![Page 1: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/1.jpg)
1
M.V. Raghu,,
Retd. Controller, KPTCL / CESC
Mysore
Welcome to a discussion on
![Page 2: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/2.jpg)
2
What is Price Variation?
As per the terms of the contract, amounts
payable / recoverable from the contractor /
vendor consequent to fluctuation in the WPI
(Wholesale Price Index) (inflation / deflation) of
the raw materials used in manufacture of
materials supplied against work award /
purchase order.
![Page 3: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/3.jpg)
3
When price variation is applicable?
Projects costing Rs.100 Lakhs and above & the period of completion is 6 months and above. Order No. KPTCL / B37 / 6426 / 2005-06 dt. 05-10-2005.
All projects costing Rs.50 Lakhs and above & the period of completion is 6 months and above. Order No. KPTCL / CS / B37 / 5966 / 2006-07 dt. 05-03-2009.
As per terms and conditions of the contract the rates quoted are not on “FIRM” basis.
Circular
Circular
![Page 4: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/4.jpg)
4
Documents required for calculation of PV
DWA (Detailed Work Award) with special reference to
Schedule 2 (2 of 2) for taxes and duties, Schedule 21
for materials sourced out side the State of Karnataka.
(Scanned copy)
IEEMA (Indian Electrical and Electronics
Manufacturers Association) / CACMAI (Cable and
Conductor Manufacturers Association of India)
circulars issued from time to time.
IEEMA / CACMAI Price Indices applicable to the
case.
Circular
![Page 5: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/5.jpg)
5
Documents required for calculation of PV (Contd.)
PERT / Activity Chart.
Date of delivery of materials / Date of materials ready for delivery / Contractual Deliver Date / Inspection offered date (with documents to prove / substantiate the claim).
Price Variation Bill.
PV Bill must have been assigned with B.R. No. and Date
Details of the bill should have been uploaded in KPTCL Bill Tracking System.
![Page 6: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/6.jpg)
6
Calculation of PV
Arrive at Ex-works price from the quoted price (Excluding Taxes and Duties) (Refer schedule 2 (2 of 2) for percentage of taxes and duties quoted by the firm)
Base date to be considered is, Techno Commercial Bid Opening Date.
Contractual Delivery Date as per PERT Chart (Material Wise)
Inspection Offered Date (Material Wise) (Readiness of the Material)
Refer Schedule 21 for confirming whether materials are actually sourced from outside the state or not for assessing the taxes.
Circular
![Page 7: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/7.jpg)
7
Calculation of PV (Contd.)
Inspection call letter date or Contractual date of delivery which ever is earlier is to be considered as per IEEMA circulars in following cases:
– Materials supplied within the contractual delivery date.
– Materials supplied beyond the contractual period but materials are ready for inspection before contractual delivery date.
– Quantity as per DWA and the actual quantity supplied which ever is less.
![Page 8: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/8.jpg)
8
Calculation of PV (Contd.)
In the following cases PV is to be admitted in
accordance with circulars issued from
Corporate Office from time to time.
(Circular)
– Materials supplied beyond contractual deliver date
and ready for inspection after contractual delivery
date with PV on the lower side.
– Materials supplied beyond contractual deliver date
and ready for inspection after contractual delivery
date with PV on the higher side.
![Page 9: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/9.jpg)
9
Calculation of PV (Contd.)
Whether PV is admissible for Additional Quantity / Revised Quantity / Non-DWA Quantity?
Answer is “YES” as per Circular No. KPTCL / B8 / 2344 / 09-10(9) dt. 15-11-2010. (Circular)
Dates to be considered for Additional / Revised Qty. of DWA materials:
(A) For Supply Portion
• Base Date will be Techno Commercial bid opening date
• Contractual Delivery Date will be earlier of the following:
Date of inspection call letter
Date of Dispatch Instructions given
Actual Date of Supply
![Page 10: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/10.jpg)
10
Calculation of PV (Contd.)
