Project Management CH9 Project Scheduling
-
Upload
izah-asmadi -
Category
Education
-
view
614 -
download
5
description
Transcript of Project Management CH9 Project Scheduling
Chapter 9
Project Scheduling: Networks, Duration Estimation, and
Critical Path
09-01
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Chapter 9 Learning Objectives
After completing this chapter, students will be able to:
Understand and apply key scheduling terminology.
Apply the logic used to create activity networks, including predecessor and successor tasks.
Develop an activity network using Activity-on-Node (AON) techniques.
Perform activity duration estimation based on the use of probabilistic estimating techniques.
09-02
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Chapter 9 Learning Objectives
After completing this chapter, students will be able to:
Construct the critical path for a project schedule network using forward and backward passes.
Identify activity float and the manner in which it is determined.
Calculate the probability of a project finishing on time under PERT estimates.
Understand the steps that can be employed to reduce the critical path.
09-03
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Project Scheduling Project scheduling requires us to follow some
carefully laid-out steps, in order, for the schedule to take shape.
Project planning, as it relates to the scheduling
process, has been defined by the PMBoK as:
The identification of the project objectives and the ordered activity necessary to complete the project including the identification of resource types and quantities required to carry out each activity or task.
09-04
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Project Scheduling Terms
• Successors
• Predecessors
• Network diagram
• Serial activities
• Concurrent activities
09-05
E D
C
B
A F
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Project Scheduling Terms
09-06
E D
C
B
A F
• Merge activities
• Burst activities
• Node
• Path
• Critical Path
FIGURE 9.2 Alternative Activity Networks for Term Paper Assignment
Network Diagrams
09-07
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
AOA Versus AON
The same mini-project is shown with activities on arc…
09-08
C
E D
B F
E
C
D B F
…and activities on node.
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Node Labels
09-9
Early Start
Activity Float
Activity Descriptor
Late Start
ID Number
Activity Duration Late Finish
Early Finish
FIGURE 9.4
Activity Node Labels Using MS Project 2010
09-10 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
FIGURE 9.5
Serial Activities
09-11
Serial activities are those that flow from one to the next, in sequence.
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
FIGURE 9.6
Activities Linked in Parallel (Concurrent)
09-12 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
When the nature of the work allows for more than one activity to be accomplished at the same time, these activities are called concurrent and parallel project paths are constructed through the network.
FIGURE 9.7
Merge Activity
09-13 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
FIGURE 9.8
Burst Activity
09-14 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
FIGURE 9.10
Complete Activity Network
09-15 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
FIGURE 9.11
Developing the Activity Network Using MS Project 2010
09-16 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Duration Estimation Methods
• Past experience
• Expert opinion
• Mathematical derivation – Beta distribution
– Most likely (m)
– Most pessimistic (b)
– Most optimistic (a) 4
= TE6
a m bActivity Duration
09-17
2
2 = 6
b aActivity Variance s
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
FIGURE 9.14 Symmetrical (Normal) Distribution for
Activity Duration Estimation
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 09-18
FIGURE 9.15 Asymmetrical (Beta) Distribution for Activity Duration Estimation
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 09-19
Activity Duration and Variance
09-20
Name: Project Delta
Durations are listed in weeks
Activity Description Optimistic Likely Pessimistic
A Contract signing 3 4 11
B Questionnaire design 2 5 8
C Target market ID 3 6 9
D Survey sample 8 12 20
E Develop presentation 3 5 12
F Analyze results 2 4 7
G Demographic analysis 6 9 14
H Presentation to client 1 2 4
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Table 9.2
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Constructing the Critical Path
• Forward pass – an additive move through the network from start to finish
• Backward pass – a subtractive move through the network from finish to start
• Critical path – the longest path from end to end which determines the shortest project length
09-21
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Rules for Forward/Backward Pass Forward Pass Rules (ES & EF)
– ES + Duration = EF
– EF of predecessor = ES of successor
– Largest preceding EF at a merge point becomes EF for successor
Backward Pass Rules (LS & LF) – LF – Duration = LS
– LS of successor = LF of predecessor
– Smallest succeeding LS at a burst point becomes LF for predecessor
09-22
Project Delta Information
09-23
Project Delta
Activity Description Predecessors Estimated Duration
A Contract signing None 5
B Questionnaire design A 5
C Target market ID A 6
D Survey sample B, C 13
E Develop presentation B 6
F Analyze results D 4
G Demographic analysis C 9
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Table 9.4
FIGURE 9.16 Partial Project Activity Network with Task Durations
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 09-24
FIGURE 9.18 Activity Network with Forward Pass
09-25 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
FIGURE 9.19 Activity Network with Backward Pass
09-26 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
FIGURE 9.20 Project Network with Activity Slack and Critical Path
Note: Critical path is indicated with bold arrows. 09-27
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
FIGURE 9.24
AON Network with Laddering Effect
09-28 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Laddering Activities
Project ABC can be completed more efficiently if subtasks are used
09-29
A(3) B(6) C(9) ABC=18 days
Laddered ABC=12 days
A1(1) A2(1) A3(1)
B1(2) B2(2) B3(2)
C1(3) C2(3) C3(3)
FIGURE 9.25
Example of a Hammock Activity
09-30 Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Reducing the Critical Path
• Eliminate tasks on the CP
• Convert serial paths to parallel when possible
• Overlap sequential tasks
• Shorten the duration on critical path tasks
• Shorten
– early tasks
– longest tasks
– easiest tasks
– tasks that cost the least to speed up 09-31
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Summary
1. Understand and apply key scheduling terminology.
2. Apply the logic used to create activity networks, including predecessor and successor tasks.
3. Develop an activity network using Activity-on-Node (AON) techniques.
4. Perform activity duration estimation based on the use of probabilistic estimating techniques.
09-32
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Summary
5. Construct the critical path for a project schedule network using forward and backward passes.
6. Identify activity float and the manner in which it is determined.
7. Calculate the probability of a project finishing on time under PERT estimates.
8. Understand the steps that can be employed to reduce the critical path.
09-33
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 09-34