R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

download R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

of 24

Transcript of R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    1/24

    Appendix 5

    Comparisons between installing 220kV undergroundtransmission cables and installing other longitudinal

    infrastructure for example, high pressure gas or waterpipe lines; underground distribution cables and

    communication cables

    Installation requirements and provision for maintenance & repairs differ

    significantly between those for extra high voltage (220kV) undergroundtransmission cables and lower voltage underground distribution cables;

    underground communication cables and high pressure gas or water pipe lines.

    There are also variations in easement requirements and easement conditions

    In simple terms:

    Metallic or polymeric (plastic) gas or water pipes are transported to site and laid

    in manageable sections (and manageable weights) and welded, or otherwise

    connected together, as trench excavation progresses.

    Trenches are narrow and, other than a bedding comprised of sand (to protect the

    outer surface of pipes) there are no special trench excavation or back-filling

    requirements.

    Similar installation conditions to those for gas & water pipes may apply for lower

    voltage underground distribution cables and communications cables (whether

    electric or fibre optic). These are often laid in ducts.

    Trenches are narrow (the width of a small back-hoe bucket) and other than for

    sand bedding there are no special trench excavation or back-filling requirements.

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    2/24

    In the case of extra high voltage underground power cables (including 220kV)

    there are factors that impose significant differences in installation & maintenance

    requirements to those for water or gas pipes or lower voltage circuits namely:

    1. Dissipation of heat generated by underground cables.As underground cables transmit energy (in this case from the wind farm to the

    main grid) the cables generate heat which, if not efficiently dissipated, will cause

    the cables to over-heat and eventually fail. (This was precisely one of the

    contributing factors that led to the cable failures and eventual black-outs in

    Auckland in 1998)

    Soil samples taken from site in the Limestone Downs Orton area are estimated

    to have a high thermal resistivity meaning the soil will impose a barrier to heatwanting to escape from the cables to the surface. This shall be confirmed by

    thermal resistivity test on site & in laboratory prior to proceeding with the project.

    Well accepted practice, world wide, is to improve this situation by bedding and

    covering the cables with a controlled medium comprised of a weak mix of sand

    and cement. (Refer diagram below)

    Vast quantities of this mix (equivalent to excavated spoil) would be required

    adding substantial costs and transport difficulties in acquiring, delivering, placing& compacting it over the entire cable route.

    Typical cable installation in trench with cables in flat formation

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    3/24

    2. Installing and jointing cables

    Cables of this size and voltage are not manufactured in New Zealand. Each

    cable drum, containing around 700metres of cable and weighing up to 20 Tones,

    would require to be transported from Auckland on multi-wheeled vehicle to sites

    at 700 m intervals, there to be craned off, winched/pulled into position (in the

    cable trench), then to be bedded & covered with protective concrete cable covers

    and special backfill and then to be jointed in a controlled environment in what is

    known as a joint bay comprising a tented enclosure of the size, and with

    features, as shown below. The duration of works associated with Joint bays

    (construction and cable jointing) could be as long as 3 to 4 weeks.

    Joint bay (4m x 12m) in roadway Interior of joint bay prior to jointing(Would exceed width of Baker Rd.

    in places)

    3. Managing cable sheath losses

    At transmission voltages, including 220kV, special bonding techniques termed

    cross bonding provide the only practical means to mitigate losses in outer

    metallic sheaths of underground power cables. (For technical explanation refer to

    Appendix 6)

    Cross bonding systems include surge arrestors and other equipment mounted in

    underground link boxes that require testing at regular intervals (usually annually).

    For that purpose that equipment is located within pits as shown below which, for

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    4/24

    ready access and safety to testing staff, are located away from trafficable roads

    in footpaths see below.

    Link box U/G concrete pit

    Baker, Wairamarama and Matakitaki Rds. would present considerable challenges

    in that they are very narrow and in many cases bounded by steep drops on one

    side and steep inclines on the other where they are carved into mountain sides

    see Photos No 4 & 5 in Attachment No.1 to Consolidated report.