(B) For Erection / Civil Portion
• Base Date will be Techno Commercial bid opening date
• Contractual Completion Date will be the date indicated in the letter of Chief Engineer concerned
Note:
oDWA rates are available / similar materials are supplied as per DWA.
oCertificate of necessity / justification by the Zonal CEE / SEE / EEE for admitting PV is required subject to approval of Work-slip / Variation by Competent Authority.
![Page 11: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/11.jpg)
11
Calculation of PV (Contd.)
For Non-DWA materials:
(A) For Supply Portion: • Date on which Turnkey agency has been intimated by KPTCL or
actual date of supply whichever is earlier is treated as “Base Date”
• “Contractual Delivery Date” will be the actual date of supply.
(B) Erection / Civil Portion • Date on which Turnkey agency has been intimated by KPTCL /
approval of drawing / work slip / variation statement or actual completion of work which ever is earlier.
• “The Contractual Completion Date” will be the date intimated by the KPTCL to complete the work to Turnkey Agency.
![Page 12: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/12.jpg)
12
CONTROL CHART
Sl.
No.
Particulars
1 Name of the work / Project
2 Description of Price Variation Bill (Supply,
Erection or Civil)
3 Name of the Material
4 Base Date as per DWA (Techno Commercial
Bid Opening Date)
5 Price Bid Opening Date
6 Date of LOI
![Page 13: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/13.jpg)
13
CONTROL CHART (Contd.)
Sl. No. Particulars
7 Date of Contract Agreement
8 Project Completion Date
9 Contractual Delivery Date as per PERT Chart
(Material Wise)
10 Inspection Offered Date (Material Wise)
(Readiness of the Material)
11 Schedule 2 (2 of 2)
12 Schedule 21 - Material sourced from outside
Karnataka.
13 IEEMA circular to be used
![Page 14: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/14.jpg)
14
Calculation of Ex-Works price when quoted price is inclusive of
Taxes and Duties (10.36 ED;5.5% VAT) (Tax Table)
Ex-Works = Quoted Price to be arrived (Excluding Taxes and Duties)
Excise Duty = 10.36% on Ex-Works
VAT = (Ex-Works + Excise Duty) 5.5%
= (Ex-works+0.1036Ex)0.055
Amount = Ex+0.1036Ex+(Ex+0.1036Ex)0.055
= Ex+0.1036Ex+0.055Ex+0.005698Ex
Amount = Ex(1+0.1036+0.055+0.005698)
Amount = Ex(1.164298)
Ex-Works = Amount
1.164298
![Page 15: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/15.jpg)
15
Calculation of Ex-Works price when quoted price is inclusive of
Taxes and Duties (10.36 ED;14.5% VAT)
Ex-Works = Quoted Price to be arrived (Excluding Taxes and
Duties)
Excise Duty = 10.36% on Ex-Works
VAT = (Ex-Works + Excise Duty) 14.5%
= (Ex-works+0.1036Ex)0.145
Amount = Ex+0.1036Ex+(Ex+0.1036Ex)0.145
= Ex+0.1036Ex+0.145Ex+0.015022Ex
Amount = Ex(1+0.1036+0.145+0.015022)
Amount = Ex(1.263622)
Ex-Works = Amount
1.263622
![Page 16: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/16.jpg)
16
Materials for which PV is admissible i. Power Transformers
ii. Circuit Breakers / Switchgears
iii. Conductors and Ground Wires (CACMAI)
iv. Lightening Arrestors
v. Transformer Oil
vi. Tower Parts / Station Structures
vii. Control Cables
viii. HT / EHT U.G. Cable
ix. Conductor Hardware
x. Battery
xi. Battery Chargers
xii. Instrument Transformers
xiii. Insulators
xiv. Civil works
Circular
![Page 17: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/17.jpg)
17
POWER TRANSFORMER – 10 MVA & above AND
VOLTAGE 33 Kv ABOVE
IEEMA formula:
W.E.F. 01-06-2003
P=P0/100(13+23(C/C0)+28(ES/ES0)+7(IS/IS0)+7(IM/IM0)+7(TB/TB0)+15(W/W0)
W.E.F. 01-01-2009
P=P0/100(13+23(C/C0)+28(ES/ES0)+7(IS/IS0)+7(IM/IM0)+7(TO/TO0)+15(W/W0)
o TB (TOBS) is substituted by TO (Transformer Oil).
