Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

25
Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University

Transcript of Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Page 1: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Quantity Take Off

Dr. Ayman A. Abu Hammad

Applied Science University

Page 2: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Topical Overview

• Chapter 1: Site Preparation• Chapter 2: Soil and Site Exploration• Chapter 3: Excavation• Chapter 4: Foundations Work• Chapter 5: Wood Formwork• Chapter 6: Steel Rebar• Chapter 7: Concrete• Chapter 8: Building structures• Chapter 9: Walls Construction• Chapter 10: Brick Works• Chapter 11: Masonry (Stone) • Chapter 12: Stair Wells

Page 3: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Finishing

Civil Works

Floor X

Planning:ScheduleProject teamSubcontractorsSuppliersSubmittalsworkforceSite electricity, access roads, phone line, water, heatCars

Mobilization:Site offices

Off. furnitureComputer, phone,

Workers residenceCement-agg.-rebar

Sto.Tools & equip.Security fence

Notice toproceed

Letter of intent

Foundations center lines

Excavation:1- Bulk Exc.2- Trimming

Foundations rebar fabrication

Blinding forms- cast

RC foundations forms- rebar

Foundations RC cast

Found. Wall forms- rebar

Found. wall cast

Compacted backfill

Floor on grade: rebar-

cast

Columns forms- rebar

Slab # 1 forms- rebar

Masonry

Slab # 1 cast Cast column & walls

Side walks

2- Weeks

Retaining Walls, fence

RC walls: forms-rebar

cast

Dismantle slab 1 forms

2-3-4…

Partition walls- block

work

E&M rough

Plaster

Tile

Doors-wind.

Paint

Page 4: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Rebar Take-off Rules• Steel diameters are:

– 8, 10, 12, 14, 16, 18mm….• Rebar Standard Lengths are:

– 4, 5, 6, 7, 12m.• Overlap standard distance is= 40*max Diameter for tension, 50*max Diameter for

compression.• Cover distance = 0.005m in foundations only and 0.025m otherwise.• Stirrup key is 0.1 *2= 0.2m• Rebar order format is as follows:

– Calculated Number Ø Standard Diameter/ Standard Length• Rebar volume is negligible in concrete quantity take-off.• AGGREGATE REBAR DATA FOR SIMILAR DIAMETERS AND LENGTHS ONLY!• FOR TONNAGE ESTIMATION MULTIPLY THE NUMBER BY THE LENGTH BY THE

UNIT WEIGHT OF BAR.• SHOULD TRANSLATE TAKE-OFF NUMBERS ON THE A-CADS.• Rebar Steps:

– Foundations: Strip, Isolated, Tie beams, FW– Floors, Columns, Walls, Retaining Walls, lintels– Slabs: P Beams, S Beams, Double Rib, Wall Beams, Ribs

Page 5: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

3.5m

0.35m 7 D14mm/1m

Wall height=3m

5D16mm/1m

4 D12mm/1m

5 D14mm/1m

0.4m0.25m0.4m 0.25m4.8m

Page 6: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

3.5mx4.5mx3m interior dim. Reservoir

• Foundation:– Stirrups: – [(4.8-0.05)*2]+[(0.35-0.05)*2]+0.2= 10.3m– Res. Length=4.5+0.65+0.65=5.8m– [5.8*5]+1= 29 +1=30 stirrup– 30D16/5m+30D16/6m– Longitudinal:

• Top bars= 4.8*7= 34 bar, length= 4.5+0.65+0.65=5.8m 6m• 68D14/6m

• Walls:– Vertical:

• length= 2.95m+0.35+0.20= 3.5m• Wall perimeter={2*(3.5+[0.25 C-C])}+{2*(4.5+[0.25C-C])}= 17m• Number of longitudinal bars= 17m*8bars per meter= 136 bar• 136D12/7m

– Longitudinal:• Short wall length= 3.5+(0.25*2)= 4m• Long wall length= 4.5+(0.25*2)= 5m• Number of longitudinal bars= 3m*10*2= 60• 120D14/4m• 120D14/5m

6m 5m

Overlap=40*max diam.= 0.64m

0.64

Page 7: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Concrete for Water ReservoirConcrete of Foundations L W H volume

Water reservoir

Blinding 5.0 6.0 0.1 3.0

RC 4.8 5.8 0.35 9.7

Walls 17.0 0.3 3.0 12.8

Rebar of foundation

w ater reserv LengthCount

foundation stirrups 10.3 6m 29.0 29Q16/6

5m 29.0 29Q16/5

foundation longitudinal12.3 6m 34.0 34Q14/6

7m 34.0 34Q14/7

Walls vertical rebar 17.00 3.65 136 136Q12/4 68Q12/7

Wall longitudinal rebar 4m 60 60Q14/4

5m 60 60Q14/5

Page 8: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Isolated Foundation 2.5m*3m*0.45m &

Column0.25m*0.6m. FWH=1.3m• Stirrups:

– (2*[(2.5-0.05)+(0.45-0.05)])+0.2= 5.9m6m

– Number of stirrups= 3m*5stirrups per meter= 15+1=16

– 16D16/6m• Longitudinal:

– (2*[(3.00-0.05)+(0.45-0.05)*2])+0.2= 6.9m7m

– Number of stirrups= 2.5m*7stirrups per meter= 18

– 17D14/7m• Column C1:

– Column Dowels: length=1.3+0.45+0.3+(overlap=40*16mm=0.65m)= 2.70m 3m8D16mm/3m 4D16mm/6m

– C1 above FL= 3.12(12 stones height)+0.3(slab)+0.64(overlap)= 4m 8D16/4m

0.45m 7 D14mm/1m

Wall height=1.3m5D16mm/1m

8D16mm

7D8mm/1m

1.125m 0.25m2.5m

1.125m

0.65 overlap

Page 9: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Civil Drawings (Foundations Drawings)

1

A

Page 10: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Civil Drawings (Foundations Drawings)

1

A

f1c1f1c1TB

TB TB

TBTB

TB

Page 11: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Civil Drawings (Foundations Drawings) 1

A

f1c1f1c1TB

TB TB

TBTB

TB

S1-1

S1-1 S1-1

S1-1S2-2

S2-2

S2-2

S2-2

S2-2

S3-3

S3-3

TB TB

4.00

9.50

13m 3.7

5m

4.6

3

9.56

63

57

5

5

7 7 5

3

3.5

3.5

44

Page 12: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Strip Footings

1.4

0.50 10*12mm5*14mm/1m

0.10

S1-1 (Stair Case)

0.100.10

0.2

1.6

0.60

0.10

S2-2 (Stone)

0.100.10

0.3

6*16mm/1m

12*14mm

5Q12/1m0.40

1m

0.50 6*12mm

5*12mm/1m

0.10

S3-3 (Balcony)

0.100.10

0.2

Page 13: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Strip foundations Rebar S1-S1

• S1-S1: 2 strips /6m& 2 strips/ 3m=3 strips length 6m– Stirrup length: [(1.4 -0.05)*2+(0.5-0.05)*2] +

0.2= 3.80= 4.00m– Stirrup count (compute length of foundation

center to center): [(6m-1.4)*2+ (3-1.4)*2]=12m

Count= 12*5 stirrups/m= 60

60Q12/4m– Longitudinal rebar: 3*10 Q12/6= 30Q12/6m

Page 14: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

S2-S2• Longitudinal Rebar:

– 1 strip of length 4m• 2Q12/4• 12Q14/4

– 3 strips of length = 5m• 2*3stripsQ12/5= 6Q12/5• 12*3stripsQ14/5= 36Q14/5

– 4 strips of length 7m• 2*4Q12/7= 8Q12/7• 12*4Q14/7= 48Q14/7

• Stirrups:1) [(1.6-0.05)*2+(0.6-0.05)*2]+0.2= 5m2) [(1-0.05)*2+(0.3-0.05)*2)]+0.2= 2.6= 3– S1-S1 length Center to center= 38m

• 1) 38*6Q16/5= 228Q16/5m• 2) 38*5Q12/3= 190Q12/3= 95Q12/6

1.6

0.60

0.10

S2-2 (Stone)

0.100.10

0.3

6*16mm/1m

12*14mm

5Q12/1m0.40

Page 15: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Square Isolated Footings

2.6m

0.60

0.10

F1

0.100.10

0.3

6*16mm/1m two way

0.60

0.30

5*12mm/1m

6*12mm

Tie Beam TB

0.30

5*8mm/1m

6*16mm

C10.60

0.20

5*8mm/1m

6*14mm

CW10.50

3.2m1.3m

Page 16: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Concrete of Foundations L W H volumeWater reservoir Subtotal

Blinding 5 6 0.1 3RC 4.8 5.8 0.35 9.7Walls 17 0.3 3 12.8

Isolated F1 blinding 3.4 2.8 0.1 0.952RC 2.6 3.2 0.6 4.992FW 0.3 0.6 1.3 0.234

Strip blinding 1-1 12.4 1.6 0.1 1.984blinding 2-2 39.3 1.8 0.1 7.074blinding 3-3 7.7 1.2 0.1 0.924

S1-S1 12.4 1.4 0.5 8.68S2-S2 39.3 1.6 0.6 37.728S3-S3 7.7 1 0.5 3.85FW 59.4 0.3 1.3 23.166

TB blinding 15.4 0.5 0.1 0.77TB 15.4 0.3 0.6 2.772

Columns 2 0.3 0.6 3.12 1.1232Slab Volumerib block count1 block volumeblock volumeConcrete volume

Slab 39 273 0.01848 5.04504 33.95496Blinding 15 14.704RC 25 137.877

Page 17: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Civil Drawings (Roof Drawings) 4

