Qatar Legal and Other Requirements

download Qatar Legal and Other Requirements

of 5

Transcript of Qatar Legal and Other Requirements

  • 8/20/2019 Qatar Legal and Other Requirements

    1/10

     

    Clause / Article /Reference

    Requirement / Obligation

     Applicable to Area of

     ApplicabilityLicense / Compliance

    Records RequiredRemarks

    CompanyContractor /

    Supplier

    EnvironmentalLaw No 30 Article 1

    To act according to the rules of environmentprotection law, this is attached with this law.

     All Depts. AuthorizedWaste

    Collector

     All areas WRITER RELOCATIONSis following all theenvironmental laws

    Environmental

    Law No 30 Article 12

    The plans and public, private, development

    projects, whatsoever their qualities orlocations, including the construction,agricultural and industrial projects, should besubmitted to the Council after planning andbefore execution, for revision and evaluation,and to check their sticking to scientificpractical styles for appropriate environmentalplanning, due to the standards, specifications,and basics, and the controls mentioned in theformer article.

    Top

    Management

     All areas WRITER RELOCATIONS

    will submitenvironmental relevantdocuments to theenvironment Minister todemonstrate the plans

    Environmental

    Law No 30 Article 15

    The authorized department should make sure

    whether the new project and the majorchanges for the operative projects are using atechnology available and economically feasibleto control the pollution and prevent the

    Environmental deterioration, at the renewal ofthe operative projects licensing, the authorizeddepartment should make sure of itscommitment in using the appropriatetechnology, that achieves the engagement ofenvironment protection measures, whichdetermined in the executive regulation.

    Top

    ManagementMRHSE

     All areas WRITER RELOCATIONS

    is using the appropriatetechnology to prevent

    Environmentaldeterioration

    EnvironmentalLaw No 30 Article 16

    The Owners of the project should keep arecord to illustrate the establishment activityimpact on the environment. The executiveregulation establish a form for this record and

    the information registered in, the General

    Secretariat should follow-up the recordinformation, to make sure that it is real, in this

    TopManagement

    MRHSE

    OfficelocationsWasteStorage

     Area

    WRITER RELOCATIONSwill maintain the recordsto illustrate theestablishment activity

    impact on environment

  • 8/20/2019 Qatar Legal and Other Requirements

    2/10

     

    respect to have the necessary samples andperform the suitable test to specify theestablishment activity impact on the

    environment, and determine its sticking to themeasures for environment protection. If thereare any violations, the General Secretariatshould inform the specialized administrativeunit to burden the owner of the establishmentto correct these violations immediately., if not,makes the correction within sixty days, thecouncil will take the necessary procedures,according to the violation, and claim of

    appropriate compensation, to treat thedamages caused by these violations

    EnvironmentalLaw No 30 Article 18

     Any body who designs or executes, oroperates any project, must stick to thesystems and measures of the environmentprotection, which determined by this law, orany other issues of application it. And also who

    intends to do work, or intends to give up anaction, which leads to negative effects onenvironment, must identify its potential effectseither through conducting environmentalimpact evaluation study related to it or by anyother way determined by this law or its

    executive regulation, and take all necessaryprecautions, actions, or procedures to preventthe occurring of these effects, or minimize the

    potentiality of their happening to the minimumpossible.In case, any one of the potentialenvironmental negative effects for any project

    due to doing an action, or not doing an action,the project owner must engage to take allnecessary actions to stop or minimize itseffects as minimum as possible however, hisdoing the environmental impact evaluation,will not release him of responsibility.

    TopManagement

    HSE

     All areas Aspect, Hazard andRisk AssessmentRegister

    WRITER RELOCATIONSwill stick to the systemand measures of theenvironment protectionand will identify the

    potential effects

  • 8/20/2019 Qatar Legal and Other Requirements

    3/10

     

    EnvironmentalLaw No 30 Article 19

    To all administrative departments and whoacts supervision on any project, which mayestablish negative effects on environment,must put emergency plans and necessarymeans of applying them to prevent thoseeffects, or reduce their risks. And must submit

    the plans and means to the Council for studyand assume his appropriate decision in thisrespect due to the executive regulation rule.

    TopManagement

     AdminHSE

     All areas Aspect, Hazard andRisk AssessmentRegister

    WRITER RELOCATIONShave emergency plansand will apply whenneeded

    EnvironmentalLaw No 30 Article 20

    For any person, natural or moral, committed aresponsibility of operating a project includingfunctions or operations that may cause acute

    negative effects on environment must assign aperson to be responsible of guarantee

    achievement of those functions and operationsdue to basics and rules stated in this law andits executive regulation.

