Project ProposalDocument Optimization
15 February 2007
Team members: Chris CatalanoChun-Yu ChangChris JosonDavid Matthes
Problem Statement
Heron Consultancy• Process in place to filter legal documents through lawyers
Aerospace Corporation• Evaluation of SysML as a Systems Engineering tool.
Background: Heron Consultancy
Current EDD Process Diagram
Statement of Work (SOW)
Develop Methodology / Process to data mine legal documents with the best lawyers and the right cost.
Scope
Technical Approach
• Understand Problem
• Analyze Historical Data
• Develop Methodology
• Define/Design/Model System
• Verify/Validate System
Understand Problem
• Determine extent & nature of deviations from past trends
• Identify/analyze factors & conditions that allow or hinder flow of documents from one stage to the next
• Interview Stakeholder
Data Types:
• Archives of Data
Sources:
• Heron
Analyze Historical Data
Develop Methodology
• Create SysML Model of Current EDD Process
• Analyze SysML Model with historical data
• Create New Document Process using Autonomy Software
• Create New Document Process using Attenex Software
• Model the Implementation of an Improved EDD Process
Define / Design / Model System
• Define and Validate System Requirements• Requires Stakeholder Input
• Develop Process Architecture
• Code / Model
Preliminary Requirements
Verification & Validation
• V&V is critical to User/Stakeholder acceptance of the system
• Verification (Did we build the thing right?)• Originating and Derived Requirements must be testable /
verifiable.• Verification Methods: Inspection & Test
• Validation (Did we build the right thing?)• Method: Demonstration
– Validate against scenarios with known outcomes
Key Deliverables
• Proposal (document and presentation)
• Status Reports
• Executable Models
• Final Report (document and presentation)
Project Management
Schedule
Team Responsibilities
Top Level Schedule
Team Collaboration
• Group site established:http://webct41.gmu.edu
• Check emails/group site at least once a day
• Set up a due date/time for each milestone