    In these situations there would be no alternative but to install link pits together

    with joint bays and pits for optic fibre cables (if fibres were to be part of the cable

    installation) in road ways.

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    5/24

    Appendix 6

    Current rating and electrical losses of highvoltage power cable systems

    1. Cable Rating Influencing Factors

    The current rating of high voltage (HV) underground (U/G) power cable circuits is,

    primarily, influenced by the environmental factors and cable losses.

    Both factors are fully considered for determination of cable type and installation

    particulars by taking into consideration the economic aspects related to the cost of

    materials, installation of cable and accessories, running cost (whole life cost),

    capitalised cost of losses and ancillary equipment such as bonding, condition

    monitoring systems and compensating equipment.

    a. Environmental Factors

    The most specific factors which have a greater impact on cable current rating or

    loading capacity are as follows:

    Air and soil maximum ambient temperature

    Soil thermal resistivity (TR) under the most severe climatic conditions in

    respect to water (humidity) content

    b. Installation Particulars

    Extra high voltage (EHV) power cable circuits (including 220kV) are

    manufactured in form of single-core cables which could be installed in trefoil or

    flat formations.

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    6/24

    The installation option is selected to correlate the cable type /conductor size with

    the environmental parameters to get the required cable carrying capacity.

    Fig1: Typical installation configuration of single-core power cables in trefoil

    formation

    This type of cable configuration has the advantage of minimising the sheath

    circulating currents induced by the magnetic flux linking the cable conductors and

    metallic sheath or copper wire screens. This configuration is generally used for

    cables of lower voltages (33 to 132kV) and of smaller conductor sizes

    However, for EHV cable systems the trefoil formation is not appropriate for heat

    dissipation because there is an appreciable mutual heating effect of the three

    cables.

    The cumulated heat in cables and cable trench has the effect of reducing the cable

    rating and accelerating the cable ageing

    In order to improve the natural heat dissipation from around the cable circuits the

    three single-core cables could be installed in flat formation (Fig2). This

    configuration allows for a significant increase of current rating of EHV cable circuits.

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    7/24

    Fig. 2: Typical installation configuration of single-core power cables in flat

    formation

    In Fig. 2 are shown the CMS (condition monitoring system) and

    communication cables installed between the 220kV single-core power

    cables.

    In addition, to the centre power cable is attached the DTS (distributed

    temperature sensing) optical fibre cable. Both the DTS and CMS are

    designed to continuously monitor the cable and environment temperatures

    and to perform other supervisory functions as well

    The installation of cables in flat formation requires special bonding solutions

    of cable metallic sheaths to reduce/eliminate the circulating currents.

    Nevertheless, in case of unfavourable environmental conditions related to

    soil thermal characteristics or of ambient temperature the sole application of

    flat configured cables and of special bonding system may not provide the

    expect result and as a consequence the following techniques should be

    employed to achieve the required current rating:

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    8/24

    Replace a certain amount of soil adjacent to the excavated cable

    trench with aggregates or imported soils of suitable thermal resistivity.

    Use of specialised bedding and backfilling materials such as:

    Sand/cement mix of 14: 1, 20:1 or of other proportions

    Fluidised backfill

    Blended sands or crushed rock of variable gain sizes

    All ducts and micro tunnels be filled with bentonite and respectively

    light concrete

    Artificial cooling

    Particular installation configurations of single-core cables or of cable

    circuits within a given cable corridor

    Special bonding system of cable metallic sheaths designed to reduce

    the electric losses

    Install double cable circuits in a single or adjacent trenches or other

    applicable site conditions

    2. Electrical Losses

    Under service conditions, regardless of magnitude of transported the power

    cables are subjected to electrical losses manifested as heat in insulation and

    metallic components.

    Based on the location were they are generated and the generation cause the

    electrical losses could be qualified as current and voltage-dependent losses.

