 0.85596 0.87140 1.02756 1.18712
30 0.0746 0.58753 0.75002 0.77997 0.79499 0.83268 0.84025 0.85540 1.00869 1.16532
35 0.0760 0.57694 0.73649 0.76590 0.78066 0.81767 0.82510 0.83998 0.99051 1.14432
40 0.0774 0.56672 0.72345 0.75234 0.76683 0.80319 0.81049 0.82510 0.97297 1.12405
45 0.0787 0.55686 0.71086 0.73925 0.75349 0.78921 0.79638 0.81074 0.95604 1.10449
50 0.0801 0.54733 0.69870 0.72660 0.74060 0.77572 0.78276 0.79688 0.93969 1.08560
55 0.0815 0.53813 0.68695 0.71439 0.72815 0.76267 0.76960 0.78348 0.92388 1.06734
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Table 9: Novec™ 1230 Weight Calculations Imperial
Table 10: Altitude Correction FactorAt elevations above sea-level, Novec™ 1230 has a greater specific volume because of the reduced atmospheric pressure A system designed for sea-level conditions will therefore develop an actual higher concentration at levels above sea-level and an actual lower concentration at levels below sea-level The adjusted agent quantity is calculated by multiplying W (from the equation on the left) by the altitude correction factor The design quantity of the clean agent shall be adjusted to compensate for ambient pressure that vary more than 11 percent (equivalent to approximately 915 m (3000 ft) of elevation change) from standard sea level pressure 760 mm Hg at 0 °C (2992 in Hg at 70 °F)
(BS5306-51 / NPFA2001 Table 3-6)
41
SECTION 4 - FLOW CALCULATIONS
Temp Specific Vapor
Volume
Weight Requirements of Hazard Volume, W/V (lb/ft3)Design Concentration (% per volume)
4.2 5.3 5.5 5.6 5.85 5.9 6 7 8
t (°F)
s (ft³/lb)
30 1.0588 0.04141 0.05286 0.05497 0.05603 0.05868 0.05922 0.06028 0.07109 0.0821340 1.0832 0.04047 0.05167 0.05373 0.05476 0.05736 0.05788 0.05892 0.06948 0.0802750 1.1077 0.03958 0.05053 0.05254 0.05356 0.05610 0.05661 0.05763 0.06795 0.0785160 1.1321 0.03873 0.04944 0.05141 0.05240 0.05489 0.05539 0.05638 0.06649 0.0768170 1.1565 0.03791 0.04839 0.05033 0.05130 0.05373 0.05422 0.05519 0.06508 0.0751980 1.1809 0.03713 0.04739 0.04929 0.05024 0.05262 0.05310 0.05405 0.06374 0.0736490 1.2053 0.03637 0.04643 0.04829 0.04922 0.05155 0.05202 0.05296 0.06245 0.07215
100 1.2297 0.03565 0.04551 0.04733 0.04824 0.05053 0.05099 0.05191 0.06121 0.07071110 1.2541 0.03496 0.04463 0.04641 0.04730 0.04955 0.05000 0.05090 0.06002 0.06934120 1.2785 0.03429 0.04377 0.04552 0.04640 0.04860 0.04904 0.04992 0.05887 0.06801130 1.3029 0.03365 0.04295 0.04467 0.04553 0.04769 0.04812 0.04899 0.05777 0.06674140 1.3273 0.03303 0.04216 0.04385 0.04469 0.04681 0.04724 0.04809 0.05671 0.06551
Altitude above sea-level
Correction Factor
ft (km)-3000 (-0.92) 1.11-2000 (-0.61) 1.07-1000 (-0.30) 1.04
0 (0.00) 1.001000 (0.30) 0.962000 (0.61) 0.933000 (0.91) 0.894000 (1.22) 0.865000 (1.52) 0.826000 (1.83) 0.787000 (2.13) 0.758000 (2.45) 0.729000 (2.74) 0.69
10000 (3.05) 0.66
SAPPHIRE (UL)570805002011-03
Engineered SystemsEngineered systems are based on a Hydraulic Flow Program developed by Hughes Associates Inc The program predicts the two phase flow of Novec™ 1230 and nitrogen through a pipe network Information detailing the enclosure is entered and the program calculates the required pipe sizes, nozzle drill sizes, average nozzle pressures and discharge time For further information on the Flow Program, refer to the Hughes Flow Program User’s Manual
As system design calculations are critical to the success of the extinguishing system, only trained personnel are permitted to perform system calculations If in the future, other companies wish to use the program, representatives will be required to attend a formal training session All system calculations are conducted ‘in house’ or by authorised suppliers
Note: The calculation method has been designed for specific types of fittings, pipes, and pipe inside diameter When these limitations are not maintained, there is a risk that the system will not supply the required quantity of extinguishing agent
Program ParametersWhen designing pipe network systems, the following design parameters should be considered to avoid system reject when running the calculation
• 50 bar (73 psi) minimum nozzle pressure
• 80% maximum agent in pipe
• Between 6 - 10 seconds discharge time
• 10 - 35 % side tee split
• 30 -70 % bull tee split
• 05 kg/l (312 lb/ft³) - 12 kg/l (749 lb/ft³) fill density
• Max liquid arrival time imbalance of 10 seconds
• Maximum liquid run out time of 20 seconds
• Maximum nozzle height is 43 m (140 ft)
• Minimum of 10% agent in pipe before first tee
• Maximum of 20 nozzles per system
• Maximum of 10 enclosures per system
• The ratio between the nozzle area and the pipe cross sectional area immediately preceding the nozzle is limited to a minimum of 020 (20%) and a maximum of 080 (80%)
(For extended discharge consult the technical support centre)
Table 11 : Max. & Min. Flow Rates
Novec™ 1230 Equation CalculationsThe weight of agent required for a hazard area can also be calculated from the formula shown below;
W = (V/S) (C/100-C)
W = Weight of agent required kg (lb)
V = Hazard volume m³ (ft³)
S = Specific Vapour Volume cum/kg (ft³/lb)
where S = 00664 + 0000274 t (°C)
or S= 09856 + 0002441 t (°F)
t = Design Temperature in Hazard Area °C (°F)
C = Required Novec™ 1230 Design Concentration (% by volume) at Design Temperature (t)
42
SECTION 4 - FLOW CALCULATIONS
Pipe Size
mm (in.)
Minimum flow rate kg/s (lb/s)
Maximum flow rate kg/s (lb/s)
15 (½) 0.454 (1.00) 1.361 (3.00)20 (¾) 0.907 (2.00) 2.495 (5.50)25 (1) 1.588 (3.50) 3.855 (8.50)
32 (1¼) 2.722 (6.00) 5.67 (12.50)40 (1½) 4.082 (9.00) 9.072 (20.00)50 (2) 6.35 (14.00) 13.61 (30.00)
65 (2½) 9.072 (20.00) 24.95 (55.00)80 (3) 13.61 (30.00) 44.92 (99.00)
100 (4) 24.95 (55.00) 56.7 (125.00)125 (5) 40.82 (90.00) 90.72 (200.00)150 (6) 54.43 (120.00) 136.1 (300.00)
Note: This information is for Schedule 40 pipe, and serves as an estimate onlyPipe and nozzle sizes need to be confirmed by the computer programme
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Table 12 : Equivalent Length for Pipe Fittings
Equivalent length table for pipe fittings.Figures based upon schedule 40 ASTM A 106 - 77 pipe(nominal pipe size given in table)
Table 13 : Equivalent Length for Other System Components
Figures based upon schedule 40 ASTM A 106- 77 pipe (nominal pipe size given in table)
43
SECTION 4 - FLOW CALCULATIONS
Diameter 90° Elbow 45° Elbow Thru Tee Side Tee Unionm (in.) m (ft) m (ft) m (ft) m (ft) m (ft)15 (1/2) 0.52 (1.6) 0.24 (0.7) 0.3 (0.9) 1.04 (3.2) 0.12 (0.4)20 (3/4) 0.67 (2.0) 0.3 (0.9) 0.42 (1.3) 1.37 (4.2) 0.15 (0.5)25 (1) 0.85 (2.6) 0.4 (1.2) 0.55 (1.7) 1.74 (5.3) 0.18 (0.6)32 (1¼) 1.13 (3.4) 0.52 (1.6) 0.7 (2.1) 2.29 (7.0) 0.24 (0.7)40 (1½) 1.31 (4.0) 0.61 (1.7) 0.82 (2.5) 2.65 (8.0) 0.27 (0.8)50 (2) 1.68 (5.1) 0.79 (2.4) 1 .06 (3.2) 3.41 (10.4) 0.37 (1.1)65 (2½) 2.01 (6.1) 0.94 (1.5) 1.25 (3.8) 4.08 (12.4) 0.43 (1.3)80 (3) 2.5 (7.6) 1.16 (3.5) 1.55 (4.7) 5.06 (15.4) 0.55 (1.7)
100 (4) 3.26 (10.0) 1.52 (4.6) 2.01 (6.1) 6.64 (20.2) 0.73 (2.2)125 (5) 4.08 (12.4) 1.92 (5 .9) 2.56 (7.8) 8.35 (25.5) 0.91 (2.8)150 (6) 4.94 (15.0) 2.32 (7.1) 3.08 (9.4) 10 (30.5) 1.07 (3.3)
Hardware Set Size Equivalent length
Valve 50 mm (2 in.) 10.668 m (35 ft)Flex Hose 50 mm (2 in.) 5.36 m (17.6 ft)Flex Hose and Check Valve Combination 50 mm (2 in.) 12.02 m (39.4 ft)
Valve Outlet Adaptor 50 mm (2 in.) 0.37 m (1.2 ft)
SAPPHIRE (UL)570805002011-03
General InformationAll installation shall be carried out by an approved contractor with the correct equipment and previous experience of gaseous extinguishing systems The supplier can provide this service or provide a list of their factory trained installation contractors Installation instructions are described under the following main headings, and in the order of installation
• Container Installation
• Piping and Nozzles
• Actuation Controls
• Ancillary Equipment
• Completion Procedures
Specific installation drawings must be prepared for the hazard area in accordance with system design as calculated by the Novec™ 1230 Hydraulic Flow Program These drawings should be followed closely in order to ensure the system meets its design criteria The pipe network is sized in order to obtain correct discharge time, nozzle pressures, agent quantity and various other design considerations If for any reason, the pipe network requires modifications the system must be recalculated before proceeding with installation Installation drawings contain the following information;
• Enclosure Volumes
• Agent Quantities
• Scaled Pipe Network Plan
• Pipe Network Isometric
• Pipe Diameters, Pipe Length Drops & Rises
• Nozzle Data
• Container Data
• Solenoid Actuator Technical Data
• Low Pressure Switch Wiring Chart
• Fittings Data
Installation drawings shall be submitted for approval to the appropriate authority prior to system installation
On receipt, unpack the supplied items and ensure that the components comply with the packing list and installation drawings
The container weight is checked at the factory prior to dispatch, and recorded on the label attached to the container If there is any doubt regarding the weight, or leakage is suspected, the container should be weighed to confirm there is no weight loss
Container InstallationThe container location is identified on the system drawings and should be protected from extremes of temperature, and be accessible for service and maintenance The containers must be firmly secured to a wall or bulkhead, in a vertical orientation only
Figure 40 - Outlet Anti-Recoil and Actuation Caps
Anti-Recoil Caps
50 mm (2 in.) 2 in. BSP Brass Part No. 570554
Actuation Cap
25 mm (1 in.) 1 in. BSP Plastic
ANTI-RECOIL CAP
ACTUATION CAP
44
SECTION 5 - INSTALLATION
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Single Container Installation1 Fix the back channels of the mounting brackets to the
wall at the appropriate heights (see Table 14), using suitable anchor type bolts (not supplied)
2 Position the container against the back channel with the valve outlet pointing left
3 Insert the container straps at top and bottom and secure with the bolts provided (see Figure 42)
4 Remove the anti-recoil cap from the valve outlet (see Figure 40)
5 With the anti-recoil cap removed from the valve outlet, install a union coupling
Figure 41 - Discharge Outlet Connections.6 Install the initial pipe run and then disconnect the container and refit the anti-recoil cap to the valve outlet
7 Re-connect the pipe to the container after the pipework system is complete and the discharge nozzles have been installed
ELBOW
PIPEUNION COUPLING
45
SECTION 5 - INSTALLATION
! CAUTION
Do not over tighten the container connection Excessive tightening may cause the valve outlet thread to be damaged and adversely affect the system operation
400 mm
1289 mm
SAPPHIRE (UL)570805002011-03
Table 14: Bracket Fixing Heights
Figure 42 - Container Strap Location
46
SECTION 5 - INSTALLATION
Container Size
No. of Unistrut
Channels
Height From Floor to Centre of Channel Bracket
mm (in.)