B1 B1 B1 B1

B2

B2

B2

B3 B3

SBSB

SB

SB

SB

SB

SB

SB

SB SB

0.2014-18-24

40

SB

SBB2

2*12

/3m

2*10

2*10

2*10

DRDR

CR

B110*16/42*18/77*16/54*14/12

6*16/6B2

12*16/48*16/78*14/58*14/6

B38*18/84*14/63*14/6

Page 18: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

3*18/3.5m 5*16/4m5*16 8*16 4*163*14 6*16 4*14

3m 5m 5.5m 2.5m

5*16/2.5m4*16

1.00m0.3

4*145*16

2*8/20cm

B1 (1:15)B1 (1:100)

Roof Details

4*16

4*14

5 .m 4m

6*16/4m4*16

1.00m

0.34*14

6*162*8/20cm

B2 (1:15)B2 (1:100)

4*14

5 .m 2.5m

8*18/8

1.00m

0.34*14

6*162*8/20cm

B3 (1:15)B3 (1:100)

6*14

0.30m0.3 6*16

*8/20cm

SB (1:15)

0.30m0.3 4*16

*8/20cm

DR&CR (1:15)

B110*16/42*18/77*16/54*14/12

6*16/6B2

12*16/48*16/78*14/58*14/6

B38*18/84*14/63*14/6

Page 19: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Slab Rebar

Upper5Q16/3 5Q16/6 4Q14/3 2Q14/6 6Q14/63Q18/2.5 2Q18/5 4Q14/6 4Q14/6 6Q16/68Q16/3.5 7Q16/7 6Q16/6 6Q16/6 2Q14/75Q16/3.5 3Q14/6 3Q14/3.5 2Q14/74Q16/3 2Q16/55Q14/34Q16/2.5

Lower

5Q16 8Q16

3Q146Q16 4Q14

3m 5 5.5m 2.5m

B1 (1:100)

2.5+0.1-0.9+0.64=2.35==2.55.5-1.85-1.9+0.64+0.64=35-1.5-1.5+0.64+0.64=3.3==3.5

0.30.30.80.70.3 2.5+0.1+.15=2.75==3

5.5+0.15+0.4=6

4Q14

5+0.4+0.35=5.75==63+0.1+0.35=3.45==3.5

Page 20: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

3.7 4.35 2.9

3.00

1.1

5.0

3.5 2.52.5

Page 21: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Masonry Types:

• Zawyah: 1 Lm per piece• Silah: Araqa & Kalb: 1 Lm per piece• Dustour: 2 Lm per piece• Marabee’: 4 Lm per piece• Roukh: 1 Lm per piece• Arch: 3 Lm per piece• Balcony: each 1 Lm is taken as 2 Lm• Burtash: each 1 Lm is taken as 4 Lm

Page 22: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

1.00 1.00 1.00 1.001.001.001.002.00 0.50

Page 23: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Masonry Take off

• Regular Masonry Take Off:– 4*(9.5-[1+4*0.25])= 30 LM– 10 (9.5-[5+10*0.25]= 20 LM– 2(9.5-[5+2*0.25]= 8 LM– 11(9.5-[2*0.25]= 99 LM

• Masonry Pieces Take Off:– Lintels (Burtash)= 2*(2.2) + 6*(1.20) = 4.4+7.2= 11.60

LM– Corner Stones= 27*2= 54– Opening corner stone= (10*7)+18= 88

Page 24: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Quantity Takeoff: Steel Estimating

• Steel bar standard diameters: 8mm, 10mm, 12mm, 14, 16, 18, 20, 32

• Steel bar standard lengths: 4, 5, 6, 7, 12• Steel overlapping follow rule 40 * Q

– If you have two bars of 10mm and 16mm, find the overlap distance?

– Select the higher diameter and multiply with 40= 16*40=640=64cm

• Distinguish between different types of steel

Page 25: Quantity Take Off Dr. Ayman A. Abu Hammad Applied Science University.

Working Example: Bathroom Quantity & Pricing:

Given information:• 3.6*2*3• Window: 0.7*1.00• Door: 0.8*2.1• Bath tub: 0.7*

• Ceramic:– Ceramic Floor: 2.9*2= 6m2

– walls: 11.2*3= 33.6 (33.6-[0.7+(0.8*2.1)])= 31.2 +2.7*0.15= 0.405 31.2+0.405= 31.6 Plaster quantity– Ceramic walls quantity= 31.6-0.7= 30.9m2

• Ceramic labor cost– 12KD for blinding= 12KD– 20KD*3days= 60KD– Joint filling: 1*12KD skilled rate= 12KD

• Ceramic material cost= 3KD/m2 *37m2= 111KD• Total Cost= 111+12+60+12= 195KD• Plaster:= 31.6m2

• Plaster material (fine aggregate) cost= 31.6*0.02*1.1= 0.7m2 *2KD= 1.4KD• Plaster cement cost (1:3 means 10 cement bags per m3)= 7bags* 1.350= 9.450• Labor cost:2days*20KD=40KD• Total cost= 1.4+9.5+ 40= 51KD•