PROGRESS UPDATE
• Demolition Works– Contract commenced on 29 July 2011– To be completed on 9 January 2012– Works in progress:
– Erection of Propping– Erection of Bamboo Scaffolding
• GBP Submission– First submission made on 22 July 2011
• Purchase Order for Chapel MVAC– Purchase Order issued on 8 June 2011– Tentative MVAC arrival in late September 2011
• Foundation/ Pile Caps/ ELS Submission– Foundation Submission: late September 2011– Pile Caps and ELS Submission: late September 2011
PROGRESS UPDATE
• Key Dates of Submission– Foundation, Pile Caps and ELS: late September 2011– Superstructure Plan: October 2011– Drainage Plan: October 2011
• Key Dates of Tendering– Foundation, Pile Caps and ELS: October 2011– Superstructure: May 2012
• Key Dates of Site Works– Foundation, Pile Caps and ELS: January 2012– Superstructure: August 2012
Projected Progress
Programme (Design and Submission)
Key Dates• General Building Plans Submission: 22 July 2011• Foundation, Pile Caps and ELS Submission: late September 2011
• Superstructure Plan Submission: October 2011• Drainage Plan Submission: October 2011
Programme (Tendering and Site Works)
Key Dates• Foundation, Pile Caps and ELS Tender: October 2011• Superstructure Tender: May 2012
• Foundation, Pile Caps and ELS Works: January 2012• Superstructure Works: August 2012
Contract Period: 165 daysNo. of days elapsed: 52 daysNo. of days remains: 113 daysDelay: -
Average no. of Labour: 7 per day
PROGRESS UPDATEDemolition Contract Status
Ongoing Site Work: - Erection of bamboo scaffolding- Erection of propping- Installation of monitoring check points
Steel Propping inside Hall
Hoarding and Bamboo Scaffolding along the Lawn
Steel Propping under Canopy
PROGRESS UPDATEHoarding Arrangement During Demolition
Existing Canopy to be Retained
Hoarding by Demolition Contractor
1.8m
Site Boundary
FrancisWong Building
Latest Layout – GF (Opened) LATEST LAYOUT
Covered Playground
Store- room(32m2)
Priest Prep. (26m2)
Chapel
TemporaryMVAC
Multi-purpose Room(98m2/90 seats)
Store- room(32m2)
Movable Partitions
Multi-purposeRoom(98m2)
Covered Playground Site Boundary
FrancisWong Building
Latest Layout – GF (Partitioned) LATEST LAYOUT
1.8m
Priest Prep. (26m2)
Chapel
TemporaryMVAC
Lav.(11m2/12m2)
Discussion Area
Dressing Room(22m2/16m2)
Green Room(22m2)
Site Boundary
FrancisWong Building
LATEST LAYOUT
4.8m
Gym(77m2)
Latest Layout – 1F (Option 1)
Chapel
Lav. andDressingRoom(33m2/34m2)
Discussion Area
Green Room(22m2)
Site Boundary
FrancisWong Building
LATEST LAYOUT
4.8m
Gym(77m2)
Latest Layout – 1F (Option 2)
Chapel
Latest Layout – 2F
Stage(3 stages - 332m2)
2m
15m
28m
Site Boundary
Auditorium/ Basketball Court(747m2/900-1000 seats)
FrancisWong Building
11m
LATEST LAYOUT
Side-stage
17m 8.8m8m
8.5mSide-stage
StoreCabinets
Chapel
Under-stage Chair Storage
MobileRetractable Seating(100 seats)
Latest Layout – 2F
Stage(3 stages - 332m2)
Site Boundary
Auditorium/ Basketball Court(747m2/900-1000 seats)
FrancisWong Building
11m
LATEST LAYOUT
Side-stage
17m 8.8m8m
8.5mSide-stage
Chapel
AccessibleRoof
FrancisWong Building
Site Boundary
Latest Layout – 5F (4 Classrooms) LATEST LAYOUT
ACPlantRoom
Class-Room(76m2)Class-
Room(67m2)
Class-Room(68m2)
Chapel
Class-Room(67m2)
Section AA’
Site Boundary
* Tree profile subject to further measurement
11m
~10m (H)(pruned)
1.2m
LATEST LAYOUT
A
A’
1.2m
6.1m
8.5m
1.5m
COST ESTIMATERevised Cost Estimate
DescriptionTotal
HK$
A. Approved budget in SDP meeting on 3 March 2011 93,000,000
B. Approved adjustment in SDP Meeting on 4 July 2011
1. MVAC installation to Chapel as discussed in SDP meeting on 9 May 2011 + 1,000,000
2. Increase in piling depth after carrying out ground investigation works + 3,000,000
3. Addition of 2 classrooms at 5/F + 2,700,000
4. Omission of link bridge - 2,000,000
5. Upgrade of escape staircase + 500,000
Adjusted budget after SDP Meeting on 4 July 2011 98,200,000
C. Design development and construction cost inflation since budget approval + 4,500,000
Updated cost estimate as at 19 September 2011 102,700,000