Sap Plant Maintenance Pm Business Blueprint Bbp

101
Vedanta Alumina Limited Plant Maintenance Page 1 of 1 SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3 CONFIDENTIAL SAP R/3 IMPLEMENTATION BUSINESS BLUEPRINT Plant Maintenance Prepared by Checked by Reviewed By Signature Approved By Signature Date Mr. Krishna Mr. Swain Mr. Coumar Mr. Kanada Vishal Rathore Pinaki Roy Mr. Manna 24.01.2006 PDF created with pdfFactory trial version www.pdffactory.com

description

SAP

Transcript of Sap Plant Maintenance Pm Business Blueprint Bbp

Page 1: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 1 of 1

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

SAP R/3 IMPLEMENTATION

BUSINESS BLUEPRINT

Plant Maintenance

Prepared by Checked by Reviewed By Signature Approved By Signature Date Mr. Krishna Mr. Swain Mr. Coumar Mr. Kanada Vishal Rathore Pinaki Roy Mr. Manna

24.01.2006

PDF created with pdfFactory trial version www.pdffactory.com

Page 2: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 2 of 2

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

CONTENTS

OBJECTIVE OF BUSINESS BLUEPRINT PHASE 3

SCOPE OF BPBP DOCUMENT 6

PLANT MAINTENANCE IN SAP - OBJECTIVE 7

SECTION I 8

SCOPE OF PLANT MAINTENANCE MODULE IN VAL 8

SECTION II 11

ORGANIZATION STRUCTURE 11

SECTION III 29

TO-BE PROCESSES 29

LIST OF REPORTS 82

SECTION IV-APPENDIX 86

PDF created with pdfFactory trial version www.pdffactory.com

Page 3: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 3 of 3

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

OBJECTIVE OF BUSINESS BLUEPRINT PHASE This document is the outcome of the As-Is study, Discussion at Training and during the To-Be process and business process requirement analysis for the Vedanta Alumina Limited. Based on this As-Is coupled with inputs from the core team members during To-Be discussion, we arrived at the Business Processes, which are incorporated in the Business Blue Print. The aim of this document is to map the best business processes related to the Plant Maintenance module in SAP ECC 5.0. This document is to be studied by core team members & process owners from Vedanta Alumina Limited. The preparation of this document is an essential precursor to prototyping and testing. The development work will start once process owner’s approval for this Blue Print is obtained followed by a corporate presentation to the senior management team, Vedanta Alumina Limited. This document will be used for configuring Plant Maintenance module in SAP implementation. Document is based on discussions/presentations between representatives of VAL & PWC. In other words it contains

1. SAP Organization Model in context of existing business scenario and future requirements/issues as envisaged by VAL. 2. Mapping of business processes/issues brought forward by PwC & VAL, with SAP functionality 3. Gaps & issues emerged during the discussion between VAL & PwC

4. Business Process Flows mapped in SAP as per the scope defined.

PDF created with pdfFactory trial version www.pdffactory.com

Page 4: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 4 of 4

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

5. Closure of Mapping Phase and start of Piloting Phase of implementation

A pictorial presentation of complete SAP implementation is depicted in the following page:

PDF created with pdfFactory trial version www.pdffactory.com

Page 5: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 5 of 5

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Page 6: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 6 of 6

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

SCOPE OF BPBP DOCUMENT

The objective of this Blue Print presented to the Project Sponsor is to document the following:

a) Business Requirements of VAL that need to be translated into SAP. This has been prepared by SAP consultants team members on the basis of As-Is document, factory visit & discussions between PwC SAP consultants and VAL core team members.

b) SAP Gaps as identified by PwC Team w.r.t. The present scope of implementation and Business Requirements of VAL. c) Details of SAP New Business Process description supported by Process Flow diagram w.r.t. Different SAP process indicating the desired “To be

Processes”. In order to bring the clarity and better understanding, the document has been divided in five sections: SECTION I : Scope of SAP Plant Maintenance module for the project SECTION II : Organization structure SECTION III : Master Data Management, As-Is/ To-Be Business processes, and Gaps identified for business processes as per SAP.

SECTION IV: Appendix-Process Flow Diagrams.

PDF created with pdfFactory trial version www.pdffactory.com

Page 7: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 7 of 7

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Plant Maintenance in SAP - Objective Ø To have Reliable Equipments with low MTTR and high MTBF

Ø To have Predictive and Condition –based plans that help to improve equipment availability.

Ø To eliminate repetitive breakdowns and thereby reduce wastage of valuable resources

Ø To have a Preventive Maintenance Plan in place that helps to maintain Equipment Health.

Ø To eliminate the need to pull out data from different systems for reporting purposes.

Ø To draw a long-term plan for Spares requirement and also help in Budgeting.

Ø These objectives will be obtained by

Ø By detailed analysis of downtimes and designing a Corrective Action Plan based on this analysis.

Ø By having up to date cost figures (Plant-wise/Location-wise/Equipment-wise) for better maintenance decision-making Ø By analysing usage data on components and services related to maintenance.

PDF created with pdfFactory trial version www.pdffactory.com

Page 8: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 8 of 8

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

SECTION I

Scope of Plant Maintenance Module in VAL PARTICULARS ALUMINA POWER Master 1.1 General Master Records 1.1.1 Material Master X X 1.1.2 Material BOM X X 1.1.3 Work Center X X 1.1.4 Service Master X X MM 1.2 Plant Maintenance 1.2.1 Technical Objects (Structuring of Technical Systems) X X 1.2.2 Measuring Points & Measuring Documents X X 1.2.3 Warrantees X X 1.2.4 Permits X X 1.2.5 Task Lists X X 1.2.6 Maintenance Strategy X X 1.2.7 Maintenance Plans X X Business 2.1 Plant Maintenance 2.1.1 Breakdown/Routine Maintenance Processing X X

PDF created with pdfFactory trial version www.pdffactory.com

Page 9: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 9 of 9

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

PARTICULARS ALUMINA POWER 2.1.1.1 Notification X X 2.1.1.2 Order X X 2.1.1.3 Material Movements X X 2.1.1.4 Completion Confirmation X X 2.1.2.5 Confirmation of external services through service sheet X X 2.1.1.6 Settlement and Completion X X 2.1.1.7 Evaluations: Information System X X 2.1.2 Preventive / Shut Down Maintenance Processing 2.1.2.1 Maintenance Planning X X 2.1.2.2 Worklist X X 2.1.2.3 Notification X X 2.1.2.4 Deadline Monitoring X X 2.1.2.5 Order X X 2.1.2.6 Material Movements X X 2.1.2.7 Completion Confirmation X X 2.1.2.8 Settlement and Completion X X 2.1.2.9 Evaluations: Information System X X 2.1.3 Refurbishment Processing in Plant Maintenance 2.1.3.1 Order X X 2.1.3.2 Material Movements X X 2.1.3.3 Completion Confirmation X X 2.1.3.4 Settlement and Completion X X 2.1.3.5 Evaluations: Information System X X

PDF created with pdfFactory trial version www.pdffactory.com

Page 10: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 10 of 10

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

PARTICULARS ALUMINA POWER 2.1.4 Development/Improvement/Re-Design Orders X X 2.1.5 Calibration Orders X X PM/QM 2.2 Inventory Management 2.2.1 Goods Movements 2.2.1.1 Reservation X X 2.2.1.2 Purchase requisition MM 2.2.1.3 Goods Receipt MM 2.2.1.4 Stock Transfers / Trans. Postings MM 2.2.1.5 Goods Issue X X Cross-Application Components 3.1 Classification System 3.1.1 Characteristics X X 3.1.2 Classes X X 3.1.3 Classification X X

PDF created with pdfFactory trial version www.pdffactory.com

Page 11: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 11 of 11

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Section II

Organization Structure

Plants The plant is an operating area or branch within a company. The plant is assigned to a single company code. A plant has its own material master data. You can maintain data at plant level for the following views on a material master record in particular: MRP, Purchasing, Storage, Work scheduling, Production resources/tools, Forecasting, Quality management, Sales, Costing. As per discussion with Finance & Materials, there will be only four Company Codes and four plants will be created which may be as follows: VAL Alumina 1000 VAL Power 2000 VAL Smelter 3000 VAL JV 4000 Out of this, the VAL Alumina Plant (1000), VAL Power Plant (2000) will have complete PM Implementation while the VAL smelter Plant (3000) and JV (4000) will only have PM basic organization structure.

