ransmission Line
CONTACT US!
Please contact the Montrose-Nucla Construction Hotline with any questions or concerns you may have throughout this process. We appreciate the support and patience of the local communities and visitors as we begin work on this critical project that will improve electric reliability for southwestern Colorado.
HOW DO I FIND OUT WHERE CONSTRUCTION CREWS WILL BE WORKING WEEK TO WEEK?
The precise location of the construction crews will depend on seasonal restrictions implemented to protect wildlife including big game, weather, as well as other land use and landowner constraints.
Tri-State has established a construction hotline for the public to track the location and schedule of the transmission line construction to better plan recreational activities, including hunting. This hotline will be available 24-7. You may also leave a message on this hotline and someone from Tri-State will return your call within 24 hours.
Call toll free: 1-833-360-3393
Tri-State will also be regularly updating our project website with construction-related scheduling information. Please go to http://www.mncrebuild.com/
Montrose-Nucla
CONSTRUCTION INFORMATION
WHAT TO EXPECT
Please be advised that heavy equipment will be used and all safety pre-cautions should be taken to avoid portions of the transmission line right-of-way where construction and tree removal is ongoing.
Heavy equipment will be using Highway 90 (FS-540), Divide Road, Mailbox Road, and other U.S. Forest Service and Bureau of Land Management public access roads open to recreational uses. Some temporary road closures may be required to ensure public health and safety.
Public safety signs will be installed at critical trail and road junctures, including FS-540, where crews will be working.
There might be short-term delays on FS-540 due to the hauling of larger equipment and during the pulling of the conductor wire across public roads.
Some project noise is expected in proximity to and within the transmission line right-of-way associated with tree removal, pad site development for transmission structures, access improvements, excavation for and placement of new transmission line poles, the stringing of the conductor and overhead optical groundwire, and the removal of the existing 115-kV transmission line.
I M P R O V E M E N T P R O J E C T
Tri-State Generation and Transmission Association, Inc. (Tri-State) will be upgrading
our existing Montrose-Nucla transmission line from 115-kV to 230-kV beginning in spring 2017. The transmission line runs from the Montrose Substation west of the city of Montrose, Colorado to the Nucla Substation at the Nucla Power Plant in Nucla, Colorado. Please find enclosed a project overview map.
The first phase of construction will include improving the roads and removing vegetation associated with the Montrose-Nucla line segment during spring and summer 2017. Rebuilding the transmission line will begin in the middle of September 2017 and continue through October 2018.
This line segment occurs in Montrose County and spans lands administered by the Bureau of Land Management-Uncompahgre Field Office, the U.S. Forest Service-Uncompahgre National Forest, and private lands. Construction of the transmission line will require 12 months and is scheduled to be completed by October 2018.
ransmission LineMontrose-Nucla
I M P R O V E M E N T P R O J E C T
#*
#*BLM
BLM
U.S. FOREST SERVICE
CO 90
FS 540
CO 90
NuclaSubstation
Montrose Substation
DivideRoad- 402
MailboxPark Road Mailbox
Park Road
FS 540CO 90
CO 90
CO 90
49N 13W49N 11W
45N 11W
45N 15W
46N 14W
50N 15W
45N 13W
47N 13W
50N 13W
47N 12W
50N 11W
47N 11W
48N 11W
47N 14W
49N 14W
48N 12W
50N 10W
48N 14W
50N 14W
45N 12W
45N 10W
49N 09W
46N 15W
45N 14W
46N 12W
48N 15W
49N 10W
48N 10W
49N 15W
46N 13W
48N 13W
47N 10W47N 15W
45.5N13W
49N 12W
50N 12W
46N 11W
46N 10W
50N 09W
Mesa CountyMontrose County
Montrose CountyOuray County
Montrose CountySan Migue l
County¬¬«145
¬¬«141
¬¬«141
¬¬«145
££¤50
££¤50
11
36
30
16
1307
0801
21
25
14
02
2017
03
16
09 10
18
10
08
18 16
31
29
36
19
18
09
09
02
23
14
24
17
15
10
1513
08 09
03
30
17
03 01
15
02
35
10
Legend
#* Substation
Access RouteTransmission Line
Transmission Corridor
Major RoadsInterstate HighwayU.S. Highway
State Route
Other Major Road
County Boundary
Township/RangeSection
Land Manager - DetailBureau of Land Management
Forest Service (USFS)
State Land
Montrose-Nucla 230kV Transmission Line Project
* Construction to begin around May 1, 2017 and will run through October 1, 2018
Montrose-Nucla 230-kV Transmission Line Improvement Project
#*
#*BLM
BLM
U.S. FOREST SERVICE
CO 90
FS 540
CO 90
NuclaSubstation
Montrose Substation
DivideRoad- 402
MailboxPark Road Mailbox
Park Road
FS 540CO 90
CO 90
CO 90
49N 13W49N 11W
45N 11W
45N 15W
46N 14W
50N 15W
45N 13W
47N 13W
50N 13W
47N 12W
50N 11W
47N 11W
48N 11W
47N 14W
49N 14W
48N 12W
50N 10W
48N 14W
50N 14W
45N 12W
45N 10W
49N 09W
46N 15W
45N 14W
46N 12W
48N 15W
49N 10W
48N 10W
49N 15W
46N 13W
48N 13W
47N 10W47N 15W
45.5N13W
49N 12W
50N 12W
46N 11W
46N 10W
50N 09W
Mesa CountyMontrose County
Montrose CountyOuray County
Montrose CountySan Migue l
County¬¬«145
¬¬«141
¬¬«141
¬¬«145
££¤50
££¤50
11
36
30
16
1307
0801
21
25
14
02
2017
03
16
09 10
18
10
08
18 16
31
29
36
19
18
09
09
02
23
14
24
17
15
10
1513
08 09
03
30
17
03 01
15
02
35
10
Legend
#* Substation
Access RouteTransmission Line
Transmission Corridor
Major RoadsInterstate HighwayU.S. Highway
State Route
Other Major Road
County Boundary
Township/RangeSection
Land Manager - DetailBureau of Land Management
Forest Service (USFS)
State Land
Montrose-Nucla 230kV Transmission Line Project
* Construction to begin around May 1, 2017 and will run through October 1, 2018
*Construction to begin around May 1, 2017 and will run through October 2018