PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar...
-
Upload
nathaniel-sandoval -
Category
Documents
-
view
219 -
download
0
Transcript of PREPARATION AND SCRUTINY OF DETAILED PROJECT REPORTS AS PER NEW TEMPLATE Prof. B.P. Chandrasekhar...
PREPARATION AND SCRUTINY PREPARATION AND SCRUTINY OF OF
DETAILED PROJECT REPORTS DETAILED PROJECT REPORTS AS PER NEW TEMPLATEAS PER NEW TEMPLATE
Prof. B.P. ChandrasekharProf. B.P. Chandrasekhar
Technical Advisor to APSRRDATechnical Advisor to APSRRDA
GoAPGoAP
To present the details of Investigations, Design
with choice of Technology, Assessment of
accurate quantities and Cost Estimation along
with necessary drawings to enable the
execution of the Project.
Objectives of DPR
ContentsContents of the DPR of the DPR
1.Introduction1.Introduction
2.Planning and basic design 2.Planning and basic design considerationconsideration
3.Topographic Survey.3.Topographic Survey.
4.Soil and Materials Survey4.Soil and Materials Survey
5.Traffic Survey5.Traffic Survey
6.Hydrological Survey6.Hydrological Survey
Contd.,Contd.,
Contd.
7. Geometric Design Standards7. Geometric Design Standards
8. Alignment Design8. Alignment Design
9.Pavement Design9.Pavement Design
10.Design of Cross Drainage10.Design of Cross Drainage
11.Protective Works & Drainage11.Protective Works & Drainage
12.Land Acquisition12.Land Acquisition
13.Utility shifting/relocation13.Utility shifting/relocation
Contd..
14.Road Safety and Traffic 14.Road Safety and Traffic
ManagementManagement
15.Specification15.Specification
16.Environmental Issues16.Environmental Issues
17.Analysis of Rates17.Analysis of Rates
18.Cost Estimate18.Cost Estimate
19.Construction Program19.Construction Program
B. ProformaeProforma B Package SummaryProforma C Check List for PIU & STAFormat Fl Package-wise Summary SheetFormat F2A Roads proposed in PMGSY for Rural ConnectivityFormat F2B Pavement LayersFormat F3 Typical Cross Section of Existing PavementFormat F4 Typical proposed cross section in Straight Section - Flexible
PavementFormat F5 Summary: Cost EstimateFormat F6 Cost estimate for Road Construction Works - Pavement WorksFormat F7 Cost estimate for Cross Drainage Works-Slab CulvertFormat F8 Rate of Materials supplied at site - Rate AnalysisFormat F9A Certificate of Ground Verification from Executive Engineer /
Head of PIUFormat F9B List of DPRs verified on Ground14. Environmental Checklist15. Checklist for community consultation on engineering
List of figures{Insert list of figures used in this report}Figure-1 Road Map of India and stateFigure-2 District MapFigure-3 Block Maps , showing all existing
connectivity like District/block HQ, new townships, National and State highway network, mandis, hospitals, colleges,schools etc.
Figure-4 Strip plan showing land and alignment details
Figure -5 Quarry Map
D. Annexures
{Insert list of Annexure provided in this report}Annexure-1 Details of soil tests (Section 4.2)Annexure-2 Detailed hydraulic calculation
of all replaced and proposed new culverts (Section 6.7)Annexure-3 Chainage-wise Cut/fill volume
STRIP PLAN
STRIP PLAN
STRIP PLAN
Site Photos
Chainage 0.00kmOne arm of the tee-intersection facing New Raipur
Chainage 0.00kmStarting point of the alignment. The road is made of moorum. The initial section is a small village with mud and permanent housing
Chainage 0.100kmThe existing moorum road is wide and has sufficient ROW. On the right hand side is the raised platform for cattle shelter during monsoon
Site PhotosChainage 0.225kmPipe culvert provided along canal forming a cross drainage structure. This is a very temporary measure with no side walls and broken edges
Culvert at chainage 0.750kmC/d structure with head wall but broken canal edge
Chainage 1.000kmCanal on both edges stops. The ROW narrows substantially. The surface condition deteriorates because of paddy field water
Road Design BriefRoad Design BriefSI. Location Issue Design Solutions1 Ch. 0.00km The proposed road is connecting
New Raipur and Aarang the block HQ. The road starts with a Tee intersection. While New Raipur gets developed there will be substantial traffic using this road. Electricity poles are located along the alignment.
