CVE 4070 Construction Engineering Construction Estimating Prof. Ralph V. Locurcio, PE.
Project Management Requirements Prof. Ralph Locurcio, PE Dr. Troy Nguyen, PE.
-
Upload
daniella-lucas -
Category
Documents
-
view
215 -
download
0
description
Transcript of Project Management Requirements Prof. Ralph Locurcio, PE Dr. Troy Nguyen, PE.
CON 4091 - PROJECT 1Project Management
Requirements
Prof. Ralph Locurcio, PEDr. Troy Nguyen, PE
Project Phases Project 1 – Prepare proposal – Fall Semester
Purpose is to win the project Proposal must state why your team is best Must include a Project Management Plan in the proposal Must include your proposed fee
Project 2 – Construct the project – Spring Semester Verify the proposal @ 5% stage Construction phases @ 15, 50, 95, 100% Develop project details & construction drawings Manage & report on status@15, 50, 95,100% Integrate all elements into unified project Prepare display for Design Showcase in April Estimate cost of construction @ 15, 50, 95,100% Prepare and include a construction schedule Turn in written report
Proposal Contents-11.Title Page – follow instructions2.Table of Contents – separate tab for each section3.Introduction
Problem Statement, Background & Scope of Work - what’s included & what’s not Discussion of Key Elements, Project Sketch – what is it,
geometry Team Organization – who will do it
4. Project Management Plan Work Breakdown Structure & Project Budget Project Flow Diagram – flow of design tasks over time
(Draft-1) Design Schedule (MS Project) – (Draft-2) Construction Cost Estimate – cost to actually build the
project Conceptual in Proposal, 5% & 15% design Detailed at 50%, 95% & 100% in Design-2 Construction schedule at 50% – when project will be built
Proposal Contents-26.Project Sketch & Layout
Shows boundaries and major features Sketch adds “proposed” size & features All team members should participate in these drawings
7.Design Investigation Report Written Technical Report – consult with advisor Include such items as:
• Problem(s) to be solved in the design• Logic of size of key features• Options considered; cite the pros & cons of each• Applicable codes, ordinances or criteria that will control the project• Cite all technical information to be used • Concept decision – what engineering design method will be used and why
• Constraints – cite any political, environmental or physical limitations
8. Appendices & List of References
Project Management ToolsYour Project Dashboard
They enable you to be proactive rather than reactive…
Project Management Tools Project Flow Diagram
your road map/GPS
Project Scheduleyour speedometer
Project Budgetyour fuel gauge
Project Design Flow Diagram
Time2 4 6 8 10 12 14 16
General Design
Planning Preparation Construct Core
Trim Exterior
Demobilize
Interior Design Room Const Interior Finishes
Bury PharoahStructure
Site Selection
Master Plan
Open Quarry Cut Blocks Cut Trim
Workforce
Train Train Train
Build Camp
DemobCamp
FinalInsp
Flow Diagram-2
Work Breakdown Structure
Work Breakdown Structure
Don’t forgetTo update durationAt each % stage!!!WBS
Design Budget
Don’t forgetTo show totalsAt each % stage!!!
Don’t forgetTo update durationAt each % stage!!!
Budget
Design & Construction Schedules
Cost Estimates Conceptual Construction Cost Based on historical data
Itemize components. Use cost per SF or unit pricing data Data from similar project Be sure to update for location & timing
Cost Estimates Detailed Construction Cost – 50%, 95%, 100%
Due in Project-2 reports Based on actual data Itemize all components More detail as design is completed Obtain pricing for elements online, RS Means,
other. Include all cost elements: materials, labor, logistics See template; all use same format Be sure to summarize cost of entire project Should be 90-95% accurate
Cost Estimate Template
Questions????
http://my.fit.edu/~locurcio/05-CON 4091-Const Capstone
Slides & Sample documents located at: