Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC -...

25
PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 0 Public Spending Code (PSC) Quality Assurance Requirements A Guidance Note for the Local Government Sector Version 2 11 th April 2016

Transcript of Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC -...

Page 1: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 0

Public Spending Code (PSC) Quality Assurance Requirements A Guidance Note for the Local Government Sector Version 2

11th April 2016

Page 2: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 1

1. Introduction Circular 13/13: The Public Spending Code: Expenditure Planning, Appraisal & Evaluation in the Irish Public Service - Standard Rules & Procedures was issued in September 2013 implementing a comprehensive set of expenditure appraisal, Value for Money requirements and related guidance covering all public expenditure. The new Code replaces all previous guidelines, circulars and directions issued in relation to appraisal and Value for Money e.g. the Capital Appraisal Guidelines 2005. The Code combines and updates the previous components of the VFM framework and also includes additional modules. The requirements in the Public Spending Code (PSC) are based on employing good practices at all stages of the expenditure life cycle. Every organisation needs to assure itself that the expenditure practices it employs are of an acceptable standard, that it consistently maintains these standards and if there are deficiencies that they are identified and addressed. Departments and other public service organisations also need to assure themselves that the expenditure practices employed by organisations reporting to them and to whom they may provide funding are of an appropriate standard. All Government Departments, local authorities, the Health Service Executive, public bodies and all bodies in receipt of public funding must comply, as appropriate, with the relevant requirements of the Public Spending Code. In the case of State Companies, the Board of each must satisfy itself annually that the Company is in full compliance with the Code. The Public Spending Code was written specifically with Government Departments in mind and some of the terminology is very specific to that sector. This Guidance Note, prepared by the CCMA Finance Committee, discusses each stage of Quality Assurance requirements providing interpretations from a Local Government perspective. This edition is the second version of the guidance and has been updated following NOAC’s (National Oversight & Audit Commission) review of the 2014 Quality Assurance reports for the Local Government Sector. The primary changes in this version are: - Change in approach to Current Expenditure “Being Considered” - Revised Inventory template in preferred format for NOAC - Minor revisions in Checklists These Guidance Notes may be further updated from time to time as the need arises.

Page 3: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 2

2. Purpose of the Guidance Note This Guidance Note will focus on the Quality Assurance element of the PSC with particular emphasis on:

o Highlighting the basic principles applicable under the PSC and to offer a definition of these principles from a local government perspective.

o Summarising “new” elements introduced by the PSC in order to facilitate a fuller understanding of these requirements from a local government perspective.

o Examining reporting and publication requirements with particular emphasis on the Quality Assurance element introduced by the PSC.

o To provide guidance to the Local Government Sector on the Quality Assurance process, including interpretation of key terms relevant in a Local Government context.

o To support consistency of approach and interpretation across the Local Government Sector.

The PSC sets out the various requirements in each of the four stages of the life-cycle of a project or programme. The four stages have been established as: o Appraisal: assessing the case for a policy intervention

o Planning/Design: a positive appraisal should lead on to a considered approach to designing how the project/programme will be implemented

o Implementation: careful management and oversight is required for both capital and current expenditure. Ongoing evaluation should also be a feature

of current programmes o Post-Project or Post-Implementation Review: checking for delivery of project

objectives, and gaining experience for future projects.

It is not the intention of this report to examine the requirements of each stage of the life cycle as the PSC code is largely self explanatory in this regard. In addition the provisions are based on best practices already in place and well grounded in local government. However, it is critical to the implementation of the Public Sector Code that the requirements of Spending Departments are fully understood and implemented by the Spending Departments and that plans are put in place to address any major deficiencies that might exist, within a realistic timeframe. As Accounting Officers for the organisation the Chief Executive, in the context of PSC returns, should notify and endorse these requirements to the organisation’s Spending Departments.

Page 4: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 3

3. Principles of the PSC The following are basic principles established for the application of the PSC

• The Public Spending Code imposes obligations, at all stages of the project/programme life-cycle on organisations that spend public money.