80 litre: 40 to 96 kg(88 to 211 lb) 2 400, 1289 (15.75, 50.25)
120 litre: 60 to 144 kg(132 to 317 lb) 2 400, 1289 (15.75, 50.25)
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Multiple Container InstallationContainers are manifolded together for three main reasons;
• To reduce the amount of piping required by connection to one feeder pipe
• For systems that require main and reserve
• Combining the correct containers to obtain the required quantity of agent within a specific hazard area
A typical 80 mm (3 in), three port manifold assembly consists of the manifold, three check valves and an end cap Each check valve is screwed to the manifold
1 Fix the back channels of the mounting brackets to the wall at the appropriate heights (see Table 14), using suitable anchor type bolts (not supplied)
2 Position the containers against the back channels with the valve outlets pointing left at the required spacing for the manifold ports
3 Insert the container straps at top and bottom and secure with the bolts provided (see Figure 42)
Manifold Bracket Installation1 Fix the two back vertical channels to the wall at the
appropriate height using suitable anchor type bolts (see Table 15)
Back channels are used to ensure that the appropriate height adjustment is available when connecting the discharge hose from the valve outlet to the manifold check valve (see Figure 43)
2 Locate and secure the cantilever brackets to each channel using M10 x 40 mm Hex Head screw and uninut long spring 10 mm
3 Locate manifold brackets in cantilever channel and unirax end caps
4 Remove anti-recoil cap and attach discharge hose between valve and manifold Adjust cantilever height as required and secure in position
5 For safety remove discharge hose and replace safety caps, while pipework is installed
47
SECTION 5 - INSTALLATION
SAPPHIRE (UL)570805002011-03
Table 15: Manifold Bracket Fixing Heights
FINISHED FLOOR LEVEL
Figure 43 - Manifold Assembly
48
SECTION 5 - INSTALLATION
Container Size
Valve Size
mm (in.)
Manifold Size
mm (in.)
Nominal Height from Floor to top of cantilever
mm (in.)
80L 40 to 96 kg
(88 to 211 lb)
50 (2)
80 (3)
2195 (86.4)
80L 40 to 96 kg
(88 to 211 lb)
50 (2)
100 (4)
2195 (86.4)
120L 60 to 144 kg
(132 to 317 lb)
50 (2)
80 (3)
2355 (92.7)
120L 60 to 144 kg
(132 to 317 lb)
50 (2)
100 (4)
2355 (92.7)
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Pipe InstallationIn general, the installation should commence at the union elbow/manifold assembly and progress along to the discharge nozzles Install the Pipework to the installation drawings provided, ensuring that the following is adhered to:
• The piping material must conform to the requirements of NFPA 2001 42
• The pipe must be reamed, blown clear and swabbed with an appropriate solvent to remove mill varnish and cutting oil before assembly as required by NFPA 2001 42
• PTFE (Teflon) tape is the only acceptable pipe sealant and must be applied to the male threads
Table 16: US Steel Pipe Requirements
Table 17: US Fittings
Note: Cautionary information indicating the calculation method has been investigated for specific types of fittings, type of pipe and pipe inside diameter Also that when the specified limitations are not maintained there is the risk that the system will not supply the required quantity of extinguishing agent The Flow Program contains pipe and fittings options together with Equivalent Length information for US pipe and fittings
49
SECTION 5 - INSTALLATION
Pipe Reference Connection Pipe Type Nominal Pipe Size
ASTM A -106 seamless Grade C Threaded Schedule 40 3/8 in. - 6 in. NPSASTM A -106/A-53 seamless Grade B Threaded Schedule 40 3/8 in. - 6 in. NPSASTM A -106/A-53 seamless Grade A Threaded Schedule 40 3/8 in. - 6 in. NPSASTM A -53 ERW Grade B Threaded Schedule 40 3/8 in. - 6 in. NPSASTM A -53 ERW Grade A Threaded Schedule 40 3/8 in. - 6 in. NPSASTM A -53 Furnace Weld Class F Threaded Schedule 40 3/8 in. - 6 in. NPSASTM A -106 seamless Grade C Welded Schedule 40 3/8 in. - 6 in. NPSASTM A -106/A-53 seamless Grade B Welded Schedule 40 3/8 in. - 6 in. NPSASTM A -106/A-53 seamless Grade A Welded Schedule 40 3/8 in. - 6 in. NPSASTM A -53 ERW Grade B Welded Schedule 40 3/8 in. - 6 in. NPSASTM A -53 ERW Grade A Welded Schedule 40 3/8 in. - 6 in. NPSASTM A -53 Furnace Weld Class F Welded Schedule 40 3/8 in. - 6 in. NPS
Fitting Description Pipe SizeClass 300 Malleable or Ductile Iron Up to or < 3 in. NPS
1000 -Ib Rated Ductile Iron or Forged Steel Class 300 Flanged Joints > 3 in. NPS All
SAPPHIRE (UL)570805002011-03
Pipe HangersPipe hangers must be spaced according to the size of pipe (see Table 18)
• Hangers must be placed within 300 mm (12 in) of the discharge nozzle (see Figure 44)
• Hangers must be placed between elbows that are more than 600 mm (24 in) apart (see Figure 45)
• Hangers must be fixed to a structure capable of supporting the Pipework
Table 18: Hanger Spacing
(Reference: BS IS0 14520-1:2000)
Figure 44 - Nozzle Fixing Figure 45 - Elbow Support
50
SECTION 5 - INSTALLATION
Pipe Size mm (in.)
Maximum Spacing m (ft)
15 (1/2) 1.5 (5)20 (3/4) 1.8 (6)25 (1) 2.1 (7)
32 (1¼) 2.4 (8)40 (1½) 2.7 (9)50 (2) 3.4 (11)
65 (2½) 3.5 (11.5)80 (3) 3.7 (12)
100 (4) 4.3 (14)150 (6) 5.2 (17)
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Earthing and Electrical ClearanceSystems within electrical substations or switchrooms shall be efficiently earthed to prevent the metalwork becoming electrically charged Adequate earthing of systems will minimize the risk of electrostatic discharge All system components shall be located to maintain no less than minimum clearances from energized electrical parts The following references shall be considered as the minimum electrical clearance requirements for the installation of clean agent systems:
• ANSI C2• NFPA 70• 29 CFR 1910, Subpart S
Where the design basic insulation level (BIL) is not available, and where nominal voltage is used for the design criteria, the highest minimum clearance listed for this group shall be used Reference NFPA 2001
Figure 46 - Dirt Trap
10 x Nominal Pipe Diameter
NozzlesAll nozzles require the installation of a dirt trap comprising 1 side tee, 2 nipples, and 1 pipe cap Fit the nozzle to the nipple on the dirt trap and check the nozzle orifice to ensure proper orientation Dirt trap lengths should be no more than 10 times nominal pipe diameter
A false ceiling comprising loose tiles must have the tiles retained within a 2 m (65 ft) radius of the nozzle, to prevent movement during system discharge Nozzles should be installed a maximum of 300 mm (12 in) below the ceiling
51
SECTION 5 - INSTALLATION
SAPPHIRE (UL)570805002011-03
4.8-5.2 mm (0.189-0.205 in.)
WITH NUT AGAINST BODY
Figure 47 - Actuator Non-Fire Position
Figure 48 - Electrical Actuator Location
If no other actuators are to be installed, ensure that the protective cap on the actuator is retained in position
Actuation InstallationThe method of actuation depends on the system configuration and any specific contract requirements and can be broken down as follows:• Single Container Actuation
• Multiple Container Actuation
Single Container Actuation
Removable Electrical Actuator
The removable electrical actuator is fitted to the top of the valve assembly as follows:
• Check the actuator mechanism to ensure that it is in the non-fired position by fully screwing in the reset tool, ie pin retracted (see Figure 47)
• Remove the actuator cap from the top of the valve assembly (see Figure 40)
• Carefully screw the actuator to the valve assembly (see Figure 48)
Note: The actuator must be hand-tight only
52
SECTION 5 - INSTALLATION
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Electrical Actuator - Bridge Rectifier
The electrical signal from the detection and/or control equipment is connected in accordance with the wiring diagram detailed in Figure 49 when all other installations have been completed
Figure 49 - Electrical Actuator Wiring Diagram - Bridge Rectifier
PLUG CONNECTOR
23
2
1
1
This Electrical Actuator is fitted with a bridge rectifier as indicated Connect +ve from control panel to either terminal 1 or 2 with the reverse for the -ve supply from control panel, on plug connector End of line monitoring device (if required) to be fitted on site
Before this system is put into operation, the removable solenoid can be checked by firing the system To do this, REMOVE THE ELECTRICAL ACTUATOR from the valve With power to the actuator, the pin should be firmly in the down position Ensure that the electrical actuator is reset prior to fitting on to the conatainer valve
Actuator Coil
Plug Connector
53
SECTION 5 - INSTALLATION
! CAUTION
FAILURE TO RESET THE ACTUATOR WILL RESULT IN THE POTENTIALLY HAZARDOUS DISCHARGE OF THE CONTAINER
SAPPHIRE (UL)570805002011-03
Figure 50 - Manual Actuator Non-Fire Position
Figure 51 - Manual Actuator Location Figure 53 - Pneumatic Actuator Location
Multiple Container ActuationWhere several containers comprise one system and are discharged simultaneously, one container is designated as the ‘master’ container, and the others are ‘slave’ containers The master container can be actuated electrically or manually The slave containers are actuated pneumatically by the action of the master container discharging
Pneumatic Actuator
Check that the actuating plungers are in the raised position (see Figure 52) Remove the actuation cap from the top of the valve assembly (see Figure 40) and carefully screw the pneumatic actuator to the valve on each slave container
Note: The actuator must be hand-tight only.
Figure 52 - Pneumatic Actuator Non-Fire Position
4.0 mm (0.157 in.) MINIMUM
4.0 mm (0.157 in.) MINIMUM
Manual Actuator
The manual actuator can be fitted to the top of the electrical actuator or directly onto the valve, after first removing the protective cap
Note: The actuator must be hand-tight only
54
SECTION 5 - INSTALLATION
! CAUTION
Before attaching the manual actuator to the electrical actuator or valve, ensure that the firing pin is retracted and the safety pin is in place (see Figure 50)
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Slave Actuation Pilot Line (Typical Arrangement)
For slave containers the pneumatic connection is made using flexible pilot hoses To fit the pilot hoses, remove the 1/4 in pilot pressure port plug from the master container valve assembly and install the 1/4 in male adaptor, (Part No 570342)
Install the actuation tee, (Part No 31811) on to all pneumatic actuators (wrench tight), except on the last container in the bank Install a male actuation elbow, (Part No 31810) on the last pneumatic actuator in the actuation line If a pressure switch is to be connected to the end of the actuation line, an actuation tee, (Part No 31811) is to be used instead of an elbow, with the actuation line terminating at the pressure switch Connect the male end of the actuation hose, (Part No 73597, 415142 or 430815) to the adaptor on the master container, (Part No 570342) and using a 1/4 in NPT coupling connect the female 1/4 in NPT end to the pilot line tee on the pneumatic actuator Connect a female actuation hose, (Part No 32336) between actuation tees on all pneumatic actuators (see Figure 54), and to the actuation elbow on the last container The maximum number of slave actuated containers is 9 (10 containers system in total) After every 10 containers another master container must be created, using either an electrical actuator or pneumatically by removing the 1/4 in pilot pressure port plug on the tenth container, installing a 1/4 in male actuation connector (Part No 570342), a 1/4 in NPT coupling and an actuation hose (Part No 73597, 415142 or 430815), and repeat as required If using electrical actuation, they must operate simultaneously to ensure the correct discharge time
Figure 54 - Multiple Container Actuation
55
SECTION 5 - INSTALLATION
SAPPHIRE (UL)570805002011-03
AUTOPULSE Actuation
The master container is actuated electrically using an electrical actuator with an AUTOPULSE control panel and then additional slave containers are pneumatically actuated off the master container valve pilot port
Figure 55 - Electrical Actuation via AUTOPULSE
ANSUL AUTOMAN Actuation
The master container is actuated pneumatically using the ANSUL AUTOMAN II-C relasing device and then additional slave containers are pneumatically actuated off the master container valve pilot portThe maximum actuation line length from the ANSUL AUTOMAN II-C release is 366 m (120 ft) of 1/4 in Schedule 40 piping or stainless hose or tubing to the pneumatic actuator located on the master container valve The maximum actuation line length from the master container valve to the last slave container valve is 305 m (100 ft) (including all drops to the valves) of 1/4 in stainless steel hose or stainless steel tubing
Figure 56 - Master and Slave Actuation via the ANSUL AUTOMAN II-C Release
30.5 m (100 ft)MAXIMUM ACTUATION LINE LENGTH
30.5 m (100 ft)MAXIMUM ACTUATION LINE LENGTH
SAFETY RELIEF VALVE
1/4 in. ACTUATION PIPING36.6 m (120 ft) MAXIMUM LENGTH
56
SECTION 5 - INSTALLATION
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Another option is to have all of the containers actuated directly from the ANSUL AUTOMAN II-C release This option allows 10 containers to be simultaneous actuated from the nitrogen pressure from the ANSUL AUTOMAN II-C releasing device All containers are actuated pneumatically via a pneumatic actuator located on top of each tank valveThe maximum length of 1/4 in. Schedule 40 piping or stainless hose or tubing that can be utilized from the ANSUL AUTOMAN II-C release to actuate one pneumatic actuator is 366 m (120 ft) (including all drops to the valves) When additional containers are required, refer to Table 19 below for maximum actuation pipe length
Table 19: ANSUL AUTOMAN II-C Piping LengthsQuantity of
Pneumatically Actuated Valves
Maximum Length of 1/4 in. Actuation Line
m (ft)1 36.6 (120)2 35.9 (118)3 35.4 (116)4 34.7 (114)5 34.1 (112)6 33.5 (110)7 32.9 (108)8 32.3 (106)9 31.7 (104)
10 31.1 (102)
Note: It is important to note that the actuation lengths listed include branch lines to accessory items (pressure switches, pressure trips, etc) For each actuation line accessory, deduct 030 m (1 ft) from the above maximum lengths
Figure 57 - Direct Actuation via the AUTOMAN II-C Release
10 CONTAINERS MAXIMUM
SAFETY RELIEF VALVE
1/4 in. ACTUATION PIPING MAXIMUM 36.6 m (120 ft) INCLUDING DROPS TO PNEUMATIC ACTUATORS
57
SECTION 5 - INSTALLATION
SAPPHIRE (UL)570805002011-03
Ancillary Equipment
Discharge Pressure Switch
Single Container Systems
On single container installations the pressure switch should be located close to the valve assembly and connected with a pilot hose from the pressure port outlet on the valve to the connector on the pressure switch (see Figure 58)
Figure 58 - Discharge Pressure Switch Installation (Single Container System)
Multiple Container Systems
On multi-container installations the pressure switch should be located close to the last slave container and connected by pilot hose to the tee connector on the pneumatic actuator (see Figure 59)
Figure 59 - Discharge Pressure Switch Installation (Multiple Container System)
58
SECTION 5 - INSTALLATION
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Figure 63 - Low Pressure Switch Wiring (Series).
