QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a...

38
QBS CONSTRUCTION WLL COMPANY PROFILE

Transcript of QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a...

Page 1: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE

Page 2: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE

- 2 -

CONTENTSFORWARD

CONFIDENTIALITY

PART 1: PROFILE

INTRODUCTION CORPORATE OVERVIEWAFFILIATE SUPPORTORGANIZATIONAL OVERVIEWQHSESERVICESCORPORATE COMPLIANCE

PART 2: TECHNICAL STRENGTH

PLANT AND EQUIPMENTHUMAN CAPITAL

PART 3: EXPERIENCE

PROJECTSREFERENCES

Page 3: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE

- I -

FOREWARD

CONFIDENTIALITY

QBS Construction WLL (QBS), a company organized under the laws of the State of Qatar, and a member of the QBS International group of companies, is pleased to present you this Company Profile.

This Company Profile is divided into three parts that, altogether, should provide you an overall picture of QBS’s technical qualifications.

The first part, PROFILE, provides a corporate overview of QBS along with a description of QBS’s various areas of competency. The applicable corporate compliance documentation as well as our organization’s organogram are also provided in this part.

The second part, TECHNICAL STRENGTH, provides a general audit of QBS’s plant and equipment from which required resources can be mobilized for local projects.

The third and final part, EXPERIENCE, includes a list of projects in which members of our team have been involved showcasing our broad experience in various areas of infrastructure development.

The information contained herein is strictly confidential and is supplied on the understanding that it will be held confidentially and not disclosed to third parties without the prior written consent of an authorized principal of QBS.

Page 4: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 1

- 1 -

PROFILEINTRODUCTION

The QBS International group of companies is a specialized design-build firm headquartered in Pennsauken, New Jersey, USA and one of the leading specialists in delivering medium scale infrastructure projects.

With an international track record of diversified projects ranging from highways and infrastructure, road works, bridges, tunnels, airports, marine ports, dams and retention ponds to health care facilities, residential and commercial development projects spanning over 3 continents, QBS brings to any project a wealth of engineering experience and construction expertise forged in diverse jurisdictions from the United States to the United Arab Emirates.

Notwithstanding our size and global reach, QBS is a hands on organization. Everyone on our teams willingly gets “into the trenches” to get the job done properly and fulfill the mission upon which our group of companies was founded; to deliver....

Quality....within Budget....on Schedule...QBS.

QBS was set up as a local company in the State of Qatar in 2008. In this short period we have been fortunate to secure work under contract worth over a billion Qatari Riyals and are currently in the process of expanding our local operations to meet the increasing demand in this region for qualified local contractors.

QBS is qualified as a Grade A contractor with the Public Works Ministry and has been approved by the PWA’s Street Lighting Department and by Kahramaa for hydro-electric works.

Page 5: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 1

- 2 -

CORPORATE OVERVIEW

The QBS International group of companies operates in three different continents under different corporate structures with varying local strategic partnerships.

In Qatar, our partner is Sheikh Ali bin Hamad Al-Thani, the President and Chairman of HBK Contracting Co WLL. Through this partnership, we have combined our global infrastructure development experience with HBK’s longstanding local market expertise and influence.

AFFILIATE SUPPORT

QBS Construction (QBS) has established independent affiliated companies to carry on specialized infrastructure construction works under the same mission and ethos that has driven QBS’s global success. These businesses operate independently of QBS under the guidance of the QBS International Steering Committee and with the advantage of sharing the ISO certified support backbone and integrated quality management system that powers QBS’s infrastructure construction operations in Qatar. These specialized businesses include:

ENTITY SUBSPECIALTY

Fullbore Drilling and Lining Microtunneling

Hummingbird Landscaping and Irrigation Hard and Soft Landscaping

Polaris Trading and Contracting Mechanical, Electrical and Plumbing Works

Quality Asphalt Products Asphalt Production and Laying

Qoncrete Precast and Readymix Plant

Toprok Aggregate Production and Mixing

Page 6: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 1

- 3 -

ORGANIZATIONAL OVERVIEW

QBS is constantly reassessing its managerial structure to ensure that project and product delivery is achieved according to our QBS mission. Below is a diagram showing our current management structure.