    The current-depending losses are generated in cable conductors, metallic sheath

    or/and metallic wires designed to carry fault currents

    For a simplified cable system (land cable circuit) the three main cable

    component responsible for electrical losses are the conductor(s), the insulation

    and the metallic sheaths or/and the metallic wire screens.

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    9/24

    2.1 Conductor Losses

    Conductors losses are ohmic losses, i.e. heat (Watt/meter) generated by the

    current flowing in the cable conductor(s) and are calculated with the following

    formula:

    Wc = I2 Ra.c

    I = current flowing in the conductor (A)

    Ra.c= A.C. electrical resistance () of conductor at given temperature (C)

    The A.C. electrical resistance () is dependent, in addition to the D.C resistance

    (Rd.c) on skin (ys) and the proximity (yp) effects which are responsible for the

    uneven distribution of load current across the conductor cross sectional area, so

    the Ra.c resistance could be defined as:

    Ra.c = Rd.c (1 + ys + yp)

    Rd.c = Ro [1 + 20 ( 20)]

    Ro = D.C electrical resistance at 20C

    20 = Constant mass temperature coefficient at 20C per Kelvin

    = maximum operating temperature (C)

    Skin effect(ys ) is attributed to the variation of conductor self-inductance which

    is greater to the centre of the conductor than to its periphery and as a

    consequence the current flow is maximum at the conductor surface and minimum

    at the conductor core This phenomenon is one cause of increased A.C.

    resistance of conductors.

    Proximity effect (yp) is generated by the magnetic field produced by the currents

    flowing in parallel cable conductors of another cable circuit or other parallel

    current carrying conductors. The associated magnetic field embraces that

    conductor and at the same time it encircles the parallel conductors in close

    proximity.

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    10/24

    The effect is explained by the fact that when two conductors carrying alternating

    current are parallel and in close proximity, the current densities on the inner area

    (side facing each other) are smaller than the current density flowing in the outer

    area (remote side) of the conductors due to the difference in magnetic flux

    densities cutting the conductors cross area.

    So, the A.C. conductor resistance is defined by the D.C resistance and the skin

    and proximity factors as indicated by the following formula:

    Ra.c = Rd.c (1 + ys + yp)

    The calculation of skin (ys) and proximity (yp) effect factors is based on the

    empirical formula given in the IEC 60287 Standard

    The proximity effect factor (yp) is determined by the cable D.C. resistance,

    system frequency, cable spacing and cable diameter while the ys is influenced

    only by conductor d.c resistance and system frequency:

    ys = (R , f)

    yp = (dc , R, s , f)

    The skin and proximity effects could be ignored for small conductors carrying low

    currents, however for high rating cables requiring large conductors these effectsare significant and it is essential to include design feature to compensate their

    effect.

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    11/24

    The Milliken or Segmental conductors, which consist of several individually or

    alternated insulated sector shaped strands, provide the desired solution (Fig. 3).

    Fig. 3: Milliken Cable Conductor (Fluidfilled Cable System)

    The modern technologies apply a layer of enamel or Cu oxide on individual wires

    forming the sector shaped strands.

    The economic justification of this type of conductor is validated when using

    cables of minimum 800mm2

    2.2 Dielectric and Charging Current Losses

    A power cable is a large capacitor of certain capacitance characterised by

    dielectric constant () and electrical resistance. The two parameters and the

    magnitude and frequency of applied voltage determine the magnitude of charging

    current and dielectric losses.

    Both, the charging current and dielectric losses are voltage-dependent and they

    are generated in cable insulation at any time the cable is connected to the grid.

    The charging currents are generated by the cable itself and produce a certain

    amount of losses which, in combination with the system reactive power generate

    losses reducing the flow of active/real power (MW).

    Cableconductor

    (Milliken)

    CableInsulation

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    12/24

    The charging current charges and discharges the cable (capacitor) 50 times per

    second. While the charging current is a reactive current the dielectric losses are

    determined by real power currents.