PDF created with pdfFactory trial version www.pdffactory.com

Page 12: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 12 of 12

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Maintenance Plant

In Plant Maintenance, a distinction is made between the organizational units "planning plant" and "maintenance plant".

• Maintenance plant

In a maintenance plant, you can manage technical objects and main work centers.

• Planning plant

In the planning plant, maintenance task lists are defined for the respective maintenance plants, material planning is carried out on the basis of bills of material in task lists and orders, maintenance plans are managed and scheduled, maintenance notifications are created and maintenance orders can be handled.

With discussion for the Organization Structure for Maintenance Planning, it has been decided to follow the based on the Material Management Plant Code. Since maintenance Planning is independent of all four plants, hence there will be four maintenance planning plants in Plant Maintenance Organization Structure. They are as follows:

PDF created with pdfFactory trial version www.pdffactory.com

Page 13: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 13 of 13

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

MAINTENANCE PLANT DESCRIPTION

1000 VAL Alumina Maintenance Plant

2000 VAL Power Maintenance Plant

3000 VAL Smelter Maintenance Plant

4000 VAL JV Maintenance Plant

MAINTENANCE PLANNING PLANT DESCRIPTION

1000 VAL Alumina Maintenance Planning Plant

2000 VAL Power Maintenance Planning Plant

3000 VAL Smelter Maintenance Planning Plant

4000 VAL JV Maintenance Planning Plant

PDF created with pdfFactory trial version www.pdffactory.com

Page 14: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 14 of 14

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Locations

A location is the physical location to identify where the equipment lies. This data helps the Plant Maintenance person to identify where the equipment is located. Here location, plant section, room number etc. can be mentioned. Proposed locations for Vedanta Alumina Limited are as follows: For Alumina Plant (1000)

Location DESCRIPTION

RED Red Area

WHT White Area

UTL Utilities

NPA Non Plant area

PDF created with pdfFactory trial version www.pdffactory.com

Page 15: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 15 of 15

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

For Power Plant (2000)

Location DESCRIPTION

TGU Power Generation

BLR Steam Generation

BOP Balance of Plant

For Mining Plant (4000)

Location DESCRIPTION

MIN Mining

CRG Crushing

PDF created with pdfFactory trial version www.pdffactory.com

Page 16: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 16 of 16

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Planner Group

Planner groups or maintenance planning groups must be defined separately for each planning plant.

Depending on the size and structure of your company, a maintenance-planning group may be an individual department (for central work preparation), a group of skilled craftsmen or a workshop.

Every piece of equipment and functional location can be allocated to a maintenance-planning group.

Maintenance planning groups can also be used for evaluation purposes.

In Vedanta Alumina Limited we have identified FOUR planner groups for each plants For Alumina Plant (1000)

Planner Group DESCRIPTION

101 Mechanical Planner Group

102 Electrical Planner Group

103 Instrumentation Planner Group

104 Civil planner Group

PDF created with pdfFactory trial version www.pdffactory.com

Page 17: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 17 of 17

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

For Power Plant (2000)

Planner Group DESCRIPTION

201 Mechanical Planner Group

202 Electrical Planner Group

203 Instrumentation Planner Group

204 Civil planner Group

For Mining Plant (4000)

Planner Group DESCRIPTION

401 Mechanical Planner Group

402 Electrical & Instrumentation Planner Group

404 Civil planner Group

PDF created with pdfFactory trial version www.pdffactory.com

Page 18: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 18 of 18

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Functional Location category

Functional Location Category to be used – “M” – Technical System Standard

Functional Location Structure Indicator

We shall be using the following Structure Indicator for Functional Location Labelling: STRUCTURE INDICATOR DESCRIPTION STRUCTURE

VAL01 Indicator for Alumina Plant NNNN--AAA-AAA-XXX-XXXX-XXXXX

VAL02 Indicator for Power Plant NNNN- AAA-XXX-XXX-XXX-XXX

VAL03 Indicator for Mining Plant NNNN- AAA-XXX-XXX-XXX-XXX

(A- Alpha, X- Any character, N-Numeric)

PDF created with pdfFactory trial version www.pdffactory.com

Page 19: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 19 of 19

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Example:

1000-RED-DIG-TR0-DIGV-DIG01

1000 – Vedanta Alumina Plant DIG – Digester Area TR0 – Train 0 Area DIGV – Digestion Vessel DIG01 – Digester 01

PDF created with pdfFactory trial version www.pdffactory.com

Page 20: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 20 of 20

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Equipment Categories and Equipment Codification Equipment Categogy for all the equipment will be used as ‘M’ It has been decided that the Equipment Code will be Externally generated for easy identification and the logic for that code will be XX XXX NNNN Main Group Sub-Group Number Spare Parts / Assemblies / Components codification All the spare parts, assemblies, components, consumables for maintenance will be defined as material in SAP for taking them in inventory and the material code will be externally generated. Logic for the material code is

XX XX XXX XXXXX Major Group Sub Group Sub- Sub Group Material No

• The codification is external. • 12 digit codification, split as mentioned above. • It is going to be all numeric

PDF created with pdfFactory trial version www.pdffactory.com

Page 21: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 21 of 21

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

1. For bearings, the codification will be strictly with the engineering department. 2. Flag in the system for insurance spares. 3. Flag for the regular inventory items. 4. Flag for the value capture of all the materials. 5. For initial project spares, value will be taken as zero and split valuation will be used for it.

PDF created with pdfFactory trial version www.pdffactory.com

Page 22: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 22 of 22

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Technical Object Types

This implies a division of a technical object for precise description.

All equipments at VAL would be categorized into various Technical Object Types. An indicative list of technical objects is given below.

Alumina Plant

Technical Object Technical Object Technical Object

PDF created with pdfFactory trial version www.pdffactory.com

Page 23: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 23 of 23

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Power Plant

Technical Object Technical Object Technical Object

PDF created with pdfFactory trial version www.pdffactory.com

Page 24: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 24 of 24

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Catalog Profile

Combination of code groups, which determine from a functional viewpoint, which code groups can be used for a particular technical object.

The following catalogs would be used for VAL. Common catalog profile will be used for different technical object types.

n Coding - D

n Object parts – B

n Problem/Event Codes – 4

n Cause Codes – 5

n Activity Codes – A

We shall be using common catalog profile for all equipments. Details of the catalogs would be maintained as follows:

Ø Coding: Coding of breakdowns as Serious/Semi-serious/Normal

Ø Object Parts: All critical Mechanical and Electrical parts would be configured for each of the technical object types defined.

Ø Problem/Event Codes: All problems that normally occur or might occur would be listed for each type of Technical Object.

Ø Cause Codes: All probable causes of the events/problems listed above would be configured for each technical object type.

Ø Activity Codes: The normal activities (generic) carried out for attending to the problems would be configured here.

PDF created with pdfFactory trial version www.pdffactory.com

Page 25: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 25 of 25

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Example:

Technical Object Type : Pump

Object Parts Problems Causes Activities

Impeller Impeller Broken Improper Cleaning Cleaned

Bearing Impeller Jammed Lubrication Failure Machined

Casing Bearing Damaged Life Expiry Rewinding Done

Shaft Abnormal Sound Impeller nut Loose Reset

Pressure Low Misalignment Replaced

Shaft Damaged

PDF created with pdfFactory trial version www.pdffactory.com

Page 26: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 26 of 26

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Notification Types

Various Notification Types would be configured in the System to take care of the various types of job requirements.