AUTHORISED BY: OSAMA CHAABANDRAWN BY: ALEN PAUL RENNIE

ORGANIZATIONAL DIAGRAM

DOCUMENT NUMBER: 00023 – VER. 7 : 01OCTOBER20172017 © QBS INTERNATIONAL WLL. ALL RIGHTS RESERVED

TECHNICAL DEPARTMENTQUALITY BASED STRUCTURES WLL

MANAGEMENT

PRODUCTION DIVISIONDIVISIONAL MANAGER

PROCUREMENT DEPTPROCUREMENT MANAGER

QUALITY DEPTQA MANAGER

HSE DEPARTMENTHSE MANAGER

PLANNING DEPTPLANNING MANAGER

ENGINEERING DEPTENGINEERING MGR.

LOGISTICS DEPARTMENTLOGISTICS MANAGER

COMMERCIAL DEPTCOMMERCIAL MANAGER

DC DEPARTMENTDC MANAGER

QSE DEPARTMENTQSE MANAGER

ADMIN DEPARTMENTADMIN MANAGER

FINANCE DEPARTMENTFINANCIAL CONTROLLER

OPERATIONS DIVISIONOPERATIONS MANAGER

PROJECTS DIVISIONPROJECTS DIRECTOR

HR DEPARTMENTHR MANAGER

INFORMATION TECH.& SYSTEMS

MARKETING BRANDBUSINESS DEVELOPMENT

OFFICEADMINISTRATION

EXECUTIVEDEPUTY MANAGING DIRECTOR

PURCHASINGPURCHASING MANAGER

PMV PMV MANAGER

QUALITY ASPHALTPRODUCTS

PLANT MANAGER

ASPHALT TEAMSR. ASPHALT FOREMAN

ASPHALT PRODUCTIONDEPUTY PLANT MANAGER

TOPROK WLLAGGREGATES PRODUCTION

PLANT MANAGER

QONCRETE WLLREADYMIX & PRE-CAST

PLANT MANAGER

GARAGE SR. MECHANIC

WORKSHOP SR. FABRICATOR

EQUIPMENT HIRE

TRANSPORT DEPARTMENT TRANSPORT FOREMAN

PMV DEPUTY PMV MANAGER

EXECUTIVEMANAGING DIRECTOR

Page 7: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 1

- 4 -

QHSE

Quality is in our name and part of our mission; with every task we execute it is our point of departure and ultimate destination. Arriving at this destination on time and within budget, safely and with minimum environmental impact is how we measure success at QBS.

Given the primacy of Quality and HSE in everything we do, our management system is designed to ensure that the QHSE function is independent from the operation and production side of the of the business. A member of the Steering Committee is charged with ultimate responsibility for our corporate-wide QHSE program and the reporting lines within the QHSE team run independently of those estabished in our operation. The intent is not to create a separate policing body, as enforcement of our QHSE policies, plans and procedures are everyone’s responsibility, but rather to ensure that QHSE considerations are analyzed and resolved by a specialized team independent of other considerations and influences.

QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture. This program and all the processes and procedures that have been implemented to effect our corporate QHSE policies are subject to regular oversight and audit.

QBS’s Quality and HSE management system are certified compliant with ISO 9001:2015, ISO 14001: 2015 and OHSAS 18001: 2007 by Bureau Veritas.

Page 8: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 1

- 5 -

QHSE

Page 9: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 1

- 6 -

QHSE

Page 10: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 1

- 7 -

SERVICES

QBS and its affiliates provide a full array of integrated infrastructure construction services related to the construction of Highways, Bridges, Tunnels and Roads, including:

• Excavation and Earth Moving Works• Utilities and Underground Services• Stormwater and Drainage• Microtunneling and Pipe Jacking• MEP Works• Stone pitching and Riprap• Hard and Soft landscaping• Irrigation Network Installations• Street furniture and Park Equipment Installation• Asphalt Production and Laying• Aggregate Production and Mixing• Ready Mix and Pre-Cast• Material Transport

Page 11: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 1

- 8 -

<Bar Code>

Page 1 of 2رقم السجل : 39326

تشهد غرفة تجارة و صناعة قطر بان المنشاة المذكورة اعاله سجلت لديناQatar Chamber certifies that the above mentioned establishment has been registered