o Except for this change the formula remains the same.
o Though the formula remains the same months to be considered is changed
W.E.F. 01-06-2010
P=P0/100(13+23(C/C0)+28(ES/ES0)+7(IS/IS0)+7(IM/IM0)+7(TO/TO0)+15(W/W0)
o IS hither too which was “Iron & Steel” is changed as IS “Ferrous Metals”
Circular
Circular
Circular
![Page 18: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/18.jpg)
18
Switchgear / Circuit Breaker above 36 KV
IEEMA formula:
W.E.F. 01-01-2002
P=P0/100(25+17(IS/IS0)+18(C/C0)+10(Al/Al0)+13(In/In0)+17(W/W0)
W.E.F. 01-06-2007
P=P0/100(19+17(IS/IS0)+17(C/C0)+13(AL/AL0)+19(IN/IN0)+15(W/W0)
“C” Price of Electrolytic copper wire bars is substituted by Average LME settlement price of copper wire bars. (months to be reckoned is also changed)
“In – price of epoxy resin” is replaced by “IN- IEEMA index for Insulator”
Circular
Circular
![Page 19: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/19.jpg)
19
Switchgear / Circuit Breaker above 36 KV
Contd…
IEEMA formula effective from: 01-06-2010
P=P0/100(19+17(IS/IS0)+17(C/C0)+13(AL/AL0)+19(IN/IN0)+15(W/W0)
IS hither too which was “Iron & Steel” is changed as IS
“Ferrous Metals”
If the project commenced prior to 01-06-2010 but
continued after this date this formula is to be used.
Circular
![Page 20: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/20.jpg)
20
Lightning Arrestor
IEEMA formula:
W.E.F. 01-09-2001
P=P0/100(20+15(ZN/ZN0)+15(CO/CO0)+10(BI/BI0)+10(BC/BC0)+10(FP/FP0)+15(W/W0)+5(AL/AL0)
W.E.F. 01-06-2010
There is no change in the formula.
FP hither too which was “whole sale price index for Fuel, Power, Light and Lubricant” is changed as FP “Power and Light”
If the project commenced prior to 01-06-2010 but continued after this date revised WPI is to be used in the formula.
Circular
![Page 21: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/21.jpg)
21
Transformer Oil
IEEMA formula:
W.E.F. 01-01-2000
P = P0 + 1.2 (TB - TB0) + 4.8 (D - D0)
W.E.F. 01-07-2011
There is no change in the formula.
Values for T.O.B.S. is revised
If the supply falls beyond 01-07-2011, then P is calculated up to July 2011 using 01-01-2000 formula and the value so obtained shall be used as P0 in the formula using new values given.
Circular
Circular
![Page 22: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/22.jpg)
22
STATION / MOUNTING STRUCUTRES /
TOWER PARTS
IEEMA formula effective from: 01-01-2002
In respect of Transmission Line Towers using both Heavy and Lighter Angles:
P=P0/100(15+18(HA/HA0)+40(LA/LA0)+16(Zn/Zn0)+11(W/W0)
In respect of Transmission Line Towers using Only Heavy Angles:
P=P0/100(15+58(HA/HA0)+16(Zn/Zn0)+11(W/W0)
In respect of Transmission Line Towers using Only Lighter Angles:
P=P0/100(15+58(LA/LA0)+16(Zn/Zn0)+11(W/W0)
Circular
![Page 23: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/23.jpg)
23
STATION / MOUNTING STRUCUTRES Contd….