    TopManagement

    HSE

     All areas WRITER RELOCATIONShas appointed a personwho is responsible to

    achievement of thefunctions and

    operations

    EnvironmentalLaw No 30

     Article 22

    The emergency plan includes the following:1- Determine the environment disasters types

    and the authorized departments, which reportof happened, or expected to happen.2- Establish a central operation chamber toreceive reports of environmental disaster and

    follow-up sending and receiving of relatedaccurate information’s aiming to mobilize thenecessary capabilities to face them.3- Forming a work group to follow thecountering of environmental disaster, whenhappened, or expected to happen, and thework group leader is authorized to have all

    necessary power to face the disaster, bycooperation and coordination with the

    TopManagement

    HSE

     All areas WRITER RELOCATIONShave emergency plans

    and will apply whenneeded

  • 8/20/2019 Qatar Legal and Other Requirements

    4/10

     

    specialized administrative departments.

    EnvironmentalLaw No 30 Article 26

    The importing, dealing, or transporting thedangerous wastes, is restricted, unlessauthorized by the related administrativedepartments. The executing regulationdeclares the procedures and conditions ofoffering authorization, and issued by the

    specialized department, with the basics andprocedures of dangerous materialsmanagement and the council issues aninformation table of dangerous materials bycoordination with the specialized

    administrative departments.

     All Depts. EnvironmentalServiceprovider

     All areas Waste Transfer NoteWaste Permit fromthe WasteManagement Centre

    WRITER RELOCATIONSproject wastes are beingdisposed off throughhired approvedEnvironmental ServiceProvider

    EnvironmentalLaw No 30

     Article 27

    Those who are in charge of producing, dealingor transporting dangerous, gas, liquid, or solid

    materials, should take all precautions toprevent any damages to the environment.

     According to the rules of this law, the owner ofthe establishment, which causes dangerouswastes, must keep a record of these wastesand means of extracting them, and also thecontracting departments that authorized tohandle those waste

    ProjectsHSE Officer

    EnvironmentalService

    provider

     All areasWRITER RELOCATIONSis taking all the required

    precaution to preventany damages to theenvironment

    Environmental

    Law No 30 Article 28

    The location of the project should be suitable

    to the establishment activity, that secure notto overtake the allowed limits of air pollutants,and the total pollution resulting from allestablishments in one area, to be in theallowed limit. The executing regulationdetermines the establishments controlled by itsrules and the specialized department to

    approval on the suitability of the location andthe allowed extents of the air pollutants and

     All Depts. 3rd Party

    Laboratory

    Office

    locations

    Laboratory test

    results for Ambient Air Quality Analysis

     Air Quality Test is

    conducted once a yearby technical expertsfrom outside to ensurecompliance.

  • 8/20/2019 Qatar Legal and Other Requirements

    5/10

     

    the noise in the area where the establishmentis built.

    EnvironmentalLaw No 30 Article 30

     All the projects subject to rules of this lawmust be obliged in practicing their functions,to prevent discharge or leak of air pollutants,to exceed the maximum possible of the limits,due to the executing regulation.

     All Depts. 3rd

     PartyLaboratory

    Officelocations

    Laboratory testresults for Ambient

     Air Quality Analysis

     Air Quality Test isconducted once a yearby technical expertsfrom outside to ensurecompliance.

    EnvironmentalLaw No 30 Article 31

    Using of equipment, machineries, or vehicles,that resulting polluted exhaust to theenvironment is prohibited with a rate higher

    than the maximum possible limit determinedby the executing regulation.

    HSE OfficerHRTop

    Management

    3rd PartyLaboratory

    Officelocations

    Laboratory TestResults

     Air Quality Test isconducted once a yearby technical experts

    from outside to ensurecompliance

    EnvironmentalLaw No 30 Article 32

    Throwing, delivering, treating, or burning thegarbage and liquid, solid wastes, is restricted,except in the arranged areas away of theagricultural, industrial and the residual areas,and the water streams. And the executing

    regulation determines the specifications andcontrols and the minimum possible for thedistance of the arranged areas away from

    those places.The administrative departments, engaged tothe treatment of the wastes and garbage

    within their specialization due to whatdetermined by the executing regulation.