    The reactive power transported by the cable is independent of cable system; it isa parameter determined by the system configuration and the elements designed

    to compensate the reactive power flow

    The charging (IC) and resistive (IR) currents flowing through the cable insulation

    are calculated with the following equations:

    IC= C Uo (charging current)IR = Uo/R (leakage current),

    While the dielectric losses are calculate from the equation:Wd = Uo

    Ic tan, orWd = CUo

    2tan Where:

    109

    ln18

    =

    d

    D

    c

    i

    c

    C = cable capacitance = 2 = system frequencyUo =

    phase voltage

    tan = dielectric power factorR = insulation resistance = dielectric constantDi = insulation diameterdc = conductor diameter

    For high and extra-high voltage cables the dielectric losses (Wd) could be

    relatively high and may have significant contribution to in determination of cable

    ratings

    The cable dimensions and the insulation dielectric constant are the basic factors

    responsible for the size of capacitance.

    [C = /18ln (Dinsulation /dconductor)] while the tan is dependent on frequency,

    temperature and the applied voltage and is being influenced by the following

    factors:

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    13/24

    Leakage current flowing across the resistive component of cable

    (capacitor) insulation is very much influenced by the quality-cleanliness of

    insulating materials. The leakage current is an ionic conduction due to

    the presence of free electrons flowing in the direction of electric field.

    Dielectric hysteresis losses caused by the interaction of alternating

    electrical field with the molecular structure of cable insulation; a sort of

    mechanical work aiming to orientate the bipolar microscopic molecules of

    insulation, or of contaminants, in the direction of electrical field. As the

    field direction changes 50 times/sec, the cumulative impact of hysteresis

    effect could be significant and, in fact, it is the major contributor to

    dielectric losses.

    Ionisation and low energy discharges inside the insulation.

    2.3 Sheath Losses

    Sheath losses are current-dependent losses and are generated by the induced

    currents when load current flows in cable conductors.

    The sheath currents in single-core cables are induced by transformer effect; i.e.

    by the magnetic field of alternating current flowing in cable conductor which

    induces voltages in cable sheath or other parallel conductors.

    The sheath induced electromotive forces (emf) generate two types of losses:

    circulating current losses (1) and eddy current losses (1), so the total losses in

    cable metallic sheath are:

    1=

    1 +

    1

    The eddy currents circulating radially and longitudinally of cable sheaths are

    generated on similar principles of skin and proximity effects mentioned in relation

    to the conductor Rac resistance; i.e. they are induced by the conductor currents,

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    14/24

    sheath circulating currents and by currents circulating in close proximity current

    carrying conductors.

    Fig. 4: Magnetic field of a three-phase single-core cable circuit

    They are generated in cable sheath irrespective of bonding system of single core

    cables or of three-core cables

    The eddy currents are generally of smaller magnitude when comparing with

    circuit (circulating) currents of solidly bonded cable sheaths and may be neglects

    except in the case of large segmental conductors and are calculated in

    accordance with formulae given in the IEC60287, which for simplification of this

    document is not presented.

    Circulating currents are generated in cable sheath if the sheaths form a closed

    loop when bonded together at the remote ends or intermediate points along the

    cable route.

    These losses are named sheath circulating current losses and they are

    determined by the magnitude of current in cable conductor, frequency, mean

    diameter, the resistance of cable sheath and the distance between single-core

    cables; i.e. the mutual inductance, calculated with the following equation:

    Cablesheath

    Eddy currentsin cable sheath

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    15/24

    Is = Es / (Rs2+ Xm

    2)1/2

    Es = I XmXm = M x10

    -3M = 0.2 ln (2S/dm)Where,

    I =conductor currentXm = inductive reactance per phase including the self inductance of the conductorand the mutual inductance with other conductors.M = mutual inductance between conductor and sheaths = Cable spacingdm = sheath mean diameter (m)Is = circulating currentRs= Sheath resistance

    The actual calculation of circulating currents need to take into consideration the

    magnetic influence of the conductor currents in all three single core cables(conductors and sheaths), the mutual impedance between cable and sheath and

    between all three cables.