• The Code applies to both Capital and Current expenditure and sets out to explain what is required of public service managers at different points of the expenditure lifecycle and advises how to fulfil those requirements.

• Section B06 of the PSC – Section 2 (page 79) provides a distinction between Capital and Current Expenditure. It states that

o Capital spending generally involves the creation of an asset where benefits accrue to the public over time e.g. a road, a rail line, a school or a hospital and

o Current expenditure involves day to day expenditure i.e. Revenue Expenditure

• Section B06 of the PSC – Section 3 (page 83) offers a more informative explanation of the requirements for current expenditure, where it states: “the obligations for appraising new current expenditure proposals do not apply automatically to the broad range of existing current expenditure schemes i.e. it is not intended that all existing programmes must be appraised each year as this would be highly resource-intensive and the VFMPR/FPA arrangements set out at section C apply instead to ongoing expenditure. Similarly, it is not intended that these arrangements for appraisal of new current expenditure apply to routine administrative budgets already in place as the focus is on new programme expenditure. However any proposed extension, renewal or re-orientation of existing schemes should be informed by expenditure appraisals.”

• Elements of the Public Spending Code apply to any project or programme

that: • May incur expenditure in the near future (Appraisal, Planning)

• Is currently incurring expenditure (Management, Monitoring, Evaluation) • Has incurred expenditure in the recent past (Review, Evaluation)

Page 5: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 4

• The Code refers to the Sanctioning Authority and the Sponsoring Agency

• The Sanctioning Authority is responsible for granting the approvals required as projects/schemes, funded with public assistance, proceed

through the project/expenditure life cycle. • The Sponsoring Agency has the overall responsibility for the proper

appraisal, planning and management of projects/schemes (incl. current expenditure). Sponsoring Agencies are also responsible for post-project

review. (The Sponsoring Agency may be a Government Department, local authority, health agency, University or other State body.)

Put simply these definitions seem to suggest that: ü The Sanctioning Authority is the organisation allocating the

grants/public monies for projects. ü The Sponsoring Agency is the organisation spending the grant/public

monies received.

ICT projects: The principles and guidelines in the Public Spending Code apply to all expenditure including expenditure on ICT. ICT projects are subject to some specific additional requirements.

Application of PSC principles in a local government context

o All local government expenditure is funded by public money whether this is by way of grant funding, rates, local property tax or service charges.

o Current expenditure can be defined as Revenue Expenditure which is formally adopted by Council Members each year in the statutory budget process.

o Capital Expenditure is project based and largely funded through capital grants, development levies and borrowing.

o Local Authorities can be both the Sanctioning and Sponsoring Agency under the terms of the PSC.

o Local Authorities will primarily be Sponsoring Agencies but where the local authority allocates grant funding to persons, other bodies, including community groups/facilities at a level that is subject to the requirements of the PSC they will also assume the responsibilities of a Sanctioning Authority for such payments.

o Capital Expenditure within LAs is project based and applying the principles of the PSC are relatively straightforward in this spending area.

o With regard to current expenditure the PSC confirms that the appraisal requirements do not apply to routine administrative budgets already in place and that the focus of the code will be on new or extending programme expenditure. Therefore only new or extended current expenditure to the value of €0.5m or greater will be subject to the application of the code from the date of implementation of the PSC within Local Authorities.

Page 6: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 5

4. QA Reporting requirements The PSC sets out a number of reporting requirements at the various stages of the Expenditure Life Cycle of a project or programme, including six monthly reports, Variance Reports and Annual Reports.

As this Guidance Note is specifically focusing on the Quality Assurance requirements of the Public Spending Code the following paragraphs will only address the reporting requirements associated with the Quality Assurance element of the code. Quality Assurance Reporting The Public Spending Code requires public bodies to establish an internal, independent, quality assurance procedure involving annual reporting on how organisations are meeting their Public Spending Code obligations. This new Quality Assurance procedure replaces and updates the “spot check” requirements previously laid down in Circular letter dated 15th May 2007.