تاريخ الطباعة: 2019/04/17مستخرج ببعض بيانات السجل التجرى

*39326*

39326رقم التسجيل الضريبي:39326رقم السجل التجارى: كيو بي اس كونستركشنالسمة التجارية: كيو بي اس كونستركشناألسم التجارى:

26/05/2020تاريخ انتهاء السجل: 27/05/2008تاريخ انشاء السجل:18000000راس المال:شركة ذات مسئولية محدودةالشكل القانونى:

قطرجنسية المنشأة:نشط حالة السجل:0عدد الفروع:

معلومات االتصال44214672+أرقام االتصال:37082صندوق البريد:

الشركاء

الحالةالنسبةالجنسيةرقم السجلرقم اإلثباتاألسمنشط 99.95قطر60340كواليتى بيسد ستركشرز

نشط 0.05لبنان1806710كواليتي بيسد ستركشرز ش.م.ل اوف شور

المدراء (المخولون بالتوقيع)

الصفة (الصالحية)الجنسيةرقم السجلرقم اإلثباتاألسم صالحيات كاملة ومطلقة - مديرلبنان27042200482اسامه محمود شعبان

مستخرج ببعض بيانات السجل التجارى

CORPORATE COMPLIANCE

Page 12: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 1

- 9 -

<Bar Code>

Page 2 of 2رقم السجل : 39326

تشهد غرفة تجارة و صناعة قطر بان المنشاة المذكورة اعاله سجلت لديناQatar Chamber certifies that the above mentioned establishment has been registered

صالحيات كاملة ومطلقة - مديرالواليات المتحدة27384000420حسام شابان صالحيات كاملة ومطلقة - مديرقطر25863400011الشيخ على حمد خالد احمد ال ثانى

األنشطة التجارية

إسم النشاطالرقممقاوالت عامة للمباني (االنشاات العامة للمبانى)452100

مقاوالت انشاء الطرق2000856القيام بإعمال البنية التحتية2002781مقاوالت الحفر والدفان452120

اعمال تركيب المعدات الكهروميكانيكية وصيانتها2000882مقاوالت انشاء الموانئ واالنشاءات البحرية2000873التجاره فى االليات والمعدات (جرافات - اوناش - 501900

[...تجارة اطارات السيارات2001388التجارة في الغراء بجميع انواعه536543التجاره فى االصباغ والدهانات537400

إسم النشاطالرقممقاوالت انشاء الجسور والكبارى452180مقاوالت رصف و تمهيد الطرق453120اعمال كهربائيه(تجهيزات كهربائيه)مثل تمديد االسالك و 457060

عمل الوصالت و ... واصالحهاالمقاوالت العامة لالنشاءات المدنية2000848مقاوالت انشاء مطارات453140

التجارة في مواد البناء4752801التجارة في قطع غيار االالت والمعدات الثقيلة4773881التجارة في االدوات الكهربائية4752501تجارة الرمل والحصى واحجار البناء2002077

مستخرج ببعض بيانات السجل التجارى

CORPORATE COMPLIANCE

Page 13: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 1

- 10 -

CORPORATE COMPLIANCE

Page 14: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 1

- 11 -

CORPORATE COMPLIANCE

Page 15: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 1

- 12 -

مدير إدارة التسجيل والتراخيص التجارية

<Bar Code>2019/04/17 تاريخ الطباعة:

No 1 of 2 صفحة رقم:

رخصة تجارية

*64061*

2014/08/14تاريخ اصدار الرخصة:64061رقم الرخصة:2020/05/23تاريخ انتهاء الرخصة: كيو بي اس كونستركشناألسم التجارى:

39326رقم السجل التجارى:شركةنوع المنشأة التجارية: كيو بي اس كونستركشنالسمة التجارية:

بيانات المدير المسؤول :

الشيخ على حمد خالد احمد ال ثانىاسم المدير المسئول:

قطرجنسية المدير المسئول:25863400011رقم اإلثبات:

نموذج ختم المنشأة التجارية :بيانات الموقع :143عقار رقم:تجاريتصنيف الموقع:

1رقم الدور/ الوحدة:مكتب تجارينوع الموقع:

الشيخ/ عبدالله عبدالرحمناسم مالك العقار :36 المسيلةالمنطقة:حمد آل ثاني

نوع الرخصة :الجزيرة العربية الشارع:بلدية الدوحة / الدور ( 1 )وصف العنوان :362رقم الشارع :

:التجاريةاألنشطة

إسم النشاطالنشاطرقممقاوالت عامة للمباني (االنشاات 452100

العامة للمبانى)مقاوالت انشاء الطرق2000856القيام بإعمال البنية التحتية2002781مقاوالت الحفر والدفان452120

اعمال تركيب المعدات 2000882الكهروميكانيكية وصيانتها

إسم النشاطرقم النشاطمقاوالت انشاء الجسور والكبارى452180مقاوالت رصف و تمهيد الطرق453120اعمال كهربائيه(تجهيزات 457060

كهربائيه)مثل تمديد االسالك و عمل الوصالت و ... واصالحها

المقاوالت العامة لالنشاءات المدنية2000848مقاوالت انشاء مطارات453140

CORPORATE COMPLIANCE

Page 16: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 1

- 13 -

مدير إدارة التسجيل والتراخيص التجارية

مقاوالت انشاء الموانئ واالنشاءات 2000873البحرية

التجاره فى االليات والمعدات (جرافات501900- اوناش - ...]

تجارة اطارات السيارات2001388التجارة في الغراء بجميع انواعه536543التجاره فى االصباغ والدهانات537400

التجارة في مواد البناء4752801التجارة في قطع غيار االالت 4773881

والمعدات الثقيلةالتجارة في االدوات الكهربائية4752501تجارة الرمل والحصى واحجار البناء2002077

