Project: Black Granite Mining Project PRE-FEASIBILITY...

21
Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites 1 1.0EXECUTIVE SUMMARY 1.1 Introduction The proposed mining lease area of M/s. Kishore Granites is located at Sy.No:121, of Nellimanda Village, Somala Mandal, Chittoor District, and Andhra Pradesh in an extent of 2.00ha. The mine lease was granted to M/s. Kishore Granites for a period of 20 years (Director of Mines and Geology, Hyderabad Proceedings No. 03250/R5-1/2011 dated 10-01-2012). The proposed area is not fit for agriculture and technical report from Department of Mines and Geology indicate that the subject area has granite deposits. The salient features of the project are given Table 1.1. Table 1.1 Salient features of the project Project name Proposed Black Granite mine of M/s. Kishore Granites Mining Lease Area 2.00ha Location of mine Sy.No:121, of Nellmanda Village, Somala Mandal, Chittoor District, Andhra Pradesh Minerals of mine Black Granite Mining Proposed production of mine 1386 m 3 /Annum Method of mining Opencast semi mechanized method Drilling/Blasting Line Drilling is proposed Blasting is proposed but will be done in a controlled manner. No of working days 300 days Water demand 5.0 KLD Sources of water Water will be supplied from water tankers/ Borewells of the nearby area Man power Direct Employment- 26 Indirect Employment-05 Solid Waste 39270 m 3 of waste will be generated during planned five years Nearest railway station Pileru railway station 22.64 km due N.E Nearest airport Tirupathi airport is 83.63km due East from the

Transcript of Project: Black Granite Mining Project PRE-FEASIBILITY...

Page 1: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

1

1.0EXECUTIVE SUMMARY

1.1 Introduction

The proposed mining lease area of M/s. Kishore Granites is located at Sy.No:121, of

Nellimanda Village, Somala Mandal, Chittoor District, and Andhra Pradesh in an extent

of 2.00ha. The mine lease was granted to M/s. Kishore Granites for a period of 20 years

(Director of Mines and Geology, Hyderabad Proceedings No. 03250/R5-1/2011 dated

10-01-2012).

The proposed area is not fit for agriculture and technical report from Department of

Mines and Geology indicate that the subject area has granite deposits. The salient

features of the project are given Table 1.1.

Table 1.1

Salient features of the project

Project name Proposed Black Granite mine of

M/s. Kishore Granites

Mining Lease Area 2.00ha

Location of mine Sy.No:121, of Nellmanda Village, Somala Mandal, Chittoor District, Andhra Pradesh

Minerals of mine Black Granite Mining Proposed production of mine 1386 m3/Annum Method of mining Opencast semi mechanized method

Drilling/Blasting Line Drilling is proposed Blasting is proposed but will be done in a controlled manner.

No of working days 300 days Water demand 5.0 KLD

Sources of water Water will be supplied from water tankers/ Borewells of the nearby area

Man power Direct Employment- 26 Indirect Employment-05

Solid Waste 39270 m3 of waste will be generated during planned five years

Nearest railway station Pileru railway station 22.64 km due N.E Nearest airport Tirupathi airport is 83.63km due East from the

Page 2: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

2

mine lease area Project Cost Rs. 30 lakhs

2.0 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION

2.1 Identification of Project and Project Proponent

The proposed project area is found to have good deposits of Black granite. Granite is

used as a construction material for flooring, coverings and cladding, making of kitchen

articles, sculptures, etc.

Sri.R.C.Kishore Kumar is the Proprietor of the proposed project. He had significant

experience in granite mining.

2.2 Brief Information about the Project

The mining lease area of 2.00ha is located in Government land. Open cast semi

mechanized mining is followed and it has been proposed to produce approximately

1386m3/ annum of Black granite. The nearest habitation, Kottapalle village is located at

a distance of 0.69 km due South from lease area.

M/s. Kishore Granites has filed an application for quarry lease for Black Granite over an

extent of 2.00 ha, in Sy.No:121, of Nellmanda Village, Somala Mandal, Chittoor District,

Andhra Pradesh to the Assistant Director of Mines and Geology, Chittoor on 04-01-

2011.

The Director of Mines & Geology, Hyderabad has decided to grant a quarry lease in favor

of M/s.Kishore Granites for a period of 20 years subject to submission of Approved

Mining Plan within a period of 6 months from the date of issue of notice

No.244/Q1/2005 dated 25-06-2005 as per Rule 12 (5) (C) of Andhra Pradesh Minor

Mineral Rules, 1966.