This new obligation involves a 5 step process as follows:

o Step 1 - Draw up inventories of projects/programmes at the different stages of the Project Life Cycle. The person responsible for the Quality Assurance process should be satisfied that they have a full and complete inventory. Here is an example: http://www.dttas.ie/sites/default/files/content/corporate/english/general/public-spending-code-compliance/appendix-1-qa-report-inventory-dttas.pdf

o Step 2 - The Organisation should publish summary information on its website of all procurements in excess of €10m, related to projects in progress or completed in the year under review. (The PSC originally required projects in excess of €2m to be published under this requirement but this has now been changed to €10m) A new project may become a “project in progress” during the year under review if the procurement process is completed and a contract is signed. Here is an example:

http://www.dttas.ie/corporate/english/procurement-over-%E2%82%AC2-million

o Step 3 - Complete the 7 checklists contained in the PSC. Only one of each checklist per Department/Agency/Local Authority is required. Checklists are not required for each project/programme. The QA process for verifying the accuracy of responses on the checklist is based on a sample of projects/programmes and is Step 4 of the process. Here is an example: http://www.dttas.ie/sites/default/files/content/corporate/english/general/public-spending-code-compliance/appendix-2-qa-report-checklists-dttas.pdf

o Step 4 - Carry out a more in-depth check on a small number of selected projects/programmes Here is an example: http://www.dttas.ie/sites/default/files/content/corporate/english/general/public-spending-code-compliance/appendix-3-nta-depth-checks.pdf

Page 7: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 6

o Step 5 - Complete a short summary report for the National Oversight and Audit Commission (NOAC). The report, which will be generated as a matter of course through compliance with steps 1-4, should be submitted by the end of February (now May for LG Sector) in respect of the previous calendar year. Here is an example: http://www.dttas.ie/sites/default/files/content/corporate/english/general/public-spending-code-compliance/approved-qa-report-2013.pdf

While the PSC suggests the Finance Unit is best placed to complete at least 4 of the 5 steps in the Quality Assurance element of the Code the local government sector are of the view that the following approach is more appropriate for the sector.

QA Step Assigned to: Data Provided by Step 1 Project Inventory Coordinator

(Assigned by CE)

Project/Programme Owners within the organisation

Step 2 Publish Summary Information of procurement in excess of €10m on Website

Procurement Officer

Project Inventory

Step 3 Complete PSC Checklists for overall LA.

Coordinator (Assigned by CE)

Compliance Statement provided by Project/Programme Owners within the organisation

Step 4 In depth check on a small number of selected projects

Internal Audit Evidence provided by Project/Programme Owners within the organisation

Step 5 Complete summary report for NOAC

Drafted by Coordinator (Assigned by CE) Signed by CE

Steps 1 – 4

Each step in the QA reporting process will now be discussed further in terms of the specifics of the requirement: Step 1 Project Inventory This report needs to include all relevant projects under 3 categories. These categories and the required inclusions in each category are set out in the table below. To assist with completion of the inventory a simple explanatory template is also included in Appendix A. NOAC have issued an excel version of their preferred format for the Project Inventory and a copy of this is included in Appendix B for reference. Completed inventories must be submitted on the excel format.

Page 8: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 7

STEP 1 QA Process - Project Inventory Reporting Criteria/Requirements Expend Type Category/Band Application of Criteria/Source of Information

A. Expenditure being considered

Capital Projects § Between €0.5m - €5m

Capital Projects § Between €5m - €20m

Capital Projects over €20m

1. 3 year Capital Programme for the year under review e.g. 2014 Return – Use 2014 projects listed in 2014 to 2016 Programme; 2015 Return – Use 2015 projects listed in 2015 to 2017 Programme; .............and so on. 2. Remove any items which have incurred expenditure during the year of review (To be included in B) 3. Add any items notified by Project/Programme Owners as additional projects that were identified

during the year under review and which were not listed in the Capital Programme for that year. 4. Include all items at Total Overall Project Cost (Lifetime Costs)

