    SAFETY AUDIT

    Date _________________ Owners Representative____________________________________ Auditor_________________________________

    Contractor ______________________________________________ Project____________________________________________________

    This is intended only as a reminder. Look for other unsafe acts and conditions, and then report them so that corrective action can be taken. Note

    accurately whether unsafe acts or conditions that have caused accidents have been corrected. Note also whether potential accident causes, markedon previous inspection have been corrected. Follow-up where required. Note unsafe act and action taken in comment section on back of sheet.

    Rating Scale 1 2 3 4 5

    Unsatisfactory Satisfactory Excellent N/A (Not Applicable)

    1) Safety Plan

    Is Safety Plan on File 1 2 3 45

    Are key elements of plan posted 1 2 3 45

    2) Safety Orientation & Training

    Awareness of Safety Plan 1 2 3 45

    Awareness of Plant Safety Rules 1 2 3 45

    Awareness of Emergency Procedures 1 2 3 4

    5 Pre-task orientation 1 2 3 4 5

    3) Substance Abuse Program

    Is random testing being done 1 2 3 45

    Documentation 1 2 3 4 5

    4) Safety Incentives

    Awareness of incentive program 1 2 3 45

    Incentive program effectiveness 1 2 3 45

    5) Incident investigation/ Case Management

    Case follow-up procedures 1 2 3 45

    OSHA Forms posted 1 2 3 45

    6) Lockout/Tagouts

    Consistent and proper use 1 2 3 45

    One lock per person 1 2 3 45

    7) Permit Required Confined Space

    Atmospheric Testing 1 2 3 45

    Permit 1 2 3 4 5

    Ventilation 1 2 3 45

    Low Volt 1 2 3 4 5

    8) Fall Protection

    Harnesses & lanyards 1 2 3 45

    Ladders in good condition & tied off 1 2 3 45

    Scaffolds built to OSHA specifications 1 2 3 5

    9) Fire Protection/Hot Work

    Hot work permit/proper use 1 2 3 5

    Proper storage of flammable material 12 3 4 5

    Gas bottles-properly secured, stored 1 2 3 5

    10) Personal Protective Equipment

    Proper eye protection 1 2 3 5

    Hard hats 1 2 3 4 5

    Gloves 1 2 3 4 5

    Foot protection 1 2 3 4 5

    Protective clothing 1 2 3 4 5

    Respiratory equipment 1 2 3 5

    11) Electrical

    Ground fault circuit interrupters 1 2 3 5

    Labels/access @ circuit breakers and disconnects 12 3 4 5

    Condition of wires, cords and receptacles 1 2 3

    5

    Temporary wire routing-cords protected or elevated 12 3 4 5

    Potable equipment tested and tagged properly 12 3 4 5

    12) Machinery

    Point of operation guards 1 2 3 5

    Maintenance and oil leakage 1 2 3 4 5

    Cleanliness 1 2 3 5

    Positioning 1 2 3 5

    13) Pressure Equipment

    Steam equipment 1 2 3 4 5

    Air receivers and compressors 1 2 3 5

    14) Chemicals

    MSDS available 1 2 3 4 5

    Container labeling 1 2 3 4 5

    Storage and use 1 2 3 4 5

    cc: Safety Office, Plant Engineer, Manager of Maintenance

    123933333.d

    1

  • 7/30/2019 s3 Safety Audit

    2/2

    Emergency shower/eyewash available 12 3 4 5

    15) Tools

    Power tools, wiring/hoses 1 2 3 45

    Hand tools condition 1 2 3 45

    Use and storage of tools 1 2 3 4 5

    16) Unsafe Practices

    Manlift/elevator usage 1 2 3 45

    Excessive speed of vehicles 1 2 3 4 5

    Improper lifting 1 2 3 4 5

    Smoking in restricted areas 1 2 3 4 5

    Horseplay 1 2 3 4 5

    Removing machine or other guards 1 2 3 45

    Work on unguarded moving machinery 12 3 4 5

    17) Material Handling Equipment

    Power trucks proper use 1 2 3 45

    Cranes and hoists 1 2 3 4 5

    Hand truck 1 2 3 45

    Cables, ropes, chains and slings 1 2 3 45

    18) Housekeeping

    Walkways free of debris and storage 1 2 3 5

    Work area free of slip/trip hazards 1 2 3 5

    Stairs free of slipping/tripping 1 2 3 5

    Clear access to all fire equipment 1 2 3 5

    NO trash/or metal scrap scattered about 1 2 3 5

    Equipment free of excessive oil, grease, grime1 2 3 5

    Signs clean, visible, in good condition 1 2 3 5

    Spare parts stored in proper area 1 2 3 5

    Column bases free of hazard storage 1 2 3 5

    Cables, ropes hoses & chains properly stored 1 2 3 5

    Wash rooms & lockers 1 2 3 5

    19) Miscellaneous

    Safety shower/eye wash work properly 1 2 3 5

    Lighting 1 2 3 4 5

    cc: Safety Office, Plant Engineer, Manager of Maintenance