CORPORATE COMPLIANCE

Page 17: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 1

- 14 -

CORPORATE COMPLIANCE

Page 18: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 1

- 15 -

CORPORATE COMPLIANCE

Page 19: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 1

- 16 -

CORPORATE COMPLIANCE

Page 20: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 1

- 17 -

AUTHORIZED SIGNATORIES QATAR ID SHIEKH ALI HAMAD K A AL-THANI HUSSAM SHAABAN

OSAMA CHAABAN

AUTHORIZED SIGNATORIES

CORPORATE COMPLIANCE

Page 21: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 2

- 1 -

TECHNICAL STRENGTHPLANT AND EQUIPMENT

PLANT NUMBER TYPE

Aggregate Processing Facility 3 GIPO, McCloskey

Asphalt Plant 1 Benninghoven ECO 3000 U

Precast Plant 1 NA

Interlock Paver and Kerb Plant 1 Hess 1500 3VA

Concrete Batching Plant 1 Imer Italy, 72-78 cbm/hr

Page 22: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 2

- 2 -

EQUIPMENT NUMBER MODEL/MAKE

Excavators - 20 Ton 48 Caterpillar

Excavators - 30 Ton 7 Caterpillar, Case

Excavators - 45 Ton 13 Caterpillar

Excavator - Tire 18 Caterpillar

Excavators - Mini 13 Caterpillar, Bobcat

Rock Breakers 70 Montabert

Rock Breakers 5 Atlas Copco

Drum Cutters 9 Erkat, Rockweel

Bulldozers 5 Caterpillar

Graders 8 Caterpillar

Single Drum Rollers 8 HAMM, Bomag

Wheel Loaders 14 Caterpillar

Backhoe Loaders 7 JCB

Backhoe Loaders 25 Caterpillar

Tele Handlers 5 Caterpillar

Skid Loaders 6 Case

Skid Loaders 7 Caterpillar

Skid Loaders 2 Bobcat

Forklifts 3 Caterpillar

Milling Machines / Cold Plane 3 Wirtgen

Feeders 2 Vogele

Wheel Pavers 4 Vogele

Chain Pavers 3 Vogele, Bomag

Tandem Rollers 8 HAMM

Tire Rollers 14 HAMM

Page 23: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 2

- 3 -

EQUIPMENT NUMBER MODEL/MAKE

Tipper Trucks 28 MAN

Tipping Trailer 20 ALAM, Mammut, Gorica

Tractor Heads 23 MAN

Low Beds 1 80 Ton

Low Beds 1 120 Ton

Compressors 4 Ingersoll Rand

Compressors 3 A/Copco

Dewatering Pumps 6 Robin

Dewatering Pumps 1 Lowara

Dewatering Pumps 4 HCP

Page 24: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 2

- 4 -

EQUIPMENT NUMBER MODEL/MAKE

Mobile Cranes 1 Mobile -P&H 20 ton

Mobile Cranes 1 TEREX 65 ton

Mobile Cranes 1 Mobile - Krupp 80 ton

Mobile Cranes 4 Truck Mounted Crane

Water Tanker 20 JAC - 3200 Gallons

Sewage Tanker 4 JAC - 4000 Gallons

Pickups 37 Mitsubishi, Toyota, Ford

Buses 8 TATA (60 Seater)

Mini Buses 3 Mitsubishi

Mini Buses 3 Toyota

Mini Buses 1 TATA (30 Seater)

Mini Buses 4 Nissan

Page 25: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 2

- 5 -

HUMAN CAPITAL

POSITION NUMBER

Heads of Department 14

Plant Manager 2

Project Managers 5

Deputy Project Manager 4

Construction Manager 8

Project Engineer 7

Site Engineer 19

MEP Manager 1

MEP Engineer 3

Planning Engineer 6

QA/QC Engineer 7

Electrical Engineer 4

Material Engineer 12

Safety Engineer 3

Safety Officer 10

Survey Engineer 14

Land Surveyor 29

Quantity Surveyor 13

Page 26: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 2

- 6 -

POSITION NUMBER

Draftsman 15

Executive Secretary 2

Administrative Secretary 8

Project Secretary 3

Document Controller 11

POSITION NUMBER

Accountant 12

Audit Accountant 1

Storekeeper 4

Procurement Officer 5

HR Coordinator 6

Campboss 4

Public Relations Officer 3

Nurse 5

Timekeeper 7

Lab Technician 6

General Foreman 11

Civil Foreman 10

Mechanical Foreman 7

Earthwork Foreman 8

Asphalt Foreman 5

Page 27: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 2

- 7 -

POSITION NUMBER

Guageman 5

Rakeman 25

Concrete Foreman 6

Crusher Foreman 3

Chargehand 24

Transport Coordinator 3

Logistic Clerk 2

Lightduty Driver 28

Heavyduty Driver 64

PMV Operators 148

Mechanic / Asst. Mechanic / Tireman 10

Workshop Staff 14

Pipe Fitter / Mechnical Fitter 18

Steel Fixer 24

Plumber 21

Welder 28

Carpenter 336

Mason 348

Labor 1102

Watchman 12

Officeboy / Cleaner / Cook 18

Page 28: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 3

- 1 -

PROJECTSEXPERIENCE

PROJECT PROFILE OWNER/CLIENT VALUE(QAR MILLIONS)

Road and Infrastructure of Government Residential Division Project in South Wukair - Packages 2, 3 and 4 (Interim Measures - P08, P09 and P10) (QB036 - P2, P03 and P04). The project is spread over an area of approximately 1327.37 Ha and will provide around 3508 single family villas, 161 single family mixed use, 247 utility plots, 17 commercial plots, 16 schools, 6 government reserved plots, 1 hospital, 32 mosques, 45 parks, 2 unallocated plot without PIN,5 parking, 2 sports/recreation, over 348 open spaces/ green areas and a Grand Masjid.

Public Works Authority 950

HIGHWAYS AND INTERNAL ROADS

Page 29: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 3

- 2 -

PROJECT PROFILE OWNER/CLIENT VALUE(QAR MILLIONS)

Development of Commercial Road to Wakrah Main Road Package 5, Wakrah Stadium Associated Temporary Road Works (DS136-05). The project consists of a road network in varying corridor ranging from 20m to 84m in Wakrah to provide connectivity to the Wakrah Stadium. The general scope of work includes but not limited to general site clearance works; roadwork’s inclusive of flexible pavements, pre-cast concrete block pavements, tactile pavements, granite pavements, speed tables and dust control; passive and active traffic management inclusive of traffic signs, road markings, traffic signals and traffic signal controller; Ducts and chambers for the Intelligent transportation systems (ITS) as per the national ITS strategy; street lighting; Surface water drainage collection and disposal system; foul sewer network; hard landscaping and irrigation provision with road crossing ducts; utility services including potable water, electrical, Telecom (Ooredoo) and QAF networks.