    In addition, for multiple cable circuits the aspect is further complicated by the

    magnetic interference of circuits in close proximity. As a consequence the

    calculation magnitude of induced voltages and circulating currents is done by

    using specialised computer routines as indicated in the IEC60287. The cable

    system and the interconnecting network represented by distributed parameters

    (Impedances) and the hypothetical electrical occurrences (power frequency or

    fast transients). The general model is quite complicated and requires some

    computer programming and use of specialised software.

    The impact of circulating currents is included in the cable rating equations as a

    proportional quantity of sheath currents and sheath resistance to the conductor

    current and conductor resistance in form of:

    RR

    II

    C

    S

    C

    S

    2

    2

    1= (Eddy currents not included), quantity which is defined as

    [Sheath Loss factor = 1] and is expressed as a proportional quantity of

    the total conductor losses.

    The general equation for calculation of current rating (100% load factor) is:

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    16/24

    By computing this equation it can be defined , the cable conductor maximumpermissible temperature rise above the ambient in the following form:

    = (I2R + Wd) T1 + [I2R (1 + 1) + Wd] nT2 + [I

    2R (1+ 1 + 2) + Wd) n (T3 +T4)

    However in the case of a simplified cable circuit consisting of three single-corecables provided with metallic sheath and no metallic armour (2 = 0 and T3 =0)and ignoring the environmental thermal resistance (T4) the temperature risebetween conductor and cable outer surface is given with the following equation:

    = I2R [T1+ T2 (1 + 1)] + Wd (T1/2 +T2)

    Where: = temperature rise above ambient temperatureI = conductor currentR = A.C conductor resistanceWd = dielectric losses

    T1, T2 = thermal resistances of cable insulation and anticorrosion jacket of cable.

    It is seen that the Loss Factor or power loss factor 1 as generated by the

    circulating currents in cable metallic sheath is impacting on the heat crossing the

    anticorrosion jacket and soil thermal resistance before being dissipated in air.

    2.4 Special Bonding Systems

    Single core distribution power cables are normally installed with cable metallic

    sheaths or metallic copper screens solidly bonded to earth at both ends.

    However, in cases of high and extra high voltage single-core cables installed in

    flat formation the circulating currents could be as high as the current in cable

    conductors, i.e. several hundred Amps especially if the cable sheaths would be

    solidly bonded to earth at both ends.

    In order to minimise the sheath circulating currents the single-core cables are

    very often laid in close touching trefoil formation. However, as the three cables

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    17/24

    have a considerable heating effect upon one another the heat dissipation is very

    poor.

    In order to increase the rate of heat dissipation the obvious solution would be to

    increase the spacing between cables, regardless if installed in trefoil or flatformations, aspect which in return would have a direct effect of an increased

    magnitude of circulating currents. A proper balance of cable spacing must be

    identified to optimise the two effects; circulating currents and heat dissipation.

    The solid bonding system does not have a limitation impact on cable systems of

    MV of up to 33kV but with larger conductor sizes and higher voltages the impact

    is significant and alternative sheath bondedind systems need to be used.

    For particular cases of short HV cable circuits (few hundred metres) thetechnique of sheath special bonding systems involves earthing the single-core

    cable sheaths at one point only and insulating all other points of the sheath from

    earth, so that the circulating sheath losses are eliminated and the single-core

    cables can be spaced apart to reduce their mutual heating effect without

    increasing sheath losses.

    Some of the most common Single-point Bonding arrangements are as shown in

    Fig. 5

    Fig. 5: Diagrammatic representation of single-point bonding systems ofcable metallic sheaths or screens and of induced voltages

    V V V

    0 0 01

    11

    a) Sheaths earthed atone end only

    b) Sheaths earthed at theimmediate point

    c) Sheaths earthed at both endsand sectionalised at theimmediate point

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    18/24

    For long cable connections, where the cable circuits consist of a series of

    individual cable sections sequentially jointed, the cable sheaths are connected in

    different configurations including the so called cross bonding system (Fig.6)

    In this system the corresponding route length is divided in multiples of three

    length of ca Each major transposition section is formed of three individual

    sections of equal length and installed at equal and uniform spacing.