IEEMA formula effective from: 01-07-2010
Consequent to substituting HA - Heavy Angles with SBL – Blooms and LA – Lighter Angles with SBI – Billets IEEMA formula has been changed
In respect of Transmission Line Towers using both Heavy and Lighter Angles:
P=P0/100(11+32(SBL/SBL0)+25(SBI/SBI0)+9(Zn/Zn0)+23(W/W0)
In respect of Transmission Line Towers using Only Heavy Angles:
P=P0/100(11+57(SBL/SBL0)+9(Zn/Zn0)+23(W/W0)
In respect of Transmission Line Towers using Only Lighter Angles:
P=P0/100(11+57(SBI/SBI0)+9(Zn/Zn0)+23(W/W0)
Circular
![Page 24: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/24.jpg)
24
STATION / MOUNTING STRUCUTRES Contd….
IEEMA formula effective from: 01-04-2014
Consequent to substituting SBL – Blooms with SBLR – Steel Blooms Retail and SBI – Billets with SBIR – Steel Billets Retail IEEMA formula has been changed w.e.f. 01-04-2014
In respect of Transmission Line Towers using both Heavy and Lighter Angles:
P=P0/100(11+32(SBLR/SBLR0)+25(SBIR/SBIR0)+9(Zn/Zn0)+23(W/W0)
In respect of Transmission Line Towers using Only Heavy Angles:
P=P0/100(11+57(SBLR/SBLR0)+9(Zn/Zn0)+23(W/W0)
In respect of Transmission Line Towers using Only Lighter Angles:
P=P0/100(11+57(SBIR/SBIR0)+9(Zn/Zn0)+23(W/W0)
Circular
![Page 25: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/25.jpg)
25
STATION / MOUNTING STRUCUTRES Contd….
IEEMA formula effective from: 01-04-2014
Care has to be exercised while calculating PV when the project has
commenced before 01-04-2014 and supply has been done after this date
as per PERT.
In such an event calculate “P” using the IEEMA formula effective from 1st
July 2010 up to April 2014. Then substitute the value of “P” so arrived as
“P0” in the formula effective from 01-04-2014.
![Page 26: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/26.jpg)
26
TRANSMISSION LINE ACCESSORIES
AND HARD WARE
As on date IEEMA formulae for this has been revised three times
IEEMA formula effective from: 01-01-2001
In respect of Accessories and Hardware using both Aluminum and Steel:
P=P0/100(20+40(AL/AL0)+5(Zn/Zn0)+20(Fe/Fe0)+15(W/W0)
In respect of Accessories and Hardware using only Aluminum:
P=P0/100(20+65(AL/AL0)+15(W/W0)
In respect of Accessories and Hardware using only Steel: P=P0/100(20+58(Fe/Fe0)+7(Zn/Zn0)+15(W/W0)
Circular
![Page 27: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/27.jpg)
27
TRANSMISSION LINE ACCESSORIES
AND HARD WARE Contd. ….
IEEMA formula effective from: 01-09-2008
“Fe – whole sale price index for Iron & Steel has been substituted with “LA –
Lighter Angles”
Consequent to this the IEEMA formula has also been changed.
Care has to be exercised while calculating PV when the project has
commenced before 01-09-2008 and supply has been done after this date
as per PERT.
In such an event calculate “P” using the IEEMA formula shown on the
previous slide up to September 2008. Then substitute the value of “P” so
arrived as “P0” in the formula effective from 01-09-2008.
Circular
![Page 28: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/28.jpg)
28
TRANSMISSION LINE ACCESSORIES
AND HARD WARE Contd. ….
IEEMA formula effective from: 01-09-2008
“Fe – whole sale price index for Iron & Steel has been substituted
with “LA – Lighter Angles”
In respect of Accessories and Hardware using both Aluminum and Steel:
P=P0/100(20+40(AL/AL0)+5(Zn/Zn0)+20(LA/LA0)+15(W/W0)
In respect of Accessories and Hardware using only Aluminum:
P=P0/100(20+65(AL/AL0)+15(W/W0)
In respect of Accessories and Hardware using only Steel: P=P0/100(20+58(LA/LA0)+7(Zn/Zn0)+15(W/W0)
Circular
![Page 29: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/29.jpg)
29
TRANSMISSION LINE ACCESSORIES
AND HARD WARE Contd. ….