Public Works Authority 257

Page 30: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 3

- 3 -

PROJECT PROFILE OWNER/CLIENT VALUE(QAR MILLIONS)

Extension of Arab League Street to Temporary Truck Route. The project covers approximately 5km new dual 3-lane carriageway road as part of extension of Arab League street to connect to existing temporary truck route (TTR), around 5km new service road with parking, 3 traffic signals and 1 roundabout on temporary truck route (TTR).

Public Works Authority 170

Page 31: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 3

- 4 -

PROJECT PROFILE OWNER/CLIENT VALUE(QAR MILLIONS)

Roads and Infrastructure in Rawdat Abal Heeran MMUP Phase 2 Package 8 (DW015 - Package 1). The project works are located on the western periphery of Doha, north of Al Sailiya Road, in the municipality of Al Rayyan, in Zone 53. Package 1 is approximately 313 hectares in size and consist of approximately 39.45km of road and associated infrastructure in the residential area of Muaither. The project comprises the construction of the roads / infrastructure works including site clearance, site access and traffic management, road signs and road markings, earthworks, preparation to road foundation, granular sub-base, road pavement works, kerbing works, footpaths and paved areas, street and public realm lighting, Intelligent Transport System (ITS), surface water drainage works, sewerage works, Treated Sewerage Effluent (TSE), landscaping and irrigation works, and provisions (pit and duct or similar) for future public utility services namely: water, electricity, telephone and security / CCTV.

Public Works Authority - Qatar 550

Construction of Commercial Terminal Infrastructure and Buildings at New Port Project (NPP - 0032). Contract for subgrade, sub base and CBGM works. 12m

HBK Contracting Co. WLL 22

Construction of Roads and Infrastructure in Bani Hajer North, Phase 1&2, Package 02. Contract for earthworks, sub-base and asphalt, drainage and utilities including supply of materials. 110m

HBK Contracting Co. WLL 110

Page 32: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 3

- 5 -

PROJECT PROFILE OWNER/CLIENT VALUE (QAR MILLIONS)

Construction of Upgrade of Al Rayyan Road/Jassim Bin Mohammed Street. The project comprises the reconstruction of Al Rayyan Road between the Al Diwan Street junction and the Jassim Bin Mohammed Street tying into Souk Qaqif access. The works also includethe construction and upgrading of Jassim Bin Mohammed Street from a point south of the Corniche Roundabout to the Wadi Musheireb Street at the south end. New signaiized junctions are provided, upgrading of underground services and installation of natural stone carriage ways in specified sections and footpaths.

Public Works Authority - Qatar 200

Development of Main Roads in Zone 46. The project comprises the reconstruction of the Najma Road extension starting about 200m south of the junction with the E Ring Road to just before the F Ring. The Road is specified as a District Distributor with 1.3km in length and 64m corridor and will provide access to Zone 46, with more than 2100 planned housing allotments. The work also includes the interface with E Ring Road (West of Najma) with the project and construction of main roads as well as internal roads. Also included in the works is the re-design and construction of road E01 (including intersections) and design and build of pumping stations and associated rising main.

Public Works Authority - Qatar 420

Development of Roads in North Khalifa and Markhiya in Zones 32 & 33. The project comprises the construction of roads and infrastructure works, occupying an approximate total area of 376 hectares which includes but not limited to surface drainage works, earthworks, granular sub-base, asphalt works, kerbing works, traffic signs and road markings, and public utility services.

Public Works Authority - Qatar 235

Page 33: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 3

- 6 -

PROJECT PROFILE OWNER/CLIENT VALUE (QAR MILLIONS)

Road Works Bridge at Interchange IP 69-Abu Dhabi. UAE - Abu Dhabi Municipality 349

Development of Truck Road, from Cement Factory R/A to Mazyad WA in Al Ain, includes 2 bridges and one major interchange.

