PUBLIC INFORMATION PLAN
PROJECT/ACTIVITY:Crozet Destination Downtown
PURPOSE AND NEED:Crozet has several projects that are either currently in-progress or about to begin in the near
future. The purpose of this plan is to establish a strategy to help us navigate the
communications aspect of these projects in an organized way.
The two main projects are:
Crozet Library Destination Downtown Streetscape & Stormwater
COMMUNICATIONS METHODS: Albemarle website: Updates to site to reflect upcoming project activities and latest
project information and photo updates.www.albemarle.org/crozet
News releases: To Charlottesville area news media Social media: Albemarle County Facebook TV and radio availability: Staff available for location and/or studio interviews about
project updates
Newspaper advertising: If needed A-Mail: Use Albemarle Countys A-mail list. Continue the loop by soliciting more
subscribers with each distribution.
Town Hall meeting: County Staff on-hand to present the most up-to-date informationand to answer any questions
CCAC Outreach Albemarle County School Division
CROZET LIBRARY:
MAJOR MILESTONES
Bids opened March 28, 2012, MB contractors low bid at $5.81M BOS approved budget, including capital program 4/11/12 Moving through contract process with MB, expect contract approval Mid-May, notice toproceed June. Anticipate 12 months construction Impacts to Crozet
o Stormpipe installation in Crozet Ave latter June/early Julyo Occasional work on frontage area that encroaches into Crozet Ave into Fallo Occasional noise, but generally reasonable level
Groundbreaking ceremony Late June, 2012
http://www.albemarle.org/crozethttp://www.albemarle.org/crozethttp://www.albemarle.org/crozethttp://www.albemarle.org/crozet -
7/31/2019 Public information plan for Crozet - Destination Downtown
2/4
Estimated duration of project: 12 monthsSTAKEHOLDERS/PARTNERSHIPS:
County staff Contractors Crozet residents CCAC CCA Area businesses Schools Library Board/Friends of the Library Donors
KEY MESSAGES:
The Crozet Library will become the focal point for the downtown community and willexpand opportunities for economic vitality for existing and new downtown businesses
The library will be designed and constructed to support the programming needs andspecifications of the Jefferson Madison Regional Library Board
DESTINATION DOWNTOWN - STREETSCAPE & STORMWATER
MAJOR MILESTONES:
Streetscape
Library Avenue and alley improvements complete Utility relocation expected to commence by May 24th estimated 30-day project Obtain remaining right-of-way/easement dedications Right-of-way consultant is completing deed of trust issues on a couple dedications; plans
to be wrapped up by end of May
Groundbreaking ceremony TBD Estimated duration of project: TBD
Stormwater Earthwork to be completed early April Channel and Forebay grading complete Currently excavating Wetland area 3 wooden bridges to be installed across channel in April Soil stabilization and planting to be installed April May Storm drain off Crozet Avenue to be installed in May Estimated project completion: June 1, 2012
STAKEHOLDERS/PARTNERSHIPS:
County staff
-
7/31/2019 Public information plan for Crozet - Destination Downtown
3/4
Contractors Crozet residents CCAC CCA Area businesses Commuters Schools
KEY MESSAGES:
Managing community expectations as to the duration and disruption of this projectunder-promise, over-deliver
The project will provide critical pieces of infrastructure for strengthening downtown asthe community focal point
The project represents significant capital and manpower investment by the county Project consultants and the county will make every effort to keep the public informed
about progress of the project and to minimize disruption to traffic and businesses duringconstruction
Funded in part with grant funds Accurately communicate project goals:
o Aesthetically enhance the entry way and main thoroughfare of Downtown(Crozet Avenue)
o Provide economic benefits and increased vitality to downtown business ownerso Effectively phase construction to help maintain both pedestrian and vehicular
access to Downtown Crozet during construction
o Provide environmentally sensitive solutions to stormwater managementPROPOSED PUBLIC INVOLVEMENT ACTIVITIES/TIMELINE:
ActivityPerson(s)
ResponsibleDate Notes
OFD to attend April CCAC meeting OFD April
County Staff to attend May CCAC meeting County Staff May 17 Review public
information plan
OFD to attend CCA meeting OFD
Website updates, fact sheet, FAQ, photo
gallery completed
County staff June 30
Information booth at Independence Day
Celebration
CCAC June 30 County will provide
appropriate
materials
-
7/31/2019 Public information plan for Crozet - Destination Downtown
4/4
Library groundbreaking County staff,
Library staff
Late June
Town Hall meeting Lee/OFD September
Streetscape Groundbreaking County Staff TBD
Weekly status updates on library and
streetscape progress
County staff Ongoing
Updated: 5/15/12