    This solution is expected to provide balanced induced voltages at a vectorial

    angle of 120of no resultant circulating current when phasorial summation was

    applied.

    Fig. 6: Cross-bonding system without cable transposition at each joint bay

    However, this is not the case, because when single-core cables are installed in

    flat formation the voltages induced in the cable sheaths of outer cables are

    higher than the induced voltage in the middle cable and the vectorial (phasor)summation is not zero. As a consequence it is not possible to eliminate the

    circulating currents in a cable circuit where only the cable sheaths are cross-

    bonded. The imbalanced phasorial voltage (Fig.7) is generating a residual

    voltage which, in return would generate circulating currents.

    A C B

    B A C

    C B A

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    19/24

    Fig. 7: Imbalanced induced voltages in a major transposition section withun-transposed minor cable sections

    When the cable sheaths of transposed cables occupying the same position in

    circuit configuration are straight connected the vectorial summation of induced

    voltage would be zero if the system would be of balanced parameters: currents,

    spacing and length (Fig.8).

    So, it is obvious that in order to significantly reduce or to eliminate the circulatingcurrent losses the cable and cable sheaths must be transposed at every joint bay

    position and the sheaths cross-connected with phase rotation in opposition to

    that of cable transposition (Fig.8). This would facilitate a direct serial connection

    of the cable sheaths of the three cable sections occupying the same position in

    cable trench along a major transposition section.

    Smaller induced voltage

    than in the 1st or 3rd

    minor section

    Imbalanced

    difference

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    20/24

    Fig. 8: Typical diagram of cross-bonding system with cable transposition

    By connecting in series the cable sheath of the three phases (120 phasor

    displacement) the circulating currents could be eliminated; the phasor sum of

    induced voltages could be zero if the geometrical data of cable circuit is uniform

    along the three cable sections.

    However, it is evident that in practice the circulating currents can not be totally

    eliminated. There would be all sorts of site limiting conditions to install the cable

    sections at equal spacing and equal length and as consequence a loss factor - 1

    in range of 3% for direct buried cable circuits and 5% for cable in ducts are

    considered realistic figures (IEC 60287). Even larger losses may be tolerated

    based on client acceptance of higher losses balanced against capital expenditure.

    A B

    O = C

    UB

    UCUA

    Fig. 9: Balanced induced voltage along three consecutivecable sheaths occupying the same position in cable trench

    O C

    A BUAB

    UBCUOA

    A B C

    R

    Y

    B

    R

    Y

    B

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    21/24

    The sheath currents and the induced voltages vary as a function of bonding

    system, as follows:

    i. Solid-bonded cable sheaths (earthing at both ends)

    The circulating currents consume the induced voltages and as aconsequence the entire cable sheath is at ground potential. The generated

    heat reduces the cable rating

    ii. Single-point bonding

    The cable sheaths are subjected to a standing voltage varying between

    earth potential at grounding point and maximum induced magnitude at

    isolated (remote or mid-point) end of cable section

    iii. Cross-bonding

    The maximum induced voltage in respect to earth depends on the position

    of each minor transposition section within the major transposition section.

    At the ends of major transposition sections the cable sheaths are at earth

    potential while at all other points along the cable the voltage is

    proportional to cable length in respect to earthing points or, for the median

    (2nd) minor section, of measuring point in respect to the other two minor

    sections.

    The maximum induced voltage amplitude is generally accepted as 150V.

    In special circumstances it could be as high as 250V provided that the

    bonding system of cable circuit is properly designed to satisfy the

    insulation coordination and safety requirements. Nevertheless there are

    examples of cable installations where the induced standing voltage could

    be as high as 400V.

