Pumps, Sizing, Dosing & Flow Pump Choice & Settings
Transcript of Pumps, Sizing, Dosing & Flow Pump Choice & Settings
Decisions for proper operation
Pump Choice &
Settings
Pumps, Sizing, Dosing & Flow
Measurement Pump choices
Purpose
Pump sizing
Operating point
Dose Volume
Demand Dosing
Time Dosing
Is there a pump?Pump Types
Type of pump:
Multi-stage
Single-stage
Grinder Pumps
Some systems will have
grinder pumps
These macerate solids
Need more power to grind
material: 230V+
Larger, heavier
More expensive
Do not discharge to field
All Equipment: Read/Follow
Manufacturer’s Manual
Equipment/component
warranties are tied to
proper maintenance
Follow mfg instructions
Understand required
maintenance intervals
Applies to all
equipment/components
This class not a substitute
for knowing requirements
Pump Variables: GPM Gallons per minute
Pump Capacity
Flow rate
Set by system in Pressure
systems
Pipe Diameter
Number of perforations
Perforation size
Discharge pressure
Pump Variables: TDH
Total dynamic head
Feet [Drip systems psi]
Amount of push
Set by Location in Pressure
systems :
Elevation difference
Piping Length
Friction loss {based on Flow rate}
Pump sizing [Gravity System]
TDH
Set by Location
Impacted by flow
GPM
10 - 45 gpm
Pump sizing [Pressure System]
TDH
Set by Elevation
Flow rate
Distribution
GPM
Set by Number of orifices [6- 10 sqft
per orifice]
Orifice size
Operating pressure
Pump vaultsVault Capacity [gpm]
must be greater than
Pump Capacity [gpm]
OWTS MATH: UNITS
Units are very important
Units can show you a mistake
Always include units in every calculation
Cancel units to verify correct units for results
What are Units?: feet, inches, gallons, square feet,
cubic feet, GPM, Gal/CF, etc
OWTS MATH: UNITS (cont.)
Understanding dimensions:
Length/Linear= one dimension (X1)feet, inches, yards, miles, meters, etc
Area= two dimensions (Square Units, X2)square feet, square inches, square meters, etc
Volume= three dimensions (Cubic Units, X3)cubic feet, gallons, liters, bushels, etc
OWTS MATH: UNITS (cont.)
Example: Calculate/convert gallons per inch.
4ft X 7ft X 0.08ft/in X 7.5 gal/ft3
4ft X 7ft = 28 ft2
28 ft2 X 0.08 ft/in = 2.24 ft3 /in
2.24ft3 /in X 7.5 gal/ft3 = 16.8 gal/in
Convert 1” into parts of a foot: 1”÷12”/ft= 0.083ft
Anything divided by itself, or an equivalent value= 1
Example
4’ x 7’ Pump Tank
Gallons Per Inch
Area x 1’ x 7.5 gal/ft3 ÷ 12 inch/ft = gal/inch {gpi}
28 ft2 x 1’ x 7.5 gal/ft3 ÷ 12 inch/ft = 17.5 gpi
12.5 ft2 x 1’ x 7.5 gal/ft3 ÷ 12 inch/ft = 7.8 gpi
What is a Demand System?
“Socially Controlled”
Controlled by flow
Piggy back Plug in
Non-electrician
Panel Better connections
Additional tools for management
Dose is Set by Sensor
Float Separation
Pressure Change
Setting of Sensor
Sensors
Floats
Pressure
Electric
Floats: Functions [Demand]
Off
Redundant off
On
Dose volume is
between OFF &ON
Alarm
Be careful with a Check valve
Dose Volume (Pumped or Net)
Maximum
25% of the Daily flow
+ Drainback [with no Check valve]
Minimum ~ {Micro dosing}
Minimum Sensor difference
3-5X the Lateral Volume [Pressure System]
+ Drainback [with no Check valve]
Gravity System ~ at least once an hour
~ Design flow ÷ 24 hr/day
Drainback?
Check valve
Purge hole
Bottom of the pipe
Drainback Drainback= Volume of Discharge pipe
Drainback= Volume/ft (Table A.4 (b)) X ft of pipe
Ex: 60’ of 2 inch pipe
Sch. 40, 2” pipe= 0.17 gal/ft
Physically measure?
