Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing...

28
Copyright © 2014. All rights reserved. 1 Project Controls Expo 18 November 2014 Emirates Stadium, London Progress | Position | Prediction The key to completing projects on time

Transcript of Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing...

Page 1: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 1

Project Controls Expo – 18 November 2014Emirates Stadium, London

Progress | Position | PredictionThe key to completing projects on time

Page 2: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 2

About the Speaker

� David Bordoli

David has over 30 years in the construction industry specialising in planning and scheduling, initially with contractors and latterly as a consultant focusing on forensic delay analysis. David is academically and professionally qualified and is the author of numerous high quality papers. He was awarded an MSc degree with distinction for his work on ‘The simulation of construction project delays using network techniques’, the method of analysis now known as ‘Time Impact Analysis’. His book, ‘A Handbook for Construction Planning and Scheduling’, co-authored with Andrew Baldwin, was published by Wiley Blackwell in May 2014. Most recently he has been engaged as an expert on major projects in South Africa and China.

Page 3: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 3

Cambridge

Page 4: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 4

Cambridge

Pos Club P W D L F A GD Pts1 Leicester City 42 21 13 8 58 38 20 552 Sunderland 42 21 12 9 69 42 27 54

3 Birmingham City 42 21 11 10 58 38 20 53

4 Chelsea 42 23 7 12 66 52 14 535 Queens Park Rangers 42 18 13 11 75 53 22 496 Luton Town 42 16 17 9 66 45 21 497 West Ham United 42 20 7 15 54 43 11 478 Cambridge United 42 14 16 12 61 53 8 449 Newcastle United 42 15 14 13 53 49 4 44

10 Preston North End 42 12 19 11 56 52 4 4311 Oldham Athletic 42 16 11 15 49 53 −4 4312 Swansea City 42 17 9 16 48 53 −5 4313 Shrewsbury Town 42 18 5 19 60 53 7 4114 Leyton Orient 42 12 17 13 48 54 −6 4115 Cardiff City 42 16 8 18 41 48 −7 4016 Wrexham 42 16 6 20 40 49 −9 3817 Notts County 42 11 15 16 51 52 −1 3718 Watford 42 12 13 17 39 46 −7 3719 Bristol Rovers 42 11 13 18 50 64 −14 3520 Fulham 42 11 7 24 42 74 −32 2921 Burnley 42 6 15 21 39 73 −34 2722 Charlton Athletic 42 6 10 26 39 78 −39 22

Page 5: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 5

Cambridge – First Half

Cambridge United v Bolton WanderersSaturday 4 April 1981

1

2

3

4

Half time 2-0

Full time 4-0

Page 6: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 6

Cambridge – Second Half

Cambridge United v Bolton WanderersSaturday 4 April 1981

1

2

3

4

Half time 2-0

Full time 2-3

Page 7: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 7

1

2

3

4

Half time 2-0

Full time 2-3

Cambridge – Full Time

Cambridge United v Bolton WanderersSaturday 4 April 1981

Page 8: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 8

Change

Page 9: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 9

Predictability Time - Construction

Page 10: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 10

Progress | Position | Prediction

� Active management of time comprises three steps

� Measure Progress� Determine Position� Completion Prediction

Progress

ImpossiblePrediction

DifficultPosition

Easy

Prediction is very difficult, especially if it's about the future

Page 11: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 11

Progress – how much has been done

� Progress� Physically complete (%)

� Time expended� Time remaining� Time to complete

Page 12: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 12

Position – what is the current status

� Activity Position� time ahead� on schedule� time behind

if S d TN d F, then if (% < 100, P = S + (D x %) – TN, else P = 0), elseif S d TN t F, then P = S + (D x %) – TN, elseif S t TN, then if (% > 0, P = S + (D x %) – TN, else P = 0)

Where: P is the activity position,S is the planned start of the activity,F is the planned finish of the activity,TN is time now,D is the planned duration of the activity, and% is the percentage complete of the activity at time now.

time now

time ahead

time behind

on schedule

Page 13: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 13

Position – what is the current status

� Project Position� Averaging� Critical Path Methods

SET UP

SUBSTRUCTURES

FRAME

ENVELOPE

FIRST FIX

JOINERY

M & E SECOND

FIT-OUT

COMMISSION

END

-2-10+1

Page 14: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 14

Position – what is the current status

� Project Position� Averaging� Critical Path Methods� Planned Progress Monitoring� Earned Value Analysis

planned

actual

planned

actual

£ m

illio

nPP

M U

nits

Page 15: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 15

Prediction – when will the project end

� Predicting is the estimation or forecasting of some future event or condition of the project as a result of the study and analysis of available data on the basis of observation, experience or scientific reason.