IEEMA formula effective from: 01-03-2011
“LA – Lighter Angles” has been substituted with “SBI – Steel Billets”
Consequent to this the IEEMA formula has also been changed.
Care has to be exercised while calculating PV when the project has
commenced before 01-03-2011 and supply has been done after this date
as per PERT.
In such an event calculate “P” using the IEEMA formula shown on the
previous slide up to March 2011. Then substitute the value of “P” so
arrived as “P0” in the formula effective from 01-03-2011.
Circular
![Page 30: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/30.jpg)
30
TRANSMISSION LINE ACCESSORIES
AND HARD WARE Contd. ….
IEEMA formula effective from: 01-03-2011
“LA – Lighter Angles” has been substituted with “SBI – Steel Billets”
In respect of Accessories and Hardware using both Aluminum and Steel:
P=P0/100(20+40(AL/AL0)+5(Zn/Zn0)+20(SBI/SBI0)+15(W/W0)
In respect of Accessories and Hardware using only Aluminum:
P=P0/100(20+65(AL/AL0)+15(W/W0)
In respect of Accessories and Hardware using only Steel: P=P0/100(20+58(SBI/SBI0)+7(Zn/Zn0)+15(W/W0)
Circular
![Page 31: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/31.jpg)
31
STATION BATTERIES
IEEMA formula:
W.E.F. 01-01-2001
P=P0/100(40+30(LD/LD0)+30(W/W0)
Same formula continues as on date.
Circular
![Page 32: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/32.jpg)
32
BATTERY CHARGER
IEEMA formula:
W.E.F. 01-01-2002
P=P0/100(20+50(IN-BTR-CHRG/IN0-BTR-CHRG)+30(W/W0)
Same formula continues as on date.
Circular
![Page 33: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/33.jpg)
33
INSTRUMENT TRANSFORMERS – CT / PT / VT
IEEMA formula effective from: 01-06-2005
In respect of Instrument Transformers BELOW 72.5 KV:
P= P0/100 (18 +18(C/C0) +20(ES/ES0) +10(IS/IS0) +12(ER/ER0)
+9(TB/TB0) +13(W/W0)
In respect of Instrument Transformers ABOVE 72.5 KV:
P= P0/100 (18 +13(C/C0) +12(ES/ES0) +12(IS/IS0) +23(IM/IM0)
+6(TB/TB0) +16(W/W0)
Circular
![Page 34: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/34.jpg)
34
INSTRUMENT TRANSFORMERS – CT / PT / VT Contd.
…
IEEMA formula effective from: 01-06-2010
There is no change in the formula.
However “IS- Whole sale price index for iron & steel” has
been replaced by “IS-Ferrous Metals”
If the contractual delivery date is beyond 01-06-2010
substitute IEEMA indices in the formula with values of
“FERROUS METALS” for IS.
Circular
![Page 35: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/35.jpg)
35
INSULATORS
IEEMA formula:
W.E.F. 01-04-2003
P=P0/100 (15 +5(Zn/Zn0) +53(IN-INSLR/IN0-INSLR) +27(W/W0)
Same formula continues as on date.
Circular
![Page 36: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/36.jpg)
36
CIVIL WORKS AND ERECTION
IEEMA formula effective from: 01-04-2005
In respect of Concreting:
P=P0/100 (20 +20(HSD/HSD0) +30(C/C0) +20(SC/SC0) +10(W/W0)
In respect of Reinforced and other steel works:
P=P0/100 (20 +65(IS/IS0) +10(HSD/HSD0) +5(W/W0)
In respect of Erection :
P=P0/100 (20 +22(HSD/HSD0) +58(W/W0)
Circular
![Page 37: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/37.jpg)
37
CIVIL WORKS AND ERECTION Contd. …
IEEMA formula effective from: 01-06-2010
There is no change in the formula.