    The special bonding system requires that the metallic sheaths and cable

    accessories (joints, terminations and connections to CMS condition monitoringsystem) are electrically insulated with respect to earth (radial direction) and

    between two adjacent cable sections (longitudinal direction).

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    22/24

    The cross-bonding of cable sheaths is made in specially designed boxes,

    generically denominated Link Boxes where the incoming bonding leads (single-

    core or concentric conductor cables) are cross-connected.

    Concentric bonding leads between link boxes and power cable joints aredesigned to minimise the surge impedance between cable sheaths and SVL

    protecting the bonding system.

    The link boxes are equipped with sheath voltage limiters (SVL) designed to

    protect the cable outer sheath (anticorrosion jacket), insulating flanges and

    barriers in cable accessories and all other insulating components of bonding

    system, against transient voltages propagated along the cable system.

    The effect of specially bonding systems is visible when comparing the cablerating of cables installed in solid and cross-bonded systems.

    The current rating of cable system of 132kV and above could be up to 50%

    higher for specially bonded cable circuits. The rating is influenced by the

    following three factors:

    Reduction of circulation currents

    Increased spacing between single-core cables with direct response of

    improved heat dissipation

    Reduction of eddy current losses with the increase of cable spacing

    However it is recognised that the specially bonding system increases the capital

    and running (maintenance) costs of the cable system. The cost of the bonding

    system for an average 220kV cable system could be in range of 1 to 1.5% of

    material cost for cable and accessories.

    Nevertheless these costs are compensated by savings in cable size and the

    number of accessories dependent of the length of cable sections (bigger cable =

    shorter length) installed in the system and the maintenance costs could be

    reduced by acquisition of reliable cable bonding system including cable outer

    jacket, joints (insulating barriers), bonding leads, link boxes and sheath voltage

    limiters (SVL).

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    23/24

    Fig.10: Cross Bonding Link Box (LB)

    The periodical maintenance of a reliable bonding system may be performed on a

    three-year basis and even longer periods, depending on local environment and

    statistical evaluation of accumulated maintenance data.

    3 Conclusions and Observations

    The basic factors influencing the current rating capacity of underground (U/G)

    power cable systems is govern by three major factors:

    a) Cable construction: conductor size, physical dimensions and quality of

    materials

    b) Installation particulars: single-core cable configuration and spacing,bonding of cable metallic sheaths, proximity to other utilities, thermal

    influencing factors and burial depth

    c) Environmental parameters: air and soil temperature and thermal

    characteristics of soil and of bedding and backfilling materials

    Sheath

    VoltageLimiters

    (SVL)

    Post

    insulators

  • 7/29/2019 R01 HMR Connection to 220kV Main Grid Undergrounding Study Attachment1 Appendix5and6

    24/24

    Note:The a) and b) factors are responsible for the magnitude of electrical losses

    which, in return, are impacting on current rating of cable system

    The calculation of losses and current carrying capacity are based on well

    established international standards (IEC 60287 and IEC 60853) or nationalstandards.However, as the fine details of cable construction are very specific to each cabletype produced by each manufacturer, an accurate calculation of losses and ofcurrent rating are performed exclusively by cable suppliers using personalisedcomputer programs and softwaresIn order to verify the accuracy of cable rating and magnitude of losses the cablemanufacturers carry out full scale trial experiments simulating hypotheticalinstallation and loading conditions.

    4 Bibliograpfyi. Rating of Electric Power Cables Ampacity Computation for Transmission,

    Distribution and Industrial Applications. IEEE Press Power Engineering byGEORGE J. ANDERS

    ii. Electric Cables Handbook BICC Cables, by G.F. MOOREiii. Underground Transmission Systems Power Technologies Inc. (J.A.

    Williams) & EPRI (RW Samm).iv. IEC 60287 Electric cables Calculation Part 1: Continuous rating

    equations (100% load factor)and calculation of losses