Current Expenditure programme

§ Increases over €0.5m

All consideration of current (revenue expenditure) is carried out as part of the statutory Budget process as set out in the Local Government Act 2001 (as amended). In the year of review the budget process undertaken relates to the next financial year e.g. for the 2015 review the 2016 budget figures are to be used and any increases of €0.5m or more in this budget versus the previous year budget are to be included. (N.B. Only the value of the increase is to be included)

B. Expenditure being incurred

Capital Projects greater than €0.5m1

1. Capital Projects with expenditure for the year under review – which inform AFS (Appendix 6) 2. List all relevant projects (Job code level), with expenditure greater than €0.5m. 3. Remove all projects that were completed in the year of review. 4. Include all items at Total Overall Project Costs. (Lifetime Costs) 5. Items listed in this section remain there year on year until the project is complete.

Current Expenditure greater than €0.5m

1. AFS (Appendix 2) for the year under review. 2. Include Items at Service Level (e.g. A01 Main/Imp LA HSG) with expenditure greater than €0.5m. 3. Remove any items/programmes that were discontinued in the year of review.

C. Expenditure that has recently ended

Capital Projects greater than €0.5m1

Include all completed Capital projects identified in (and removed from) B above.

Include at Total Overall Project Cost.

Current Expenditure greater than €0.5m

1. Include all discontinued Service Expenditure identified in (and removed from) B above. 2. Include Current Expenditure at total Cost of Service reported in AFS for the year under review.

N.B. Projects/Programmes should only appear in one category in the inventory.

1 The PSC includes a category for Capital Grants Scheme under B and C above – The LG Sector have interpreted this as not relevant to the LG Sector

Page 9: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 8

Step 2 Summary Information on Website The Project Inventory will inform the projects to be published on the organisation’s website. Summary details of all procurements (capital and current) where the value exceeds €10m are required to be published under a heading PROCUREMENT/PROJECT PROGRESS. The list must be published by March each year and should include the information on the following table for each project/procurement greater than €10m regardless of its status. All €10m + projects/procurements will remain on the list until they have been reported as completed.

Project Details Year: Parent Department: Name of Contracting Body: Name of Project/Description:

Procurement Details Advertisement Date: Tender Advertised in: Awarded to: EU Contract Award Notice Date: Contract Price:

Progress Start Date: Expected Date of Completion per Contract: Spend in Year under Review: Cumulative Spend to End of Year: Projected Final Cost: Value of Contract Variations: Date of Completion:

Outputs Expected Output on Completion (E.G. XX kms of Road, No of units etc)

Output Achieved to date (E.G. X kms of Roads, No of Units etc)

Notes:

o The requirement to publish relates specifically to procurement and not the project so where a project is reported at over €10m the interpretation here is that the project is examined and only the elements of that project that were the subject of a procurement process for a contract in excess of €10m needs to be reported. Therefore if a project with a total expenditure in excess of €10m is made up of procurements assigning more than one contractor and none of these contracts exceed the €10m threshold then there is no requirement to include them in the list for publication.

o Year = Year of review o Parent Department = LA name

Page 10: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 9

Step 3 Checklists to be completed There are 7 Checklists and the purpose of the checklists is to provide a self assessment overview of how compliant they have been with the Public Spending Code. The checklists published in the original spending code publication have been amended and the revised checklists are included in Appendix B.

The 7 Checklists are as follows: Checklist 1: General Obligations not specific to individual projects/programmes Checklist 2: Capital Projects or Capital Grant Schemes being considered Checklist 3: Current expenditure being considered Checklist 4: Capital Expenditure being incurred Checklist 5: Current Expenditure being incurred Checklist 6: Capital Expenditure completed Checklist 7: Current expenditure completed

All seven checklists must be completed. Checklist 1 is designed to capture obligations/good practices that apply to the organisation as a whole. Each of the remaining 6 checklists are required to be completed by each organisation for each of the expenditure types (Only one per expenditure type is required i.e. it is not a requirement to complete a checklist for each project or programme) with the following approach being taken.