Page 3: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

3

Mining plan was approved by Department of Mines & Geology letter no. 1019/MP-

PLMR/2012, Dated 07-04-2012

2.3 Need for the Project and Its Importance to the Country or Region

The demand for granite increased due to rapid industrialization and growth in

infrastructure. So the number of granite producing quarries is increasing in

India. Granite is the chief material for the export industries like monuments,

flooring slabs, Kitchen articles, sculptures & export. Based on the demand of

Granite, the lessee intends to produce the required quantity of Black Granite for

domestic market.

As per EIA notification 2006 the project falls under Category- B, the proponent is

submitting the proposal to get Clearance for production capacity of 260 m3/

annum of granite blocks from SEAC, SEIAA, A.P for the purpose of grant of quarry

lease.

2.4 Demands-Supply Gap

The demand and supply for the Black granite is growing which makes a lot of

scope for revenue generation. Once the stone is obtained after quarrying it is

further processed and supplied to industries.

India is amongst the leading exporter countries of stones in the world. The major

importers of Indian stones are USA, China, UK, Italy, Belgium, Germany, UAE,

Hong Kong, Spain, Taiwan, Netherlands, Canada, Turkey, France, Russia and CIS

countries. The growth is continuing and the demand for marble, granite,

sandstone and other dimensional stones and stone products is anticipated to

grow at around 15% CAGR.

Page 4: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

4

2.5 Domestic/ Export Markets

Although granite is a minor mineral, it is a major contributor in foreign exchange

earnings. India is a major exporter of natural stone and granite, which is the

second largest foreign exchange earner for India besides iron ore in minerals

category.

(Source:http://commerce.nic.in/pressrelease/pressrelease_detail.asp?id=682)

2.6 Employment Generation

Proposed mining is semi-mechanized method and this project operation will

provide livelihood to the 26 workers. It will provide employment to the people

residing in vicinity.

Page 5: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

5

3.0 PROJECT DESCRIPTION

3.1 Type of Project Including Interlinked and Interdependent Projects, If Any.

The proposed Black Granite mine is of 2.00 ha. No interlinked projects were associated

with this project.

3.2 Location

The mining lease area is located in Sy.No:121, of Nellmanda Village, Somala Mandal,

Chittoor District, Andhra Pradesh. The mining lease area falls in Survey of India

Toposheet No. : 57 K/14

Latitude : 13° 30’ 39.00’’ N

Longitude : 78° 47’ 11.82’’ E

Location of the mining lease in Chittoor District is shown in Figure – 1.

Topo Map Showing 10 km Radius of Mine lease area is enclosed as Figure-2.

Page 6: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

6

FIGURE – 1

LOCATION MAP

Page 7: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

7

FIGURE – 2

TOPOGRAPHICAL MAP SHOWING 10 KM RADIUS

Page 8: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

8

Page 9: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

9

3.3 Details of Alternate Sites

No alternate site was considered as the project is mineral specific and site specific.

3.4 Size or magnitude of operation

The proposed mine has lease over an area of 2.00ha and the production rate is

1386m3/Annum. The lessee follows open cast semi mechanized mining.

Production parameters

The Mineral production target for five years is given in Table 3.1

Table 3.1

Year wise Production Programme

Granite @ 15%

recovery

Rock Waste @ 85%

generation 1st year 1386 7854 2nd year 1386 7854 3rd year 1386 7854 4th year 1386 7854 5th year 1386 7854

Total 6930 39270 Source: Mine plan prepared by RQP, P.Veeran Goud and approved by Director of Mines & Geology, Hyderabad) 3.5 Geology and Reserves

3.5.1 Regional Geological setup

The Geological formations in the Chittoor District can broadly be divided in distinct and

well marked groups and older group of Metamorphic rocks belonging to Archean and

Younger group of Sedimentary rocks belonging to the Proterozoic age the later cover

part of Punganur block. The remaining parts of District is Occupied by Archean rocks

Page 10: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

10

which consist of Schist, Gneisses, Quartz veins and basic dykes. The Archean rocks have

suffered considerable degree of tectonic disturbances, as a result of which the rocks

have been metamorphosed and recrystallized.

Stratigraphic Sequences established in the area as follows:

Geological age Lithology

Recent Alluvium

Pleistocene Younger Intrusive, Epidote Veins

Quartz veins and reefs .