    EnvironmentalServiceprovider

    WasteTransportUtilities

    Waste Permit fromthe WasteManagementCentreTrade License

    Waste are disposed offthrough approvedEnvironmental ServiceProviders

    EnvironmentalLaw No 30 Article 33

    In burning any type of fuel or any othermaterial, in industry, energy generating, orconstructions, or any other commercialpurpose, the smokes, gases and harmfulvapors, must result in the allowed limits, andthe responsible of this function should take all

    necessary precaution to minimize pollutantsquantity in the burning results indicatedbefore, and the executing regulation toillustrate those precautions and the allowed

    HSE OfficerHRTop

    Management

    3rd PartyLaboratory

    Officelocations

    Laboratory TestResults

     Air Quality Test isconducted once a yearby technical expertsfrom outside to ensurecompliance

  • 8/20/2019 Qatar Legal and Other Requirements

    6/10

     

    limits and specifications ofchimneys, and any other means of controls insmoke, gases, and the vapors discharged from

    the burning operation.

    EnvironmentalLaw No 30 Article 35

    For all departments and individuals, whendoing the works of solidification, or cracking,or exploration,, or digging, or building, orrunning, or transport what resulting fromthem, like materials or wastes, or dusts, musttake the necessary precautions for safe storingand transporting to prevent aching due to

    what determined by the executing regulation.

    ProjectsHSE

    Transporter

    EnvironmentalServiceprovider

    WasteDisposal,HandlingandTransport

    Waste DisposalPermit

    Waste are beingdisposed off throughapproved EnvironmentalService ProvidersWaste Permit fromWaste ManagementCentre available

    EnvironmentalLaw No 30 Article 36

    For all department and individuals, whenconducting the serving, or productiveactivities, or else, and especially in operatingthe machinery, and equipment, and usingalarm machines and loud speakers, must notto exceed the allowed limit of the sound

    oscillation that determined by the executingregulation. The specialized departments mustconsider that total of sound discharged fromthe fixed sources in one area in the allowedpossible range. And to make sure of the

    establishment engagement of choosingappropriate equipment and machinery to fulfillthat.

    HSE Dept. All areas Noise LevelMonitoring

    Permissible limits isobserved throughmonthly monitoring ofnoise level SuitablePPE’s (like ear plugs)issued to workers to

    prevent them frompotential harm of noise

    EnvironmentalLaw No 30 Article 37

    The owner of the project or establishment,emerged to take necessary actions andprecautions to prevent leak or discharge of airpollutants inside the working area, except inthe allowed limit, determined by the executingregulation, either it is caused by the nature ofthe establish function, or by a defect in theequipment, and must provide the necessaryprotection according to vocational safety andhealth conditions, besides selection of suitable

    HSE Dept. All Depts.

     All areas Emergency ResponseProcedures

    Emergency SituationPlans are in placed andall safety paraphernaliaare issued to workersdepending on thenature of their work.Emergency situationsare identified in the

     Aspect-Impact Registerand Hazard and Risk

  • 8/20/2019 Qatar Legal and Other Requirements

    7/10

     

    machinery,equipment, materials, and types of fuels,considering the exposure period for these

    pollutants, and has to secure the sufficientventilation and assembling chimneys and othermeans of air purification.

    RegisterMock-drills areimplemented and

    records are maintained

    EnvironmentalLaw No 30 Article 38

    The owner of the project or the establishmenthas to take the necessary procedures tomaintain the degree of temperature andhumidity inside the working area not to exceed

    the allowed maximum limit and not to be lessthan the allowed minimum limit. In case of

    work necessity may required the movement oftemperature and humidity to be out of limit, sohe must secure suitable protection means forthe workers in terms of special uniforms andany other means of protection. The executingregulation illustrates the maximum andminimum limits for the degree of temperatureand humidity and duration of exposure and

    means of protection from them.

    HSE Dept. All Depts.

     All areas Emergency ResponseProcedures

    Emergency SituationPlans are in placed andall safety paraphernaliaare issued to workers

    depending on thenature of their work.

    Emergency situationsare identified in the

     Aspect-Impact Registerand Hazard and RiskRegisterMock-drills areimplemented and

    records are maintained

    EnvironmentalLaw No 30 Article 39

    The public closed and semi-closed areas, andestablishment and projects, are conditional tobe fulfilled to the sufficient ventilation means,which suit the area volume and its capacityand kind of activity practiced in, to maintain airrenewal, purification and keeping a suitabletemperature degree.

    HSE Dept. All Depts.

     All areas Emergency ResponseProcedures

    Emergency SituationPlans are in placed andall safety paraphernaliaare issued to workersdepending on thenature of their work.