The Checklists are informed by the Project Inventory so put simply the following table outlines the approach for the completion of the Checklists

Checklist Completion aligned with Project Inventory Expenditure Type Checklist to be completed

General Obligations General Obligations - Checklist 1 A. Expenditure being considered Capital Projects/Programmes - Checklist 2

Current Expenditure – Checklist 3 B. Expenditure being incurred Capital Projects/Programmes – Checklist 4

Current Expenditure – Checklist 5 C. Expenditure that has recently

ended Capital Projects/Programmes – Checklist 6 Current Expenditure – Checklist 7

• Organisations are asked to estimate their compliance on each item on a 3 point scoring scale

o Scope for significant improvements = a score of 1 o Compliant but with some improvement necessary = a score of 2 o Broadly Compliant = a score of 3

• This self-assessed estimate of compliance can be based on an appropriate sample

of the projects/areas of expenditure that are relevant to the checklist. • The sample could be 5-10% of projects/programmes. • The sample should rotate from year to year.

The Checklists need to be interpreted from a Local Authority perspective e.g. Reference in the checklists to “Department” should be interpreted as Local Authority. See question 1 on Checklist 1 for a sample of such a reference.

Page 11: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 10

Step 4 Indepth Check on small number of projects The value of the projects selected for in depth review each year should be at least 5% of the total value of all projects on the Project Inventory. This minimum is an average over a three year period.

The same projects should not be selected more than once in a three year period unless it is a follow up to a serious deficiency discovered previously. Over a 3 – 5 year period all stages of the project life cycle and every scale of project should have been included in the in depth check.

Step 4 looks at a small subset of schemes reported on the Project Inventory, looking in more detail at the quality of the Appraisal, Planning and/or Implementation stages to make a judgement on whether the work was of an acceptable standard and that they are in compliance with the Public Spending Code. Step 5 Complete Summary Report for NOAC The summary report for NOAC is required to be submitted by the end of May each year (agreed with NOAC in 2015) in respect of the previous calendar/financial year.

The report is required to contain: 1. Project Inventory prepared. 2. Website reference for where the procurements over €10m are published. 3. A copy of the completed checklists. 4. The report compiled following the in depth review of a subset of schemes. 5. A note of how inadequacies identified in the QA process will be addressed.

The report is to be certified by the Accounting Officer and published on the organisation’s website.

Page 12: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 11

6. Summary and Conclusion The Public Spending Code can be broken down into 3 main elements as follows A. Compliance with requirements at each stage of the Expenditure life cycle as

follows • Appraisal: assessing the case for a policy intervention

• Planning/Design: a positive appraisal should lead on to a considered approach to designing how the project/programme will be implemented

• Implementation: careful management and oversight is required for both capital and current expenditure. Ongoing evaluation should also be a feature

of current programmes • Post-Project or Post-Implementation Review: checking for delivery of project

objectives, and gaining experience for future projects.

Sections B – D of the Public Spending Code specifically relate to this requirement B. Compliance with reporting requirements during each stage of a capital project by

reporting regularly (at least every six months) to its MAC or Management Board and to the Minister on the appraisal of capital projects prior to approval, the management of capital projects and on progress on its capital programmes and highlighting variances against the agreed budget and by preparing an Annual Report on the capital investment programme.

C. Compliance with the Quality Assurance requirements of the PSC

The QA exercise involves 5 steps 1. Drawing up inventories of projects/programmes at the different stages of the

Project Life Cycle. 2. Publishing summary information on its website of all procurements in excess

of €10m, related to projects in progress or completed in the year under review.

3. Completing the checklists contained in the PSC. Only one of each of the 7 checklists per Department/Agency/Local Authority is required.

4. Carrying out a more in-depth check on a small number of selected projects/programmes.

5. Completing a short summary report for the National Oversight and Audit Commission (NOAC) to be submitted by the end of May in respect of the previous calendar year.

Based on the summary above the following table sets out, from a local government perspective how the Public Spending Code should be implemented and operated in Local Authorities.

