PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar...

21
PREPARATION AND SCRUTINY PREPARATION AND SCRUTINY OF OF DETAILED PROJECT REPORTS DETAILED PROJECT REPORTS AS PER NEW TEMPLATE AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Prof. B.P. Chandrasekhar Technical Advisor to Technical Advisor to APSRRDA APSRRDA GoAP GoAP

Transcript of PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar...

Page 1: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

PREPARATION AND SCRUTINY PREPARATION AND SCRUTINY OF OF

DETAILED PROJECT REPORTS DETAILED PROJECT REPORTS AS PER NEW TEMPLATEAS PER NEW TEMPLATE

Prof. B.P. ChandrasekharProf. B.P. Chandrasekhar

Technical Advisor to APSRRDATechnical Advisor to APSRRDA

GoAPGoAP

Page 2: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

To present the details of Investigations, Design

with choice of Technology, Assessment of

accurate quantities and Cost Estimation along

with necessary drawings to enable the

execution of the Project.

Objectives of DPR

Page 3: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

ContentsContents of the DPR of the DPR

1.Introduction1.Introduction

2.Planning and basic design 2.Planning and basic design considerationconsideration

3.Topographic Survey.3.Topographic Survey.

4.Soil and Materials Survey4.Soil and Materials Survey

5.Traffic Survey5.Traffic Survey

6.Hydrological Survey6.Hydrological Survey

Contd.,Contd.,

Page 4: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

Contd.

7. Geometric Design Standards7. Geometric Design Standards

8. Alignment Design8. Alignment Design

9.Pavement Design9.Pavement Design

10.Design of Cross Drainage10.Design of Cross Drainage

11.Protective Works & Drainage11.Protective Works & Drainage

12.Land Acquisition12.Land Acquisition

13.Utility shifting/relocation13.Utility shifting/relocation

Page 5: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

Contd..

14.Road Safety and Traffic 14.Road Safety and Traffic

ManagementManagement

15.Specification15.Specification

16.Environmental Issues16.Environmental Issues

17.Analysis of Rates17.Analysis of Rates

18.Cost Estimate18.Cost Estimate

19.Construction Program19.Construction Program

Page 6: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

B. ProformaeProforma B Package SummaryProforma C Check List for PIU & STAFormat Fl Package-wise Summary SheetFormat F2A Roads proposed in PMGSY for Rural ConnectivityFormat F2B Pavement LayersFormat F3 Typical Cross Section of Existing PavementFormat F4 Typical proposed cross section in Straight Section - Flexible

PavementFormat F5 Summary: Cost EstimateFormat F6 Cost estimate for Road Construction Works - Pavement WorksFormat F7 Cost estimate for Cross Drainage Works-Slab CulvertFormat F8 Rate of Materials supplied at site - Rate AnalysisFormat F9A Certificate of Ground Verification from Executive Engineer /

Head of PIUFormat F9B List of DPRs verified on Ground14. Environmental Checklist15. Checklist for community consultation on engineering

Page 7: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

List of figures{Insert list of figures used in this report}Figure-1 Road Map of India and stateFigure-2 District MapFigure-3 Block Maps , showing all existing

connectivity like District/block HQ, new townships, National and State highway network, mandis, hospitals, colleges,schools etc.

Figure-4 Strip plan showing land and alignment details

Figure -5 Quarry Map

Page 8: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

D. Annexures

{Insert list of Annexure provided in this report}Annexure-1 Details of soil tests (Section 4.2)Annexure-2 Detailed hydraulic calculation

of all replaced and proposed new culverts (Section 6.7)Annexure-3 Chainage-wise Cut/fill volume

Page 9: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

STRIP PLAN

Page 10: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

STRIP PLAN

Page 11: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

STRIP PLAN

Page 12: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

Site Photos

Chainage 0.00kmOne arm of the tee-intersection facing New Raipur

Chainage 0.00kmStarting point of the alignment. The road is made of moorum. The initial section is a small village with mud and permanent housing

Chainage 0.100kmThe existing moorum road is wide and has sufficient ROW. On the right hand side is the raised platform for cattle shelter during monsoon

Page 13: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

Site PhotosChainage 0.225kmPipe culvert provided along canal forming a cross drainage structure. This is a very temporary measure with no side walls and broken edges

Culvert at chainage 0.750kmC/d structure with head wall but broken canal edge

Chainage 1.000kmCanal on both edges stops. The ROW narrows substantially. The surface condition deteriorates because of paddy field water

Page 14: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

Road Design BriefRoad Design BriefSI. Location Issue Design Solutions1 Ch. 0.00km The proposed road is connecting

New Raipur and Aarang the block HQ. The road starts with a Tee intersection. While New Raipur gets developed there will be substantial traffic using this road. Electricity poles are located along the alignment.