However Indices in respect of Cement & Lime, Structural
Clay, HSD have been changed.
If the contractual delivery date is beyond 01-06-2010
substitute IEEMA indices in the formula with new
values.
Circular
![Page 38: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/38.jpg)
38
PVC and XLPE Insulated Cables
W.e.f. 01-01-2001 Formula (A) : For aluminium conductor PVC insulated cables.
P = Po+ AIF (AI - Alo) + CCFAI (CC - CCo)
Formula (B) : For aluminium conductor PILC cables. P = Po+ AIF (AI - Alo) + PbF (Pb - Pbo)
Formula (C) : For copper conductor PVC insulated cables. P = Po+ CuF (Cu - CUD)+ CCFCu (CC - CCo)
Formula (D) : For steel armoured PVC insulated copper control cables P = Po+ CuF (Cu - CUD)+ CCFCu (CC - CCo) + FeF (Fe - Feo)
Circular
![Page 39: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/39.jpg)
39
Insulated Cables
W.e.f. 01-01-2007
Even though the formula remains the same,
months to be reckoned have been changed.
New variation factors have been introduced.
Circular
![Page 40: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/40.jpg)
40
Conductor and Ground Wire PV formula for ACSR Conductor:
At present the formula will be as per the DWA of the concerned work to be followed:
For example formulae from one of the DWA is as follows:-
P = P0 + K1 (Ar – AO) + K2 (Sr – SO)
For All Aluminum Conductors
P= P0 + ALF (AL-AL0)
For All Aluminum Alloy Conductors
P= P0 + ALF (ALY-ALY0)
For ACSR Conductors
P= P0 +ALF(AL-AL0) + FeF (Fe –Fe0)
PV formula for Ground Wire:
P = (P0 * 0.20) + 0.70(A1/A0) + 0.10(L1/L0)
Circular
![Page 41: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/41.jpg)
Applicability of VAT
for different materials Transformer, CT, PT, NCT, Transmission Line Towers,
Cable / HT xlpe, Instrument Transformer, Aluminum
conductor / GI wire, GI flat VAT = 5.5 %
VAT for other materials - 14.5 %
41
![Page 42: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/42.jpg)
ACSR conductor Accessories &
HARDWARE – Material Content
Vibration Damper, T & S clamp, Post insulator
clamp, PG clamp, MSC joint has Steel &
aluminum content
Pre formed Armored Rods, Repair Sleeve has
only aluminum content
Tension clamp, Suspension clamp, PG clamp,
MSC joint, Hardware relating to ground wire
has only STEEL content
42
![Page 43: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/43.jpg)
TRANSMISSION LINE TOWERS
where Heavy Angles are used
(1) Stubs of normal 220 KV
(2) 66kv Stubs of Narrow Base / 220 kv Stubs
of Narrow Base Tower
(3) stubs of Multi voltage multi circuit Towers
43
![Page 44: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/44.jpg)
TRANSMISSION LINE TOWERS
where Heavy and Lighter Angles are used
(1) Towers of 220kv & Towers of narrow base
except their Stubs
44
![Page 45: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/45.jpg)
TRANSMISSION LINE TOWERS where only Lighter Angles are used
(1) Stubs & towers of 66 KV & Station
structure such as 2T1 & 2T2, 6T1 & 6T2,
Mounting structure
45
![Page 47: Retd. Controller, KPTCL / CESC - KPTCL Accounts …kptclaoa.com/docs/PDPPVRAGHU.pdf3 When price variation is applicable? Projects costing Rs.100 Lakhs and above & the period of completion](https://reader031.fdocuments.net/reader031/viewer/2022022003/5aa3211e7f8b9a1f6d8e28a8/html5/thumbnails/47.jpg)
47