Presentation Sample KAAU
-
Upload
abdullah-bakhsh -
Category
Documents
-
view
23 -
download
0
Transcript of Presentation Sample KAAU
PROJECT PRESENTATION
AL MUHAIDIB CONTRACTING CO.
September 11, 2014
KAU PROJECTSAL MUHAIDIB CONTRACTING CO.
2
INDEX1- CN 1300 & 1400 - Completion of Faculty Environmental Design…………………. 4
2- CN 6600 - General Materials and Laboratories…………………………………….. 5
3- CN 6601 - Completion of Faculty of Science……………………………………….. 6
4- CN 6300 - Biotechnoly and Laboratories…………………………………………… 7
5- CN 2650 - Car Parking……………………………………………………………...... 8
6- CN 460 - Class Rooms for 3 Buildings ( slemaniyah 1 – slemaneyah 2 – faysaleyah ). 9
7- CN 711 - Completion of Scientific Societies……………………………………….. 10
8- CN 241 - English Language Center ( 2 Building )…………………………………… 11
9- Organization Chart…………………………………………………………………... 12
10- Planned VS Actual…………………………………………………………………… 13
11- Penalty Amount……………………………………………………………………… 14
3
Page
Al Muhaidib Contracting Co.
KAU PROJECTS ( CN 1300 & 1400 )
Client FLUOR Arabia Limited
Contract Type Re-Measured
Start AUG 2010
Finish DEC 2012
Progress 100 %
Project Value 36,554 Million SAR
Earned Value 33,244 Million SAR
Invoiced 3,310 Million SAR Penalty deducted
Variance Balanced 0 SAR
Manpower 0Al Muhaidib Contracting Co. 4
Project ScopeCompletion of Faculty Environmental Design
Remaining Work & Issues
• Paper works on going
Comments Building already occupied by client
Expected Final Handover
20-OCT-2014
Client FLUOR Arabia Limited
Contract Type Re-Measured
Start AUG 2006
Finish OCT 2010
Progress 100 %
Project Value 87,999 Million SAR
Earned Value 87,999 Million SAR
Net Invoiced 0 SAR
Variance Balanced 0 SAR
Manpower 0
CN 1300
CN 1400
KAU PROJECTS ( CN 6600 )Client FLUOR Arabia Limited
Contract Type Re-Measured
Start DEC 2008
Finish MAR 2013
Progress 100 %
Project Value 87,999 Million SAR
Earned Value 75,388 Million SAR
Net Invoiced 1,760 Million SAR 2% retention 31/NOV/2013 Submit21/DEC/2013 Approved
10,851 Million SAR Penalty
Variance Balanced 0 SAR
Manpower 0
Al Muhaidib Contracting Co. 5
Project Scope
General Materials and Laboratories
. The structure includes lower level parking and five levels for the facilities including the pent house.. Scope of work includes construction of the structure and the finishing of the first and the fourth floor including electro-mechanical facilities
Remaining Work & Issues • Completed and paper works on going
Comment Building already occupied by client
Expected Final Handover 20-OCT-2014
KAU PROJECTS ( CN 6601 )
Client FLUOR Arabia Limited
Contract Type Re-Measured
Start OCT 2011
Finish SEP 2013
Progress 100 %
Project Value 47,971 Million SAR
Earned Value 41,890 Million SAR
Net Invoiced 960,117 Thousand SAR 2% retention
5,120 Million SAR Penalty
Variance Balanced 0 SAR
Manpower( Direct ) 0
Manpower( Indirect ) 3 Guard
Al Muhaidib Contracting Co. 6
Project Scope
Completion of Faculty of Science
. Scope of work includes finishing works of second and the third floor including electro-mechanical facilities
Remaining Work & Issues• Completed and paper works on going
Comment Building already occupied by client
Expected Final Handover 20-OCT-2014
KAU PROJECTS ( CN 6300 )Client FLUOR Arabia Limited
Contract Type Re-Measured
Start MAY 2010
Finish JUL 2013
Progress 90 %
Project Value 106,094 Million SAR
Earned Value 105,701Million SAR
Net Invoiced 0 SAR
392,770 Thousand SAR Supervision Fees
Variance Balanced 0 SAR
Manpower ( Direct ) 37
Manpower ( Indirect ) 41
Saudi 22
Al Muhaidib Contracting Co. 7
Project Scope
Biotechnology and Laboratories
. The structure includes lower level parking and four levels for the facilities including the pent house.
. Scope of work includes construction of laboratories, research areas, museums, storage for chemicals / gases, office spaces, and conference facilities.
Remaining Work & Issues
• Radiation Room ( Additional Work )• Fire Fighting ( Only Chemical Flashing )• White and Turk Board • Air balance• B.M.S
Expected Final Handover END OF DEC 2014
KAU PROJECTS ( CN 2650 )
Client FLUOR Arabia Limited
Contract Type Re-Measured
Start APR 2011
Finish SEP 2013
Progress 100 %
Project Value 20,358 Million SAR
Earned Value 17,810 Million SAR
Net Invoiced 407,172 Thousand SAR 2% Retention
2,140 Million SAR Penalty
Variance Balanced 0 SAR
Al Muhaidib Contracting Co. 8
Project Scope
Car Parking
. Scope of work includes finishing works in the car parking under the academic square.