Accessories
Door NoticesWarning notices are required at all exits and entrances to protected area, ideally mounted on the door Plates may be drilled and screw fixed or attached using suitable adhesive
Low Pressure Switch
Note: When the device (ie pressure switch) is connected in series to a standard supervisory input circuit, there will be no distinction between a wiring fault and device actuation This device is to only be utilised when accepted by the authority having jurisdiction
4.7 KΩ EOL Resistor
1 3
Low Pressure Switch
4.7 KΩ EOL Resistor
1
2
Figure 62 - Low Pressure Switch Wiring (Parallel).
Discharge Pressure Switch (Continued)There are two ways this switch can be wired; for feedback to a control panel or, for direct equipment shutdown
For pressure switch feedback to a panel, the toggle on the switch should read “OFF” and the switch should be oriented such that the toggle is pointing downward, facing the plunger, with an EOL resistor wired across the terminals as shown This orientation allows for the contacts of the switch to be open at atmospheric pressure so the panel will see the EOL device When the system is actuated, the plunger will cause the switch to close, creating short circuit and indicating a discharge at the panel
For direct equipment shutdown, the toggle position is reversed from above: the toggle is moved to the “ON” position (such that the contacts are closed during normal operation) with the orientation remaining the same (toggle pointed down towards the plunger) Both contacts can then be used to wire to equipment, one side to a rated power source (120 VAC, 250 VDC, etc) and the other to the equipment being controlled This will allow for the circuit to open up upon system actuation, interrupting current flow to the equipment being controlled
Low Pressure SwitchAll container valves are ‘Factory fitted’ with low pressure warning switches Voltage input can be applied to either terminalThe low pressure switch can be connected two different ways, in parallel or in series with the end of line (EOL) device The prefered method is in parallel with the EOL device as this will allow the panel to differentiate between an open-circuit fault in the wiring and an actual low container pressure supervisory conditionConnecting the low pressure switch in series with the EOL device may result in some authorities having jurisdiction (AHJs) not accepting this particular wiring scheme
A AC C
BB D D
4.7 KΩ EOL ResistorPanel
+
-
OFF
Reset Stem
Plunger
Figure 60 - Discharge Pressure Switch Wiring (Feedback).
Figure 61 - Discharge Pressure Switch Wiring (Shutdown).
A AC C
BB D D
ON
Reset Stem
Plunger
+
-
+
-
To Power
To Equipment
59
SECTION 5 - INSTALLATION
SAPPHIRE (UL)570805002011-03
Completion ProceduresFor ease of reference completion procedures may be subdivided into the following sections;
• Pre Checks and Visual Inspections
• Final Connections
• Hand over Procedures
Pre-checks and Visual Inspections
General
When the installation is complete, and before making the final connections, the following checks should be made:
Mechanical Checks
Inspect protected area closely for conformance to original risk specifications and for enclosable openings or sources of agent loss which may have been overlooked in the original specification
• Building work should be thoroughly checked to ensure that enclosures have been properly constructed and that voids in floors and above suspended ceilings have been sealed
• All back channels should be secured firmly to the wall or bulk head
• Containers should be securely held within brackets
• Piping should be securely fixed within hangers
• All pipe connections must be tight
• Nozzles to be the proper type, correctly placed, and properly orientated
• Check model and weight markings on container nameplates to verify that correct containers and charges have been installed as required
• Verify that all warning and instruction plates are mounted where required
Electrical Checks
The electrical systems may include interfaces with many other systems for alarm, indication, actuation, shutdown, etc For complex electrical systems the scope and operating requirements will be described in other documents Electrical checks are given below for a basic system using electrical actuation of the container valve;
• Remove top mounted electrical actuator from valve Check that electrical actuator is activated when system is triggered
During detection system actuation verify the following functions operate;
• All apertures in hazard enclosure are closed by dampers or other suitable methods
• Electrical equipment in the protected area is tripped and isolated
Pneumatic Checks
The slave actuators on manifolded systems are fired by agent discharge Pneumatic checks are detailed below;
• Remove all pneumatic actuators from container valves
• Disconnect pilot hose from the master container valve adaptor (see Figure 54)
• Provide 4 bar (58 psi) pressure to the master container valve pilot hose
• Verify all pneumatic actuator pistons are in the fired position
• Check for leaks There must be less than 10% loss in pressure within 1 minute)
• Provide 292 bar (4235 psi) pressure to the master container valve pilot hose
• Verify all pneumatic actuator pistons are in the fired position
60
SECTION 5 - INSTALLATION
! CAUTION
The completion of the installation system, commissioning tests and hand-over may occur before the area is ready for use In the event of delay between hand-over and the risk area being available for protection, then the system must be left in a ‘safe’ condition to avoid accidental discharge The system must only be made operative once the area for protection has been completed and is operational
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Hand-over ProceduresThe entire system shall be thoroughly inspected to make sure that it is complete and that all tests required during installation have been properly carried out In addition, the following items are particularly important1 A container should be refilled or replaced when it
shows a loss in agent quantity of more than 5% or a loss in pressure (adjusted for temperature) of more than 10% (Operating pressure of unit at 25 bar at 21 °C, 360 psi at 70 °F) Refer to Appendix A for pressures at other container temperatures
2 Check container weight information label against system requirement If there is any doubt or if there has been a loss of weight, then the container must be weighed
3 Make sure the system is armed and the actuating systems are operational
Ensure adequate escape routes with directional signs are provided Issue of the appropriate documentation shall constitute completion of the Hand-over procedure
Appropriate records shall be issued by fire and/or insurance authorities as to the suitability, acceptability and availability of the system for the hazard area
• Check for leaks There must be less than 10% loss in pressure within 1 minute)
Before replacing the pneumatic actuators, ensure that all pistons are fully reset (see Figure 52) After reinstalling the pneumatic actuators, reconnect the pilot hose to the master container valve adaptor (see Figure 54)
Final Connections
Discharge Piping
The final connection of the discharge piping occurs at the container valve assembly For single container systems, the valve anti-recoil cap can be removed and the discharge pipe connected to the container outlet For multi-container systems, the valve anti-recoil caps can be removed and all discharge hoses fitted
61
SECTION 5 - INSTALLATION
SAPPHIRE (UL)570805002011-03
IntroductionThe hazard integrity is the ability to retain the discharged Novec™ 1230 For a total flooding extinguishing system to be effective, the design concentration must be achieved and then maintained for at least ten minutes The only method of testing the agent retention within the protected area is to verify the integrity of the enclosure by applying proven test procedures
The enclosure integrity test has been developed to locate the source of leaks and, from the data collected, predict the retention time, proving system performance and removing the need for actual Novec™ 1230 discharge In order to determine with any degree of confidence that the hazard area will hold the gas for the required time period, where necessary an Enclosure Integrity Test in accordance with NFPA 2001 appendix C or the authority having jurisdiction must be conducted
PrincipleThe test is conducted with a device known as a door fan, which has been used in the energy conservation field for over 25 years It has three basic components as follows:
• An adjustable panel that fits in the doorway of the protected area
• A calibrated fixed speed fan
• A variable speed fan
The pressure created by the door fan causes the air to move through leaks in the enclosure at high speed making it easy to pinpoint where leaks exist A cool chemical smoke or other air current indicator is used to detect the approximate size and location of leaks
Equivalent Leakage Area (ELA)The test to measure the ELA is conducted by blowing air into or out of the enclosure to develop the same pressure differential as would be created by the discharging Novec™ 1230 By measuring the air flow required it becomes possible to calculate the ELA, which is the total of all cracks, gaps and holes in the enclosure The leakage measurement achieved by taking air out of the enclosure (depressurisation), and then blowing air into the enclosure (pressurisation), is then averaged
Below Ceiling Leakage Area (BCLA)Experience has shown that leakage above a suspended ceiling has a negligible effect on the Novec™ 1230 concentration Like water leaking from the holes in the bottom of a swimming pool, Novec™ 1230 tends to escape from leaks in the lower part of the enclosure due to the weight of the mixture above it The rate at which Novec™ 1230 is lost is therefore primarily governed by the leakage below the floor, and walls beneath the ceiling This is called the Below Ceiling Leakage Area
Predicting Retention TimeOnce the ELA, BCLA and static pressures have been measured the next step is to calculate the retention time of the enclosure The formula is derived from a standard engineering/fluid dynamics principle The result of the calculation is the number of minutes it takes for the Novec™ 1230/air interface to reach the minimum protected height required, normally about 75% of the enclosure area
Slab to Slab WallsThe only major limitation is that it cannot be used to accurately predict a retention time if the perimeter walls do not extend from slab to slab The enclosure will almost invariably fail due to extensive leakage through the ceiling tiles
Coordination and PlanningIt should only be necessary to conduct one integrity test, therefore it is essential to ensure that the enclosure is ready, and that the relevant people have been informed Having established that any outstanding works are completed prior to the test date, advise all interested parties in writing, if necessary outlining the testing method and principles involved
62
SECTION 6 - INTEGRITY TESTING
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Integrity Test Procedure
Evaluation. The enclosure and immediate surrounding area is initially examined visually to assess the readiness for testing, the existence of any attached spaces that could affect the results, and that there is an adequate relief area and return air path The volume of the enclosure is confirmed and the highest equipment measured to ascertain the required level for retention time
Preparation. All doors outside the area that are required to be open for the test are wedged open with suitable notices posted to advise personnel Where voids are protected by Novec™ 1230, tiles are removed to ensure a uniform air flow
The enclosure is put in the state it would be in prior to a discharge, eg ventilation system shut down, dampers closed, etc
Note: Equipment within the enclosure that does not affect the integrity may be left running even if it will be shut down in the event of a discharge, preventing unnecessary disruption and inconvenience
Ventilation. Air conditioning and/or forced ventilation can affect the system performance and the quantity of agent required
(i) Self-contained air conditioning unit
A self-contained unit conditions the air within the enclosure and does not rely on a fresh air supply, or draw air from other parts of the building If the hazard has a self-contained unit and it is located within the area without an outside air supply, no additional agent is required It is not necessary to shut down the unit prior to a discharge as the mixing effect is beneficial However if the air-conditioning unit is left running, a depleting concentration rather than a descending Novec™ 1230/air interface will be formed The concentration will be depleted due to leakage Therefore overgassing the enclosure may help to obtain the required ten minute retention time at minimum concentration
(ii) Central air conditioning unit
A central air conditioning unit relies on air from outside and is often linked by ducts to other parts of the building, therefore, prior to a discharge, the unit should be shut down and/or dampers operated to close the ducts Sufficient time must be allowed for the plant to stop, or dampers to close, before discharge occurs
Dampers should be installed in both supply and return air ducts, as close as possible to the area The duct volume between the hazard and the damper must be added to the overall volume
Door Fan Installation. A door fan unit is installed in the designated test door in accordance with the manufacturer’s instructions
The gauges are zeroed by taking them to full scale deflection and holding for approximately ten seconds, after which the gauges are gently tapped and zeroed
Enclosure Evaluation
Static Pressure Measurements. With the door fan equipment fully installed and set up, but with all openings closed, a measurement of any pressure difference between the enclosure and the relief area is made If the measurement is unduly high its causes are ascertained and if possible permanently reduced or eliminated
Total Enclosure Leakage Method. Using an adequate range on one fan, or a number of fans, a pressure difference of between column pressure and column pressure plus 30% is created The pressure difference, and the air flow required to generate this, is then recorded This is carried out for both pressurisation and depressurisation modes The total equivalent leakage area and the predicted retention time is calculated
Suspended Ceiling Leakage Neutralisation Method. This procedure is used to improve the accuracy of the predicted retention time where a reasonable air-tight ceiling exists, whether or not the ceiling is protected with Novec™ 1230
Note. Leak paths through the ceiling may be temporarily sealed
The volumes above and below the false ceiling are depres-surised to the same extent but using separate fans This is confirmed by using cool chemical smoke to check that no air is flowing through the false ceiling
Readings of the pressure difference between the enclo-sure, relief area, and the air flow through the fan(s) used to depressurise the room and false ceiling are made, and then the procedure is repeated in the pressurisation mode The below ceiling leakage area is then calculated and used in conjunction with the ELA to predict a revised retention time
63
SECTION 6 - INTEGRITY TESTING
SAPPHIRE (UL)570805002011-03
CalculationA portable computer is used to collate the data and calculate the values The associated printer provides a detailed hard copy of the data on site An example of a typical hard copy print out is shown in Figure 64 below
Figure 64 - Typical Printout Example
Leakage LocationIf the enclosure fails the test, or if the client requests, an inspection of the enclosure with the door fan running can be made This makes it possible to locate the source of any leakage by using cool chemical smoke This procedure also tests the efficiency of any dampers, etc
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
DISCHARGE SIMULATION VER HA51RETENTION TIME PREDICTION MODEL
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Location: Ansul Test EnclosureRoom Name: Test HouseTesting Company: ANSULTechnician: C WickhamDate: 121296Whole Room TestAll Outputs are in METRIC Units
Gas Being Modelled: Novec 1230Kgs of Agent in Cylinder(s): 1700Net Room Volume (m3): 3000Room Height (m): 320Minimum Protected Height (m) 290Minimum Retention Time (min): 1000Initial Gas Concentration (%): 722Static Pressure @ Discharge: 000
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Equivalent Leakage Area (ELA m²): 00050Hole in Ceiling (m²): 00025Hole in Floor (BCLA m²): 00025
This Room PASSES the Test as the Predicted Retention Time is 101 minutes for the agent/air interface to drop below the minimum protected height
Witnessed By:
X ___________________________________
Software Conforms to 1992 NFPA 12A/2001 TCD Room Integrity Procedure
Maximum Allowable ELA (m²): 0005Interface Height @ 10 minutes: 2903- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
FAN TEST READINGS & DATA
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Location: Ansul Test EnclosureRoom Name: Test House
Temperature IN: 20 Temperature OUT: 20Static Pressure@FanTest: 0
DEPRESSURE PRESSUREOperator and Gauges Location OUT OUTRoom Pressure Gauge Reading 140 140Corrected Room Delta P (pa) -140 140Blower Range Config Used 01 01Flow Pressure Gauge Reading 450 450Corrected Flow Pressure 310 450Calculated Air Flow (1s) 134 162Temp Corrected Flow 134 162Leakage Area (m²) 00046 00055Average Leakage Area (m²) 00050
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
R M = 1639 P C = 137A T= 0003 A L L - 0002C 3 = 3019 C 4= 0000G D = 7260 K 1- 18850A R = 9374 T= 605679P A = 137 F A = 0500C F = 1000 K 2= 00046E L = 0000 TD = 20000
64
SECTION 6 - INTEGRITY TESTING
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
General CommentsPersonnel required to work in the protected area should be conversant with the detection and extinguishing equipment installed, and trained in fire procedures All life-saving equipment must be properly maintained
The method of system operation is chosen at the design stage to suit the protection required for the hazard area and the environmental factors appropriate to that area This part of the document provides information relevant to ALL the standard operational systems to cover the eventuality of changes to, or expansion of the original design
System Detection and Actuation
GeneralEach system is designed to suit the hazard area, whether the area is normally manned or unmanned, and whether the detection/actuation devices are to be manual or automatic The permutation of systems is large but from an operational point of view, the systems are best grouped as:-
• Manual
• Fully Automatic
• Automatic with Manual Intervention
Manual SystemManual systems depend on human detection of a fire in the hazard area and prompt action to actuate the manual actuator for the Novec™ 1230 system to discharge and flood the protected area and extinguish the fire
All other instructions associated with manual operation form part of the user’s procedures on safety precautions and fire drill If required assistance can be provided to help the user prepare procedures for safety and fire precautions
Fully Automatic SystemWhere a sensitive fire detection system is included for the automatic release of extinguishing agent, the system shall only be capable of automatic release once two or more sensors detect the fire
The number of detectors and their spacing is designed to ensure a satisfactory response time To ensure personnel may safely evacuate the risk area an adjustable time delay should be fitted such that sufficient time may elapse prior to system discharge Ideally, the delay period shall not exceed 30 seconds
Prior to system discharge (and at the commencement of any time delay period) a clearly audible alarm different from any other used shall sound and continue until the complete system is reset In areas of high ambient noise level, a visual indication may also be required, in addition to the audible warning
The design of a system for automatic detection, signal distribution, alarms, etc is not always of our supply Therefore, details appertaining to fire detection and alarm operation and maintenance are not included in this document
UL Listed Detection & Control Equipment
Detectors shall be UL Listed for the intended application Control Panels shall be UL Listed for releasing device service and compatible with detection and SAPPHIRE Engineered Total Flooding Fire Extinguishing System
65
SECTION 7 - SYSTEM OPERATION
SAPPHIRE (UL)570805002011-03
Fully Automatic System with Manual Inter-ventionManual intervention of an automatic system may be included for the following condition;• Where personnel are required to work within the
protected area.
In protected areas where personnel are present and the concentration is greater than NOAEL, it is recommended that the automatic feature of the system is isolated during occupation This may be achieved either by an electrically contacted lock assembly or by a clearly marked key switch at a suitable location outside the risk area
Conditions During a FireThe user’s fire and safety instructions to personnel should include advice on the conditions prevailing during the discharge of a SAPPHIRE system This advice is intended to prepare the personnel for the situations likely to arise and therefore minimise the risks of panic Three major conditions prevail during Novec™ 1230 discharge of which personnel should be made aware:
Novec™ 1230 ConcentrationSAPPHIRE total flooding systems greater than 10% design concentration should only be used with manual actuation in normally occupied areas A normally occupied area is defined as an area intended for occupancy
Any area protected by Novec™ 1230 should be evacuated prior to start of system discharge Where egress of normally occupied areas cannot be accomplished within one minute, SAPPHIRE total flooding systems shall be designed not to exceed 10% concentration
Refer to NFPA 2001 for additional information
Novec™ 1230 DecompositionNovec™ 1230 decomposes when exposed to temperatures exceeding 482 °C (900 °F); such as flames, hot metal surfaces, etc The rate of this decomposition is dependent upon the size of the area where extreme temperatures are found, and also upon the length of Novec™ 1230 exposure time
To reduce decomposition, SAPPHIRE systems are designed to discharge and extinguish the fire quickly The maximum duration of discharge for these systems at 21 °C (70 °F) is 10 seconds, so the minimum amount of decomposition occurs Hydrogen Fluoride is the most toxic decomposition product This material generates a sharp acrid odour, which is easily detected and acts as a warning and a good safeguard to personnel
Novec™ 1230 Discharge ConditionsNovec™ 1230 has a low boiling point Consequently the discharge is very cold at the point where it leaves the nozzle Care should be taken to avoid working within 1 m (328 ft) of Novec™ 1230 discharge nozzles
The velocity of discharge of Novec™ 1230 from a discharge nozzle is very high Care should be taken to ensure that objects which may become dangerous projectiles are secured or removed from the hazard area
66
SECTION 7 - SYSTEM OPERATION
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Actions Following a Fire
GeneralThese notes are only applicable to the hazard area(s) protected by a SAPPHIRE fire extinguishing system Where such a system may form part of, or combine with other forms of fire protection systems, then composite instructions for all systems are necessary to ensure the safety of personnel and property following a fire Assistance is available to help a client prepare composite instructions If the organisation has appointed, or nominated, a responsible person to act as a ‘Fire Officer’, actions following a fire should be co-ordinated and/or directed by the Fire Officer
Actions Immediately Following a FireThese actions should, at a minimum, include the following:
• Advise the emergency services, Fire, Accident, Police if appropriate
• Organize a ‘roll-call’ of employees and any visitors
• Prevent unauthorised personnel from entering the hazard area
• In the case of deep-seated fires, the hazard space should be kept tightly closed for at least 60 minutes after discharge of the Novec™ 1230 extinguishing agent
It is essential that the fire be completely extinguished before ventilating the space Before permitting any one to enter the space, ventilate thoroughly or ensure self-contained breathing equipment is used
• Do not enter the hazard area in which fire has been extinguished with an open flame or lighted cigarette as the possible presence of flammable vapours may cause re-ignition or explosion
Should it be necessary to enter a space containing Novec™ 1230 or decomposition products, the following precautions should be taken:
• Use a fresh air mask or self contained breathing equipment
• Do Not use a filter mask or canister type mask
• Do Not enter space unless you are under observation from outside the space, or tethered by a lifeline
• Ensure that all pressurised equipment is isolated or safe from release
67
SECTION 7 - SYSTEM OPERATION
SAPPHIRE (UL)570805002011-03
IntroductionThis section provides user inspection and maintenance guidance for SAPPHIRE Engineered Systems A log book will be provided to record all inspections, maintenance, measurements and actions taken The continued capability for effective performance of an SAPPHIRE Total Flooding Fire Suppression System depends on fully adequate maintenance procedures, with periodic testing Reference NFPA 2001 and ISO 14520-1
User’s Programme of InspectionThe installer should provide the user with an inspection programme for the system and components The programme shall include instructions on the action to be taken in respect of faults The user’s inspection programme is intended to detect faults at an early stage to allow rectification before the system may have to operate
A suitable programme is as follows:-
Weekly Check of Hazard Area
Inspect the hazard area against the original layout to ensure that there have been no changes that might affect the proper performance of the fire protection system Changes might include:
• Contents of area
• Use of area
• Air Handling equipment in area
• Openings in area
• Floor/ceiling voids
• Partitioning
Weekly Check of Containers
Check storage container pressure gauges and ambient temperature Compare these pressures to the Temperature Correction Chart to determine temperature corrected pressure If the container corrected pressure shows a loss of more than 10%, the containers should be removed for weighing All measurements and actions shall be recorded in the log book
Weekly Check of System Components
Make a visual inspection of the system components, distribution piping and nozzles Check the immediate vicinity of all equipment to ensure that no accidental damage or tampering has occurred
Weekly General Check
Inspect the hazard area, access routes, container storage area, floor voids and areas above suspended ceilings to ensure housekeeping is good and that no refuse has accumulated Ensure that access to the system container assemblies and local remote controls is unobstructed
Monthly Check of Notices
Inspect system and protected spaces to ensure that warning signs, safety precautions and operating instructions are posted and clearly visible
Monthly Personnel Training Check
Check that all personnel who may have to operate the equipment or system are properly trained and are authorized to do so, and in particular that new employees have been instructed in its use
68
SECTION 8 - MAINTENANCE
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Contract Service and MaintenanceSystems shall be thoroughly inspected and tested for proper operation by qualified contract personnel in accordance with NFPA as well as any other standard accepted to the authority having jurisdiction Before any checks are carried out, ensure the extinguishing system is isolated electrically and mechanically and remove all electrical and pneumatic actuators No maintenance work should be carried out without obtaining approval from the Fire Officer and advising any personnel within the hazard area The following Programme should be carried out in addition to the User’s Programme of Inspection The user shall be provided with a signed and dated report of the inspection advising any rectification carried out or needed
3 Month Actuator Check
Test and service all actuating mechanisms
3 Month Electrical Systems Check
Test and service all electrical detection and alarm systems as recommended in NFPA as well as any other standard accepted to the authority having jurisdiction
6 Month Container Check
Externally inspect containers for signs of damage or unauthorised modifications Check container labels are securely fixed and legible Check container brackets and fittings
6 Month Contents Check
Examine the container pressure gauge reading and refer to the temperature correction chart If the container pressure corrected to temperature is below 10% of the stated pressure, it must be replaced or recharged