NOTIFICATION TYPE DESCRIPTION

M1 Maintenance Request (Predictive w/o production loss)

M2 Breakdown Report (Breakdown Maintenance with production loss)

M3 Activity Report (Preventive Maintenance)

M5 Improvement (Modification/Development/Re-Design) Notification

M6 Safety Notification

M7 Shutdown Notification

M8 Calibration Notification

M9 Workshop Notification

PDF created with pdfFactory trial version www.pdffactory.com

Page 27: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 27 of 27

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Maintenance Order Types

Seven different types of Maintenance orders will be defined for the various types of maintenance/repair activities to be carried out.

MAINTENANCE ORDER TYPE DESCRIPTION

PM01 Maintenance order w/o production loss

PM02 Breakdown order with production loss

PM03 Preventive maintenance order

PM04 Re-furbishment Order

PM05 Improvement (Modification/Development/Re-Design) order

PM06 Safety Order

PM07 Shutdown Order

PM08 Calibration Order

PM09 Workshop Orders

PM10 Annual Maintenance Contracts

PDF created with pdfFactory trial version www.pdffactory.com

Page 28: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 28 of 28

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Assignment of Notification Types to Order Types

Notification type Order type

M1 PM01

M2 PM02

M3 PM03

M5 PM05

M6 PM06

M7 PM07

M8 PM08

M9 PM09

There will be no notification for refurbishment orders & Annual Maintenance Orders.

PDF created with pdfFactory trial version www.pdffactory.com

Page 29: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 29 of 29

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

SECTION III

To-Be Processes Plant Maintenance Processes The Business Blue Print is divided into various sections as defined by the different processes as discussed during to-be and Expectation from SAP. These processes are: Routine/Predictive Maintenance Breakdown Maintenance Preventive Maintenance (based on duration and measuring point) Refurbishment Spares Improvement / Development / Modification / Re-design Maintenance Shutdown Maintenance (Planned maintenance) General Maintenance (to be done through maintenance request) Annual Maintenance Orders Maintenance Budgeting (Through FI/CO Module) Condition Monitoring (Through measuring points/counters) Spare Part Planning Report Analysis To carry out these processes, certain Masters are required to be maintained prior to carry out the Transactions and Reports.

PDF created with pdfFactory trial version www.pdffactory.com

Page 30: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 30 of 30

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

1.0 Masters

1.1 Spare Parts, Components, Assemblies

Fully system supported

All Spare Parts, Consumables used in building of machine or repair will get a unique material code. This code will be unique for the whole organisation and will not change at Plant level. Basic data of the materials will be maintained at client level while the other data will be maintained at purchase organization and plant level. The material master for spare parts will have several views like Basic Data, Purchasing View, MRP, Accounting view etc. The Spare Parts, which are accepted after inspection will be subjected to Quality Inspection. For such material Quality Management View will be activated and necessary master date will be created for the automatic inspection lot creation and results recording and usage decision for the Spare parts. For VED analysis (V-Vital, E-Essential, D-Desirable) one field will be used in the material master of the spares so that this analysis can be done.

N

Will be done with the co-ordination of MM

PDF created with pdfFactory trial version www.pdffactory.com

Page 31: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 31 of 31

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

1.2 Valuation type of Spare Parts

Fully system supported

The spare part in SAP is maintained with the valuation category. In the valuation category, the valuation type is maintained. These valuation types can be damage, repair etc. Each of the valuation type has certain value attached to it. During the maintenance activities, spare parts are replaced with new or repaired one. The defective spare parts are repaired also. In SAP, the maintenance and cost of repair of such defective spare parts is maintained using Refurbishment Order. Repaired part can be stored at different storage location. The activity is directly linked to MM as well. Hence the valuation class and type will be in accordance and consultation with MM.

N

Will be done with the co-ordination of MM

1.3 Catalog Fully system supported

Catalogs are used to manage, uniformly define, and standardize information (for example, cause analysis for the failure of the machine) on a client-wide basis. The catalogs help in recording the information with ease and sorting out the activities as well. In the catalogs, each unit of information is assigned a unique alphanumeric code and an explanatory text.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 32: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 32 of 32

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

The different catalog types are Object Parts, Cause, Damage, Task, Activities, etc. The task and Activities are similar with different presentation structures. In Task Screen, for each task, Planned Start date, Planned Finish date, Completed By and Completion Date can be mentioned. In Activities Screen, Start Date and End Date can be mentioned.

1.4 Code Group Fully system supported

Code groups are used to combine and structure codes within a catalog type. Code groups are used at client level to group codes that have the same contents or relate to one another, within a catalog type. Assigned codes to a group are called as Code Group.

N

1.5

Functional Location Create / Change/Display Functional Location Master Data

Fully system supported

Functional location is an organizational unit within Logistics, which structures the maintenance objects of a company according to functional, process-related or spatial criteria. A functional location represents the place at which a maintenance task is to be performed. A functional location represents an area at which an object can be

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 33: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 33 of 33

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

installed. The objects that can be installed at functional locations are called pieces of equipment

Records can be kept of the maintenance tasks that are performed; technical data can be collected and evaluated over long periods of time and the costs of maintenance tasks can be monitored for the individual areas. Analysis can be carried out on the influence of usage conditions on the damage susceptibility of the pieces of equipment installed.

1.6

Equipment Master Create/Change/Display Equipment master Data

Fully system supported

The use of equipment master records in the Plant Maintenance (PM) application component enables to define individual machine, motor as a piece of equipment. Equipment for which any maintenance activities are carried out, are maintained in the Equipment Master. The cost of maintenance of equipment based on type of maintenance can be monitored. If the equipment is very big, then equipment and sub-equipment can be created in SAP.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 34: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 34 of 34

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

1.6.1 Start up & Acquisition Date

Fully system supported

The Start up date field indicates the installation & commissioning date. This indicates the date on which the equipment is operational. The Acquisition date indicates when the asset is purchased. The use of this date is for information as well as for deciding the ageing of the equipment so that the maintenance planning can be updated e.g. during the initial installation period the preventive maintenance requirement is lower but after years of usage, the requirement of preventive maintenance planning frequency increases.

N

1.6.2 ABC Indicator Fully system supported

The ABC Indicator in an Equipment signifies the importance of that equipment in the manufacturing scenario. This helps in prioritising the maintenance planner to execute the maintenance activities in the plant. There will be four types for maintenance and one for calibration for the ABC Indicator as the outcome of the discussion:

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 35: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 35 of 35

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

A: Very high Production Loss B: Major Production Loss C: Minor Production Loss D: No production loss (Spare assembly) Q: Quality Loss (for Calibration Instruments)

1.6.3 Warranty Fully system supported

Warranties define the scope of the services that a company performs at a technical object in the event of damage or problems. It is a commitment of the manufacturer, vendor, or retailer to guarantee services to a customer either free-of-charge or only charged in part, over a certain period of time. The warranty period of the equipment can be mentioned in the equipment master. This gets pop up when a user wants to create maintenance order for the equipment during the warranty period.

N

1.6.7 Permits Fully system supported

Agreement required depending on setting before an order may be released or technically completed.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 36: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 36 of 36

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

Permits are used to ensure that special approval must be obtained before orders are executed.

Permits can be assigned to the following objects:

• Technical objects – functional locations and equipment

• Orders

Permits can cover the following areas:

• The way the order is executed or the safety aspects involved

Safety precautions for the employees and surroundings: Providing ear protection for employees or acidproof equipment, safeguarding the work area, installing a flame-proof zone, work clearance certificate

• How the execution of an order is organized

Budget guarantee, approval of plant manager

PDF created with pdfFactory trial version www.pdffactory.com

Page 37: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 37 of 37

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

1.7 Budget System supported

Budget for maintenance can be done at the maintenance cost center level. Apart from budget, we can also give the planned expenses for maintenance.

