Project Management Professional Development Series:
eBuilder Power User Series – “Reporting”
Facilities and Campus Services Engineering and Project ManagementMay 2019
![Page 2: Project Management Professional Development Series ... · Project presentation to Il-PC Commission which was approved as submitted CD Phase ongoing Project Issues Full funding for](https://reader034.fdocuments.net/reader034/viewer/2022050513/5f9dabe8619dca5578531478/html5/thumbnails/2.jpg)
eBuilder Power User Series – “Reporting”
• Key Project Indicators (KPIs) across FCS
• Status Update Field in eBuilder
• Business Intelligence - Project Status Update
Exciting Reporting Initiatives Underway
![Page 3: Project Management Professional Development Series ... · Project presentation to Il-PC Commission which was approved as submitted CD Phase ongoing Project Issues Full funding for](https://reader034.fdocuments.net/reader034/viewer/2022050513/5f9dabe8619dca5578531478/html5/thumbnails/3.jpg)
Key Project Indicators (KPIs) across FCS
1. E&PM Project Volume (by project phase)
2. PCO Categories (three project budget ranges)
3. OPC vs Bid
4. Standards Reviewed, Updated and Added
5. Number of Design Reviews Performed
6. Number of Construction Documents Issued
E&PM Big Picture KPIs
Capi
tal P
roje
cts
Stew
ards
hip
& D
esig
n
![Page 4: Project Management Professional Development Series ... · Project presentation to Il-PC Commission which was approved as submitted CD Phase ongoing Project Issues Full funding for](https://reader034.fdocuments.net/reader034/viewer/2022050513/5f9dabe8619dca5578531478/html5/thumbnails/4.jpg)
E&PM Project Volume
![Page 5: Project Management Professional Development Series ... · Project presentation to Il-PC Commission which was approved as submitted CD Phase ongoing Project Issues Full funding for](https://reader034.fdocuments.net/reader034/viewer/2022050513/5f9dabe8619dca5578531478/html5/thumbnails/5.jpg)
OPC vs BidBy Project
By Consultant
![Page 6: Project Management Professional Development Series ... · Project presentation to Il-PC Commission which was approved as submitted CD Phase ongoing Project Issues Full funding for](https://reader034.fdocuments.net/reader034/viewer/2022050513/5f9dabe8619dca5578531478/html5/thumbnails/6.jpg)
Phase Dropdown- Pre-Design- Design- Construction- Closeout
Status Update Field in eBuilder
Pilot Program Feedback
![Page 7: Project Management Professional Development Series ... · Project presentation to Il-PC Commission which was approved as submitted CD Phase ongoing Project Issues Full funding for](https://reader034.fdocuments.net/reader034/viewer/2022050513/5f9dabe8619dca5578531478/html5/thumbnails/7.jpg)
Project Status Update Field in eBuilder
Collaboration Report (Per PM Group)
![Page 8: Project Management Professional Development Series ... · Project presentation to Il-PC Commission which was approved as submitted CD Phase ongoing Project Issues Full funding for](https://reader034.fdocuments.net/reader034/viewer/2022050513/5f9dabe8619dca5578531478/html5/thumbnails/8.jpg)
Project Status Update Field in eBuilder
Bid Phase Schedule Report
![Page 9: Project Management Professional Development Series ... · Project presentation to Il-PC Commission which was approved as submitted CD Phase ongoing Project Issues Full funding for](https://reader034.fdocuments.net/reader034/viewer/2022050513/5f9dabe8619dca5578531478/html5/thumbnails/9.jpg)
Business Intelligence - Project Status
Update
![Page 10: Project Management Professional Development Series ... · Project presentation to Il-PC Commission which was approved as submitted CD Phase ongoing Project Issues Full funding for](https://reader034.fdocuments.net/reader034/viewer/2022050513/5f9dabe8619dca5578531478/html5/thumbnails/10.jpg)
Business Intelligence - Project Status Update
Status Field!!
Description Budget Summary
Schedule Milestones!!
Commitment Summary
A/E Invoice Summary
ContingencySummary
![Page 11: Project Management Professional Development Series ... · Project presentation to Il-PC Commission which was approved as submitted CD Phase ongoing Project Issues Full funding for](https://reader034.fdocuments.net/reader034/viewer/2022050513/5f9dabe8619dca5578531478/html5/thumbnails/11.jpg)
Business Intelligence - CM Statistics
![Page 12: Project Management Professional Development Series ... · Project presentation to Il-PC Commission which was approved as submitted CD Phase ongoing Project Issues Full funding for](https://reader034.fdocuments.net/reader034/viewer/2022050513/5f9dabe8619dca5578531478/html5/thumbnails/12.jpg)
No More Slides!!
June 1st