Verification of the content of Novec™ 1230 in the containers may be achieved through container weighing If containers show a extinguishant loss of more than 5% or a pressure loss (adjusted for temperature) of more than 10%, the container should be refilled or replaced
Container Weighing
Where a client does not wish to use an approved distributors maintenance contract, then containers must be weighed to establish the Novec™ 1230 content The weighing procedure is as follows:
• Remove all manual controls, pressure actuators and pressure actuation pipe or tubing and flexible electrical connectors
• Disconnect and remove discharge piping / discharge hoses from container valves
• Fit anti-recoil caps onto container valves
• Remove containers from bracketing and weigh containers Any container showing more than the maximum allowable weight loss must be recharged by a qualified recharge agent
• Record weight of container on record tag
• Replace containers in bracketing and remove anti-recoil caps
• Reconnect discharge piping / discharge hoses and all control heads, pressure actuators, pressure actuation pipe or tubing and flexible electric connectors
69
SECTION 8 - MAINTENANCE
SAPPHIRE (UL)570805002011-03
6 Month Control Valve & Actuator Check
Check all manual and pneumatic actuators for free movement of the piston Replace whole unit where appropriate Check all control valves for correct manual function and automatic valves additionally, for correct automatic function
6 Month Pipe Network Check
Externally check pipework to determine its conditions Replace or pressure test and repair as necessary pipework showing corrosion or mechanical damage
6 Month Nozzle Check
Inspect nozzles for dust and debris, clean out where necessary
6 Month Enclosure Check
Carry out a full visual check of the enclosure for integrity and confirm the dimensions and the configuration of the hazard are as the original drawings or previous visit If drawings are not available and this is the first visit, then dimensions should be taken and passed to the engineering department together with the quantity of agent to enable a calculation to be carried out to ensure the correct quantity of gas has been used
12 Month Hose Check
All system hoses should be examined for damage If visual examination shows any deficiency, the hose shallbe replaced
12 Month Integrity Test
Integrity test the enclosure to determine if the leakage area has changed sufficiently from that measured during installation
Electrical Actuator Ten Year Lifespan
The removable electrical actuator has a life span of 10 years from manufacture, which is indicated on the label, and so should be replaced before this date is reached
Personnel Training
All persons who may be expected to inspect, test, maintain or operate the fire extinguishing system shall be kept adequately trained in the functions they are expected to perform Personnel working in an enclosure protected by a gaseous extinguishant shall receive training in the operation, use of the system and safety issues
70
SECTION 8 - MAINTENANCE
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
3) Examine the auxiliary electrical device/alarm, door closers etc, have all operated correctly
4) Ensure actuator is reset before refitting, using the reset tool provided
d For master/slave system, remove the appropriate port plug and reconnect the pilot actuation line to the slave port on the back of the master valve
e Reset pressure switches after the test has been completed
(1) An approved distributor is carrying out the maintenance on the detection system
(2) If the servicing of the detection system is being carried out at the same time as the mechanical service by another nominated body
Specialised Maintenance Duties
Container Hydrostatic Pressure Testing
In countries where NFPA 2001 applies, the following criteria are used for hydrostatic pressure testing :Containers only need hydrostatic pressure testing after discharge Systems under local jurisdiction may have other rules of hydrostatic pressure testing Please follow these rules
Final InspectionCarry out a final visual inspection of the system and the protected area to ensure that all equipment has been reinstalled and reconnected properly Ensure that any associated control/indication panel is displaying normal operation Complete the site log book, recording work carried out and parts used Inform the responsible person that the work is complete and that the system is back on-line
Mechanical Servicing Procedure
a Remove valve actuator(s) from the container valve(s)
b For master/slave system, complete the following steps to check the slave actuation system:-
1 Disconnect pneumatic valve actuators from the slave container valves
2 Disconnect the pilot loop from the master container valve and install the appropriate plug
3 Introduce 4 bar (58 psi) pressure into the pilot actuation line to the pneumatic actuators
4 Check that the pistons in the pneumatic valve actuators have fully operated
5 Check for leaks There must be less than 10% loss in pressure within 1 minute
6 Vent pressure in the pilot actuation line and re-set all of the actuators
7 Introduce 292 bar (4235 psi) pressure into the pilot actuation line to the pneumatic actuators
8 Check that the pistons in the pneumatic valve actuators have fully operated
9 Check for leaks There must be less than 10% loss in pressure within 1 minute
10 Vent pressure in the pilot actuation line and re-set all of the actuators
c To check the electrical actuation system (for single container systems only electrical actuators are fitted):
1) Remove electrical actuators from valve assembles
2) Activate the detection system in accordance with procedures provided with the system When this test is performed, the release circuit of the detection system must operate the electric actuators causing the plungers to be firmly extended
71
SECTION 8 - MAINTENANCE
SAPPHIRE (UL)570805002011-03
Recharging (O.E.M Only)This section describes the procedures to enable the refilling of a container that has been discharged and will require rechargingThe O-ring kit, (Part No 570584) includes:• Neck O-ring (Part No 570711)• Syphon tube O-ring (Part No 570712)• Top cap (bonnet) O-ring (Part No 570711)
Valve Refurbishment (O.E.M Only)On receiving a container that requires to be recharged, the following operations are carried out See Figure 65 for component description Ensure all parts are cleaned fully before any part is replaced
1 Check that the container is empty
2 Remove valve, syphon tube grub screw and syphon tube from container
3 Unscrew top cap by removing locking grub screw located behind safety cap chain fixing screw Once it has been taken off, the Schrader valve should also be removed
All O-ring seals must be lubricated using PTFE silicone grease
4 O-ring seal for the top cap (bonnet) must be removed:
50 mm (2 in) valve O-ring (Part No570713)
5 Remove shuttle from valve body and dispose
6 Locate replacement shuttle assembly:
50 mm (2 in) valve shuttle (Part No570552)
7 Apply PTFE silicone grease to new top cap O-ring
8 Replace shuttle into valve and spray a small quantity of PTFE silicone grease into the bore of the valve body
9 Replace O-ring seal for the top cap:
50 mm (2 in) valve O-ring (Part No576396)
10 Screw new Schrader valve into top cap using Schrader tool set to 0275 Nm, (025 to 03 Nm tolerance) Replace top cap to valve and lock into place with grub screw
11 If valve has been removed from neck ring, replace neck seal (This is to pre-dome burst disc if required)
50 mm (2 in) valve Neck O-ring (Part No 570711)
In the event that the pressure gauge or pressure switch needs to be replaced:
12 Remove to reveal grub screw Check the grub screw setting This should be initially tightened fully and then loosened by 1/2 a turn
13 Apply PTFE tape to replacement components and refit
14 Remove 534 bar (775 psi) burst disc assembly if damaged from burst disc port and replace:
50 mm (2 in) valve: M18 assembly, torque to 35 Nm, (Part No 570793)
15 Valve assembly is now ready to be leak tested See Testing section
Refurbishment of container valves can only be carried out by the Original Equipment Manufacturer (O.E.M). This section is for information only.
72
SECTION 9 - RECHARGING PROCEDURE
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Figure 65 - 50 mm (2 in.) Valve exploded view.
CHAIN SCREW
CHAIN WASHER
CHAIN
ANTI-RECOIL CAP
CHAIN SCREW LOCK NUT
OUTLET
BURST DISC ASSEMBLY
COLLAR O-RING
PRESSURE SWITCH
PRESSURE GAUGE
PLASTIC CAP
SCHRADER VALVE
TOP CAP
SHUTTLE O-RING
SHUTTLE
MAIN SEAT DISC
BOTTOM CAP
TOP CAP O-RING
1/8 in. PLUG
SHUTTLE ASSEMBLY
73
SECTION 9 - RECHARGING PROCEDURE
Section 9 - RECHARGING PROCEDUREHYGOOD
72 FM-200® Installation Guide/11100/02.08.05/Issue 3.3
Replacing Valve Assembly to container
1 Take container and clean neck thread using apower drill and the appropriate attachment Use carewhen cleaning neck threads as the O ring seal could bedamaged
2 Remove debris from inside the container as wellas from the neck thread, this should be done using theworkshop vacuum cleaner and airline
3 PTFE grease must be applied to the clean con-tainer neck thread
4 Take the appropriate syphon tube for the correctcontainer and valve assy, making sure that the syphontube and grub screw hole has been properly de-burred
5 The syphon must be cleaned either by hand withpaper towels or in the workshop washer
6 Apply Loctite 572 around the circumference ofthe syphon tube above the grub screw hole Fit the sy-phon tube into the valve assy, ensuring that the grubscrew hole's line up (does not apply to 75mm valve-tuberemains in container)
7 Remove excess loctite adhesive and screw in grubscrew
8 Fit valve and syphon tube assembly to container,insuring that the neck O ring is in place
25mm (1") valve - 2"8UN neck ring No 327
50mm (2") valve - 3 1/4"8UN neck ring No 337
75mm(3") valve- neck O ring No570294 (Pyro-chem)
9 Secure the container in to the pneumatic belt viceand tighten the valve using the "C" spanner, until thevalve bottoms onto the top of the neck ring
Testing
On completion of a valve refurb the valve assy issubjected to two tests - Valve Assy Pre-dome and LeakTest (test required if burst disc was replaced)
The tests are conducted on a Nitrogen rig using aoutlet filling adapter cap, test bottom cap and closingdown adaptor (See figure 51)
1 The valve assy is assembled to the nitrogen rigbottom cap using PTFE/silicon greased O ring on thevalve neck thread The outlet adapter cap is also fitted,ensuring that the vent tap is closed
2 The nitrogen regulator is opened to 40 bar (580psi)and the pressure to the valve is slowly increased to thispressure, this is to pre-dome the burst disc This pres-sure is held for 1 minute ensuring that there is no drop inpressure indicated by nitrogen rig gauge
3 A Water /soap solution is poured into the top capschrader and leak detection spray is applied to all portson the valve to check for leakage If no leaks are presentthe pressure to the valve must be reduced to 25 bar(3625psi) and the closing down adapter fitted To closethe valve shuttle down, 40 bar (580psi) is applied throughthe closing down adapter
Figure 51Nitrogen Test Station Component Layout
4 Once again check for leaks
5 Slowly release the gas from the test rig, vent fromclosing down adapter and ensure that the outlet capadapter tap is opened before attempting to remove theadapter
If a leak is identified it should be rectified, if the leakpersists the valve assembly should be rejected
SAPPHIRE (UL)570805002011-03
Testing (O.E.M Only)On completion of a valve refurbishment the valve assembly is subjected to two tests - Valve Assembly Pre-dome and Leak Test (Test required if burst disc was replaced)
The tests are conducted on a Nitrogen rig using an outlet filling adapter cap, test bottom cap and closing down adaptor (See Figure 66)
Figure 66 - Nitrogen Test Station Component Layout
1 The valve assembly is assembled to the nitrogen rig bottom cap using a PTFE/silicon greased O-ring on the valve neck thread The outlet adapter cap is also fitted, ensuring that the vent tap is closed
2 The nitrogen regulator is opened to 40 bar (580 psi) and the pressure to the valve is slowly increased to this pressure This is to pre-dome the burst disc This pressure is held for 1 minute ensuring that there is no drop in pressure indicated by the nitrogen rig gauge
3 A water/soap solution is poured into the top cap Schrader valve and leak detection spray is applied to all ports on the valve to check for leakage If no leaks are present, the pressure to the valve must be reduced to 25 bar (3625 psi) and the closing down adapter fitted To close the valve shuttle down, 40 bar (580 psi) is applied through the closing down adapter
4 Once again, check for leaks
5 Slowly release the gas from the test rig Vent from closing down adapter and ensure that the outlet cap adapter tap is opened before attempting to remove the adapter
If a leak is identified, it should be rectified If the leak persists, the valve assembly should be rejected
Replacing Valve Assembly to container
1 Take container and clean neck thread using a power drill and the appropriate attachment Use care when cleaning neck threads as the O-ring seal could be damaged
2 Remove debris from inside the container as well as from the neck thread This should be done using the workshop vacuum cleaner and airline
3 PTFE grease must be applied to the clean container neck thread
4 Take the appropriate syphon tube for the correct container and valve assembly, making sure that the syphon tube and grub screw hole has been properly de-burred
5 The syphon must be cleaned either by hand with paper towels or in the workshop washer
6 Ensure the siphon tube O-ring is in place Fit the syphon tube into the valve assembly, ensuring that the grub screw holes line up
7 Remove excess loctite adhesive and screw in grub screw
8 Fit valve and syphon tube assembly to container, ensuring that the neck O-ring is in place
50 mm (2 in) valve - Neck O-ring (Part No 570711)
9 Secure the container into the pneumatic belt vice and tighten the valve using the spanner wrench until the valve bottoms onto the top of the neck ring
NEEDLE VALVE
PRESSURE GAUGE
NEEDLE VALVE
PRESSURE GAUGE
OUTLET CAP
VENT
CLOSING DOWN ADAPTOR
NEEDLE VALVE
TEST BOTTOM CAP
NEEDLE VALVE
NITROGENREGULATORNEEDLE
VALVEPRESSURE GAUGE
VENT
74
SECTION 9 - RECHARGING PROCEDURE
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
FillingFilling can only be undertaken by trained and authorised UL fill stations using containers assembled and tested by the O.E.M. Verify that the Novec™ 1230 agent is a UL recognised virgin material.
