Agenda
• Call Meeting to Order • Approval of Minutes • Program Schedule Review • Phase 1 MOT Plan Update • LS 87 Landscape Plan • Phase 1 Schedule Review • Outstanding Business • New Business • Public Input • Adjournment
![Page 3: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/3.jpg)
Program Overview
PHASE 3 LS 87 Gravity
Mains
PHASE 1 LS 87 Microtunneling
PHASE 2 LS 87 Structure
PHASE 3 LS 7 Demo and
Restoration
ALTA VISTA STREET
US 41
POMELO AVE O
SPR
EY
AVE
POM
ELO
PL
ACE
Construction Sequencing – 3 Phases
![Page 4: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/4.jpg)
Program Overview
Phase Start Finish
2015 2016 2017 2018 2019 2020
Q 1/2
Q 3/4
Q 1/2
Q 3/4
Q 1/2
Q 3/4
Q 1/2
Q 3/4
Q 1/2
Q 3/4
Q 1/2
Q 3/4
Con
stru
ctio
n
Phase 1 May 2016
July 2017
Phase 2 May 2017
Oct. 2019
Phase 3 Aug. 2019
Dec. 2020
Projected Construction Timelines
![Page 5: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/5.jpg)
Phase 1 – Lift Station 87 Microtunneling Maintenance of Traffic Plan Update
To maintain safe traffic flow during construction by:
• Directing traffic to Mound Street/US 41 to avoid neighborhoods
• Addressing pedestrian detours and sidewalk closures
• Identifying access to businesses on Osprey Avenue
![Page 6: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/6.jpg)
Lift Station 87 Landscape Plan
Public Participation Overview
• Series of Public Meetings Hover Arcade
Brick Façade
• Public Meeting – July 26, 2016
![Page 7: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/7.jpg)
Red Brick Option
![Page 8: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/8.jpg)
Sarasota High School
![Page 9: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/9.jpg)
Landscape Architectural Renderings
• Site Plan Application
December 2014
Input from Urban Design Studio
• Landscape Architect – David W. Johnston Associates, Inc.
Phillip J. Smith, ASLA
![Page 10: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/10.jpg)
![Page 11: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/11.jpg)
![Page 12: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/12.jpg)
![Page 13: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/13.jpg)
![Page 14: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/14.jpg)
![Page 15: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/15.jpg)
![Page 16: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/16.jpg)
![Page 17: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/17.jpg)
![Page 18: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/18.jpg)
Phase 1 Schedule Review
• Jacking Shaft MH17 (Between Lincoln and Bridge)
October/November 2016
• Receiving Shaft MH21 (Osprey/US 41 Intersection) December 2016/January 2017
• Jacking Shaft MH24 (Luke Wood Park) December 2016/January 2017
![Page 19: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/19.jpg)
Phase 1 Schedule Review
• MT Drive 1 (Osprey Avenue)
December/January 2017
• MT Drive 2 (Luke Wood Park) February 2017
• Demobilization July 2017
![Page 20: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/20.jpg)
• Outstanding Business
• New Business
![Page 21: Public Meeting November 9, 2016 SRQ Media Room](https://reader031.fdocuments.net/reader031/viewer/2022020203/58a31d1f1a28ab41128bc526/html5/thumbnails/21.jpg)
Public Input