Cost center and budget will be done in CO module.

N Through FI/CO Module

1.8

Classification Creation/change of Class and Characteristics

Fully system supported

The classification system allows you to use characteristics to describe all types of objects, and to group similar objects in classes – to classify objects, in other words, so that you can find them more easily later.

You then use the classes to help you to find objects more easily, using the characteristics defined in them as search criteria. This ensures that you can find objects with similar or identical characteristics as quickly as possible.

Characteristic is a property that describes and differentiates objects.

Example: length, color, weight, etc.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 38: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 38 of 38

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

Class is an assembly of characteristics that can be attributed to a product (or to several similar products). It can also be defined as a grouping of similar products according to common characteristics

Example – Pump class, Boiler class etc.

1.9

Maintenance Strategy Creation/Change of Maintenance strategy

Fully system supported

A rule for the sequence of planned maintenance and predefined tasks. A maintenance strategy contains the maintenance packages that define the cycle in which the tasks must be performed, for example, every two months, every 5,000 km, every 500 operating hours. Maintenance strategies are obligatory in strategy plans.

N

1.10 Work Center Creation/Change of Work centers

Fully system supported

Work center describes the logical station where work is being carried out. The plant will have one or more work centers.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 39: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 39 of 39

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

1.11

Maintenance Task List Creation/Change of Task-lists (For Preventive Maintenance, Shut down Activities, and Calibration)

Fully system supported

Equipment Task List is the description of the procedure for maintaining a maintenance object called Equipment. Maintenance task lists is the generic term used for all task lists specifically to Equipment task list. A maintenance task list contains operation. The maintenance task list uses a strategy for planning of Equipment Maintenance for the defined period say weekly, monthly, quarterly etc. Operation can be processed internally or externally. The activities defined for an external operation are requested using orders. There are two types of Equipment Task List: Equipment Task List and General Task List. Equipment task List can be attached only to one Equipment Task List. But General Maintenance Task List can be attached to several Equipments. The General Equipment task List is used for the Preventive Maintenance where the similar equipments undergo Preventive Maintenance Scheduling.

N

1.12

Strategy Plan Creation/Change of Maintenance Plans

Fully system supported

Strategy Plan defines the description of maintenance and tasks to be performed on maintenance objects. The dates and scope of the tasks are also defined here.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 40: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 40 of 40

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

(For Preventive Maintenance, Shut down Activities, Calibration

A maintenance plan is structured based on a maintenance strategy. A maintenance plan contains one or more maintenance items, in which the maintenance objects to be maintained and the corresponding task list has been defined. The maintenance tasks to be performed on a due date are determined by the maintenance task list assigned to the maintenance item. The necessary maintenance orders are automatically generated for a due maintenance date.

1.13 Scheduling for the Equipment

Fully system supported

Based on the maintenance plan, we can schedule the Preventive/Shut down/Calibration Plan for the whole of the scheduling period or we can use deadline monitoring to carry out the scheduling of the Preventive Maintenance Orders for fixed period of say one month etc.

N

1.14

Equipment / Material BOM (Bill of Material) Creation/ Change of BOM

Fully system supported

Any equipment is made of some assemblies and the assemblies are further made of spare parts and small components down the level.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 41: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 41 of 41

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

The equipment BOM gives ready list available to record the critical spare part list for any equipment. The same list can be referred to create preventive maintenance planning. In the equipment BOM, create the spare part list, quantity and stock type (non-stock or stock item). This master helps in identifying for which material Purchase Requisition will be made or Reservation is created. For assemblies also we need to create BOM (Material BOM).

1.15

Measuring Points and Counters Creation/ Change of Measuring Points

Fully system supported

A physical or logical place at which a condition is described. Example can be Temperature inside a reactor, Speed of revolution of a wind wheel, the status is described using measurement readings, the operating duration of Diesel Generator etc. Measuring points are stored in the SAP System as master data for the Equipment. It can work as a counter to record the duration, based on manufacturer guidelines, the Preventive Maintenance Orders can be generated for the same.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 42: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 42 of 42

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

Counter are defined as Measuring Point in SAP and Counter readings are taken at counters at particular intervals and in particular measurement units. For example, counter readings for kilometers driven, operating hours or electricity used.

2.0 Notification Fully system supported

A key that determines the origin, content, and other features of maintenance activities. The Maintenance notification includes malfunction, activity reports and maintenance requests. It gives the equipment location data, malfunction start and end date/time, duration of total breakdown, priority etc. Maintenance notifications document maintenance tasks completely, and make them available for analysis in the long term. You can use them for preliminary planning and execution of tasks.

N

3.0 Maintenance Order Fully system supported

Order is a task to perform within a company. The order specifies the type of task to perform, how and when it will be performed. It also defines the rules for the settlement of the costs. Maintenance order to be used whenever any cost is involved for

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 43: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 43 of 43

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

maintenance activity, i.e., external services required or components required for maintenance. Orders will be used in Plant Maintenance Module for classifying different type of activities for an equipment, functional location etc. For the new purchased assets, Internal Order can be used for cost involved in purchasing, erecting and commissioning activities. These orders will be created in CO module.

4.0 External Services Fully system supported

External Services are the external support required from the expert for the maintenance of equipments. This process can be required for Preventive, Breakdown or any other type of maintenance. Hence this becomes a common process required for any maintenance activities. The different steps of confirming an external service are given below.

N

4.1 Creation of operation using PM03 control key

Fully system supported

In general, Plant Maintenance Internal control Key (PM01) is used. Wherever the external services are required, in the relevant

N PM/MM

PDF created with pdfFactory trial version www.pdffactory.com

Page 44: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 44 of 44

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

operation of that order, the PM03 (Plant Maintenance External Services) control key is used. Using this key, the system requires the Service No. / Description, Quantity and price of the service. Based on the MM requirement for Purchase Requisition, certain fields are required to enter. On saving the order, the system creates the Purchase Requisition number for the external services. This PR number is used to create the Service Purchase Order by MM.

4.2 Confirming the External Services

Fully system supported

For confirmation of external services, Service Entry Sheet is used. The service entry sheet is created with reference to the Service PO. In the service entry sheet, the number or percentage of services is confirmed. Accordingly the data is updated in Controlling and Financial Accounting for releasing the payment for the external services.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 45: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 45 of 45

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

5.0

Predictive Maintenance/ Routine Maintenance/General Maintenance

Fully system supported

There are many instances when based on the noise factor, heat dissipation etc. the prediction of machine failure can be made. In such cases, maintenance activities are carried using Predictive Maintenance. The decisive factor in this case is that there is no malfunction. Here Predictive Maintenance Notification is created to record the damage cause, activities undertaken.

N

5.1

Notification by the user / maintenance in-charge of the machine (M1)

Fully system supported

User / maintenance in-charge creates a Predictive Maintenance Notification (Maintenance Request) based on the abnormal behaviour indicated in the machine during the operation in the machine. Notification type M1 is to be used. In this the status of the machine before and after malfunction, date and time of malfunction and priority etc. are defined. The location and other necessary data get copied into the notification from the equipment master.

N

5.2 Create maintenance order from Notification

Fully system supported

After receipt of the notification, the maintenance department creates the Maintenance Order (Order Type - PM01) using the screen of notification in change mode. Then describes the

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 46: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 46 of 46

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

screen of notification in change mode. Then describes the operations, requirement of spare parts for the maintenance activities in the order and Release for and issue of spares and confirming the activities. If any operation requires External Services, then Steps as mentioned in 5.1 and 5.2 will also be used.

5.3 Order Execution Fully system supported

During maintenance of the machine (outside SAP), spares required will be mentioned in the order. Saving the order will create a reservation for the stock-able spares. Then Order to be released and against the Order Number or reservation number, material will be issued by the store. For non-stock spares, Purchase Requisition is created from the order. Based on the release strategy it can be released for procurement and Purchase Order will be created by the MM. Upon receiving the material, it will be issued against the maintenance order.

N

5.4 Order Completion Confirmation

Fully system supported

After completion of maintenance activities, the order needs to be confirmed. Order confirmation can be done partially or final. It is

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 47: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 47 of 47

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

confirmed. Order confirmation can be done partially or final. It is used to record how the work is progressing. For partial confirmation, order must not yet have been completed fully.

You use the remaining functions for the completion of an order, after the order has been completed fully and a final completion entered.

You enter time completion confirmations for operations and sub-operations for maintenance and service orders to document the status of the processing for these operations. After that all the operations of the order needs to be confirmed. Extra stockable issued material can be returned to stores from the order.

5.5 View Costs Fully system supported

The Planned vs. actual costs can be viewed after all issues and service entry sheets are completed

N

5.6 Change / Complete Notification

Fully system supported

Notification will be closed after noting down all catalog & details of maintenance required to be recorded.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 48: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 48 of 48

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

5.7 Technically and Business Completion

Fully system supported

After confirmation for the maintenance order, the order needs to be technically completed and settled to the appropriate cost centre based on settlement profile. When all the costs are settled and no further activities are pending against that order, business completion for the order is done.

N

6.0 Breakdown Maintenance

Fully system supported

The Breakdown maintenance refers to the sudden failure of the machine to produce the desired results / output. An employee from production would use a malfunction report to report that:

• A production system is not functioning properly. • Performance has reduced for a production system, or that

the system is not functioning at all. • A production system is producing goods of poor quality.

This is carried using a formal intimation by user department for the maintenance of the equipment. The record of total repair time is used to calculate Mean Time To Repair.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 49: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 49 of 49

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

6.1

Notification by the user of the machine (Malfunction Report M2)

Fully system supported

Like the Breakdown slip, here in SAP the user creates a breakdown notification to intimate the Maintenance Department for the breakdown in the machine. In this the user defines the status of the machine, date and time of breakdown and priority of the breakdown. The location and other necessary data get copied into the notification from the equipment master.

N

6.2 Create maintenance order from Notification

Fully system supported

After receipt of the notification, the maintenance department creates the Maintenance Order (Order Type - PM02) using the screen of notification in change mode. Then describes the operations, requirement of spare parts for the maintenance activities in the order and Release for and issue of spares and confirming the activities. If any operation requires External Services, then Steps as mentioned in 5.1 and 5.2 will also be used.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 50: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 50 of 50

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

6.3 Order Execution Fully system supported

During maintenance of the machine (outside SAP), spares required will be mentioned in the order. Saving the order will create a reservation for the stock-able spares. Then Order to be released and against the Order Number or reservation number, material will be issued by the store. For non-stock spares, Purchase Requisition is created from the order. Based on the release strategy it can be released for procurement and Purchase Order will be created by the MM. Upon receiving the material, it will be issued against the maintenance order.

N

6.4 Order Completion Confirmation

Fully system supported

After completion of maintenance activities, the order needs to be confirmed. Order confirmation can be done partially or final. It is used to record how the work is progressing. For partial confirmation, order must not yet have been completed fully.

You use the remaining functions for the completion of an order, after the order has been completed fully and a final completion entered.

You enter time completion confirmations for operations and sub-

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 51: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 51 of 51

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

operations for maintenance and service orders to document the status of the processing for these operations. After that all the operations of the order needs to be confirmed. Extra stockable issued material can be returned to stores from the order.

6.5 View Costs Fully system supported

The Planned vs. actual costs can be viewed after all issues and service entry sheets are completed

N

6.6 Change / Complete Notification

Fully system supported

Notification will be closed after noting down all catalog & details of maintenance required to be recorded.

N

6.7 Technically and Business Completion

Fully system supported

After confirmation for the maintenance order, the order needs to be technically completed and settled to the appropriate cost centre based on settlement profile. When all the costs are settled and no further activities are pending against that order, business completion for the order is done.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 52: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 52 of 52

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

7.0 Preventive Maintenance

Fully system supported

Preventive maintenance is the scheduled / planned maintenance based on the manufacturer recommendation or own experience. Here a frequency called Strategy for Maintenance is maintained based on Duration or the operating hours. The activities unlike other maintenance are much clear in advance and are documented in the maintenance Task list. The spare parts as well can be planned and stocked for the periodic maintenance activities.

N

7.1

Preventive Maintenance order generation from schedule.

Fully system supported

In Preventive Maintenance, certain master data needs to be maintained. The task list, strategy plan, measurement counter (optional) etc. are maintained for equipment. Measurement Counter uses a class characteristics say operating duration. The counter is created for the equipment. For recording the status / data of the counter, measurement document is created. The equipment task list contains the list of operation and sub-operations. The spare and consumables required for the completion of the maintenance operations can also be maintained

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 53: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 53 of 53

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

in the task list. Based on the release of maintenance order, the reservation for the stock-able spares and consumables are created in the system. For non-stock spares, the PR is created from the maintenance order. The equipment plans are then scheduled (periodically) using deadline monitoring for a target period of say one month. The scheduling creates Preventive Maintenance Orders (Order type – PM03) automatically for the period.

7.2

Notification for recording activities Activity Report (M3)

Fully system supported

On the due date, the required spares can be issued from the store. Based on the order created, a notification is also generated by the system. The purpose to create a notification is to record the activities done during the Preventive Maintenance. Also it can be the ready reference for the activities left for future Maintenance. If any operation requires External Services, then Steps as mentioned in 5.1 and 5.2 will also be used.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 54: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 54 of 54

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

7.3 Order Execution Fully system supported

During maintenance of the machine (outside SAP), spares required will be mentioned in the order. Saving the order will create a reservation for the stock-able spares. Then Order to be released and against the Order Number or reservation number, material will be issued by the store. For non-stock spares, Purchase Requisition is created from the order. Based on the release strategy it can be released for procurement and Purchase Order will be created by the MM. Upon receiving the material, it will be issued against the maintenance order.

N

7.4 Order Completion confirmation

Fully system supported

After completion of maintenance activities, the order needs to be confirmed. Order confirmation can be done partially or final. It is used to record how the work is progressing. For partial confirmation, order must not yet have been completed fully.

You use the remaining functions for the completion of an order, after the order has been completed fully and a final completion entered.

You enter time completion confirmations for operations and sub-

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 55: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 55 of 55

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

operations for maintenance and service orders to document the status of the processing for these operations. After that all the operations of the order needs to be confirmed. Extra stockable issued material can be returned to stores from the order.

7.5 View Costs Fully system supported

The Planned vs. actual costs can be viewed after all issues and service entry sheets are completed

N

7.6 Change / Complete Notification

Fully system supported

Notification will be closed after noting down all catalog & details of maintenance required to be recorded.

N

7.7 Technically & Business Completion

Fully system supported

After confirmation for the maintenance order, the order needs to be technically completed and settled to the appropriate cost centre based on settlement profile. When all the costs are settled and no further activities are pending against that order, business completion for the order is done.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 56: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 56 of 56

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

8.0 Refurbishment Order

Fully system supported

Refurbishment order is the special order, which are used for the refurbishment of repairable spares. In the refurbishment order, contract a work centre to restore faulty repairable spares to full working order at a certain date. The repairable spares scheduled in the order are brought from a uniform initial condition to a uniform end condition. To distinguish the condition of damage to repair for spares different valuation types are used.

N

8.1 Notification for Refurbishment (M4)

Fully system supported

Maintenance person will create a notification to intimate the workshop Department for the refurbishment in the component

N

8.2

Create Refurbishment Order for the damage spare Order Type (PM04)

Fully system supported

Create the Refurbishment order with order type PM04. The order is created for the damaged Spare Part Material. The valuation type of spares is maintained in the Accounting 1 view in the material master.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 57: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 57 of 57

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

Create appropriate operations with internal maintenance, consumables required for the Repair of the spare part. The valuation type present and future (after repair) is mentioned in the order. Release the order and save it.

