Public Information Meeting #6 City of Fargo Flood Risk Reduction Projects Rose Creek Coulee
description
Transcript of Public Information Meeting #6 City of Fargo Flood Risk Reduction Projects Rose Creek Coulee
Public Information Meeting #6
City of Fargo Flood Risk Reduction Projects
Rose Creek Coulee
October 9, 2012
Agenda Phase 1 - Project Overview Phase 1 - Project Status Update Phase 2 - Project Overview Phase 2 - Project Schedule Questions
Introduction
Phase 1 – Project Completed June 2012
Phase 1 – Project Status Update
Construction Began October 3, 2011 Project Construction Cost
North Pine Aggregate - $620,000 Completion Date – June 2012 Phase 1 - “To-Do” List/Warranty Items
Minor Grading Around Catch Basins & Area Drains
Seeding Removal of Erosion Control Devices
Phase 2 – Project Overview
Design Considerations Long Term Stability Minimizing Encroachment on to Your Property
While Maintaining the Long Term Stability Original Goal was No Encroachment on to
Private Property, but it was determined to not be Possible due to Existing Site Limitations
Grading Level Rear Yards to the Extent Practical
Phase 2 – Project Overview
Design Considerations (continued) Bike Trail
Replace Bike Trail at Generally the Same Elevation as it is was Prior to Construction
Internal Drainage System PVC Storm Sewer with Concrete Catch
Basins 5 Year Design (3.05” in 24 Hours)
□ 10 Year Event (3.77” in 24 Hours)□ July 2011 Event (1.18” in 1 Hour)
Three (3) Surge Basins
Phase 2 – Project Overview
Flood Protection Levels Earthen Levee
Flood Stage 43 (1 Foot Below Temporary Levee)□ This is lower than what has been done in other locations
in Town due to the Geotechnical Engineer’s findings that the existing material on site has become consolidated due to the temporary levee being in place for the past couple years.
Structural Wall Flood Stage 45 (1 Foot Below Temporary Levee) 5 Feet Exposed
Phase 2 – Project Overview
Phase 2 – Project Overview
Phase 2 – Project Overview
Phase 2 – Project Overview
Phase 2 – Project Overview
Phase 2 – Project Overview
Phase 2 – Project Overview
Phase 2 – Project Overview
Phase 2 Project Overview – Timberline Flood Wall
Backfilled Flood Wall withApproximately 7 feet of Exposed
Flood Wall
Flood Wall Prior to Backfilling
Phase 2 Project Overview – Timberline Flood Wall
Phase 2 Project Overview – Timberline Flood Wall
Phase 2 Project Overview – Timberline Flood Wall
Phase 2 Project Overview – Timberline Flood Wall
Phase 2 – Project Schedule
October 2012/November 2012 Finalize Construction Plans and Specifications Begin Easement Acquisition
Stake Permanent Easements Meet with the City of Fargo & Ulteig Right-of-Way
Agent(s)
December 2012 Prepare Project to Present to the City
Commissioners for Approval to go to out for Bids Finalize Easement Acquisition
Phase 2 – Project Schedule
January 2013 Advertise & Receive Contractor BidsFebruary 2013 Award Construction ContractsMay 2013 – November 2013 Construction
Easement Acquisition Process Initial Contact (Easement Acquisition Form)
□ Donate□ Minimum Payment Policy□ Mutual Agreed Amount□ Appraised
Appraisal Review Offer with Copy of Appraisal Mailed Out Closing Set Up Recording of Documents
Phase 2 – Project Schedule
Easement Acquisition Process (Continued) The City also has an irrigation policy in
place that will reimburse the property owner for repairs to their irrigation system that was damaged due to the temporary levee construction.
This policy has a maximum staff discrepancy of $1,000.00.
Phase 2 – Project Schedule
Questions?