Pegmattite’s Veins of Alkali Feldspar Granite & syenite

Dolerite/Basalt/Gabbro Dykes

Leuco Granite

Nebulitic to homophonous biotite Granite

---------------------------------Unconformity-----------------------------------------

Peninsular gneissic

complex

Nebulitic to homophonous Hornblende granite &

Leuco Hornblende granite

Archeans Biotite Granite Gneiss, Hornblende Granite Gneiss,

Porphyritic Hornblende Granite.

3.5.2 Local Geology

The Black Granite in the Distinct form of occurrence as dolerite dyke swarms in either side of the Grey granites & Gneisses. The Subject area belongs to a hillock extended in EW direction and gently sloping towards South direction with Black Granite Sheet Rock intruded as Dolerite dyke. The rock is highly puckered, sheared and faulted and has schistosity trending between EW with moderate to steep dips in either southerly and Westerly directions. The peninsular gneissic complex comprises gneisses (migmatite), gray granite, and Pink Granite and Gneissic granite. The gneiss in general show banding due to alteration of light colored quartzo- feldspathic minerals and dark colored biotite or hornblende minerals. These rocks may be separated in to two distinct groups namely the massive foliated types occur as low dome shaped hillocks. The intrusive relationship of the granite rock is evident by the presence of tongues and

Page 11: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

11

apophyges within the older rocks and the occurrence of xenoliths of the older rocks within the granite.

(Source: Mining plan)

3.5.3 Exploration

Present Status:

There are four pits in the Q.L area and it is observed in the pits that the surface

consists of the soil and bouldey waste only and a small quantity of granite blocks are

recovered and the undressed blocks are laying around the pits. The present lessee has

no information about the production. The boulders are highly weathered and lot of

defects like Colour patches and cracks are there. However immediately below this zone

lies the sheet rock which is productive zone.

The Q.L. area does not contain any forest cover. The area does not consist any

wild life.

3.5.4 Reserves

Geological reserves are given below in Table 3.2.

Table 3.2-Details of Reserves

Category Reserves @10% in m³ Rock Wastage@ 90% in

m³ Proved 33048 187272

Probable 6870 38930 Possible 6870 38930

Total 46788 265132

Mineable Reserves of the Quarry:

Initially the total quantity of the mineable reserves is considered as

marketable or economic reserves. In this way a total minable reserves of 46788

m³ are available in this Q.L area. The production is proposed to obtain1386 m³ per

Page 12: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

12

year. At this rate of Production, The Expected life of the mine is calculated as given

below.

Life of Mine:

Mineable reserves/Annual production=46788/1386=33.8 years

Say (38 years).

(Source: Mining plan)

3.6 PROJECT DESCRIPTION WITH PROCESS DETAILS

3.6.1 Method of Mining

a) Type of Mining:

Open cast method of mining is carried out in this mine by manually and semi

mechanization by using compressor operated jack hammer drills, excavators, and

dumper etc, Transportation will be made by trucks to dispatching point.

b) Brief Description: (Existing method of working)

The mining operations are carried out by semi-mechanization as open cast mining.

Hydraulic excavator and compresses operated jack hammers were used for cutting the

rock. Close spaced drilling of 0.2m was adopted along a straight line and charged with

low explosives to avoid feather cracks.

c) Removal / Excavation of O.B. and other Quarry Waste:

The middle of Northern side of the Q.L.area is selected for dump yard for next five years

and the waste will be stocked over a length of 60mts, width of 40 mts, to a height of 8

mts as a earmarked in plate No.4. Step dumping will be resorted. This material can be

utilized to fill the pits after quarry operations are over. When dumps reach their

optimum height suitable greenery will be grown on these dumps to stabilize them.

Page 13: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

13

d) Separation of large primary Blocks from the mother rock by pre-splitting

(Primary):

The mining will be followed in the form of linear cut method. This involves loosing of

the primary block from mother rock. Hence primary cutting will be done by line drilling

method where close spaced parallel holes along straight line will be made. Line drilling

method is used for separation of primary blocks.

i. Once the free face is developed in working place, the primary cuts are taken up

over a maximum length of 10m to a width of 3m and to a depth of 6m depends

upon the joints availability. These dimensions are confirmed as for field studies.

Primary block will be cut into secondary blocks by Jackhammer drilling and

wedge cutting and this block will be dislodged from in-situ position by an

excavator.

ii. Line drilling method will be used for cutting the primary blocks which involve

drilling and blasting.

iii. The holes are charged with low explosive cartridge like gun powder and non-

delay detonators for smooth blasting.

iv. The use of delay detonates causes fragmentation and cracks in rocks. The non

detonating cords are inserted into the holes and the holes are stemmed with

muck and plugged at the mouth and fired.

v. Thus the block will separate from the mother rock, which is pulled off from the

face with cranes or shovel.

e) Sub-Division of large Primary Blocks into Secondary Block:

This will be done drilling close spaced holes (along a line) down to the depth and the

secondary block will be removed easily by just pulling it with the help of proclain.