8.3 Order Execution Fully system supported

During refurbishment of spare (outside SAP), consumables required will be issued against the reservation created in the order. Internal maintenance will be carried inside the plant. After that for external repair, MM will create subcontracting order for the spare. The receipt of the subcontracting order will result into the valuation type change from damage to repair and cost of repair will be loaded into the spare. For internal maintenance, the spare will be repaired using internal spares and consumables. The cost of such repair will be settled to the maintenance cost centre.

N

8.4 Order Completion Confirmation

Fully system supported

After completion of maintenance activities for the spare, all the operations of the order need to be confirmed. Based on the valuation type, the spare valuation is modified from the damage to

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 58: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 58 of 58

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

valuation type, the spare valuation is modified from the damage to repair and good receipt is made for the spare.

8.5 View Costs Fully system supported

The Planned vs. actual costs can be viewed after all issues and service entry sheets are completed.

N

8.6 Technically and Business Completion

Fully system supported

After confirmation for the maintenance order, the order needs to be technically completed and settled to the appropriate cost centre based on settlement profile. When all the costs are settled and no further activities are pending against that order, business completion for the order is done.

N

9.0 Safety Order Fully system supported

A Safety activity describes a notification meant for carrying out jobs related to safety requirements.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 59: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 59 of 59

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

9.1

Notification by the user / maintenance in-charge of the equipment (M6)

Fully system supported

User / maintenance in-charge creates a Notification for activities required for safety purpose for the equipment. The location and other necessary data get copied into the notification from the equipment master.

N

9.2 Create maintenance order from Notification

Fully system supported

After receipt / creation of the notification, the maintenance planner creates the Maintenance Order (Order Type- PM06) using the screen of notification in change mode. The other way is to create order directly, describing the operations, requirement of material for the development activities in the order and Release the order. If any operation requires External Services, then Steps as mentioned in 5.1 and 5.2 will also be used.

N

9.3 Order Execution Fully system supported

During maintenance of the machine (outside SAP), spares required will be mentioned in the order. Saving the order will create a reservation for the stock-able spares. Then Order to be released

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 60: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 60 of 60

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

reservation for the stock-able spares. Then Order to be released and against the Order Number or reservation number, material will be issued by the store. For non-stock spares, Purchase Requisition is created from the order. Based on the release strategy it can be released for procurement and Purchase Order will be created by the MM. Upon receiving the material, it will be issued against the maintenance order.

9.4 Order Completion Confirmation

Fully system supported

After completion of maintenance activities, the order needs to be confirmed. Order confirmation can be done partially or final. It is used to record how the work is progressing. For partial confirmation, order must not yet have been completed fully.

You use the remaining functions for the completion of an order, after the order has been completed fully and a final completion entered.

You enter time completion confirmations for operations and sub-operations for maintenance and service orders to document the status of the processing for these operations. After that all the operations of the order needs to be confirmed. Extra stockable

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 61: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 61 of 61

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

issued material can be returned to stores from the order.

9.5 View Costs Fully system supported

The Planned vs. actual costs can be viewed after all issues and service entry sheets are completed.

N

9.6 Change / Complete Notification

Fully system supported

Notification will be closed after noting down all catalog & details of maintenance required to be recorded.

N

9.7 Technically and Business Completion

Fully system supported

After confirmation for the development maintenance order, the order needs to be technically completed and settled to the appropriate cost centre based on settlement profile. When all the costs are settled and no further activities are pending against that order, business completion for the order is done.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 62: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 62 of 62

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

10.0

Improvement / Modification / Re-design / Development/CAPEX

Fully system supported

Improvements, Developments, Modifications or design changes are necessary part of maintenance to upkeep the equipment for higher productivity period, lower breakdown repair time etc. These design change / modifications costs will be separated from other costs of maintenance using a separate order type.

N

10.1

Notification by the user / maintenance in-charge of the equipment (M5)

Fully system supported

User / maintenance in-charge creates a Notification for required design change / modification activities required for the equipment mentioning the purpose and results expected. The location and other necessary data get copied into the notification from the equipment master.

N

10.2 Create maintenance order from Notification

Fully system supported

After receipt / creation of the notification, the maintenance planner creates the Maintenance Order (Order Type – PM05) using the screen of notification in change mode. The other way is to create order directly, describing the

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 63: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 63 of 63

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

operations, requirement of material for the design change / modification activities in the order and Release the order. If any operation requires External Services, then Steps as mentioned in 5.1 and 5.2 will also be used.

10.3 Order Execution Fully system supported

During maintenance of the machine (outside SAP), spares required will be mentioned in the order. Saving the order will create a reservation for the stock-able spares. Then Order to be released and against the Order Number or reservation number, material will be issued by the store. For non-stock spares, Purchase Requisition is created from the order. Based on the release strategy it can be released for procurement and Purchase Order will be created by the MM. Upon receiving the material, it will be issued against the maintenance order.

N

10.4 Order Completion Confirmation

Fully system supported

After completion of maintenance activities, the order needs to be confirmed. Order confirmation can be done partially or final. It is used to record how the work is progressing. For partial confirmation, order must not yet have been completed fully.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 64: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 64 of 64

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

You use the remaining functions for the completion of an order, after the order has been completed fully and a final completion entered.

You enter time completion confirmations for operations and sub-operations for maintenance and service orders to document the status of the processing for these operations. After that all the operations of the order needs to be confirmed. Extra stockable issued material can be returned to stores from the order.

10.5 View Costs Fully system supported

The Planned vs. actual costs can be viewed after all issues and service entry sheets are completed.

N

10.6 Change / Complete Notification

Fully system supported

Notification will be closed after noting down all catalog & details of maintenance required to be recorded.

N

10.7 Technically and Business Completion

Fully system supported

After confirmation for the development maintenance order, the order needs to be technically completed and settled to the appropriate cost object based on settlement profile. The cost of

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 65: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 65 of 65

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

appropriate cost object based on settlement profile. The cost of these types of orders can be settled to the fixed asset. When all the costs are settled and no further activities are pending against that order, business completion for the order is done.

11.0 Shut Down Maintenance

Fully system supported

During plant shut down, maintenance department get good opportunity to do some maintenance work to upkeep the equipment for higher productivity period, lower breakdown repair time etc. Shutdown activities can be planned and scheduled in advance. These shut down maintenance cost will be separated from other costs of maintenance using a separate order type. Shut Down Activities for the equipment are planned therefore it can be taken similar to preventive maintenance.

N

11.1 Create maintenance order

Fully system supported

As per the schedule, system will generate shutdown orders (PM07) for the equipments.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 66: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 66 of 66

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

The other way is to create order directly, describing the operations, requirement of material for the design change / modification activities in the order and Release the order. If any operation requires External Services, then Steps as mentioned in 5.1 and 5.2 will also be used.

11.2 Shut Down Notification (M7)

Fully system supported

System will creates a Notification for shutdown activities required for the equipment mentioning the purpose and results expected. The location and other necessary data get copied into the notification from the equipment master.

N

11.3 Order Execution Fully system supported

During maintenance of the machine (outside SAP), spares required will be mentioned in the order. Saving the order will create a reservation for the stock-able spares. Then Order to be released and against the Order Number or reservation number, material will be issued by the store. For non-stock spares, Purchase Requisition is created from the order. Based on the release strategy it can be released for procurement and Purchase Order will be created by

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 67: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 67 of 67

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

the MM. Upon receiving the material, it will be issued against the maintenance order.

11.4 Order Completion Confirmation

Fully system supported

After completion of maintenance activities, the order needs to be confirmed. Order confirmation can be done partially or final. It is used to record how the work is progressing. For partial confirmation, order must not yet have been completed fully.

You use the remaining functions for the completion of an order, after the order has been completed fully and a final completion entered.