The intersection needs to be developed properly for safety. The electricity poles need to relocated.

2 Ch.0.100 to 0.300 km

The section has a pipe laid across the road without any head wall or foundation. This is for the water from the irrigation channels for cross flow. This causes soil erosion in the channel. Because of the pipe the alignment has been adjusted in skew.

^Proper cross drainage structure to be provided. The road has to be realigned.

3 Ch. 0.700 to 0.900 km

Because of the skew in channel alignment the road has been skewed. The channel walls have eroded due to flow of water.

The alignment has to be readjusted. The channel walls need to be protected from erosion.

4 Ch. 0.900 to 1.200 km

Due to agricultural cultivation the road has only the c/w and no shoulders.

Land acquisition/donation will be required to provide for c/w and shoulder. It also needs to be raised to avoid water logging.

Page 15: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

Road Design BriefRoad Design Brief5 Ch. 1.200 to

1.300 kmThe foot track is different from the actual vehicle path provided.

Curve needs to be properly designed.

7 Ch. 1.400km The culvert provided skews the alignment.

The culvert has to be redesigned so that proper geometry can be provided to the alignment.

~

Draft Format for DPR

8 Ch. 1.400 to 1.860

The cc pavement does not have any

Proper shoulder to be provided

km shoulder. This is very risky for vehicles

on either side.

crossing each other. It is necessary for the designers

The road ends at the village and

to assess the feasibility of the

crosses the major irrigation canal on

provision of bypass from ch.

the other side of the village. The road

1.500km as desired by the

width inside the village is not

villagers

Page 16: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

Objectives of ScrutinyObjectives of Scrutiny

To make sure of adequacy of investigations.To make sure of adequacy of investigations.

To Check the authenticity of the data.To Check the authenticity of the data.

To verify the optimality of design and estimation.To verify the optimality of design and estimation.

To check the provisions made as per the PMGSY To check the provisions made as per the PMGSY guidelines.guidelines.

Page 17: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

Important Factors for ScrutinyImportant Factors for Scrutiny

Selection of Alignment.Selection of Alignment. Land Availability.Land Availability. Traffic Volume.Traffic Volume. Soil Characteristics.Soil Characteristics. Design and Specification.Design and Specification. CD works.CD works. Drawings.Drawings.

Page 18: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

DPR Scrutiny ProcessDPR Scrutiny Process

Stage 1Stage 1 - - Executive Engineer.Executive Engineer.

Stage 2Stage 2 - - Superintending EngineerSuperintending Engineer

Stage 3Stage 3 - - State Technical Agency (STA)State Technical Agency (STA)

Stage 4Stage 4 - - Principal Technical Agency Principal Technical Agency

(PTA) (Random Check)(PTA) (Random Check)

Stage 5Stage 5 - - Random Check at NRRDARandom Check at NRRDA

Page 19: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

Scrutiny at DPIUScrutiny at DPIU

Co-relation of the data during Transect Walk, Co-relation of the data during Transect Walk,

Site investigations and that used in the DPR.Site investigations and that used in the DPR.

Verification of leads and availability of material.Verification of leads and availability of material.

Verification of specifications and Schedule of Verification of specifications and Schedule of

Rates.Rates.

Verification of Maps and Drawings prepared by Verification of Maps and Drawings prepared by

Junior Staff.Junior Staff.

Page 20: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.

Mandatory CertificatesMandatory Certificates

1.1. Resolution of Grama SabhaResolution of Grama Sabha

2.2. Recommendation of Hon’ble MPsRecommendation of Hon’ble MPs

3.3. Certificate of Land availabilityCertificate of Land availability

4.4. Certificate that the proposed road is not one of Certificate that the proposed road is not one of

the dropped roads in the earlier proposalsthe dropped roads in the earlier proposals

5.5. Certificate that the road now proposed is not Certificate that the road now proposed is not

funded / proposed to be funded in any other funded / proposed to be funded in any other

programmeprogramme

Page 21: PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar Technical Advisor to APSRRDA GoAP.