The intersection needs to be developed properly for safety. The electricity poles need to relocated.
2 Ch.0.100 to 0.300 km
The section has a pipe laid across the road without any head wall or foundation. This is for the water from the irrigation channels for cross flow. This causes soil erosion in the channel. Because of the pipe the alignment has been adjusted in skew.
^Proper cross drainage structure to be provided. The road has to be realigned.
3 Ch. 0.700 to 0.900 km
Because of the skew in channel alignment the road has been skewed. The channel walls have eroded due to flow of water.
The alignment has to be readjusted. The channel walls need to be protected from erosion.
4 Ch. 0.900 to 1.200 km
Due to agricultural cultivation the road has only the c/w and no shoulders.
Land acquisition/donation will be required to provide for c/w and shoulder. It also needs to be raised to avoid water logging.
Road Design BriefRoad Design Brief5 Ch. 1.200 to
1.300 kmThe foot track is different from the actual vehicle path provided.
Curve needs to be properly designed.
7 Ch. 1.400km The culvert provided skews the alignment.
The culvert has to be redesigned so that proper geometry can be provided to the alignment.
~
Draft Format for DPR
8 Ch. 1.400 to 1.860
The cc pavement does not have any
Proper shoulder to be provided
km shoulder. This is very risky for vehicles
on either side.
crossing each other. It is necessary for the designers
The road ends at the village and
to assess the feasibility of the
crosses the major irrigation canal on
provision of bypass from ch.
the other side of the village. The road
1.500km as desired by the
width inside the village is not
villagers
Objectives of ScrutinyObjectives of Scrutiny
To make sure of adequacy of investigations.To make sure of adequacy of investigations.
To Check the authenticity of the data.To Check the authenticity of the data.
To verify the optimality of design and estimation.To verify the optimality of design and estimation.
To check the provisions made as per the PMGSY To check the provisions made as per the PMGSY guidelines.guidelines.
Important Factors for ScrutinyImportant Factors for Scrutiny
Selection of Alignment.Selection of Alignment. Land Availability.Land Availability. Traffic Volume.Traffic Volume. Soil Characteristics.Soil Characteristics. Design and Specification.Design and Specification. CD works.CD works. Drawings.Drawings.
DPR Scrutiny ProcessDPR Scrutiny Process
Stage 1Stage 1 - - Executive Engineer.Executive Engineer.
Stage 2Stage 2 - - Superintending EngineerSuperintending Engineer
Stage 3Stage 3 - - State Technical Agency (STA)State Technical Agency (STA)
Stage 4Stage 4 - - Principal Technical Agency Principal Technical Agency
(PTA) (Random Check)(PTA) (Random Check)
Stage 5Stage 5 - - Random Check at NRRDARandom Check at NRRDA
Scrutiny at DPIUScrutiny at DPIU
Co-relation of the data during Transect Walk, Co-relation of the data during Transect Walk,
Site investigations and that used in the DPR.Site investigations and that used in the DPR.
Verification of leads and availability of material.Verification of leads and availability of material.
Verification of specifications and Schedule of Verification of specifications and Schedule of
Rates.Rates.
Verification of Maps and Drawings prepared by Verification of Maps and Drawings prepared by
Junior Staff.Junior Staff.
Mandatory CertificatesMandatory Certificates
1.1. Resolution of Grama SabhaResolution of Grama Sabha
2.2. Recommendation of Hon’ble MPsRecommendation of Hon’ble MPs
3.3. Certificate of Land availabilityCertificate of Land availability
4.4. Certificate that the proposed road is not one of Certificate that the proposed road is not one of
the dropped roads in the earlier proposalsthe dropped roads in the earlier proposals
5.5. Certificate that the road now proposed is not Certificate that the road now proposed is not
funded / proposed to be funded in any other funded / proposed to be funded in any other
programmeprogramme