Preliminary Geotechnical Investigation
40-44 Broadway Avenue
Toronto, Ontario
Prepared For:
Collecdev
DS Project No : 18-701-10
Date : November 19, 2018
DS CONSULTANTS LTD.
6221 Highway 7, Unit 16
Vaughan, Ontario, L4H 0K8
Telephone: (905) 264-9393
www.dsconsultants.ca
Project: 18-701-10
Geotechnical Investigation 40-44 Broadway Avenue
Toronto, Ontario 1
DS Consultants Ltd. October 16, 2018
Table of Contents
1. INTRODUCTION ................................................................................................................................ 2
2. FIELD AND LABORATORY WORK ....................................................................................................... 3
3. SUBSURFACE CONDITIONS ............................................................................................................... 3
3.1 Soil Conditions .......................................................................................................................... 3
3.2 Groundwater Conditions .......................................................................................................... 5
4. FOUNDATIONS ................................................................................................................................. 6
5. FLOOR SLAB AND PERMANENT DRAINAGE ....................................................................................... 6
6. ELEVATOR AND SUMP PITS ............................................................................................................... 7
7. FROST PROTECTION ......................................................................................................................... 7
8. EARTH AND WATER PRESSURES........................................................................................................ 7
9. EXCAVATION AND GROUNDWATER CONTROL .................................................................................. 8
10. EARTHQUAKE CONSIDERATIONS ...................................................................................................... 9
11. TEMPORARY SHORING ..................................................................................................................... 9
12. GENERAL COMMENTS AND LIMITATIONS OF REPORT .................................................................... 10
DRAWINGS
BOREHOLE LOCATION PLAN 1
GENERAL COMMENTS ON SAMPLE DESCRIPTIONS 1A
BOREHOLE LOGS 2 – 7
GRAIN SIZE DISTRIBUTION CURVES 8
DRAINAGE RECOMMENDATIONS 9 TO 11
Project: 18-701-10
Preliminary Geotechnical Investigation 40-44 Broadway Avenue
Toronto, Ontario 2
DS Consultants Ltd. November 19, 2018
1. INTRODUCTION
DS Consultants Limited (DSCL)was retained by Collecdev to undertake a preliminary geotechnical
investigation for the proposed development located at 40-44 Broadway Aveneue in Toronto,
Ontario.
It is understood that the existing site is occupied by a church which will be demolished.
It is also understood that the proposed development will consist of a new church and a thirty-five
(35) storey residential building with up to five (5) levels of underground parking below the entire
church and the high-rise building. The finished floor elevation of P5 floor is not known to us to us at
the time of writing this report.
Trafalgar environmental Consultants (TEC) carried out an environmental inspection and soil sampling
program (Project No. T16124, dated May 15, 2017) and a total of nine Boreholes (BH1 through BH9)
were drilled to depths ranging from 6.1 to 7.6m below ground surface.
A Phase 2 Environmental Investigation (Project No. T17121, dated Jan. 12 to April 13, 2018) at the
subject site was carried out by Trafalgar Environmental Consultants (TEC) and a total of twenty-one
(21) boreholes were drilled to depths ranging from 1.5 to 7.6m below ground surface. Four (4)
boreholes MW1, MW3, MW5 and MW7 were equipped with monitoring wells of 50mm dia. The logs
of the boreholes MW1, MW3, MW5 and MW7 are attached in Appendix A of this report.
DS is also carrying out environmental and hydrogeological investigations at the subject site and the
findings will be documented under separate covers. This report deals with the geotechnical aspects
of the site.
The purpose of this geotechnical investigation was to determine the subsurface conditions at the
three (3) deep borehole locations and from the findings at the boreholes make geotechnical
recommendations for the following:
1. Foundations
2. Floor slabs and permanent drainage
3. Excavations and groundwater control
4. Temporary shoring
5. Earth pressures
6. Earthquake considerations
This report is provided on the basis of the terms of reference presented above and on the
assumption that the design will be in accordance with applicable codes and standards. If there are
any changes in the design features relevant to the geotechnical analyses, or if any questions arise
concerning the geotechnical aspects of the codes and standards, this office should be contacted to
review the design. It may then be necessary to carry out additional borings and reporting before the
recommendations can cater to the changed design.