Close spaced holes will be drilled to the half the length of the block on either side of

it by using wedges blocks can be separated.

f) Production of Commercial Blocks:-

After primary separation the rock mass will be carefully examined to avoid hair line

cracks, mineral segregations and veins etc., The dressing of the rough blocks will be

Page 14: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

14

made by chipping the edges and geometrically equating the edges of the block at the

dressing yard. The rough blocks obtained after primary cut it will be dressed for

obtained good geometric shape of granite. Thus the commercial blocks are produced.

g) Extent of Mechanisation

The machinery used to carry out the mining operations are given Table 3.3

Table 3.3Mining Machinery

S. No. Name of the Machinery Capacity No’s

1. Excavator Bucket Capacity-1 cu.m.

Boom Length - 7m Model:Tata Hitachi-200Lc

1

2. Air Compressor 50 CFM 1 3. Jack Hammer ------ 4 4. Tipper 17 tonnes 2

5. Minor Tools Chisels, Crowbars, Pick axes spades

and hammers of different sizes. (Source: Mining plan)

3.7 Raw Material Required Along With Estimated Quantity, Likely Source,

Marketing Area of Final Product/S, Mode of Transport of Raw Material and

Finished Product

No raw material will be required in the proposed project. The operation involves

the extraction of Black granite and dumping in stock yard. The dressed

dimensional granite will be transported through hired trucks to the granite

market

Page 15: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

15

3.7.1 Use of Mineral

Black granite will be used in domestic and international market. Its hard nature

made it a very suitable and durable material for most Civil Engineering and

Construction works. It is used in various ways as in

Road Construction and Dimensional stones

Building of Houses, Bridges and Drainages

Manufacture of Marbles and Flooring Tiles

Production of cement blocks

Interior Decorations

Art works (Antiquities) etc.

3.7.2 Processing

Processing of Black granite is not involved.

3.8 Resource Optimization/ Recycling and Reuse

Not envisaged.

3.9 Availability of Water Its Source, Energy/ Power Requirement and Source

3.9.1 Water Requirement

Water is required only for drinking purposes, green belt, wire saw cutting and

dust suppression. The number of working people is around 26 so the total water

requirement will be around 5.0 KLD. This water will be supplied from

tankers/bore wells of nearby area.

Page 16: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

16

Table 3.4: Water Requirement

Enduse Quantity (KLD)

Dust suppression 2.05

Green Belt Development 0.73

Domestic Use 1.0

Process(Wire Saw Cutting) 1.0

Total 4.819 say 5.0 Kld

3.10 QUANTITY OF WASTES TO BE GENERATED (LIQUID AND SOLID) AND

SCHEME FOR THEIR MANAGEMENT/ DISPOSAL

3.10.1 Solid Waste Generation& its Disposal

About 85% of the material from granite production is going to be generated as rock

waste. About 39270 m3 (7854 m3 /annum) generated waste will be dumped along the

middle of the Northern Side of the quarry lease applied area with the dumping area of

stock is of 60mts, width of 40mts with height of 8m(Source: Mine Plan)

3.10.2 Liquid Effluent

No liquid effluent will be generated at the mine site. The domestic wastewater

generated will be sent to septic tanks followed by soak pits.

4.0 SITE ANALYSIS

4.1 Connectivity

4.1.1 Nearest Railway Station

Pileru railway station 22.64 km due N.E from the mine lease

Page 17: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

17

4.1.2 Nearest Airport

Tirupathi airport is 83.63 km due East from the mine lease area

4.2 Topography

Topographically the QL applied area is general the area is small hill. The area is devoid

of any forest or tree cover. It comprises shrubs only .There are no prominent Drainage

channels in the area. In general the area is plain studded with isolating Hillocks’.

Sometimes they may rise gently as continuous hills, presenting a rugged topography.

The Q.L area is having Scatterd boulders.