Page 13: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 12

Public Spending Code – A Local Government Perspective Element of PSC Action Required

A Compliance with requirements at each stage of the Expenditure life cycle

• Notice from CE to all staff in Local Authority notifying them of their obligations to meet the requirements of the PSC.

• Communication from CE to any organisation/body receiving funding from LA in excess of €0.5m notifying them of their obligations to meet the requirements of the PSC and confirm this to the LA

B Compliance with reporting requirements during each stage of a capital project

• Notices from CE at A above to include an element referring to the reporting requirements for each stage of the project.

C Compliance with Quality Assurance requirements of PSC

Step 1 – Project Inventory (To be assigned to Coordinator as determined by CE)

• As Sponsoring Authority – compile inventory of all projects (current & capital) of €0.5m or greater

• As Sanctioning Authority – compile inventory of all project allocations (if any) of €0.5m or greater

Step 2 – Summary Information on Website

Coordinator to extract projects of €10m or greater and publish any procurement element of €10m or greater for publication in the format required.

Step 3 – Complete Checklists Checklist 1 – General Overview Checklists 2 – 7 required to be based on an overall assessment supported by a sample test of projects/programmes relevant to the Checklist.

Coordinator to complete Checklist 1 and based on the projects in the Project Inventory select the appropriate projects and complete Checklists 2 – 7 based on evidence provided by Project/Programme Owners within the organisation.

Step 4 – In depth Check on a small number of projects

Internal Audit to include this check in their Annual Audit Plan and complete and report on the check as required in the PSC.

Step 5 – Summary Report for NOAC and for publishing on Website

Coordinator to compile report and include all elements from Steps 1 to 4 as required by PSC.

Page 14: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 13

APPENDIX A

PUBLIC SPENDING CODE (PSC)

EXPLANATORY TEMPLATE FOR PROJECT INVENTORY

Page 15: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 14

XXXXXX County Council Inventory of Projects and Programmes over €0.5m

The following contains an inventory of Expenditure on Projects/Programmes with a value above €0.5m, categorised by Expenditure being considered, Expenditure being incurred and Expenditure recently ended. Only projects with expenditure matching these criteria are included in the Inventory table

Expenditure Being Considered

Project/ Programme Description

Revenue Expenditure

Capital Expenditure

Note 1 Note 2 Note 3

Expenditure Being Incurred

Project/ Programme Description

Revenue Expenditure

Capital Expenditure

Note 1

Expenditure Recently Ended

Project/ Programme Description

Revenue Expenditure

Capital Expenditure

Note 1

Note 1: New Line to be added for each named Project/Programme Capital Project to be included at individual project level Revenue Programme to be included at Service Level. Note 2: Capital Expenditure is to be included as total value of project Revenue Expenditure is to be included as total of Service Note 3: Only increases in Revenue Budget of €0.5m or more are included in this category This template is now only for the purpose of explanation of entries. NOAC have provided LAs with an excel version of the template to be used for submissions from 2015. A copy of the revised version is included in Appendix B for reference purposes

Page 16: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 15

APPENDIX B

PUBLIC SPENDING CODE (PSC)

PROJECT INVENTORY TEMPLATE

For reference only

Submissions to NOAC must be submitted in Excel Format

Page 17: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 16

Local Authority Expenditure being considered Expenditure being incurred Expenditure recently ended

Current Capital > €0.5m > €0.5m

Local Authority

> €0.5m Capital Grant Schemes >

Capital Projects

Current Expenditure

Capital Grant Schemes

Capital Projects

Current Expenditure

Capital Grant Schemes

Capital Projects

€0.5m €0.5 -

€5m €5 - €20m €20m plus

Council

Housng & Building

Road Transportation and Safety

Water Services

Development Management

Environmental Services

Recreation and Amenity

Agriculture, Education, Health and Welfare

[Insert other category/s if required]

Miscellaneous Services

Page 18: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 17

APPENDIX C

PUBLIC SPENDING CODE (PSC)

CHECKLISTS 1 - 7

Page 19: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 18

Checklist 1 – To be completed by All Local Authorities General Obligations not specific to individual projects/programmes

Self-Assessed Compliance

Rating: 1 – 3

Comment/Action Required

Does the Local Authority ensure, on an ongoing basis that appropriate people within the Local Authority and in its agencies are aware of the requirements of the Public Spending Code?