1 With the container ready for filling, check the filling instruction sheet and the container fill weight, time, date and fill details record
2 Place the container on a scale and attach the appropriate filling adapter attached to the container valve discharge port
3 Attach the fill hose/vent line from the filling rig outlet to the filling adapter
4 Reset the scale to zero to compensate for weight of container and fill hose
5 Switch on the pump marked ‘Liquid’ on filling cabinet and fill container to required weight Refer to Fill Tolerances Table 20 (Less approximately 07 kg (15 lb) which is present in pipework and will be forced through the piping during pressurisation) When the required fill is reached, switch off pump
6 Remove container from scales, zero scales and weigh to verify fill is within tolerance Adjust if required
7 Attach low pressure switch wires to test box and regulate nitrogen pressure to 138 bar (200 psi) on fill rig and switch on supply
8 Slowly increase the nitrogen pressure on the approved pressure regulator to the stated pressure on the filling instruction sheet, making the relevant allowances in pressure to compensate for the current room temperature (see the Temperature Correction Chart, Table 21) Read off the calibrated external fill pressure gauge to determine when the intended charging pressure has been reached (Check that the container pressure gauge reads within ± 1 bar (± 145 psi) of the fill gauge Replace container gauge if outside this tolerance)
Ensure that the test box registers a change in state (normally open to normally closed or normally closed to normally open) at approximately 24 bar (350 psi) rising
9 Agitate the container using the agreed mechanical agitation equipment until the nitrogen has been fully absorbed (saturated) into the agent
10 Attach the closing down adaptor to the container valve top cap and connect the nitrogen closing down line Regulate the nitrogen pressure to 40 bar (580 psi) with the fill rig
11 Open the closing down valve for 1 second only to force the valve shuttle down The container valve will be heard to close Turn off the nitrogen supply and vent the closing down line with the needle valve
12 Vent the fill hose to atmosphere If the pressure drops to zero as shown on fill rig gauge marked outlet within 10 seconds, the valve has closed Top up if necessary
13 Remove the closing down line adapter
14 If valve does not close after 5 applications, the cylinder must be de-pressurised Ensure vent valve is closed when not required to prevent contamination on fill line
15 Test all ports with leak detection spray, and test Schrader valve with water/soap solution If a minor leak is observed, it may be cured by tightening the offending components
16 Remove fill hose and filling adapter Leak test the outlet and attach anti-recoil cap Note: When leak testing outlet with spray, do not look directly into port Rather, examine quickly from an angle
17 Reset scales and record gross weight
18 Make certain all safety and protection caps are in place
19 Attach label to container stating the following information: Job number, Customer, Project, Container size, Fill weight, Gross weight, Date filled, and Type of agent
75
SECTION 9 - RECHARGING PROCEDURE
! CAUTION
When superpressurising, a pressure regulator must be used when the pressure source is a tank of high pressure gas
SAPPHIRE (UL)570805002011-03
20 Place container in bonded area for leak monitoring for at least 24 hours prior to dispatch
21 After 24 hours a Leak Test on the container is conducted See section on Container/Valve assembly leakage test
22 Insert fill information on to container label
80 and 120 Litre Container: Label part No 570804
23 Adhere label to container 50 mm (2 in) below the container top fixing bracket height
Table 20 : Fill Tolerance Table
76
SECTION 9 - RECHARGING PROCEDURE
Container Size Fill Tolerance Charging Tolerance80 litre +0.26, -0 kg (+0.57, -0 lb) +0.75, -0 bar (+11, -0 psi)
120 litre +0.50, -0 kg (+1.10, -0 lb) +0.75, -0 bar (+11, -0 psi)
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Table 21: Temperature Correction Chart
Note: Filling can only be carried out by UL approved fill stations using containers assembled and tested by the OEM
77
SECTION 9 - RECHARGING PROCEDURE
Temperature Developed Pressure
°C (°F) Bar (psi)0.0 (32) 22.3 (323.8)
0.6 (33 22.4 (324.7)
1.1 (34) 22.5 (325.6)
1.7 (35) 22.5 (326.6)
2.2 (36) 22.6 (327.5)
2.8 (37) 22.6 (328.4)
3.3 (38) 22.7 (329.4)
3.9 (39) 22.8 (330.3)
4.4 (40) 22.8 (331.2)
5.0 (41) 22.9 (332.2)
5.6 (42) 23.0 (333.1)
6.1 (43) 23.0 (334.0)
6.7 (44) 23.1 (335.0)
7.2 (45) 23.2 (335.9)
7.8 (46) 23.2 (336.8)
8.3 (47) 23.3 (337.7)
8.9 (48) 23.4 (338.7)
9.4 (49) 23.4 (339.6)
10.0 (50) 23.5 (340.5)
10.6 (51) 23.5 (341.5)
11.1 (52) 23.6 (342.4)
11.7 (53) 23.7 (343.3)
12.2 (54) 23.7 (344.3)
12.8 (55) 23.8 (345.2)
13.3 (56) 23.9 (346.1)
13.9 (57) 23.9 (347.1)
14.4 (58) 24.0 (348.0)
15.0 (59) 24.1 (348.9)
15.6 (60) 24.1 (349.8)
16.1 (61) 24.2 (350.8)
16.7 (62) 24.2 (351.7)
17.2 (63) 24.3 (352.6)
17.8 (64) 24.4 (353.6)
Temperature Developed Pressure
°C (°F) Bar (psi)18.3 (65) 24.4 (354.5)
18.9 (66) 24.5 (355.4)
19.4 (67) 24.6 (356.4)
20.0 (68) 24.6 (357.3)
20.6 (69) 24.7 (358.2)
21.1 (70) 24.8 (359.2)
21.7 (71) 24.8 (360.1)
22.2 (72) 24.9 (361.0)
22.8 (73) 25.0 (361.9)
23.3 (74) 25.0 (362.9)
23.9 (75) 25.1 (363.8)
24.4 (76) 25.1 (364.7)
25.0 (77) 25.2 (365.7)
25.6 (78) 25.3 (366.6)
26.1 (79) 25.3 (367.5)
26.7 (80) 25.4 (368.5)
27.2 (81) 25.5 (369.4)
27.8 (82) 25.5 (370.3)
28.3 (83) 25.6 (371.3)
28.9 (84) 25.7 (372.2)
29.4 (85) 25.7 (373.1)
30.0 (86) 25.8 (374.0)
30.6 (87) 25.9 (375.0)
31.1 (88) 25.9 (375.9)
31.7 (89) 26.0 (376.8)
32.2 (90) 26.0 (377.8)
32.8 (91) 26.1 (378.7)
33.3 (92) 26.2 (379.6)
33.9 (93) 26.2 (380.6)
34.4 (94) 26.3 (381.5)
35.0 (95) 26.4 (382.4)
35.6 (96) 26.4 (383.4)
36.1 (97) 26.5 (384.3)
Temperature Developed Pressure
°C (°F) Bar (psi)36.7 (98) 26.6 (385.2)
37.2 (99) 26.6 (386.1)
37.8 (100) 26.7 (387.1)
38.3 (101) 26.8 (388.0)
38.9 (102) 26.8 (388.9)
39.4 (103) 26.9 (389.9)
40.0 (104) 26.9 (390.8)
40.6 (105) 27.0 (391.7)
41.1 (106) 27.1 (392.7)
41.7 (107) 27.1 (393.6)
42.2 (108) 27.2 (394.5)
42.8 (109) 27.3 (395.5)
43.3 (110) 27.3 (396.4)
43.9 (111) 27.4 (397.3)
44.4 (112) 27.5 (398.2)
45.0 (113) 27.5 (399.2)
45.6 (114) 27.6 (400.1)
46.1 (115) 27.7 (401.0)
46.7 (116) 27.7 (402.0)
47.2 (117) 27.8 (402.9)
47.8 (118) 27.8 (403.8)
48.3 (119) 27.9 (404.8)
48.9 (120) 28.0 (405.7)
49.4 (121) 28.0 (406.6)
50.0 (122) 28.1 (407.6)
50.6 (123) 28.2 (408.5)
51.1 (124) 28.2 (409.4)
51.7 (125) 28.3 (410.4)
52.2 (126) 28.4 (411.3)
52.8 (127) 28.4 (412.2)
53.3 (128) 28.5 (413.1)
53.9 (129) 28.5 (414.1)
54.4 (130) 28.6 (415.0)
SAPPHIRE (UL)570805002011-03
Container/ Valve Assembly leakage TestA leakage test is required for all filled SAPPHIRE valves and container assemblies after being left to stand in a bonded area for at least 24 hours Three test options are available The test equipment used for the first two test options are a leak detector and calibration gas, with a water bath being used for the third
Halocarbon Leak Detector Test
1 After 24 hours standing, the valve pressure gauge should be checked for pressure loss (refer to temperature correction chart to adjust for temperature change) The container and valve assembly should then be checked for leakage using the halocarbon leak detector unit
2 Testing should take place in an area free of Novec™ 1230 contamination
3 Take the halocarbon leak detector unit and calibration gas and within the Novec™ 1230 free environment, calibrate the unit
4 Adjust the halocarbon leak detector to gain a steady audible pulse, in free air, of about 2 to 4 pulses per second
5 Conduct a stability check by leaving the halocarbon leak detector for approximately 3 minutes in a clean air environment If the pulse rate is observed to stay within the range of 2 to 4 pulses per second, proceed to the repeatability check
If the stability check is inconclusive, repeat stability check in an alternative clean environment If stability problems persist, contact the technical support centre for instruction
6 The leak standard of 013 oz/year should be conditioned to a temperature of 20 °C +/-5 °C (68 °F ± 9 °F) for at least 24 hours
7 Conduct a calibration repeatability test
8 Remove the cap from the leak standard, screw the calibration nozzle into the outlet of the bottle and open the hand valve fully
9 Place the halocarbon leak detector probe into the calibration nozzle Within 5 seconds the pulse rate should start to increase and be a continuous tone within 15 seconds
10 Remove the probe from the nozzle and position the halocarbon leak detector unit away from the gas source The pulse rate should revert back to the original rate of 2 to 4 pulses per second within 15 seconds
11 Repeat test a further two times If repeatability test indicates that the unit is functioning within the set parameters, proceed to the container leak test
However, if the repeatability check is inconclusive, repeat check in an alternative clean environment If repeatability problems persist, contact the technical support centre for instruction Close the hand valve of the leak standard after use
Helium Leak Detector Test (Alternative Test)
Details of the procedure and equipment required are available from the Original Equipment Manufacturer (OEM) on request
Submerged Leak Test (Alternative Test)
The third option is a water bath test The charged sample(s) are placed in water bath for a period of no less than one hour A transparent collection apparatus is placed over each sample in a manner so as to collect any escaping Novec™ 1230 or nitrogen gas The one hour period begins after all air bubbles appearing in the device at the start of the test have been removed and the water bath is at the required temperature
Container Leak TestCarefully probe the container/valve assembly at all probes and openings Ensure that the probe is not brought into direct contact with any objects as this can lead to spurious results and ensure that the dwell time of the probe is sufficiently long (more than 5 seconds) to ensure any leak is detected Any significant and repeatable increase of the audible pulse rate should be taken as an indication of a leak and the container and valve assembly should be rejected
Once the leakage source has been rectified, the container and valve assembly should be subjected to a further leak test using the halocarbon leak detector unit
78
SECTION 9 - RECHARGING PROCEDURE
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
79
SECTION 10 - APPENDICES
SAPPHIRE (UL)570805002011-03
0
5
10
15
20
25
30
35
40
-20 0 20 40 60 80 100
Temperature (degrees Celcius)
Pre
ssur
e (b
ar, a
bsol
ute)
80
APPENDIX A - TEMPERATURE CORRECTION CHART
Novec™ 1230 PRESSURISED TO 248 BAR (360 psig)WITH NITROGEN AT 21˚C
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
81
APPENDIX B - HUGHES PROGRAM PRINTOUT
SAPPHIRECalculation Program
Computer printoutExample Calculation
Consolidated Report
9 pages
SAPPHIRE (UL)570805002011-03
Spring Fire Protectoin123 Main StreetAnywhere, USA
12345-1234Phone: (123) 123-1234
Sapphire™ Designer Program (India) - ANSL3.81bUL: EX4510
Project: Computer AdditionFile Name: C:\Fc\ANSLn381b\Projects\Sample Project.FLC
Consolidated ReportCustomer Information
Company Name: AAA Data Processing CenterAddress: 123 Washington Street
Bigcity, USA12345-1234
Phone: (123) 456-7890Contact:
Title:John DoeSafety Manager
Project DataProject Name: Computer Addition
Designer: James WarrenNumber:Account:Location:
Description:
ABC-41234-1232nd FloorProtection of new computer equipment.
