RES Americas Kansas Wind and Renewable Energy Conference 2008.
-
Upload
jasper-strong -
Category
Documents
-
view
215 -
download
1
Transcript of RES Americas Kansas Wind and Renewable Energy Conference 2008.
RES Americas
Kansas Wind and Renewable Energy Conference 2008
2
RES Americas Inc
Organization
RES Americas is primarily a leading Wind Energy Company but is moving into other renewable fields
Established Broomfield, CO office as Corporate Headquarters
Development
Technical, Resource Assessment
Construction
3
History of RES Americas
RES Americas’ U.S. construction surpasses 1,000 MW
RES Americas began developing projects for ownership
RES Americas’ U.S. construction surpasses 3,000 MW
Commercial operations of RES Americas’ first owned project, Whirlwind, in the U.S.
RES constructs its first project
Renewable Energy Systems Limited founded by Sir Robert McAlpine
RES Americas constructs its first U.S. project
1981 1992 1999 2006 2008
The RES Group has a long history in wind technology development
RES Americas takes projects from conception - leasing land, acquiring transmission rights and setting up Power Contracts with Utilities
RES Americas is currently constructing approximately 1,400 MW, representing more than 30% of the wind capacity currently under construction in the U.S. and will have constructed approximately 3,500MW by the end of 2008.
2001
RES Americas co-developed and constructed the 278 MW King Mountain Wind Ranch, the largest wind project in the world at the time it was constructed
4
Wind Power Industry Overview
Between 2007 and 2030, electricity demand in the U.S. and Canada is expected to increase approximately 30%
Significant portion will be met with renewables
PTCs Accelerated tax depreciation State / provincial policies and wind energy incentives
− Renewable Portfolio Standards (“RPS”)
Renewable energy is expected to capture a significant portion of the electricity sector
Wind energy incentives
Wind expected to represent 7% of U.S. capacity by 2015
Cumulative capacity of 57,000 MW by 2015
RES currently has over 600 MW in various stages of development in Kansas
Wind energy is the future of renewable power generation
Through 2012, natural gas prices are forecast to remain in the $8-$12/mmbtu range, keeping wind cost-competitive with gas-fired electricity generation in many state electricity markets
Increasing cost of traditional fuels
Focus on greenhouse gas emissions in both the U.S. and Canada has further prompted the growth in renewable generation
Greenhouse gas considerations
5
-
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
U.S. Canada
North American Wind Opportunity
North American Installed Wind Capacity Growth
Source: EER, Nov 2007.
(in MW)
6
Emerging Renewables
RES is using wind power expertise to develop and construct projects that generate power using solar thermal, solar PV, and biomass
Also interested in energy storage, though this is still a developing field.
Focused on utility-scale, grid-connected projects.
RES is leveraging existing land positions, interconnection agreements, and relationships with utilities
Solar PV can generate power almost anywhere – but it’s still expensive
Solar thermal is less expensive – but requires the direct sunlight found in the Southwest US
Ausra C
LFR
7
RES Americas Inc
Construction
U.S. Business
Constructed - 20 Projects in US = 2,060 MW; 1999 – 2007
Under Construction - 12 Projects = 1,480 MW
Construction Activities
Wind Farm Design
Civil and Electrical Design
Procurement
Civil, Electrical, Mechanical Construction
Construction Management
Turbine Procurement
8
Central Plains Wind Farm
Size: 99 MW
Location: Wichita County, Kansas
Developer: RES Americas
Ownership: Westar
Contract Type: EPC
Construction Start: April 2008
Substantial Completion: December 2008
Turbine Technology: 33 Vestas V90 3.0 MW
Interconnection Voltage: 115 kV
Total Length of New Road: 7 miles
Total Length of Collector System:
19 miles
9
Central Plains Wind Farm – The Beginning
•The project was originally scheduled to be constructed in 2003 and then 2004
•Resurrected as Central Plains Wind Farm.
•Construction began in April, 2008
•Wichita Economic Development, Inc.
•Wheatland Electric Coop
•Sunflower Electric Power Corp.
•Local source for road base material
•Kansas civil contractor for roads construction
•Kansas contractor to construct O&M Building
10
Central Plains Wind Farm - Roads
•Oakley, KS roads contractor
•6.7 miles of roads, 20 foot wide with 8 foot shoulders
•Roads built from crushed base material over a Geotextile fabric
•Roads completed in July
•Extensive testing on sub-grade and road base.
•Shoulders are tested for bearing capacity
•Crane pads designed and tested for the specific loads encountered during lifts.
11
Central Plains Wind Farm - Foundations
•55 foot octagonal spread foot
•11 foot total height
•Approximately 410 cubic yards of concrete per foundation
•Approximately 80,000 pounds of rebar per foundation
•Total foundation weight is over 1,600,000 pounds
•Foundations are designed internally
•Design is specific to turbine and site conditions
12
Central Plains Wind Farm - Electrical
•Power is transmitted from the turbines to the substation at 34,500 volts
•Over 19 miles of underground cable
•All turbines, substation and O&M building connected by fiber optics
•Collection system nearing completion
•Substation transformer steps up the 34,500 volts to 115,000 volts for connection to the transmission line
•Metering and system protection take place in the project substation
•Substation scheduled for to be energized on October 20th
13
Central Plains Wind Farm - Turbines
•Vestas V90, 3 Megawatt turbines
•Tower is 80 meters, 262 feet, tall and weighs over 370, 000 pounds
•Each blade is 44 meters, 144 feet, long and weighs over 14,000 pounds
•The nacelle and hub weigh over 175,000 pounds
•Total weight of turbine is approximately 600,000 pounds
•Wind farm will produce enough power for approximately 35,000 homes
14
Central Plains Wind Farm - Turbines
•The crane used will have a track length of 38 feet, width of 34 feet and a boom height of 320 feet
•The assembled crane will weigh about 1.2 million pounds
•The crane will be transported to the site on over 20 tractor trailers.
•The major components will be shipped from the port to Kansas by rail
•First tower section will be erected by the second week in October.
•The blades will be installed one at a time, single blade erection
•First turbine will be completely erected by the end of October
•Project will reach Substantial Completion before the end of December
15
RES Americas