Remaining Work & Issues
• paper work on going
Expected Final Handover
20-OCT-2014
KAU PROJECTS ( CN 460 )
Client Zuhair Fayez Partnership
Contract Type Re-Measured
Start AUG 2010
Finish AUG 2011
Progress 90 %
Project Value 55,785 Million SAR
Earned Value 54,687Million SAR
1,097 Million SAR Penalty
Net Invoiced 0 SAR
Variance Balanced 0 SAR
Al Muhaidib Contracting Co. 9
Project Scope
Class Rooms for 3 Buildings :1. Boys2. Girls3. Faysaliyah
Remaining Work & Issues
• Cladding ( Under Inspection )• AHU ( by end of OCT )
Comment • Building already occupied by client
Expected Final Handover
Pending Complete
KAU PROJECTS ( CN 711 )Client Zuhair Fayez
Partnership
Contract Type Re-Measured
Start DEC 2011
Finish JUL 2012
Progress 100 %
Project Value 14,856 Million SAR
Earned Value 14,113 Million SAR
Net Invoiced 742,838 Thousand SAR 2% Retention
Variance Balanced 0 SAR
Al Muhaidib Contracting Co. 10
Project Scope
Completion of Scientific Societies
. Scope of work includes finishing of conference facilities, office spaces, seminar lounges and auditorium along with the site development which involves, asphalt road, interlocking pavements and landscape.
Remaining Work & Issues • Paper work on going
Expected Final Handover 20-OCT-2014
KAU PROJECTS ( CN 241 )Client Zuhair Fayez Partnership
Contract Type Re-Measured
Start JAN 2012
Finish DEC 2014
Progress 67.37 %
Project Value 141 Million SAR
Earned Value 77,694 Million SAR
Net Invoiced 2,150 Million SAR 25-AUG-2014
Variance Balanced 63,306 Million SAR
2,848 Million SAR Invoice submitted not approved from Consultant
Manpower ( Direct ) 273
Manpower ( Indirect ) 76
Saudi 40
Al Muhaidib Contracting Co. 11
Project ScopeEnglish Language Center ( 2 Building )The structure includes four levels for the facilities including the pent house.
Remaining Work & Issues
• Elevator ( In Progress )• BMS
Expected Primary Handover
• 30-DEC-2014
Part A
Part B
CN 241 - Part A
Project ScopeEnglish Language Center ( 2 Building )The structure includes four levels for the facilities including the pent house.
Remaining Work & Issues
• ( In Progress )
Expected Primary Handover
• 30-DEC-2014
CN 241 - Part B
12
Organization Chart
CN 240
Planned VS Actual
13
1.2
4%
0.7
5%
0.7
9% 0
.96
%
0.4
8% 0.6
0% 0
.75
%
0.4
5%
0.3
1%
0.2
5%
0.4
3%
0.5
1%
0.4
3%
0.1
6% 0.2
8%
0.0
8%
0.4
5%
0.4
3%
0.7
4%
0.2
8%
0.1
0%
0.2
9%
0.5
0%
0.5
0%
0.9
9%
0.2
1%
0.4
7%
1.3
1%
0.4
0%
0.1
3%
0.3
1% 0.4
4% 0
.59
%
0.5
9%
0.9
0%
0.3
7%
0.6
3%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
0.00%
0.50%
1.00%
1.50%
2.00%
2.50%
3.00%
7-J
an
-14
14-J
an-1
4
21-J
an-1
4
28-J
an-1
4
4-F
eb
-14
11-F
eb
-14
18-F
eb
-14
25-F
eb
-14
4-M
ar-
14
11-M
ar-
14
18-M
ar-
14
25-M
ar-
14
1-A
pr-
14
8-A
pr-
14
15-A
pr-
14
22-A
pr-
14
29-A
pr-
14
6-M
ay-1
4
13-M
ay-1
4
20-M
ay-1
4
27-M
ay-1
4
3-J
un
-14
10-J
un-1
4
17-J
un-1
4
24-J
un-1
4
1-J
ul-
14
8-J
ul-
14
15-J
ul-1
4
22-J
ul-1
4
29-J
ul-1
4
5-A
ug
-14
12-A
ug
-14
19-A
ug
-14
26-A
ug
-14
2-S
ep
-14
9-S
ep
-14
16-S
ep
-14
23-S
ep
-14
30-S
ep
-14
7-O
ct-
14
14-O
ct-
14
WEEKS
Actual Weekly WorkProgess %
Penalty Amount
PROJECT Total Penalty Remarks
KAAU-6601 5,120,420.644,797,120.00 ( 10% of contract )323,300.64 ( supervision fees )
KAAU-6600 10,851,929.528,799,998.59 ( 10% of contract )912,420.91 ( supervision fees )
1,139,510.02 ( penalty CN:1400 )
KAAU-460 1,097,566.63
KAAU-2650 2,140,778.752,035,860.50 ( 10% of contract )104,918.25 ( supervision fees )
KAAU-1400 3,310,167.573,655,453.39 ( all this invoice deducted-penalty is 10% of contract )
794,224.20 ( supervision fees )- 1,139,510.02 ( so remaining penalty deducted from 6.600 )
KAAU-6300 392,770.00337,778.91 ( 0.32% of contract )
54,991.34 ( fees supervision )
22,913,633.11
14Al Muhaidib Contracting Co.
THANK YOUAL MUHAIDIB CONTRACTING CO.
15
ENG. Abdullah Bakhsh