UAE - Al Ain Municipality 314

Al Towaiyah Area Development - 3rd Phase. UAE - Al Ain Municipality 232

Development of Mina Area. UAE - Abu Dhabi Municipality 208

Internal Roads for low cost houses in Al Faqa. UAE - Al Ain Municipality 161

Construction of Internal Roads in Al Grayh. UAE - PWD 156

Road Works to UAE Armed Forces, Contracts Nos. EC/470, EC/472, EC/932. EC/1999, EC/676 & EC/316.

UAE - Abu Dhabi Municipality 141

Roads to New Swehan Grave Yard. UAE - Abu Dhabi Municipality 99

Road Works at Maqta Bridge. UAE - Abu Dhabi Municipality 79

Sector Road West 15/1. UAE - Abu Dhabi Municipality 78

Construction of Ashoosh Farm Roads. UAE - Al Ain Municipality 77

Roads and Parking for Sheikh’s Palaces in Al Ain Phase 10 UAE - Al Ain Municipality 72

Abu Al Abyad Interchange. UAE - Abu Dhabi Municipality 61

Roads and Parking for Sheikh’s Palaces in Al Ain Phase 9. UAE - Al Ain Municipality 61

Al Ain-Mazyad Road Development. UAE - Al Ain Municipality 56

Improvement of HH Sheikh Hamdan Bin Zayed Palace. UAE - Abu Dhabi Municipality 41

Page 34: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 3

- 7 -

HYDRAULICS AND SEWARAGE

PROJECT PROFILE OWNER/CLIENT VALUE (QAR MILLIONS)

Al Kharaitiyat and Surrounding Districts – Package 01 TSE Sewer Tunnels (DN060-P01). The project covers the construction of strategic treatment sewerage Effluent (TSE) supply pipelines in Al Kharaitiyat and the surrounding districts.

Public Works Authority 95

Infrastructure FS Gap Mall of Qatar Area and Celebration Road Foul Sewer-Package 05. The project covers installation of trunk sewer line with various pipe diameters using micro tunnelling techniques; installation of shallow sewer lines with various pipe diameters using open cut method; providing connection to the existing manholes; providing adequate Traffic Management Plans during construction works; providing necessary Health & Safety documents; interface with DN110-P02 Contractor, DN117 P02 Contractor and PWA O&M; and traffic maintenance.

Public Works Authority 24

Al Faqa water and sewerage network as well as a 2km out of al Faqa Sewerage Treatment Plant (STP).

UAE - Al Ain Municipality 160.6

Sewerage & Water Contract (452) Mid-South Region, Nabatieh Area. CDR - European Bank 104.8

Sewerage Water contract (no. 1864) Region 1, Qubayat - Akar Area. CDR - European Bank 97.1

Doha North Sewerage Treatment Plant, Area Development which includes Sewerage Treatment Plant, sewerage tanks, aeration tanks, emergency lagoons, pumping stations, administration building and roads.

Qatar - Public Works Authority 75.2

Page 35: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 3

- 8 -

PROJECT PROFILE OWNER/CLIENT VALUE (QAR MILLIONS)

Um-Alnar Military Airport, The construction included the extension of the runway, the development of Taxi way and internal roads, ADNOC pipeline protection culvert, upgrading and extension of the lighting and control tower system.

UAE - Defense 86.1

Al Ghaffai Island Military Airport, The construction included a 2.2km runway, control tower, edge lights, approach lights and the water front shore protection for the runway.

UAE - Defense 37.6

AIRPORTS

Page 36: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 3

- 9 -

We pride ourselves on client satisfaction and invite you to contact the following people to hear first hand about our project performance.

Project Name: Road and Infrastructure of Government Residential Division Project in South Wukair - Packages 2, 3 and 4 (Interim Measures - P08, P09 and P10) (QB036 - P2, P03 and P04) Client: Public Works Authority – AshghalQBS Role: Main Contractor Contract Date: April 2018 Reference: Mr. Hamad Salem S H Almejaba Project Manager Public Works Authority PO Box 22188 Doha, Qatar