Pipeline Volume(Gallons per foot)
PVC Rigid Pipe
PVC Flexible Pressure
Pipe
Nominal
Size
(inches)
Schedule 40 Schedule 80 SDR 26 (160
psi)
SDR 21 (200
psi)
Corrugated
tubing
¾ 0.028 0.022
1 0.045 0.037 0.058 0.055
1 ¼ 0.078 0.067 0.096 0.092
1 ½ 0.106 0.092 0.126 0.121
2 0.174 0.153 0.196 0.188
3 0.384 0.343 0.426 0.409
4 0.661 0.597 0.704 0.677 0.653
6 1.50 1.35 1.53 1.47 1.47
Table A.4 (b)
Drainback Drainback = Volume of pipe
Drainback = Volume / ft (Table A.4 (b)) x ft of pipe
Ex: 60’ of 2 inch pipe
2” Sch. 40 pipe = 0.17 gal/ft
Drain back = 60’ x 0.17 gal/ft = 10.2 gal
Max Dose Calculation
25% of daily flow
Design flow= 600 gpd
600 gpd x 0.25= 150 gal
+ Drainback
Drainback= 60 ft X 0.17 gal/ft= 10.2 gal
150 gal + 10.2 gal= 160.2 gal
Minimum Dose Minimum Sensor difference
RJ Floats are 3” Min DV = Min float x gpi
Min DV = 3” x 17.5 gpi
Minimum Dose 4 x the Lateral Volume [Pressure System]
Lateral Vol. = Volume / ft (Table A.4 (b)) x ft of pipe
Pipeline Volume(Gallons per foot)
PVC Rigid Pipe
PVC Flexible Pressure
Pipe
Nominal
Size
(inches)
Schedule 40 Schedule 80 SDR 26 (160
psi)
SDR 21 (200
psi)
Corrugated
tubing
¾ 0.028 0.022
1 0.045 0.037 0.058 0.055
1 ¼ 0.078 0.067 0.096 0.092
1 ½ 0.106 0.092 0.126 0.121
2 0.174 0.153 0.196 0.188
3 0.384 0.343 0.426 0.409
4 0.661 0.597 0.704 0.677 0.653
6 1.50 1.35 1.53 1.47 1.47
Table A.4 (b) Minimum Dose 4 X the Lateral Volume [Pressure System]
Lateral Vol.= Volume / ft (Table A.4 (b)) X ft of pipe
Ex: 150’ of 1 1/4 inch pipe
Sch. 40 1 1/4” pipe= 0.078 gal/ft
Lateral Vol.= 0.078 g/ft X 150 ft of pipe
Lateral Vol.= 11.7 gal
Drainback Drain back= Volume of Discharge pipe
Drain back= Volume/ft (Table A.4 (b)) X ft of pipe
Ex: 60’ of 2 inch pipe
2” Sch. 40 pipe= 0.17 gal/ft
Drain back= 60’ X 0.17 gal/ft= 10.2 gal
Minimum Dose 4 X the Lateral Volume [Pressure System]
+ Drainback
Min Dose= [4 x 11.7 gal] + 10.2 gal
Minimum Dose= 57 gal
Gravity System [Minimum]
at least dose per hour + Drainback
Min DV= Design flow ÷ 24 hr/day
Min DV= 600 gpd ÷ 24 hr/day= 25 gal/dose
DV= Dose Volume
Demand float setting
Gallons per inch
Area (sqft) x 7.5 (gal/sqft) ÷ 12 (in/ft)
Maximum
25 % daily + drainback
Minimum
Pressure System= Lateral volume x 4 + drainback
Minimum sensor Setting
Gravity System= One dose/hour
Demand Float Setting
Gallons per inch
17.5 gals/inch
Sensor Settings
Separation= DV ÷ gpi
Separation [inch]= 87.5 gal ÷ 17.5 gals/inch
DV= Dose Volume
Demand Dosing
Single or Double
floats
On level sets the
volume
Check valve holds
effluent in the piping
Off level above the
pump
47”-3”= 44”ON Alarm
Dose Volume (DV) Existing Settings
Inches pumped (Drawdown)=
Pump OFF – Pump ON
52” – 47” = 5” Ex: Timed with watch 3 minutes
Alarm@44”
Dose Volume (DV)
GPI = 17.5
Pump drawdown (inches): 5 in.
Dose Volume (DV)= Drawdown (in) x GPI
DV= 5 in x 17.5 gal/in= 87.5 gal
Pump delivery rate (PDR)
Dose Volume (gal) From Item 5
Verified Pump run time “ON” (min)
Dose Volume ÷ Pump run time “ON” (min) = (GPM)
(With a Check Valve) 87.5 gal ÷ 3 min = 29.2 GPM
Measuring Total Gallons Cycle Counter
# of Doses x Dose Volume
Elapsed time Meter
Time x GPM
Remember to Consider
Drainback
Measuring Flow: CC
Using Cycle Counters (CC)
What do I need to have?
Days between readings (only when in operation)
Change in value= Total Number of Cycles (NC)
Dose Volume (DV)
(Use net volume)
Total flow NC X DV [to system]= Total flow
Total flow ÷ Days= Average Daily Flow
Total Gallons [CC] w/ check valve
Cycle Counter (CC)
[(PCR) – (LCR)] x (DV) = Total gallons
(45,289 – 44,891) x 87.5 gal = 34,825 gal
Total gallons ÷ (# of days) = GPD
34,825 gal ÷ 100 days = 348 GPD
PCR= Present Counter Reading
LCR= Last Counter Reading
Total Gallons [CC] no check valve
Cycle Counter (CC)
[(PCR) – (LCR)] x (DV) = Total gallons
(45,289 – 44,891) x 77.3 gal = 30,765 gal
Total gallons ÷ (# of days) = GPD
30,765 gal ÷ 100 days = 308 GPD
Measuring Flow: ETM Using Elapsed Time Meter (ETM)
What do I need?
