PROJECT UPDATE Construction Progress PROJECT UPDATE

4
Construction Progress A significant milestone has been reached in the construcon with the compleon of stage 3a of the redevelopment project. Witness tesng and training was completed in March and the building (levels 3– 7) handed over to LBH in April 2016. Operaonal commissioning of the new departments has commenced and access to these areas remains restricted. Staff tours of the new building will be arranged within the next two weeks and all staff will be advised of the same. Some pictures of the new facility: Level 4 Link Bridge Level 4 Lift Lobby Renal Unit - Haemodialysis Treatment Renal Unit - Staff Station Renal Unit—Reception Peritoneal Dialysis - Staff Station PROJECT UPDATE Project Update - Issue 26 May 2016 Want to know more about the project? Visit: www.lbhredevelopment.health.nsw.gov.au Email: [email protected] The Lismore Base Hospital Stage 3A redevelopment project is a jointly funded health service infrastructure investment iniave under the Health and Hospitals Fund Program, with the Australian Government contribung $60 million and the State providing $20 million. PROJECT UPDATE - MAIN WORKS

Transcript of PROJECT UPDATE Construction Progress PROJECT UPDATE

Page 1: PROJECT UPDATE Construction Progress PROJECT UPDATE

Construction Progress

A significant milestone has been reached in the construction with the

completion of stage 3a of the redevelopment project. Witness testing and

training was completed in March and the building (levels 3– 7) handed over to

LBH in April 2016. Operational commissioning of the new departments has

commenced and access to these areas remains restricted. Staff tours of the new

building will be arranged within the next two weeks and all staff will be advised

of the same.

Some pictures of the new facility:

Level 4 Link Bridge Level 4 Lift Lobby

Renal Unit - Haemodialysis Treatment Renal Unit - Staff Station

Renal Unit—Reception Peritoneal Dialysis - Staff Station

PROJECT UPDATE

Project Update - Issue 26

May 2016

Want to know more about the project? Visit: www.lbhredevelopment.health.nsw.gov.au Email: [email protected]

The Lismore Base Hospital Stage 3A redevelopment project is a jointly funded health service

infrastructure investment initiative under the Health and Hospitals Fund Program, with the

Australian Government contributing $60 million and the State providing $20 million.

PROJECT UPDATE - MAIN WORKS

Page 2: PROJECT UPDATE Construction Progress PROJECT UPDATE

ED - Admin Area ED - Short Stay Staff Station

ED - Short Stay Treatment Bays ED - Acute Staff Station

ED - CT Scanning Unit ED—Resuscitation Area

ED Fastrack - Staff Station New Theatre Floor

Want to know more about the project? Visit: www.lbhredevelopment.health.nsw.gov.au Email: [email protected]

Project Update - Issue 26

May 2016

The Lismore Base Hospital Stage 3A redevelopment project is a jointly funded health service

infrastructure investment initiative under the Health and Hospitals Fund Program, with the

Australian Government contributing $60 million and the State providing $20 million.

Page 3: PROJECT UPDATE Construction Progress PROJECT UPDATE

New Theatre Floor

Stage 3b1

Stage 3b1 is the construction of the shell and core for levels 8 - 12 and

the construction of a Helicopter Landing Site (HLS) on levels 13 & 14.

Works are also progressing on completing construction of the front

entrance forecourt area outside the renal unit, the ED ambulance bay and

the extended vehicle drop off zone.

ED Ambulance Bay Helicopter Landing Site

Helicopter Landing Site Liftwell

Want to know more about the project? Visit: www.lbhredevelopment.health.nsw.gov.au Email: [email protected]

Project Update - Issue 26

May 2016

The Lismore Base Hospital Stage 3A redevelopment project is a jointly funded health service

infrastructure investment initiative under the Health and Hospitals Fund Program, with the

Australian Government contributing $60 million and the State providing $20 million.

Page 4: PROJECT UPDATE Construction Progress PROJECT UPDATE

Multi Level Car Park

Construction of the new car park is nearing completion with all floor slabs and on grade car park works completed. Lighting and street signage installed and façade works ongoing.

Interesting Facts

In construction so far:

9150 cubic metres of concrete has been poured which equates to

approximately 91.5km’s of footpath.

715 tonnes of steel reinforcement have been laid to date which equates to

approximately 477 Holden Commodores.

175 tonne of structural steel installed to date. Total structural for the

project is 100 tonnes.

To end of the month, 25,050 man hours with cumulative total of 461,528

man hours for the project to date.

Any feedback or enquiries should be directed to Scott Huxley

([email protected]) and will be addressed by the project

team

Want to know more about the project? Visit: www.lbhredevelopment.health.nsw.gov.au Email: [email protected]

Project Update - Issue 26

May 2016

The Lismore Base Hospital Stage 3A redevelopment project is a jointly funded health service

infrastructure investment initiative under the Health and Hospitals Fund Program, with the

Australian Government contributing $60 million and the State providing $20 million.