Project Name: Infrastructure FS Gap Mall of Qatar Area and Celebration Road Foul Sewer-Package 05.Client: Public Works Authority – AshghalQBS Role: Main Contractor Contract Date: April 2018 Reference: Mr. Jamal Mohammed Ajina Project Manager Public Works Authority PO Box 22188 Doha, QatarProject Name: Al Kharaitiyat and Surrounding Districts – Package 01 TSE Sewer Tunnels (DN060-P01)Client: Public Works Authority – AshghalQBS Role: Main Contractor Contract Date: August 2018 Reference: Mr. Jamal Mohammed Ajina Project Manager Public Works Authority PO Box 22188 Doha, Qatar

Project Name: Development of Commercial Road to Wakrah Main Road – Package 5, Wakrah Stadium Associated Road Works (DS-036)Client: Public Works Authority – AshghalQBS Role: Main Contractor Contract Date: August 2017 Reference: Mr. Ahmed Al Obaidly Project Manager Public Works Authority PO Box 22188 Doha, Qatar

REFERENCES

Page 37: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 3

- 10 -

Project Name: Extension of Arab League Street to Temporary Truck Route Client: Public Works Authority – AshghalQBS Role: Main Contractor Contract Date: May 2017 Reference: Mr. Alex Van Loggerenberg Project Manager Public Works Authority PO Box 22188 Doha, Qatar

Project Name: Construction of Roads and Infrastructure in Bani Hajer North, Phase 1&2, Package 02 Client: Public Works Authority – AshghalQBS Role: Subcontractor to HBK Contract Date: January 2016Reference: Sheikh Ali Bin Hamad Al-Thani Chairman & Managing Director HBK Contracting Co. WLL PO Box 1362 Doha, Qatar Mobile No.: (+974) 5550 2537

Project Name: Roads and Infrastructure in Rawdat Abal Heeran MMUP Ph2 Pkg 1 (DW015 - Package 1)Client: Public Works Authority – AshghalQBS Role: Main ContractorContract Date: 4 February 2014Reference: Mr. Ahmad Al Salah Projects Manager Public Works Authority PO Box 22188 Doha, Qatar

Project Name: Construction of Upgrade of Al Rayyan Road / Jassim Bin Mohammed StreetClient: Public Works Authority – AshghalQBS Role: Main ContractorContract Date: 28 June 2012Contract Status: CompletedReference: Mr. Manar Abu Ghalwa Projects Manager Public Works Authority PO Box 22188 Doha, Qatar Mobile No.: (+974) 5551 1203

Project Name: Development of Main Roads in Zone 46Client: Public Works Authority – AshghalQBS Role: Main ContractorContract Date: 27 December 2010Contract Status: Completed

REFERENCES

Page 38: QBS CONSTRUCTION WLLqbsconstruction.com/wp-content/themes/qbstheme-1/... · QBS has implemented a rigorous QHSE induction and continued education program to foster a QHSE aware culture.

QBS CONSTRUCTION WLLCOMPANY PROFILE PART 3

- 11 -

Reference: Mr. Rida Obaid Project Engineer Project Management – Infrastructure Affairs Public Works Authority PO Box 22188 Doha, Qatar Mobile No.: (+974) 5528 8628

Project Name: Development of Main Roads at North Khalifa and Markhiya Zones 32 & 33Client: Public Works Authority – AshghalQBS Role: Main ContractorContract Date: 16 August 2009Contract Status: CompletedReference: Mr. Ayman S. Ahmed Project Manager Infrastructure Affairs – Roads Department Public Works Authority PO Box 22188 Doha, Qatar Mobile No.: (+974) 6641 2140 (see certificates attached)

Project Name: Qatar Entertainment City (QEC) Development Client: Abu Dhabi Investment House QBS Role: Subcontractor to HBK Contracting Co. WLLContract Date: 2010Contract Status: CompletedReference: Mr. Hani Fidawi Senior Project Manager Project Analysis & Control Systems Co. WLL (Qatar) Projacs PO Box 7286 Doha, Qatar Mobile No.: (+974) 6696 9213

Project Name: Doha North Sewerage Treatment Plant Client: Public Works Authority – AshghalQBS Role: Subcontractor to HBK and CFEContract Date: 2009Contract Status: CompletedReference: Sheikh Ali Bin Hamad Al-Thani Chairman & Managing Director HBK Contracting Co. WLL PO Box 1362 Doha, Qatar Mobile No.: (+974) 5550 2537

REFERENCES