Days between readings (only when in operation)
Change in value = Total number of units Minutes
Hours
Pump capacity (gpm)- will not be the net volume
Total flow= NC x gpm
Total flow – (total d-back) ÷ Days = Average daily flow
Total Gallons
Elapsed Time Meter (ETM)
[(PTR) – (LTR)] x (GPM)= Total gallons
(15,703 min – 14, 509) X 29.2 gpm= 34,865 gal
(15,703 – 14, 509)÷ 3 min/cycle= 398 cycles
398 cycles X 10.2 gal/cy= 4,060 gal
Gallons Per Day (GPD)
Total gallons ÷ (# of days this period)= gpd
Comparison
CC: 30,765 gal ÷ 100 days= 307 gpd
ETM: 34,865 gal ÷ 100 days= 349 gpd
Drainback 398 cycles X 10.2 gal= 4,060 gal
34,865 gal – 4,060 gal = 30,805 gal≈ 308 gpd
Design flow= 600 gpd
(308 gpd ÷ 600 gpd) x100 = 51%
Controls
Type
Piggy Back
NO MANAGEMENT
Panel
CC ~ Pump
CC ~ Alarm
ETM
Water Meter Present
If a meter is present:
Present reading
Last reading
Present – Last = Gallons used
257,456 gal – 222,656 gal = 34,800 gal
Gallons used ÷ No. of days
34,800 gal ÷ 100 days = 348 gpd
Some Outside Use
What is a Timer System?
Flow controlled by time
Timers
ON: OFF
Programmable Logic
Controller
PLC
Computer
Why Bother w/Timer?
Uniform distribution is the goal
Area
Time
Loading- Spreading out use in the system
Allows for oxygen recovery
Flow equalization
Uses the whole day
OR even the whole week
Time-Dosed Systems
Timer allows a ‘soft’
failure
1. Controls
Manufacturer: Model
a. Is it watertight
b. Alarm test switch working properly
Alarm
“Verify timer”
Check the timer
With a watch
Functions OFF
Turns timer off
ON Timer operates the
pump
Alarm Turns on the alarm
Peak enabler Changes the dosing
frequency (PLC)
Timed Dose Panel
www.sjerhombus.com
Control Fuse
Pump Timer
HOA Switch
Alarm Fuse
Wiring Diagram
Spare Fuse
Magnetic MotorContactor
Circuit Breaker
Timer setting Calibrated GPM
Dose volume ÷ GPM =
Time ON
Time ÷ # Doses – ON=
Time OFF
Cycle time=
ON + OFF
Timer Setting (Pump ON)
ON Setting
Pump ‘ON’ time (min) =
Desired dose (gal) ÷ Pump flow rate (gal/min)
87.5 gallons per dose
87.5 gal/dose ÷ 29 gpm = 3 minutes
3 min x 60 sec/min = 180 seconds
PUMP DISCHARGE=
29 GPM~ CALIBRATED
Timer Setting (Cycle) OFF Setting
Design Flow ÷ Gal per dose = # of Doses
600 gpd ÷ 87.5 gal = 6.8 doses per day
600 gpd ÷ 77.3 gal = 7.8 doses per day
1440 minutes ÷ # of doses- On time = Off time
1440 min ÷ 6.8 doses – 3 min. = 212 min
212 min ÷ 60 min/hr = 3.53 hour
Cycle time
ON time + Off Time
3 min + 212 min = 215 min
Controls SettingsIf timer was changed from above, new setting is:
“On”_________ Mode setting____
“Off”_________ Mode setting____
3 MIN
212 MIN
Checking Operation Using Cycle Counters (CC)
What do I need to have?
Days between readings
(only when in operation)
Designed number of cycles (Dose frequency)
Designed maximum cycles
Max cycles = Days X Dose frequency
Compare to actual
Change in value = Total Number of Cycles (NC)
Calculated Number of Doses (Cycles) Per
Day
CC:
Total cycles
Days x cycles
Max = 100 x 6.8 = 680 cycles
Actual: 17,111 – 16,716 = 395 cycles
Flow = Cycles x DV
395 cy x 87.5 = 34,562.5 gals
Elapsed Time Meter (ETM)
Reading
Current: 15,703 minutes
Last: 14,523 minutes
15,703 min. – 14,509 min. =
1,194 minutes
1,194 min ÷ 3 min/cyc = 398 cyc
Units
Minutes
Hours
Current Reading
15,703
Last Reading
14,509
Elapsed Time Meter (ETM) Reading
Current: 15,703 minutes
Last: 14,523 minutes
15,703 min. – 14,509 min. = 1,194 minutes
1,194 min x 29 gpm = 34,220 gal
With Check Valve
34,626 gal ÷ 100 days = 346 gpd
Without Check valve
DB = 10 gal [from system]
{34,626 – (395 x10)} ÷ 100 days =
{34,626 – 3,950} ÷ 100 days =
30,676 ÷ 100 days = 306.7 gpd ~ 307 gpd
Current Reading
15,703
Last Reading
14,509
DB= Drainback
What’s in Your pump tank?
Any
Questions?