Renewables Portfolio Standard Status Report
-
Upload
mackensie-hinton -
Category
Documents
-
view
46 -
download
3
description
Transcript of Renewables Portfolio Standard Status Report
Renewables Portfolio StandardStatus Report
California Public Utilities Commission
February 26th, 2008
What is RPS?
Established under SB 1078 (2002) and SB 107 (2006)
Load-serving entities must procure an additional 1% of retail sales per year from eligible renewable sources until 20% is reached, no later than 2010
CPUC oversees RPS procurement of Investor-Owned Utilities (IOUs), Electric Service Providers (ESPs) and Community Choice Aggregators (CCAs)
Compliance is based on delivered energy
Publicly-owned utilities must design similar programs, report progress to the California Energy Commission
RPS Procurement Process is Working
Year 2002 2003 2004 2005 2006 2007 Total
Number ofcontractsapproved
14 7 3 20 10 26 80
MWapproved
295 MW 262 MW 74 MW 1255 MW 635 MW 1395 MW 3916 MW
CPUC is responsible for overseeing RPS solicitations and reviewing IOU contracts for RPS-eligible energy. 80 contracts approved since 2002, for almost 4,000 MW. CPUC contract approval is not to exceed 6 months; approval time averaged 5 months over the past year.
Participation in RPS solicitations is accelerating Solar energy saw a dramatic increase in participation from developers in the 2007 RPS
solicitation. Wind and geothermal will continue to be large contributors to RPS generation.
RPS Bids by Fuel Type
0
20,000
40,000
60,000
80,000
100,000
En
erg
y (
GW
h)
Solar 8,808 1,725 5,278 7,484 33,046
Wind 3,959 7,406 10,479 9,339 29,990
Geothermal 4,747 5,841 12,263 2,514 4,027
Biomass 1,470 1,635 2,403 2,694 8,186
Biogas 349 1,220 272 245 15
Small Hydro 107 14 200 49 0
Other 0 105 208 1,413 996
2003 RFO 2004 RFO 2005 RFO 2006 RFO 2007 RFO
RPS Generation by Fuel Type
IOU Actual and Forecasted RPS Generationby Fuel Type
0
10,000
20,000
30,000
40,000
50,000
60,000
20
03
20
04
20
05
20
06
20
07
20
08
20
09
20
10
20
11
20
12
20
13
GW
h/y
r
expiring (fuelunknown)
solar
wind
geothermal
small hydro
bioenergy
34,8640
Target: 20% of Expected IOU Retail Sales
Wind and geothermal will be the largest contributors to RPS generation in 2010.
IOU Actual and Forecasted RPS Generation
0
10,000
20,000
30,000
40,000
50,000
60,000
20
03
20
04
20
05
20
06
20
07
20
08
20
09
20
10
20
11
20
12
20
13
GW
h
Pre-2002 Contracts 2002 Contracts 2003 Contracts 2004 Contracts
2005 Contracts 2006 Contracts 2007 Contracts Pending Approval
Short-listed Bids Expired Contracts RPS Target
Target: 20% of Expected IOU Retail Sales
Contracts signed and under negotiation may put IOUs close to 20% in 2010
However, project viability is a concern
IOU Expected RPS Generation and Risk
0
10,000
20,000
30,000
40,000
50,000
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
Gw
h/y
r
Target: 20% of Expected IOU Retail Sales
977 MW
1370 MW
808 MW
Online/existing
Expiring
Low Risk
Medium Risk
High Risk
Project development hurdles are the major source of risk
0%5%
10%15%20%25%
30%35%40%45%50%
Transm
issi
on
Devel
oper
Finan
cing
Site C
ontrol
Perm
ittin
g
Price
Reopen
er
Radar
Techn
ology
Fuel S
upply
Equip
men
t Pro
curm
ent
CPUC contract approval is only one step in the complex project development process.
Inter-agency coordination is key to reaching 20%
Barriers facing projects needed to meet 2010 goal
CPUC working on project development solutions SB 1036 Implementation
Addressing transmission barriers: Renewable Energy Transmission Initiative (RETI), ISO Queue reform, streamlined permitting
Increasing supply: Feed-in tariffs (AB 1969), tradable RECs (CSI), Emerging Renewable Resource Program (ERRP)
Contract management work to track projects, improve analysis and reporting of challenges to project development
Future: Solutions team works with relevant agencies
Prices for renewables are rising
Annual IOU Expected Above-MPRCosts from RPS Energy
approved contracts, contracts pending approval, and short-listed bids
0
20
40
60
80
100
120
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
An
nu
al C
ost
s (M
illio
n $
/ Y
ear) Non-SEP-Eligible Above-MPR Costs
SEP-Eligible Above-MPR Costs
Above-market funds may not be sufficient
Expected Above-MPR RPS Energy Costs2002-2020
0
200
400
600
800
1000
1200
1400
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Mill
ion
$
Total above-MPR costs
Eligible for above-MPR funds
Not eligible for above-MPR funds
Above market fund cap ≈$770 million
Flexible Compliance Rules Penalty for non-compliance is 5 cents per kWh, up to $25 million per year
Banking/Earmarking: LSEs can “apply excess procurement in one year to subsequent years or inadequate procurement in one year to no more than the following three years”, pursuant to Public Utilities Code §399.14(a)(2)(C)(i).
Penalties may be avoided or deferred pursuant to statutory or Commission adopted conditions, such as;
inadequate public goods funds to cover above-market costs (399.16(a)(8)),
insufficient transmission (399.14(a)(2)(C)(ii)), lack of competition (399.14(d)) insufficient response to solicitation, seller non-performance.
An LSE is expected to reasonably diversify its RPS procurement portfolio, taking generation and transmission project development risk into account.
Any requested relief, including the use of flexible compliance, will be examined by the CPUC
Flexible compliance may allow for more rational build-out, mitigate market power
New MW under
contract
New MW needed without flexible
compliance
New MW needed with
flexible compliance
2002 0 0 0
2003 36 36 36
2004 66 66 66
2005 51 51 51
2006 75 75 75
2007 114 114 114
2008 620 1,092 546
2009 309 1,092 546
2010 709 1,092 546
2011 827 113 659
2012 82 119 665
2013 1,030 116 662
Total 3,919 3,966 3,966
Utilities over-contract to account for possible project failure About 3,000 MW of new RPS development needed to meet 20% About 3,600 new MW now under contract or pending CPUC approval
0
1,000
2,000
3,000
4,000
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
MW
New MW online
New MW needed each year with out flexible
compliance
New MW each year under contract
New MW needed each year with flexible
compliance
Tradable Renewable Energy Credits What is a Renewable Energy Credit?
A Renewable Energy Credit (REC) generally represents the environmental and renewable attributes of renewable electricity as a separate commodity from the energy itself. A REC can be sold either "bundled" with the underlying energy or "unbundled" into a separate REC trading market.
Currently, unbundled RECs do not count for RPS compliance. Pursuant to SB 107, CPUC is currently considering the use of
tradable (unbundled) RECs within the California RPS. Staff proposal for a tradable REC regime was issued in October 2007.
Goals for TREC regime, if adopted: Encourage renewable development Help overcome transmission issues Increase market efficiency Facilitate compliance by smaller LSEs Lower RPS compliance costs
In the Western region of the U.S., RECs (both voluntary and compliance) will be tracked using the Western Renewable Energy Generation Information System (WREGIS).
1. http://www.cpuc.ca.gov/PUC/energy/electric/RenewableEnergy/misc/070824recworkshop.htm