Copyright (c) Hughes Associates, Inc. Licensed to: Ansul Incorporated
Page: 1 9ofCalculation Date/Time: Monday, January 24, 2011, 9:21:23 PM
82
APPENDIX B - HUGHES PROGRAM PRINTOUT
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Consolidated Report
Elevation: 0 m (relative to sea level)Atmospheric Correction Factor: 1
Enclosure Information
Enclosure Number: 1Name: Front Computer Room
Enclosure Temperature...Minimum: 20.0 C
Maximum: 20.0 CMaximum Concentration: 5.370 %
Design Concentration...Adjusted: 5.369 %Minimum:
Minimum Agent Required:
Width:Length:Height:
Volume:Non-permeable:
Total Volume:
Adjusted Agent Required:Number of Nozzles:
5.300 %199.4 kg
8.00 m8.00 m4.00 m
256.00 cubic m0.00 cubic m
256.00 cubic m
202.1 kg2
Copyright (c) Hughes Associates, Inc. Licensed to: Ansul Incorporated
Page: 2 9ofCalculation Date/Time: Monday, January 24, 2011, 9:21:23 PM
83
APPENDIX B - HUGHES PROGRAM PRINTOUT
SAPPHIRE (UL)570805002011-03
Consolidated Report
Elevation: 0 m (relative to sea level)Atmospheric Correction Factor: 1
Enclosure Information
Enclosure Number: 2Name: Rear Computer Room
Enclosure Temperature...Minimum: 20.0 C
Maximum: 20.0 CMaximum Concentration: 5.371 %
Design Concentration...Adjusted: 5.370 %Minimum:
Minimum Agent Required:
Width:Length:Height:
Volume:Non-permeable:
Total Volume:
Adjusted Agent Required:Number of Nozzles:
5.300 %37.4 kg
4.00 m3.00 m4.00 m
48.00 cubic m0.00 cubic m
48.00 cubic m
37.9 kg1
Copyright (c) Hughes Associates, Inc. Licensed to: Ansul Incorporated
Page: 3 9ofCalculation Date/Time: Monday, January 24, 2011, 9:21:23 PM
84
APPENDIX B - HUGHES PROGRAM PRINTOUT
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Consolidated ReportAgent Information
Agent: Novec / Propellant N2(Novec is a trademark of 3M)
Adjusted Agent Required: 240.0 kgContainer Name: 120L Container Assy
Container Part Number: NeedNumber of Main Containers:
Number of Reserve Containers:30
Manifold: 3 Port 80mm End Manifold Assy (screwed)
HorizontalPipe Take Off Direction:Agent Per Container: 80.0 kg
Fill Density: 0.667 kg / lContainer Empty Weight: 1.0 kg
Weight, All Containers + Agent: 243.0 kgFloor Area Per Container: 0.10 square m
Floor Loading Per Container: 810 kg /square m
24.8 barStarting Pressure:
Pipe Network
Part 1 - PipeDescription Start End Type Diameter Length Elevation
Pipe
Main Cyl. X 3 0 1 50 mm 1.54 m 1.54 mManifold X 3 1 2 40T 50 mm 0.74 m 0.62 mManifold X 1 2 3 80T 80 mm 1.17 m 0.00 mPipe 3 4 40T 65 mm 1.00 m 0.00 mPipe 4 5 40T 65 mm 3.00 m 3.00 mPipe 5 6 40T 65 mm 1.00 m 0.00 mPipe 6 7 40T 40 mm 3.00 m 0.00 mPipe 7 8 40T 32 mm 2.00 m 0.00 mPipe/E1-N1 8 9 40T 32 mm 0.50 m -0.50 mPipe 7 10 40T 32 mm 2.00 m 0.00 m
Copyright (c) Hughes Associates, Inc. Licensed to: Ansul Incorporated
Page: 4 9ofCalculation Date/Time: Monday, January 24, 2011, 9:21:23 PM
85
APPENDIX B - HUGHES PROGRAM PRINTOUT
SAPPHIRE (UL)570805002011-03
Consolidated ReportPart 1 - PipeDescription Start End Type Diameter Length Elevation
Pipe
Pipe/E1-N2 10 11 40T 32 mm 0.50 m -0.50 mPipe 6 12 40T 25 mm 5.00 m 0.00 mPipe/E2-N1 12 13 40T 25 mm 0.50 m -0.50 m
Part 2 - Equivalent LengthStart End 90 45 Thru Side Union Other Added Total
0 1 0 0 0 0 0 0.00 m 10.67 m1 2 0 0 0 0 0 50mmDH&CV 0.00 m 12.74 m2 3 0 0 2 1 0 0.00 m 9.33 m3 4 0 0 0 0 0 0.00 m 1.01 m4 5 1 0 0 0 0 0.00 m 5.00 m5 6 1 0 0 0 0 0.00 m 3.02 m6 7 0 0 1 0 0 0.00 m 3.81 m7 8 0 0 0 1 0 0.00 m 4.30 m8 9 1 0 0 0 0 0.00 m 1.62 m7 10 0 0 0 1 0 0.00 m 4.30 m10 11 1 0 0 0 0 0.00 m 1.62 m6 12 0 0 0 1 0 0.00 m 6.74 m12 13 1 0 0 0 0 0.00 m 1.34 m
Part 3 - NozzlesStart End Flow Name Size Type Nozzle Area0 1 80.0 kg1 2 80.0 kg2 3 240.0 kg3 4 240.0 kg4 5 240.0 kg5 6 240.0 kg6 7 202.1 kg7 8 101.1 kg8 9 101.1 kg E1-N1 32 mm 16 Port - BR 725.83 square mm7 10 101.0 kg10 11 101.0 kg E1-N2 32 mm 16 Port - BR 725.83 square mm6 12 37.9 kg
Copyright (c) Hughes Associates, Inc. Licensed to: Ansul Incorporated
Page: 5 9ofCalculation Date/Time: Monday, January 24, 2011, 9:21:23 PM
86
APPENDIX B - HUGHES PROGRAM PRINTOUT
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Consolidated ReportPart 3 - NozzlesStart End Flow Name Size Type Nozzle Area6 12 37.9 kg12 13 37.9 kg E2-N1 25 mm 16 Port - BR 211.24 square mm
Parts Information
Total Agent Required: 240.0 kgContainer Name: 120L Container Assy (Part: Need)Number Of Containers: 3Manifold: 3 Port 80mm End Manifold Assy (screwed)
Nozzle Type Diameter Nozzle Area Part Number
E1-N1 16 Port - BR 32 mm 725.83 square mm 570605
E1-N2 16 Port - BR 32 mm 725.83 square mm 570605
E2-N1 16 Port - BR 25 mm 211.24 square mm 570604
Nozzle Drill Diameter Drill Size
E1-N1 7.6000 mm 7.60 mm
E1-N2 7.6000 mm 7.60 mm
E2-N1 4.1000 mm 4.10 mm
Pipe: Type Diameter Length40T 25 mm 5.50 m40T 32 mm 5.00 m40T 40 mm 3.00 m40T 65 mm 5.00 m80T 80 mm 1.17 m
'Other' Items:3 - 50 mm Check&Flex (Part: 570538/570568)
List of 90 degree elbows:1 - 25 mm2 - 32 mm2 - 65 mm
Copyright (c) Hughes Associates, Inc. Licensed to: Ansul Incorporated
Page: 6 9ofCalculation Date/Time: Monday, January 24, 2011, 9:21:23 PM
87
APPENDIX B - HUGHES PROGRAM PRINTOUT
SAPPHIRE (UL)570805002011-03
Consolidated ReportList of Tees:1 - 40 mm1 - 65 mm
System Acceptance
8.7 secondsSystem Discharge Time:Percent Agent In Pipe: 31.5%
Percent Agent Before First Tee: 23.6%
1Enclosure Number:Enclosure Name: Front Computer Room
Minimum Design Concentration: 5.300%Adjusted Design Concentration: 5.369%
Predicted Concentration: 5.357%Maximum Expected Agent Concentration: 5.357% (At 20.0 C)
MinimumAgent
RequiredNozzle
AdjustedAgent
Required
PredictedAgent
Delivered
NozzlePressure(Average)
E1-N1 99.7 kg 101.1 kg 100.8 kg 6.754 barE1-N2 99.7 kg 101.0 kg 100.8 kg 6.754 bar
2Enclosure Number:Enclosure Name: Rear Computer Room
Minimum Design Concentration: 5.300%Adjusted Design Concentration: 5.370%
Predicted Concentration: 5.437%Maximum Expected Agent Concentration: 5.437% (At 20.0 C)
MinimumAgent
RequiredNozzle
AdjustedAgent
Required
PredictedAgent
Delivered
NozzlePressure(Average)
E2-N1 37.4 kg 37.9 kg 38.4 kg 10.271 bar
Copyright (c) Hughes Associates, Inc. Licensed to: Ansul Incorporated
Page: 7 9ofCalculation Date/Time: Monday, January 24, 2011, 9:21:23 PM
88
APPENDIX B - HUGHES PROGRAM PRINTOUT
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
Consolidated ReportDrawing View: 1
Drawing View: 5
Copyright (c) Hughes Associates, Inc. Licensed to: Ansul Incorporated
Page: 8 9ofCalculation Date/Time: Monday, January 24, 2011, 9:21:23 PM
89
APPENDIX B - HUGHES PROGRAM PRINTOUT
SAPPHIRE (UL)570805002011-03
Consolidated ReportDrawing View: 9
Copyright (c) Hughes Associates, Inc. Licensed to: Ansul Incorporated
Page: 9 9ofCalculation Date/Time: Monday, January 24, 2011, 9:21:23 PM
90
APPENDIX B - HUGHES PROGRAM PRINTOUT
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
91
APPENDIX C - NOVEC™ 1230 DATA SHEET
Novec™ 1230 Material Safety Data Sheet
(MSDS)
(5 PAGES)
SAPPHIRE (UL)570805002011-03
MATERIAL SAFETY DATA SHEET 3M™ Novec ™ 1230 Fire Protection Fluid [FK-5-1-12] 11/09/10
_________________________________________________________________________________________________Page 1 of 8
Material Safety Data Sheet
Copyright, 2010, 3M Company All rights reserved Copying and/or downloading of this information for the purpose of properly utilizing 3M products is allowed provided that: (1) the information is copied in full with no changes unless prior written agreement is obtained from 3M, and (2) neither the copy nor the original is resold or otherwise distributed with the intention of earning a profit thereon
SECTION 1: PRODUCT AND COMPANY IDENTIFICATION
PRODUCT NAME: 3M™ Novec ™ 1230 Fire Protection Fluid [FK-5-1-12]MANUFACTURER: 3M
DIVISION: Electronics Markets Materials Division
ADDRESS: 3M CenterSt Paul, MN 55144-1000
EMERGENCY PHONE: 1-800-364-3577 or (651) 737-6501 (24 hours)
Issue Date: 11/09/10Supercedes Date: 04/09/07
Document Group: 16-3425-2
Product Use:Intended Use: STREAMING AND FLOODING FIRE PROTECTION
SECTION 2: INGREDIENTS
Ingredient C.A.S. No. % by Wt1,1,1,2,2,4,5,5,5-NONAFLUORO-4-(TRIFLUOROMETHYL)-3-PENTANONE 756-13-8 > 999
SECTION 3: HAZARDS IDENTIFICATION
3.1 EMERGENCY OVERVIEW
Specific Physical Form: LiquidOdor, Color, Grade: clear colorless, low odorGeneral Physical Form: LiquidImmediate health, physical, and environmental hazards:
3.2 POTENTIAL HEALTH EFFECTS
Eye Contact:Contact with the eyes during product use is not expected to result in significant irritation
92
APPENDIX C - NOVEC™ 1230 DATA SHEET
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
MATERIAL SAFETY DATA SHEET 3M™ Novec ™ 1230 Fire Protection Fluid [FK-5-1-12] 11/09/10
_________________________________________________________________________________________________Page 2 of 8
Skin Contact:Contact with the skin during product use is not expected to result in significant irritation
Inhalation:If thermal decomposition occurs:
May be harmful if inhaled
Ingestion:No health effects are expected
3.3 POTENTIAL ENVIRONMENTAL EFFECTS
This substance has a high Henry's Law constant and therefore will be primarily found in the atmosphere where photolysis will be the dominant reaction pathway The ultimate degradation products of the photolysis reaction are HF, CO2 and trifluoroacetic acid (TFA)
This substance does not contribute to ozone depletion; it has an atmospheric lifetime of approximately 5 days and a Global Warming Potential (GWP) of 1 ( IPCC 2001 Method)
SECTION 4: FIRST AID MEASURES
4.1 FIRST AID PROCEDURES
The following first aid recommendations are based on an assumption that appropriate personal and industrial hygiene practices are followed
Eye Contact: No need for first aid is anticipated
Skin Contact: No need for first aid is anticipated
Inhalation: If signs/symptoms develop, remove person to fresh air If signs/symptoms persist, get medical attention
If Swallowed: No need for first aid is anticipated
SECTION 5: FIRE FIGHTING MEASURES
5.1 FLAMMABLE PROPERTIES
Autoignition temperature Not ApplicableFlash Point Not ApplicableFlammable Limits - LEL Not ApplicableFlammable Limits - UEL Not Applicable
5.2 EXTINGUISHING MEDIAProduct is a fire-extinguishing agent
93
APPENDIX C - NOVEC™ 1230 DATA SHEET
SAPPHIRE (UL)570805002011-03
MATERIAL SAFETY DATA SHEET 3M™ Novec ™ 1230 Fire Protection Fluid [FK-5-1-12] 11/09/10
_________________________________________________________________________________________________Page 3 of 8
5.3 PROTECTION OF FIRE FIGHTERS
Special Fire Fighting Procedures: Wear full protective equipment (Bunker Gear) and a self-contained breathing apparatus (SCBA)
Unusual Fire and Explosion Hazards: Not applicable
Note: See STABILITY AND REACTIVITY (SECTION 10) for hazardous combustion and thermal decomposition information.