    Emergency situationsare identified in the

     Aspect-Impact Registerand Hazard and RiskRegisterMock-drills areimplemented andrecords are maintained

  • 8/20/2019 Qatar Legal and Other Requirements

    8/10

     

    EnvironmentalLaw No 30 Article 51

    It is restricted to the ships and carriers in theregional sea or the pure economical area ofthe state, to conduct any of the following:

    1- Throwing or drain any wastes, pollutant,injurious liquid materials, or perished animals,intentionally, or unintentionally, directly, orindirectly, that caused damage in the wateryenvironment, or general health, or any otherlegal usages in the sea.2- Throwing of injurious materials packed inparcels, containers, or mobile tankers ortrucks.

    3- Drowning of dangerous wastes andmaterials and the executing regulation,

    determines the liquid, solid materials, whichdamage the watery environment, and exposeit to danger.

    EnvironmentalLaw No 30 Article 56

    It is restricted for all projects andestablishments including the public places andthe commercial, industrial, touristic andserviceable establishments, to drain or throwany materials, or wastes, or untreated liquidsthat cause pollution in the coasts or theneighboring waters, either caused intentionallyor unintentionally, directly, or indirectly.

     All Depts. All areas WRITERRELOCATIONS's officelocations are always farfrom marine life

    Environmental

    Law No 30

     Article 57

    The licensing for establish, any projects or

    establishments or shops at the sea beach, or

    nearby, that caused pollutant materialsdrainage as a violation to the rules of this lawand decisions supporting it, the licenseapplicant must conduct the environmentalimpact studies, and stick to provide thenecessary means to treat the wastes.

     All Depts. All areas WRITER

    RELOCATIONS's office

    locations are always farfrom marine life

  • 8/20/2019 Qatar Legal and Other Requirements

    9/10

     

    EnvironmentalLaw No 30 Article 58

    The executing regulation determines thespecifications and standards that engaged theindustrial projects, which are authorized to

    drain the soluble pollutant materials, aftertreatment, also determines the unsolublepollutant materials, which are restrict to bedrained in the watery environment by theindustrial establishment.

     All Depts. All areas WRITERRELOCATIONS's officelocations are always far

    from marine life

    EnvironmentalLaw No 30 Article 59

    The representative, or the responsible of theproject or the establishment management,that stated in Article (56) of this law, which

    drain in the water environments, is responsibleof any in violation performed by the workers,and also responsible of providing thetreatment means typical to the standards andspecifications that determined by theexecuting regulation.

    EnvironmentalLaw No 30

     Article 60

    With consideration to the rules of law No. (10)dated 1987, indicated above, it is restricted

    foundation of any projects or establishmentson the sea beaches to a distance of 200meters minimum inside from the coast line,unless agreed by the specialized administrative

    department, which is subject to coordinationwith the council, and the executing regulationorganized the procedures and conditions,

    which must be followed in this respect.

     All Depts. All areas WRITERRELOCATIONS's

    establishment is alwaysfar from marine life

    Chapter 4Foreword

    beforeEnvironmental

    Law No 30 Article 63

     Administrative and Judicial proceduresThe General Secretariat personnel, who aredelegated by a decision issued from theChairman of the Council, a capacity of judicialarrest commissioners, also this capacitydelegated to the other administrativepersonnel, who are deputated to the Councilfor this purpose. And that in the crimesevidence, that occur as a violation for the rules

     All employees EnvironmentalServiceprovider

     All areas No such incidentshappened yet inWRITER RELOCATIONS

  • 8/20/2019 Qatar Legal and Other Requirements

    10/10

     

    of this law and its executing regulation, anddecrees supporting it. They must have theauthority of search on all places practicing a

    function affects on environment, to observethe rules of this law and its executingregulation, and have the right at any time toenter all places committed violations for theenvironmental legislations rules, and writing

     journals of capturing these violations and takethe legal procedures related to them, theyhave specifically to do the following:1- Entry and inspection of establishments, with

    considering operation and safety laws forthem.

    2- Apply for reports about functions expectedto cause environmental pollution/deterioration.3- Take samples from wastes and used,stored, produced materials from the project to

    make sure of its engagement of environmentprotection measures and systems.4- Climb on board ships and sea platforms,and entry of establishments founded at thesea coast and inspect means of oil transportand pollutant materials to the maritimeenvironment to identify their engagement ofrules application of this law and its executingregulation, and the issued decrees supportingit, and provide equipment and means ofwastes treatment committed by determined

    safety & operation conditions and regulations