4.3 Climatic data from secondary sources

Table 4.1 Climatic Conditions

Nearest IMD station Vellore -91.00km-South

Maximum,Minimum Temperature Maximum:450CMinimum:10.40C

Heaviest rainfall in 24 hours 37.38mm

Mean Wind Speed 7.7km/hr

Rainfall of area 299 mm

(Source: Climatalogical Normals (1961-1990) :IMD)

5.0 PLANNING BRIEF

5.1 Planning Concept

Mining Plan approval has approved by Joint Director of Mines & Geology, Hyderabad

Letter Number No:1019/MP-PLMR/2012, Dated 07-04-2014.It is proposed to produce

1386 m3/annum of Black granite from the proposed mining lease.

Page 18: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

18

5.2 Population projection

The project will employ mostly workers from nearby villages. There will not be any

increase in population due to the project.

5.3 Land use planning

The project is located in 2.00ha of Government land. There will be change in landuse as

the granite will be excavated. After the exhaustion of granite, the pit will be backfilled

with the waste generated

5.4 Assessment of Infrastructure Demand (Physical & Social)

On the basis of the preliminary site visit, the infrastructure demand in the villages was

assessed on the basis of need and priority. The assessment will be made in the socio

economic survey &will be submitted at the time of final presentation regarding EC.

5.5 Amenities/Facilities

Office, Rest shelter, first aid room, workshop, canteen, will be constructed.

6.0 PROPOSED INFRASTRUCTURE

6.1 Industrial Area (Processing Area)

No infrastructure is proposed.

Page 19: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

19

6.2 Residential Area (Non Processing Area)

As the local persons will be given employment, no residential area/ housing is proposed

within the mining lease area.

6.3 Green Belt

Green belt will be developed along the boundaries of mine lease area.

6.4 Water Management

About 2.05 KLD will be required dust suppression, 0.73 KLD for greenbelt purpose, 1.0

KLD for wire saw cutting and about 1. 035 KLD for domestic therefore total water

requirement is 5.0 KLD. This water will be supplied from tankers/bore wells of the

nearby area.

6.5 Sewerage System

The domestic wastewater generated will be sent to septic tanks followed by soak pits.

6.6 Industrial Waste Management

Not applicable.

6.7 Solid Waste management

About 85% of the material from granite production is going to be generated as solid

waste 7854 m3 of granite waste is produced per year.

The waste will be dumped within lease area towards middle of Northern side and will

be backfilled into the mined out pit at the end of the mining.

7.0 REHABILITATION AND RESETTLEMENT (R&R) PLAN

Page 20: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

20

There will be no displacement of houses. Hence rehabilitation and resettlement

is not envisaged.

8.0 PROJECT SCHEDULE & COST ESTIMATES

The Total cost of project would be around Rs. 30 lakhs. M/s.Kishore Granites is

allocating capital budget of 1.36 Lakhs and 2.13Lakhs Recurring cost. The details

are given below in Table 8.1

Table 8.1

Environmental Management Plan budget

Sl no Work name Guiding Law Details of work & frequency

Unit Cost

Total fixed cost

Maintenance/ recurring cost

with periodicity

1 Safety shoe MMR 182 Once in a year 500 - 13,000

2 Helmet MMR 182A Once in three years 100 - 2,600

3 Hand gloves MMR 182B Twice in a year 30 - 1,560

4 Ear plugs DGMS Circulars 36

of 1972

Monthly to the persons working near machines 10 - 2,600

5 Cloth for protection from dust

MMR 124 Once in a month for all the staff 20 - 5,200

6 Gunny bags for drill hole coverage

MMR 124 As and when needed

Lump sum - 10,000

7 Dust Masks Thrice in a year 300 - 23,400

8 Construction of Retaining Wall

Circular 36-1972 26,600

-

9

Construction of garland drain (Hard ground)

Circular 36-1972 9,120 5,000

10 Check Dam

20,000 5,000

Page 21: Project: Black Granite Mining Project PRE-FEASIBILITY ...environmentclearance.nic.in/writereaddata/FormB/... · Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant:

Project: Black Granite Mining Project PRE-FEASIBILITY REPORT Applicant: M/s. Kishore Granites

21

11 Water sprinkling - 50,000

12 Green belt establishment

80,800 10,000

13 Medical examination

Sec-25 Mines Act 1952 - 5,200

14 Environmental Monitoring APPCB guidelines - 40,000

15 Social welfare Activities

40,000

Total 136,520 213,560

9.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)

9.1 Financial and Social Benefits with Special Emphasis on the Benefit to the

Local People Including Tribal Population, If Any, In the Area.

Although granite is a minor mineral, it is a major contributor in foreign exchange

earnings. India is the second largest exporter of raw granite after China and ahead

of Brazil and South Africa.

This project will also provide employment to local people helping them earn livelihood.

***********