SECTION 6: ACCIDENTAL RELEASE MEASURES
Personal precautionsVentilate the area with fresh air For large spill, or spills in confined spaces, provide mechanical ventilation to disperse or exhaust vapors, in accordance with good industrial hygiene practice Warning! A motor could be an ignition source and could causeflammable gases or vapors in the spill area to burn or explode
Environmental proceduresFor larger spills, cover drains and build dikes to prevent entry into sewer systems or bodies of water Place in a metal container approved for transportation by appropriate authorities Dispose of collected material as soon as possible
Clean-up methodsObserve precautions from other sections Call 3M- HELPS line (1-800-364-3577) for more information on handling and managing the spill Contain spill Working from around the edges of the spill inward, cover with bentonite, vermiculite, or commercially available inorganic absorbent material Mix in sufficient absorbent until it appears dry Collect as much of the spilled material as possibleClean up residue Seal the container
In the event of a release of this material, the user should determine if the release qualifies as reportable according to local, state, and federal regulations.
SECTION 7: HANDLING AND STORAGE
7.1 HANDLINGFor industrial or professional use only Contents may be under pressure, open carefully Do not breathe thermal decomposition products
7.2 STORAGEKeep container in well-ventilated area Store out of direct sunlight Store away from heat Store away from strong bases, amines, and alcohols
SECTION 8: EXPOSURE CONTROLS/PERSONAL PROTECTION
8.1 ENGINEERING CONTROLSProvide appropriate local exhaust ventilation on open containers For those situations where the fluid might be exposed to extreme overheating due to misuse or equipment failure, use with appropriate local exhaust ventilation sufficient to maintain levels of thermal decomposition products below their exposure guidelines
94
APPENDIX C - NOVEC™ 1230 DATA SHEET
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
MATERIAL SAFETY DATA SHEET 3M™ Novec ™ 1230 Fire Protection Fluid [FK-5-1-12] 11/09/10
_________________________________________________________________________________________________Page 4 of 8
8.2 PERSONAL PROTECTIVE EQUIPMENT (PPE)
8.2.1 Eye/Face ProtectionNot applicable
8.2.2 Skin ProtectionNot applicable Gloves are not required
8.2.3 Respiratory ProtectionAs a good industrial hygiene practice:
Avoid breathing of vapors, mists or spray Under normal use conditions, airborne exposures are not expected to be significant enough to require respiratory protection If thermal decomposition occurs:
Do not breathe vapors
Select one of the following NIOSH approved respirators based on airborne concentration of contaminants and in accordance with OSHA regulations: Half facepiece or fullface supplied-air respirator Consult the current 3M Respiratory Selection Guide for additional information or call 1-800-243-4630 for 3M technical assistance If thermal decomposition occurs, wear supplied air respiratory protection
8.2.4 Prevention of SwallowingNot applicable
8.3 EXPOSURE GUIDELINES
Ingredient Authority Type Limit Additional Information1,1,1,2,2,4,5,5,5-NONAFLUORO-4-(TRIFLUOROMETHYL)-3-PENTANONE
3M TWA 150 ppm
SOURCE OF EXPOSURE LIMIT DATA:ACGIH: American Conference of Governmental Industrial HygienistsCMRG: Chemical Manufacturer Recommended GuidelineOSHA: Occupational Safety and Health AdministrationAIHA: American Industrial Hygiene Association Workplace Environmental Exposure Level (WEEL)
SECTION 9: PHYSICAL AND CHEMICAL PROPERTIES
Specific Physical Form: LiquidOdor, Color, Grade: clear colorless, low odorGeneral Physical Form: LiquidAutoignition temperature Not ApplicableFlash Point Not ApplicableFlammable Limits - LEL Not ApplicableFlammable Limits - UEL Not ApplicableBoiling point 49 ºC
Vapor Density 116 [Ref Std: AIR=1]
Vapor Pressure 244 mmHg [@ 20 ºC]
95
APPENDIX C - NOVEC™ 1230 DATA SHEET
SAPPHIRE (UL)570805002011-03
MATERIAL SAFETY DATA SHEET 3M™ Novec ™ 1230 Fire Protection Fluid [FK-5-1-12] 11/09/10
_________________________________________________________________________________________________Page 5 of 8
Specific Gravity 16 [Ref Std: WATER=1]pH Not ApplicableMelting point -108 ºC
Solubility in Water NilEvaporation rate > 1 [Ref Std: BUOAC=1]Volatile Organic Compounds 1600 g/l [Test Method: calculated SCAQMD rule 4431]Kow - Oct/Water partition coef No Data AvailablePercent volatile 100 %VOC Less H2O & Exempt Solvents 1600 g/l [Test Method: calculated SCAQMD rule 4431]Viscosity 06 centipoise [@ 25 ºC]Materials to avoid Alcohols
SECTION 10: STABILITY AND REACTIVITY
Stability: Stable
Materials and Conditions to Avoid: 10.1 Conditions to avoidLight
10.2 Materials to avoidStrong basesAminesAlcohols
Additional Information: Listed materials to avoid should not be mixed with liquid Novec 1230 fluid Avoid direct sunlight and ultraviolet light
Hazardous Polymerization: Hazardous polymerization will not occur
Hazardous Decomposition or By-Products
Substance ConditionCarbon monoxide During CombustionCarbon dioxide During CombustionHydrogen Fluoride During Combustion
Hazardous Decomposition: Hydrogen fluoride has an ACGIH Threshold Limit Value of 3 parts per million (as fluoride) as a Ceiling Limit and an OSHA PEL of 3 ppm of fluoride as an eight hour Time-Weighted Average and 6 ppm of fluoride as a Short Term Exposure Limit The odor threshold for HF is 004 ppm, providing good warning properties for exposure
SECTION 11: TOXICOLOGICAL INFORMATION
Please contact the address listed on the first page of the MSDS for Toxicological Information on this material and/or its components
96
APPENDIX C - NOVEC™ 1230 DATA SHEET
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
MATERIAL SAFETY DATA SHEET 3M™ Novec ™ 1230 Fire Protection Fluid [FK-5-1-12] 11/09/10
_________________________________________________________________________________________________Page 6 of 8
SECTION 12: ECOLOGICAL INFORMATION
ECOTOXICOLOGICAL INFORMATION
Not determinedPlease refer to existing literature on TFA
CHEMICAL FATE INFORMATION
Not determinedPhotolytic half-life: 3-5 daysPhotolytic degradation products may include Trifluoroacetic acid (TFA)NOTE: Hydrolysis is not expected to be a significant degradation pathway Product ishighly insoluble in water and volatile, and use as a clean extinguishing agent wouldnot typically result in releases to aquatic environments
SECTION 13: DISPOSAL CONSIDERATIONS
Waste Disposal Method: Incinerate in an industrial or commercial facility in the presence of a combustible material Combustion products will include HF Facility must be capable of handling halogenated materialsAs a disposal alternative, dispose of waste product in a facility permitted to accept chemical waste Reclaim if feasible For information on product return, contact your distributor
EPA Hazardous Waste Number (RCRA): Not regulated
Since regulations vary, consult applicable regulations or authorities before disposal.
SECTION 14:TRANSPORT INFORMATION
For Transport Information, please visit http://3M.com/Transportinfo or call 1-800-364-3577 or 651-737-6501.
SECTION 15: REGULATORY INFORMATION
US FEDERAL REGULATIONSContact 3M for more information
311/312 Hazard Categories:Fire Hazard - No Pressure Hazard - No Reactivity Hazard - No Immediate Hazard - No Delayed Hazard - No
STATE REGULATIONSContact 3M for more information
97
APPENDIX C - NOVEC™ 1230 DATA SHEET
SAPPHIRE (UL)570805002011-03
MATERIAL SAFETY DATA SHEET 3M™ Novec ™ 1230 Fire Protection Fluid [FK-5-1-12] 11/09/10
_________________________________________________________________________________________________Page 7 of 8
CHEMICAL INVENTORIESThe components of this product are in compliance with the chemical notification requirements of TSCA
One or more of the components of this product have been notified to ELINCS (European List of Notified or New ChemicalSubstances) Certain restrictions apply Contact the selling division for additional information
All the components of this product are listed on China's Inventory of Chemical Substances
The components of this material are in compliance with the new chemical notification requirements for the Korean Existing Chemicals Inventory
Contact 3M for more information
Additional Information: The components of this product are in compliance with the chemical notification requirements of the National Industrial Chemical Notification and Assessment Scheme (NICNAS) of Australia, the Canadian Environmental Protection Act (CEPA) and the Ministry of Economy, Trade and Industry of Japan This product is notified in the Philippines as PMPIN-2005-3
INTERNATIONAL REGULATIONSContact 3M for more information
ADDITIONAL INFORMATION
US EPA Significant New Alternatives Policy Program (SNAP) approved for uses is streaming and flooding fire protection application
This MSDS has been prepared to meet the U.S. OSHA Hazard Communication Standard, 29 CFR 1910.1200.
SECTION 16: OTHER INFORMATION
NFPA Hazard ClassificationHealth: 3 Flammability: 0 Reactivity: 1 Special Hazards: None
National Fire Protection Association (NFPA) hazard ratings are designed for use by emergency response personnel to address the hazards that are presented by short-term, acute exposure to a material under conditions of fire, spill, or similar emergencies Hazard ratings are primarily based on the inherent physical and toxic properties of the material but also include the toxic properties of combustion or decomposition products that are known to be generated in significant quantities
HMIS Hazard Classification
98
APPENDIX C - NOVEC™ 1230 DATA SHEET
EQUIPMENT: SAPPHIRE (UL)PUBLICATION: 570805ISSUE No. 00DATE: 2011-03
MATERIAL SAFETY DATA SHEET 3M™ Novec ™ 1230 Fire Protection Fluid [FK-5-1-12] 11/09/10
_________________________________________________________________________________________________Page 8 of 8
Health: 0 Flammability: 0 Reactivity: 1 Protection: X - See PPE section
Hazardous Material Identification System (HMIS(r)) hazard ratings are designed to inform employees of chemical hazards in the workplace These ratings are based on the inherent properties of the material under expected conditions of normal use and are not intended for use in emergency situations HMIS(r) ratings are to be used with a fully implemented HMIS(r) program HMIS(r) is a registered mark of the National Paint and Coatings Association (NPCA)
No revision information is available
DISCLAIMER: The information in this Material Safety Data Sheet (MSDS) is believed to be correct as of the date issued 3M MAKES NO WARRANTIES, EXPRESSED OR IMPLIED, INCLUDING, BUT NOT LIMITED TO, ANY IMPLIED WARRANTY OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE OR COURSE OF PERFORMANCE OR USAGE OF TRADE User is responsible for determining whether the 3M product is fit for a particular purpose and suitable for user's method of use or application Given the variety of factors that can affect the use and application of a 3M product, some of which are uniquely within the user's knowledge and control, it is essential that the user evaluate the 3M product to determine whether it is fit for a particular purpose and suitable for user's method of use or application
3M provides information in electronic form as a service to its customers Due to the remote possibility that electronic transfer may have resulted in errors, omissions or alterations in this information, 3M makes no representations as to its completeness or accuracyIn addition, information obtained from a database may not be as current as the information in the MSDS available directly from 3M
3M MSDSs are available at www.3M.com
99
APPENDIX C - NOVEC™ 1230 DATA SHEET