3

All information made available in respect of the PSC is circulated within the organisation to keep appropriate people fully informed of

Has there been participation by relevant staff in external training on the Public Spending Code (i.e. DPER)

Has Internal training on the Public Spending Code been provided to relevant staff?

Has the Public Spending Code been adapted for the type of project/programme that your Local Authority is responsible for? i.e. have adapted sectoral guidelines been developed?

Has the Local Authority in its role as Sanctioning Authority satisfied itself that agencies that it funds comply with the Public Spending Code?

Have recommendations from previous Quality Assurance exercises (incl. old Spot-Checks) been disseminated, where appropriate, within the Local Authority and to your agencies?

Have recommendations from previous Quality Assurance exercises been acted upon?

Has an annual Public Spending Code Quality Assurance Report been submitted to the National Oversight and Audit Commission (NOAC)?

Was the required sample subjected to a more in-depth Review i.e. as per Step 4 of the QA process?

Has the Accounting Officer signed off on the information to be published to the website?

Page 20: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 19

Checklist 2: – to be completed in respect of capital projects or capital programme/grant scheme that is or was under consideration in the past year. Capital Expenditure being considered - Appraisal and Approval

Self-Assessed Compliance

Rating: 1 – 3

Comment/Action Required

Was a Preliminary Appraisal undertaken for all projects > €5m

Was an appropriate appraisal method used in respect of each capital project or capital programme/grant scheme?

Was a CBA/CEA completed for all projects exceeding €20m?

Was the appraisal process commenced at an early stage to facilitate decision making? (i.e. prior to

the decision)

Was an Approval in Principle granted by the Sanctioning Authority for all projects before they entered the Planning and Design Phase (e.g. procurement)?

If a CBA/CEA was required was it submitted to DPER (CEEU) for their view?

Were the NDFA Consulted for projects costing more than €20m?

Were all projects that went forward for tender in line with the Approval in Principle and if not was the detailed appraisal revisited and a fresh Approval in Principle granted?

Was approval granted to proceed to tender?

Were Procurement Rules complied with?

Were State Aid rules checked for all supports?

Were the tenders received in line with the Approval in Principle in terms of cost and what is expected to be delivered?

Were Performance Indicators specified for each project/programme which will allow for the evaluation of its efficiency and effectiveness?

Have steps been put in place to gather the Performance Indicator data?

Page 21: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 20

Checklist 3: – New Current expenditure or expansion of existing current expenditure under consideration Current Expenditure being considered - Appraisal and Approval

Self-Assessed Compliance

Rating: 1 - 3

Comment/Action Required

Were objectives clearly set?

Are objectives measurable in quantitative terms?

Was an appropriate appraisal method used?

Was a business case incorporating financial and economic appraisal prepared for new current expenditure?

Has an assessment of likely demand for the new scheme/scheme extension been estimated based on empirical evidence?

Was the required approval granted?

Has a sunset clause been set?

Has a date been set for the pilot and its evaluation?

Have the methodology and data collection requirements for the pilot been agreed at the outset of the scheme?

If outsourcing was involved were Procurement Rules complied with?

Were Performance Indicators specified for each new current expenditure proposal or expansion of existing current expenditure which will allow for the evaluation of its efficiency and effectiveness?

Have steps been put in place to gather the Performance Indicator

Page 22: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 21

Checklist 4: - Complete if your organisation had capital projects/programmes that were incurring expenditure during the year under review. Incurring Capital Expenditure

Self-Assessed Compliance

Rating: 1 – 3

Comment/Action Required

Was a contract signed and was it in line with the approval in principle?

Did management boards/steering committees meet regularly as agreed?

Were Programme Co-ordinators appointed to co-ordinate implementation?

Were Project Managers, responsible for delivery, appointed and were the Project Managers at a suitable senior level for the scale of the project?

