RISK ASSES-82- Installation of Condenser Unit 2

8
Location: Terga Date o Assessor(s): FRIDI.ALI System Probabili ty & Frequenc y Definite 5 5 10 15 20 High 4 4 8 12 16 Moderate 3 3 6 9 12 Low 2 2 4 6 8 Negligible 1 1 2 3 4 1 2 3 4 Minor Serious Major Catastrophic Severity Key to Priorities Medium Priority (5 days) High Priority (2-3 days) Immediate INTRODUCTION The table below provides a simplified representation of the Management) to be undertaken by OCIA and all Subcontractors IDENTIFICATION - Pre planning, Method statement , Job safety analysis. ASSESSM Mitigation Identify activities , Identify hazards Assess Im Establish M RISK ASSESSMENT FORM of Assessment: 08 -05-2010 Assessment No: m/Activity: Installation of Condenser Unit 2 methodology used and the processes involved in this Hazard Ident in order to initiate, act on, review and effectively manage proje ct-relate MENT Impact, Risk factor, n measure, Residual risk IMPLEMENTATION & COMMUNICATION R mpacts, Analyze Risk , Mitigation Measures. Communication & Training A Page 2 of 9 82 tification & Risk Analysis Procedure (Risk ed risks throughout the Construction Phase. REVIEW & UP DATE Audit, Inspection & Up dating of Log.

Transcript of RISK ASSES-82- Installation of Condenser Unit 2

  • Location: Terga Date of Assessment:

    Assessor(s): FRIDI.ALI System/Activity:

    Prob

    abili

    ty&

    Freq

    uenc

    y

    Definite 5 5 10 15 20High 4 4 8 12 16

    Moderate 3 3 6 9 12Low 2 2 4 6 8

    Negligible 1 1 2 3 41 2 3 4

    Minor Serious Major Catastrophic

    Severity

    Key to PrioritiesMedium Priority (5

    days)High Priority (2-3 days) Immediate

    INTRODUCTION

    The table below provides a simplified representation of the methodology used and the processesManagement) to be undertaken by OCIA and all Subcontractors in order to initiate, act on, review and effectively manage proje

    IDENTIFICATION - Pre planning, Methodstatement , Job safety analysis.

    ASSESSMENTMitigation measure, Residual risk

    Identify activities , Identify hazards Assess Impacts, Analyze Risk ,Establish Mitigation Measures.

    RISK ASSESSMENT FORM

    Date of Assessment: 08-05-2010

    Assessment No:

    System/Activity: Installation of Condenser Unit 2

    The table below provides a simplified representation of the methodology used and the processes involved in this Hazard Identification &Management) to be undertaken by OCIA and all Subcontractors in order to initiate, act on, review and effectively manage proje ct-related risks

    ASSESSMENT Impact, Risk factor,Mitigation measure, Residual risk

    IMPLEMENTATION &COMMUNICATION

    REVIEW & UP DATE

    Assess Impacts, Analyze Risk ,Establish Mitigation Measures.

    Communication & Training Audit, Inspection & Up dating of Log.

    Page 2 of 9

    82

    involved in this Hazard Identification & Risk Analysis Procedure (Riskrelated risks throughout the Construction Phase.

    REVIEW & UP DATE

    Audit, Inspection & Up dating of Log.

  • Tasks Hazards Identified (includethe exposed groups)

    Probability1 - 5

    Transfer ofequipment

    Transfer device collidewith other things;

    Oil leakage

    4

    Locate the crane Hitting injury 4

    Transport Traffic risk

    Collision with person

    Collision device

    3

    RISK ASSESSMENT FORM

    Probability Severity1 - 4

    Risk1 - 20

    Control Measures to beImplemented

    Probability1 - 5

    3 12 Chose a qualified driver beforework

    Check the calibration of alltools

    Make sure the transport devicein good condition

    2

    3 12 Solid the ground

    Reinforce the pads beneath theoutriggers

    Check the around circumstancebefore working

    2

    3 9 The trucks must respect:

    The limited speed in the site

    The circulation signs

    The circulation plan (updated)

    2

    Page 3 of 9

    Probability Severity1 - 4

    Risk1 - 20

    ResidualRisk

    DateAction

    Completed

    1 2

    1 2

    3 6

  • Tasks Hazards Identified (includethe exposed groups)

    Probability1 - 5

    Movement oftraffic

    Slip/trip/all3

    Lifting Fall from height andhurt workers

    Component fall down

    Component collidewith other thingssurrounded

    Collision with person

    Falling materials

    Poor visibility for thedriver

    Crane tilt

    4

    RISK ASSESSMENT FORM

    Probability Severity1 - 4

    Risk1 - 20

    Control Measures to beImplemented

    Probability1 - 5

    3 9 All hose/ropes/cables in use

    shall be secured to the side ofwalkways and handrails

    All unnecessary materials andequipment to be immediatelyremoved from site

    All exits and walkways to bekept clear for use of personnel

    High standard of housekeepingto be maintained at all times

    2

    4 16 Lifting crane, wires should be

    regularly calibrated, safeworking loads are announcedmax speed at site is respectedfor all vehicle