You enter time completion confirmations for operations and sub-operations for maintenance and service orders to document the status of the processing for these operations. After that all the operations of the order needs to be confirmed. Extra stockable issued material can be returned to stores from the order.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 68: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 68 of 68

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

11.5 View Costs Fully system supported

The Planned vs. actual costs can be viewed after all issues and service entry sheets are completed

N

11.6 Change / Complete Notification

Fully system supported

Notification will be closed after noting down all catalog & details of maintenance required to be recorded.

N

11.7 Technically and Business Completion

Fully system supported

After confirmation for the development maintenance order, the order needs to be technically completed and settled to the appropriate cost centre based on settlement profile. When all the costs are settled and no further activities are pending against that order, business completion for the order is done.

N

12.0 Workshop Orders Fully system supported

The Workshop orders will be used for repair of spares/parts in the Central Workshop. The expenditure of such maintenance is recorded through Workshop Notification only.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 69: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 69 of 69

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

12.1

Notification by the user / maintenance in-charge for the functional location (M9)

Fully system supported

User / maintenance in-charge creates a Notification for required general maintenance activities required for the functional location mentioning the purpose. The location and other necessary data get copied into the notification from the functional location master.

N

12.2 Create maintenance order from Notification (PM09)

Fully system supported

After receipt / creation of the notification, the maintenance planner creates the Maintenance Order using the screen of notification in change mode. The other way is to create order directly, describing the operations, requirement of material for the general maintenance activities in the order and Release the order. If any operation requires External Services, then Steps as mentioned in 5.1 and 5.2 will also be used.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 70: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 70 of 70

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

12.3 Order Execution Fully system supported

During maintenance of the machine (outside SAP), spares required will be mentioned in the order. Saving the order will create a reservation for the stock-able spares. Then Order to be released and against the Order Number or reservation number, material will be issued by the store. For non-stock spares, Purchase Requisition is created from the order. Based on the release strategy it can be released for procurement and Purchase Order will be created by the MM. Upon receiving the material, it will be issued against the maintenance order.

N

12.4 Order Completion Confirmation

Fully system supported

After completion of maintenance activities, the order needs to be confirmed. Order confirmation can be done partially or final. It is used to record how the work is progressing. For partial confirmation, order must not yet have been completed fully.

You use the remaining functions for the completion of an order,

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 71: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 71 of 71

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

after the order has been completed fully and a final completion entered.

You enter time completion confirmations for operations and sub-operations for maintenance and service orders to document the status of the processing for these operations. After that all the operations of the order needs to be confirmed. Extra stockable issued material can be returned to stores from the order.

12.5 View Costs Fully system supported

The Planned vs. actual costs can be viewed after all issues and service entry sheets are completed.

N

12.6 Change / Complete Notification

Fully system supported

Notification will be closed after noting down all catalog & details of maintenance required to be recorded.

N

12.7 Technically and Business Completion

Fully system supported

After confirmation for the general maintenance order, the order needs to be technically completed and settled to the appropriate cost centre based on settlement profile. When all the costs are settled and no further activities are pending

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 72: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 72 of 72

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

against that order, business completion for the order is done.

13.0 Annual Maintenance Orders

Fully system supported

The Annual Maintenance Orders are special type of external services wherein contract for maintenance for equipment or functional location is given to external agency. Here the total responsibility to do preventive and breakdown maintenance shifts from the Plant Maintenance to External Body. Such type of maintenance and confirmation to the services for payment is done using the Service Purchase Order and Service entry sheet. To track the cost of maintenance for any equipment, PM10 Annual Maintenance Contract will be used.

N

13.1 Create Maintenance Order (Type PM10)

Fully system supported

Create a maintenance order for the equipment or a functional location using order type PM10. In the operation screen, mention the control key as PM03 as

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 73: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 73 of 73

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

required in External Services. Using this key, the system requires the Service No. / Description, Quantity and price of the service. Based on the MM requirement for Purchase Requisition, certain fields are required to enter. On saving the order, the system creates the PR number for the external services. This PR number is used to create the Service PO by MM.

13.2 Confirming the External Services

Fully system supported

For confirmation of external services, Service Entry Sheet is used. The service entry sheet is created with reference to the Service PO. In the service entry sheet, the number or percentage of services is confirmed. Accordingly the data is updated in Controlling and Financial Accounting for releasing the payment for the external services. In AMC services, the payment release (service entry sheet confirmation) can be carried in parts say quarterly release for payment.

N

13.3 Order Completion Confirmation

Fully system supported

Only after completion of the AMC services (exhausting the whole service order for AMC), the operation in the order is final confirmed and case the Final Confirmation, No remaining work,

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 74: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 74 of 74

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

confirmed and case the Final Confirmation, No remaining work, clear open reservation ticks are made. In other case, order can be confirmed partially. In this case the Final Confirmation, No remaining work, clear open reservation tick is not made. The confirmation text can be written for comments.

13.4 Technically and Business Completion

Fully system supported

After final confirmation for the AMC order, the order needs to be technically completed and settled to the appropriate cost centre based on settlement profile. When all the costs are settled and no further activities are pending against that order, business completion for the order is done.

N

14.0 Calibration Orders Fully system supported

Special order that tests whether a specified piece of test equipment fulfills the performance criteria defined. For calibration, we need to define Characteristics and assigned it to the task list.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 75: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 75 of 75

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

When the order is released, the system generates an inspection lot. The inspection lot appears in the work list for results recording in the Quality Management (QM) application component.

You create a creation order if you want to check the accuracy of a piece of test equipment or a technical object.

• If you want to do this regularly (= planned), you use a maintenance plan, which regularly generates calibration orders.

If you do not want to do this regularly (= spontaneously), you create a calibration order directly. Prerequisite- The equipment, for which you want to create a calibration order, must be created as a piece of test equipment. An inspection type for Plant Maintenance must be defined. This inspection type must be created for origin 14 (Plant Maintenance).

PDF created with pdfFactory trial version www.pdffactory.com

Page 76: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 76 of 76

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

14.1 Create Calibration order

Fully system supported

The maintenance planner creates the Maintenance Order (Order Type – PM08) manually or the system will generate it if it’s planned.

N

14.2 Order Release Fully system supported

After creating the order, for execution purpose the planner need to release the order.

N

14.3 Inspection Lot Generation

Fully system supported

When the order is released, the system generates an inspection lot. The inspection lot appears in the work list for the results recording in Quality Management.

N

14.4 Results Recording Fully system supported

The results recording and usage decision for the test equipment are made using the functions in Quality Management. As soon as you have made the usage decision, the system automatically executes follow-up actions, for example, status change of the test equipment ("Ready for use" -> "Not ready for

N Will be done by QM

PDF created with pdfFactory trial version www.pdffactory.com

Page 77: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 77 of 77

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

use") or updating measurement readings.

14.5 Order Completion Confirmation

Fully system supported

After that all the operations of the order needs to be confirmed. Extra stock-able issued material can be returned back from the order.

N

14.6 Technically and Business Completion

Fully system supported

After confirmation for the general maintenance order, the order needs to be technically completed and settled to the appropriate cost centre based on settlement profile. When all the costs are settled and no further activities are pending against that order, business completion for the order is done.

N

15.0 Spare Parts Planning

Fully system supported

In SAP, all the spares of equipment are formally structured as maintenance bill of material (BOM). The list contains the component number along with their quantity and unit of measure. The components mentioned in BOM can be stock-able or non

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 78: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 78 of 78

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

stock-able. This becomes easy reference for the Spare Part Planning for carrying out maintenance activities.

15.1 Order Release Fully system supported

During the creation of maintenance order, spares and consumables required for the maintenance of the equipment are mentioned in the order. For all stock-able materials, reservation is created in the system automatically. The reservation is available for the Store so that material can be issued against the reservation. For all non stock-able materials, Purchase Requisition (PR) is created automatically following the release of the order and saving the order. After release of the PR based on release strategy, the material department creates the Purchase Order with reference to the PR and arranges the material for maintenance.