� Experience� Critical Path Analysis� Extrapolation� Reprogramming

� Parkinson’s Law� Student Syndrome

� Earned Value Analysis

Page 16: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 16

0.00

0.50

1.00

1.50

2.00

2.50

3.00

0 5 10 15 20 25 30

valu

e (£

m)

week number

y = -2E-07x6 + 2E-05x5 - 0.0006x4 + 0.0092x3 - 0.0472x2 + 0.1084x - 0.0257R² = 0.9994

Forecasting Using Earned Value Analysis

BAC(planned

completion)

BCWS(planned)

time now

BCWP(actual)

EAC(forecast

completion)

Page 17: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 17

Forecasting Using Earned Value Analysis

0.00

0.50

1.00

1.50

2.00

2.50

3.00

0 5 10 15 20 25 30

valu

e (£

m)

week number

BAC(planned

completion)

BCWS(planned)

time now

BCWP(actual)

EAC(forecast

completion)

Planned completion date (BACt) = 22.0Time now (BCWSt) = 12.0Current position (BCWPt) = 10.0Rate of Progress (SPI) = 10.0 / 12.0 = 0.83Time not yet completed = 22.0 – 10.00 = 12.0Forecast time to complete (ETCt) = 12.0 / 0.83= 14.5Forecast completion date (EACt) = 12.0 + 14.5 = 26.5

Page 18: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 18

Forecasting UsingPlanned Progress Monitoring

0

10000

20000

30000

40000

50000

60000

70000

80000

0 5 10 15 20 25 30

PPM

uni

ts

week number

planned completion

planned

time now

actual

forecast completion

Original project duration (D)= 22Project position (P) = 10Time now (TN) = 12

Completion = D x TN / P= 22 x 12 / 10 = 26.4

Page 19: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 19

A Simple Approach to ForecastingThe Planned Model

0

5

10

15

20

25

0 5 10 15 20 25 30

posi

tion

week number

x = y

planned completion

planned

Page 20: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 20

The Actual Model

0

5

10

15

20

25

0 5 10 15 20 25 30

posi

tion

week number

planned

time now

actual

Page 21: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 21

0

5

10

15

20

25

0 5 10 15 20 25 30

posi

tion

week number

Simple Linear RegressionThe Forecast Model

plannedactual

actual trend

forecast

y = 0.8208x + 0.1522R² = 0.9994Regression Equation: y = a + bxIntercept: a = (ΣY - b(ΣX)) / N Slope: b = (NΣXY - (ΣX)(ΣY)) / (NΣX2 - (ΣX)2)

Where x and y are the variables. b = The slope of the regression line a = The intercept point of the regression line and the y axis. N = Number of values or elements X = First Score Y = Second Score ΣXY = Sum of the product of first and Second Scores ΣX = Sum of First Scores ΣY = Sum of Second Scores ΣX2 = Sum of square First Scores

Page 22: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 22

0

5

10

15

20

25

0 5 10 15 20 25 30

posi

tion

week number

Simple Linear RegressionThe Forecast Model

planned

forecast completion

actual

actual trend

forecast

y = 0.8208x + 0.1522R² = 0.9994

x = 26.6x = y - 0.15220.8208

x = 22 - 0.15220.8208

Page 23: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 23

Project Recovery

0

5

10

15

20

25

0 5 10 15 20 25 30

posi

tion

week number

forecastmaintain

accelerate

Page 24: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 24

0

5

10

15

20

25

0 5 10 15 20 25 30

posi

tion

week number

Ahead and On Programme

ahead

on programme

Page 25: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 25

Conclusion

> Profitability

� Simple linear regression � Takes account of all the position data� Presents in simple straight-line graphs� Understood by non-specialists� Trends are easier to understand� Change needed to bring the project back on schedule is straightforward

to see.

� Progress trends tend to be influenced by leadership, management, resources, experience and strategy decisions.

� Progress > Position > Prediction

Page 26: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 26

Questions?

Page 27: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 27

A Handbook forConstruction Planning and Scheduling

David Bordoli Andrew Baldwin

John Mullen Robert Horne

John Mullen Peter Davison

Page 28: Project Controls Expo, 18th Nov 2014 - "Progress | Position | Prediction The key to completing projects on time" By David Bordoli

Copyright © 2014. All rights reserved. 28

Project Controls Expo – 18 November 2014Emirates Stadium, London

Progress | Position | PredictionThe key to completing projects on time