Yvonne D. Eaves, PhD, RN Associate Professor, WellStar School of Nursing
Presentation Hospital Commissioning Case Study Rusty Ross, PE, CxA – SSRCx Rick Ziegler, PE –...
-
Upload
jane-tillie -
Category
Documents
-
view
227 -
download
8
Transcript of Presentation Hospital Commissioning Case Study Rusty Ross, PE, CxA – SSRCx Rick Ziegler, PE –...
Presentation
Hospital Commissioning Case Study
Rusty Ross, PE, CxA – SSRCx
Rick Ziegler, PE – SSRCx
Michael Paul - WellStar
WellStar Paulding HospitalHiram, Georgia
The Project
• $125 Million Replacement Hospital• 295,000 SQFT, Eight Floors• 56 beds, expandable to 112 beds (6th & 7th floors shelled)• 40 ER exam rooms• 4 surgical suites• First Patient – March 28, 2014
Commissioning Scope
• Review the energy model • Design reviews at 100% DDs and 100% CDs• Cx Specifications
Commissioning Scope
• Cx Plan• Shop Drawing Review• Prepare Installation
Checklists monitor subs execution of these checklists
• Prepare Functional Test Procedures, direct execution, document findings
Commissioning Scope
• Review:– T&B report– O&Ms– O&M staff training
• Final Report• Opposed Season
Testing• Warranty Meeting
Commissioning Scope
• Mechanical Systems • Domestic Hot Water• Fire Protection• Fire Alarm• Electrical Distribution • Essential Electrical System (Emergency Power)• Elevators• Lighting Controls• Building Envelope
Mechanical systems
• Multistack chiller (1,050 T) uses ground water loop when needed– Full Load testing to be conducted summer 2014– Primary mode is simultaneous heating and
cooling
Mechanical systems
• Desiccant AHUs serve Surgery• DOAS units serve multiple AHU systems• Air valves on supply and return in OR systems• 412 Tons of air-cooled Chillers serve DOAS
units
Energy Model Review
• Energy Star Target Score: 94
• Model not updated for 100% CD design
• Walls sections in model don’t match design
• Insulation in roof in model different from design
• Roof deck design (thickness) ≠ model
Energy Model Review
• Thermal resistance of windows over estimated in the model
• Sun shade sizing differ between mode and design
• DOAS, AHU and exhaust fan power understated in model vs 100% CDs
• AHU SAT reset schedule in the EM ≠ the design
Energy Model Review
• Energy model over estimates unoccupied operating timeframe, thus under estimating energy usage
95% CD Plan Review - Mechanical
• No detail provided for piping propane (secondary fuel) to steam boilers
95% CD Plan Review - Mechanical
• No conditioned air in main electrical room
• Plans did not indicate all isolation valves and flushing connections in Ground Loop system or at the Heat Pump Chiller
• No SOO defined for atrium smoke evacuation function
• No SOO for VAV boxes in kitchen tracking variable flow in range hood exhaust and dishwasher exhaust
95% CD Plan Review - Mechanical
• Incomplete or missing SOO for stairwell pressurization and elevator shaft smoke vent
• Purging and pressure testing procedures for ground loop piping not defined in the specifications
95% CD Plan Review - Electrical
• No lighting controls SOO provided• No lighting controls specification included• Obstruction lighting control not defined, no
photocell shown• Initiation of stairwell pressurization not
defined• Electrical riser diagram, 4 dry type
transformer shown fed from incorrect panels• 13 Panel schedules omitted from drawings• No IR scanning windows in some SWGR
95% CD Plan Review - Electrical
• BOD states emergency generators shall be bi-fuel. Specifications do not require this capability.
• “Pole” requirements for shunt trip breakers serving loads under kitchen hoods not identified in panel schedule
Findings – HVAC Hydronics
• CHW flow required for AHUs greater that CHW system output. (Strainers were loaded, had to be cleaned 3 times over course of FPTs)
• Surgery Unit and AHU-Imaging not able to maintain DAT 55º with CHS @ 42º. (Strainers)
Findings - BAS
• OR AHU SAT controlled by 3 factors. Design sequence changed to insure SAT did not rise above desired conditions.– SAT– Dew point control– Temperature reset in unoccupied mode
• OR pressure control incorrect (setpoints incorrect) • OR pressure alarms did not alarm when rooms
negative (programming)• Critical zone reset for SP setpoint not
programmed for Surgery system
Findings - BAS
• Surgery AHU Return Air SP safety tripped 5x when in un-occupied mode (added sensors)
• DOAS and AHU SP control initially caused tripping of both systems on SP alarms (programming - rate of operation of control dampers)
• HWPs and CHWPs did not operate in parallel (ramped individually in series)
• Lag HWP and CHWP did not cycle off as load reduced
Findings - BAS
• SAT reset based on dew point not programmed
• Humidifier not able to control to setpoint (programming)
• DOAS filter alarms not programmed• Isolation Room alarms failed to alarm
(programming)
Findings - BAS
• Isolation exhaust stand-by fan does not start when “lead” fan fails (N+1 programming)
Findings - BAS
• Graphics incomplete and/or inaccurate
Findings - BAS
• No time of use schedule programmed for boilers (3 total, 1 stand-by)
• No communication between FO system and BAS
• Sensors defective (MAT)• Domestic Booster pump alarms not
programmed• Domestic Hot water alarms not
programmed
Findings – Fire Alarm System/ Life Safety
• Dry Pipe system annunciation did not identify area protected
• Inoperable tamper switches on A/S control valves
• Elevator recall programming incorrect
Findings – Lighting Controls
• Occupancy sensors not programmed• Occupancy sensors would not time out• Lighting controls not programmed• Sensors blocked by OFE
Findings – Emergency Power
• Load Demand control setpoint initially set too low (operated 2 gensets when load required 1)
• Day Tank FO return pump did not operate when high level alarm activated (G1)
• FO return pump not operable (G2)
• Priority Loads and Load Demand functions operated correctly
MEP Lessons Learned
• Ready to test – Despite scheduling, not ready to test– Programming incomplete, incorrect setpoints– Conflict between incomplete state and need
to finish prior to occupancy
• Controls associated with OR AHUs and OR space controls
• Restart of AHUs on Emergency Power
Project Timeline
• Control heat flow• Control airflow • Control vapor flow• Control rain• Control groundwater• Control light and solar
radiation• Control noise and vibration
• Control insects, rodents, and vermin
• Control fire• Provide strength and
rigidity• Be durable
Environmental Separation
Enclosure Commissioning
• Design life of at least 50 years• No systemic water leaks, all leaks resolved prior
to occupancy• Whole building air leakage rate of 0.1 cfm/sf @
75 Pa• Slight positive pressure• Intent is to have continuous air, water, and
thermal protection
Owner’s Project Requirements
• Owner’s Project Requirements• Two Design Reviews• Specification Development• Review of Energy Model
Design Phase
Design Phase
• Submittal and shop drawing reviews• Mock-up construction and testing• Update to functional performance test plan
Pre-Construction Phase
Mock-up
Mock-up
Mock-up
Mock-up Summary
• Water leakage at window collar flashings• Masonry tie air leakage at one location• Whole mock-up air leakage testing pass • Significant air leakage at roof to wall interface• Curtain wall water leaks• Retesting and next steps
Construction Phase
Construction Phase
Construction Phase
Construction Phase
Questions