N

15.2 Order Confirmation

Fully system supported

There are many instances that the maintenance is left with the stock-able spares unconsumed. Such spares can be returned to store for future maintenance activities at the time of order completion confirmation.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 79: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 79 of 79

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

16.0 Condition Monitoring

System supported

In SAP, condition monitoring can be done through measuring points. For that we need to create and assign measuring points and then on regular basis we need to take readings at those measuring points and post measuring document. Once we capture all the reading then we can get the graph or take corrective action based on that.

N

16.1 Create Measuring Points for equipment

System supported

A physical or logical place at which a condition is described. Example can be Temperature inside a reactor, Speed of revolution of a wind wheel, the status is described using measurement readings, the operating duration of Diesel Generator etc. Measuring points are stored in the SAP System as master data for the Equipment. It can work as a counter to record the duration, based on manufacturer guidelines, the Preventive Maintenance Orders can be generated for the same. Counter are defined as Measuring Point in SAP and Counter readings are taken at counters at particular intervals and in

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 80: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 80 of 80

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No. Process Name Mode Process Description/remarks Gap

(Y/N) Remarks

particular measurement units. For example, counter readings for kilometers driven, operating hours or electricity used.

16.2 Create Measuring Document

System supported

The measurement document is the result of a measurement or counter reading being entered in the system.

N

16.3

Take necessary action (Maintenance Request)

System supported

If the reading is not in the range of accepted value then you need to take a corrective action by creating maintenance request and do the maintenance work.

N

PDF created with pdfFactory trial version www.pdffactory.com

Page 81: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 81 of 81

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Special Points:

1. All maintenance order costs will be settled at the cost centre level but development orders can be settled at fixed asset. 2. With MM discussion, there will have two valuation types for a spare: With value and zero value. The cost of damage spare will be taken as

zero and cost of repair spare will be booked at the maintenance cost center. The maintenance cost of spare will be settled to the maintenance order and will not be loaded to the spare.

3. Name of person creating the maintenance notification and notification attended will be given in the two separate fields in (notification ‘reported By’ and ‘Technically Inspected By’) notification.

4. Permits will be used in SAP but at the time of release system will only give warning message if permit is not issued but error at the time of order completion.

5. Separate storage locations for maintenance (in workshop) can be defined for transferring low value components from stores. 6. Authorization for order creation & execution will be at shift engineer level but the order release will be at planning head (HOD) level. 7. For insurance claim, we can create a general notification type for capturing the information (if required).

PDF created with pdfFactory trial version www.pdffactory.com

Page 82: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 82 of 82

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Integration with Other Modules: MM

1. Valuation Classes will be defined for Electrical Spares/Mechanical Spares, Instrumentation Spares, Civil components and General Items (e.g. Engg. Consumables). Also valuation classes would be defined for Electrical Service, Mechanical Service, Civil Repairs and Instrumentation service.

2. MRP views to be maintained for critical spares (Insurance) and consumables.

3. Service Master to be maintained

FI/CO

1. Product-wise / department-wise cost center will be created, e.g., Hydrate Mechanical, Hydrate Electrical, Hydrate Instrumentation, Hydrate Civil; Alumina Mechanical, Alumina Electrical, Alumina Instrumentation, Alumina Civil; Utilities; Non-Plant etc.

2. G/L accounts will be created for all the different valuation classes mentioned above.

3. Cost-center-wise Budget allocation will be done.

PDF created with pdfFactory trial version www.pdffactory.com

Page 83: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 83 of 83

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

List of Reports for Analysis

1. Detailed Breakdown Analysis-Equipment-wise/object part wise/Problem-wise/cause wise 2. MTTR and MTBF analysis for Equipments 3. Order type-wise cost analysis 4. Planner-group wise cost analysis 5. Equipment/Functional Location/Location/Plant wise cost Analysis 6. Report on usage of spares for Equipments 7. Report on service and Spares costs – Equipment-wise 8. Planned vs. Actual cost comparisons 9. Preventive Maintenance Schedule 10. Report on Preventive Maintenance Activities 11. Equipment History 12. Report on Measuring points/Measurement Documents 13. Report on Equipments having specific characteristics

SPECIAL REQUIREMENT (ABAP) Ø For condition monitoring, requirement has come to us that the upload program for entering the DCS values to the SAP system (from xls) to

be developed. Ø A report containing data of Consumption, Unrestricted stock, QI stock, Open PR quantities and open PO quantities for critical spares needs

to be developed for the purpose of Spares Planning.

PDF created with pdfFactory trial version www.pdffactory.com

Page 84: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 84 of 84

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No.

Purpose Description of Report Remarks

Few Transaction for Reports Transaction

Structural Display-Equipment IH03 1 Technical Objects Structural Display- Functional Location IH01 Display notifications IW29 (Multi-Level) Notification List IW30 Display Tasks IW67 Display Notification Items IW69

2 Maintenance notification

Display activities IW65 Material Where-used List IW13 Display Orders IW39 Display Orders (Multi-Level) IW40 Display Operations IW49 Display Order and Operation List IW49N Display Component List IW3L

32 Maintenance order

Material Availability IWBK 4 Completion

confirmation Confirmation List IW47

5 Measuring Document Display Measurement Documents IK17 6 Maintenance Item List display IP18

PDF created with pdfFactory trial version www.pdffactory.com

Page 85: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 85 of 85

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Sl. No.

Purpose Description of Report Remarks

Maintenance Plan List IP16 Scheduling overview list form IP24 MaintSchedule Date Monitoring IP30

Maintenance planning

Scheduling overview IP19,IP24 PMIS: Object Class Analysis MCI1 PMIS: Manufacturer Analysis MCI2 PMIS: Location Analysis MCI3 PMIS: Planner Group Analysis MCI4 PMIS: Object Damage Analysis MCI5 PMIS: Obj.Statistic.Analysis MCI6 PMIS: Breakdown Analysis MCI7 PMIS: Cost Evaluation MCI8 MTTR/MTBR Equipment MCJB

7 Evaluation of information system

MTTR/MTBR Functional Location MCJC

PDF created with pdfFactory trial version www.pdffactory.com

Page 86: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 86 of 86

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

SECTION IV

ANNEXURE – PROCESS FLOW CHARTS

PDF created with pdfFactory trial version www.pdffactory.com

Page 87: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 87 of 87

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Page 88: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 88 of 88

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Page 89: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 89 of 89

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Page 90: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 90 of 90

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Page 91: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 91 of 91

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Page 92: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 92 of 92

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Page 93: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 93 of 93

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Page 94: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 94 of 94

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Page 95: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 95 of 95

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Page 96: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 96 of 96

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Page 97: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 97 of 97

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Page 98: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 98 of 98

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Page 99: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 99 of 99

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

Spare identified for refurbishm

ent

PRO

CESS

FOR

HA

NDLIN

G R

EFURB

ISHM

ENT A

CTIVITIES

Carry out

Refurbishm

ent A

ctivity O

utside SAP

Yes

No

Is material or E

xternal Service required to carry

out the job?

Create Refurbishm

ent O

rder (Work O

rder

Carry out

Refurbishm

ent activity( O

utside SA

P

Is the spare working

satisfactorily?

Yes

No

Close the job Allocate com

ponents services to O

rder

Is the spare rectified ?

Yes

No

Create Service E

ntry sheet and accept

Technically complete the

order Settle the order

Issue Components

Purchase O

rder Keep the spare in stock

for future use

PDF created with pdfFactory trial version www.pdffactory.com

Page 100: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 100 of 100

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com

Page 101: Sap Plant Maintenance Pm Business Blueprint Bbp

Vedanta Alumina Limited Plant Maintenance Page 101 of 101

SAP ECC 5.0 IMPLEMENTATION Business Process Blueprint Version No - 1.3

CONFIDENTIAL

PDF created with pdfFactory trial version www.pdffactory.com