    It is not allowed to work underloads

    Handling by qualified riggersworn the related PPE and undersupervision

    Qualified crane operator andqualified rigger to operatelifting work

    Crane in calibrated period

    Barricade the lifting area

    2

    Page 4 of 9

    Probability Severity1 - 4

    Risk1 - 20

    ResidualRisk

    DateAction

    Completed2 4

    3 6

  • Tasks Hazards Identified (includethe exposed groups)

    Probability1 - 5

    Lifting

    RISK ASSESSMENT FORM

    Probability Severity1 - 4

    Risk1 - 20

    Control Measures to beImplemented

    Probability1 - 5

    Proper lifting tools

    Make sure lifting wok operatedin good weather

    Mark the area of operations ofthe crane

    Officer commanding the shipmaneuver through regulatoryactions to avoid accidents

    Control of the safety catch hookthe slings

    Ensure the crane on hisdashboard that the load weightdoes not exceed the maximumallowed

    Ban the person be under asuspended load

    Defining the radius of the rotarycrane

    Prohibit the movement ofpeople around the handling

    Stop the lifting operation instrong winds exceed the 50km/h and heavy rain

    Not lifting at night

    Page 5 of 9

    Probability Severity1 - 4

    Risk1 - 20

    ResidualRisk

    DateAction

    Completed

  • Tasks Hazards Identified (includethe exposed groups)

    Probability1 - 5

    Erection anddismantling ofscaffolding

    Personnel falling fromheight

    4

    RISK ASSESSMENT FORM

    Probability Severity1 - 4

    Risk1 - 20

    Control Measures to beImplemented

    Probability1 - 5

    4 16 Safeguards needed to controlrisk to acceptable level

    No erection/dismantling ofscaffolding shall be carried outduring the hours of darkness

    Over the site scaffoldingoperations shall cease in case ofhigh winds. Wind speedmaximum 20 knots

    Safety belt/harness shall beworn by scaffolders workingover the side

    All gaps in scaffolding structureshall be highlighted by tigertape

    Gaps in scaffold boards shall bewell secured

    Scaffold boards shall be wellsecured

    Use of scafftag

    Removal of garnet from boardsto avoid stress on scaffolding

    2

    Page 6 of 9

    Probability Severity1 - 4

    Risk1 - 20

    ResidualRisk

    DateAction

    Completed3 6

  • Tasks Hazards Identified (includethe exposed groups)

    Probability1 - 5

    Work at height

    (Scaffolding and

    Man basket)

    falls from height

    falling objects

    4

    Use tools Hand injuries crushed fingers smooth head against the

    frame

    3

    Welding Burn Sting Glare Fumes Fire

    4

    RISK ASSESSMENT FORM

    Probability Severity1 - 4

    Risk1 - 20

    Control Measures to beImplemented

    Probability1 - 5

    3 12 the scaffolding should be basedon graded soil with goodfoundation

    protect a guard with a height of1.15 m

    Protection of Persons withsafety harnesses

    protect with an end-board 10 to15 cm high

    prohibit work at height if theweather affected the safety ofpersons

    2

    3 9 ensure protection adequate PPE(gloves, helmet, goggles,harness

    2

    4 16 Port PPE: Face shield orgoggles, gloves, aprons andleggings

    Respiratory protection

    Aeration of the workspace

    Dilution of gas and smoke withventilation

    Cleanliness of welding at risk ofabrasive particles

    2

    Page 7 of 9

    Probability Severity1 - 4

    Risk1 - 20

    ResidualRisk

    DateAction

    Completed2 4

    2 6

    3 6

  • Tasks Hazards Identified (includethe exposed groups)

    Probability1 - 5

    Electricity Electrocution

    3

    Fire Explosion Abrasive particles

    3

    RISK ASSESSMENT FORM

    Probability Severity1 - 4

    Risk1 - 20

    Control Measures to beImplemented

    Probability1 - 5

    4 12 Protect electrical equipment

    from ingress of water

    Identify equipment risk

    Warning notices

    Verification of electric cablesbefore the start of work by anelectrician

    2

    3 9 Check the cleanness of the

    workplace

    Site emergency plan to befollowed in event fire orexplosion.

    All personnel to be inductedand aware of emergencyprocedures.

    Installation of fireextinguishers visible andaccessible

    No smoking or naked lights

    2

    Page 8 of 9

    Probability Severity1 - 4

    Risk1 - 20

    ResidualRisk

    DateAction

    Completed3 6

    3 6

  • Tasks Hazards Identified (includethe exposed groups)

    Probability1 - 5

    Waste control Waste of cut

    33

    Environmental Pollution the air:

    Exhaust gas, The dust

    Leaking oil or dieselmachines on soil

    3

    Assessor Print :

    RISK ASSESSMENT FORM

    Probability Severity1 - 4

    Risk1 - 20

    Control Measures to beImplemented

    Probability1 - 5

    4 12 Waste material recycle bin

    will set up and clear upregularly

    To finish the work site clean

    2

    3 9 Checking the condition of

    equipments before beginningthe work

    ventilation Workstation

    2

    Sign: Date:

    Page 9 of 9

    Probability Severity1 - 4

    Risk1 - 20

    ResidualRisk

    DateAction

    Completed3 6

    2 4