Were monitoring reports prepared regularly, showing implementation against plan, budget, timescales and quality?

Did the project keep within its financial budget and its time schedule?

Did budgets have to be adjusted?

Were decisions on changes to budgets/time schedules made promptly?

Did circumstances ever warrant questioning the viability of the project and the business case incl. CBA/CEA? (exceeding budget, lack of progress, changes in the environment, new evidence)

If circumstances did warrant questioning the viability of a project was the project subjected to adequate examination?

If costs increased was approval received from the Sanctioning Authority?

Were any projects terminated because of deviations from the plan, the budget or because circumstances in the environment changed the need for the investment?

For significant projects were quarterly reports on progress submitted to the MAC and to the Minister?

Page 23: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 22

Checklist 5: - For Current Expenditure Incurring Current Expenditure

Self-Assessed Compliance

Rating: 1 - 3

Comment/Action Required

Are there clear objectives for all areas of current expenditure?

Are outputs well defined?

Are outputs quantified on a regular basis?

Is there a method for monitoring efficiency on an ongoing basis?

Are outcomes well defined?

Are outcomes quantified on a regular basis?

Are Unit Costings compiled for performance monitoring?

Is there a method for monitoring effectiveness on an ongoing basis?

Is there an annual process in plan to plan for new VFMs, FPAs and evaluations?

How many formal VFMs/FPAs or other evaluations have been completed in the year under review?

Have all VFMs/FPAs been published in a timely manner?

Is there a process to follow up on the recommendations of previous VPMs/FPAs and other evaluations?

How have the recommendations of VFMs, FPAs and other evaluations informed resource allocation decisions?

Page 24: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 23

Checklist 6: - to be completed if capital projects were completed during the year or if capital programmes/grant schemes matured or were discontinued. Capital Expenditure Completed

Self-Assessed Compliance

Rating: 1 - 3

Comment/Action Required

How many post-project reviews were completed in the year under review?

Was a post project review completed for all projects/programmes exceeding €20m?

If sufficient time has not elapsed to allow a proper assessment of benefits has a post project review been scheduled for a future date?

Were lessons learned from post-project reviews disseminated within the Sponsoring Agency and to the Sanctioning Authority?

Were changes made to the Sponsoring Agencies practices in light of lessons learned from post-project reviews?

Was project review carried out by staffing resources independent of project implementation?

Page 25: Public Spending Code (PSC) - County Kildarekildare.ie/CountyCouncil/PublicSpendingCode/PSC - Guidance Note on QA (Version 2).pdfThe requirements in the Public Spending Code (PSC) are

PSC – Quality Assurance Requirement (Guidance Note for Local Authorities) Version 2 Page | 24

Checklist 7: - to be completed if current expenditure programmes that reached the end of their planned timeframe during the year or were discontinued. Current Expenditure that (i) reached the end of its planned timeframe or (ii) Was discontinued

Self-Assessed Compliance

Rating: 1 - 3

Comment/Action Required

Were reviews carried out of, current expenditure programmes that matured during the year or were discontinued?

Did those reviews reach conclusions on whether the programmes were effective?

Did those reviews reach conclusions on whether the programmes were efficient?

Have the conclusions reached been taken into account in related areas of expenditure?

Were any programmes discontinued following a review of a current expenditure programme?

Was the review commenced and completed within a period of 6 months?

Notes:

(a) The scoring mechanism for the above tables is set out below I. Scope for significant improvements = a score of 1

II. Compliant but with some improvement necessary = a score of 2 III. Broadly Compliant = a score of 3

(b) For some questions, the scoring mechanism is not always strictly relevant. In these

cases, it is appropriate to mark as N/A and provide the required information in the commentary box as appropriate.

(c) The focus should be on providing descriptive and contextual information to frame the

compliance ratings and to address the issues raised for each question. It is also important to provide summary details of key analytical outputs for those questions which address compliance with appraisal/evaluation requirements i.e. the annual number of CBAs, VFMs/FPAs and post project reviews.