Project: 18-701-10
Preliminary Geotechnical Investigation 40-44 Broadway Avenue
Toronto, Ontario 3
DS Consultants Ltd. November 19, 2018
The site investigation and recommendations follow generally accepted practice for geotechnical
consultants in Ontario. The format and contents are guided by client specific needs and economics
and do not conform to generalized standards for services. Laboratory testing for most part follows
ASTM or CSA Standards or modifications of these standards that have become standard practice.
This report has been prepared for Collecdev, its architect and designers. Use of this report by third
party without DS consent is prohibited.
2. FIELD AND LABORATORY WORK
A total of six deep and shallow boreholes (BH18-1 through BH18-6 and BH18-1A see Drawing 1 for
borehole locations) were drilled at the subject site. Boreholes BH18-1, BH18-2 and BH18-5 were
drilled for the geotechnical and hydrogeological study to depths ranging from 18.6 to 25.0m below
ground surface. Boreholes BH18-3, BH18-4 and BH18-6 were drilled to shallower depths ranging
from 2.1 to 3.5m. BH18-1A was drilled adjacent to BH18-1 for the environmental purposes to a
depth of 13.7m below ground surface.
These boreholes were drilled with solid and hollow stem continuous flight auger equipment by a
drilling sub-contractor under the direction and supervision of DS personnel. Samples were retrieved
at regular intervals with a 50 mm O.D. split-barrel sampler driven with a hammer weighing 624 N and
dropping 760 mm in accordance with the Standard Penetration Test (SPT) method. The samples
were logged in the field and returned to the DS laboratory for detailed examination by the project
engineer and for laboratory testing.
As well as visual examination in the laboratory, all soil samples from geotechnical boreholes were
tested for moisture contents. Grain size analyses of four (4) selected soil samples were conducted
and the results are presented on individual logs and on Drawing 8.
Water level observations were made during and upon completion of drilling. Boreholes BH18-1,
BH1A, BH18-2 and BH18-5 were equipped with 50mm dia. monitoring wells for the long-term
groundwater measurements.
Surveying at the borehole locations was undertaken by DS personnel and the elevations at the
borehole locations were referenced to geodetic benchmark.
3. SITE AND SUBSURFACE CONDITIONS
The Site is comprised of a 0.42 hectare (1.037 acre) parcel of land, which is currently developed with
a church (St. Monica’s Church). The borehole location plan is shown on Drawing 1. General notes on
sample description are provided on Drawing 1A. The subsurface conditions at the boreholes are
presented in the individual borehole logs presented on Drawings 2 to 7.
3.1 Soil Conditions
PAVEMENT STRUCTURE: Boreholes BH18-3 to BH18-6 were drilled on paved surface and
encountered a pavement structure consisting of 60 to 120mm of asphaltic concrete overlying 150 to
700mm of granular base.
Project: 18-701-10
Preliminary Geotechnical Investigation 40-44 Broadway Avenue
Toronto, Ontario 4
DS Consultants Ltd. November 19, 2018
FILL: Fill material was found in all boreholes extending to depths ranging from 1.5 to 3.8m below
ground surface. The fill consisted of sand and gravel, silty clay to clayey silt and silty sand. Fill was
found in a stiff consistency/compact to dense state with, measured SPT ‘N’ values ranging from 10 to
40 blows per 300 mm penetration. Traces of organics and brick fragments were also observed in fill
material.
UPPER COHESIONLESS DEPOSITS: Below fill and silty sand till at BH18-1, silty sand till at BH18-2 and
below clayey silt silty at BH18-5, upper cohesionless deposits of silty sand, sand and gravel and sandy
silt were encountered and extended to depths ranging from (9.1m at BH18-5) to (17.8 to 19.8m at
BH18-1 and BH18-2). Upper cohesionless deposits were found wet at BH18-1 at a depth of 3.8m and
10.7m below ground surface. Upper cohesionless deposits were found generally in a dense to very
dense state with occasional compact layers with, measured SPT ‘N’ values ranging from 15 to more
than 50 blows per 300mm of penetration.
Grain size analyses of one sand sample from upper cohesionless deposits (BH18-1/SS12) was
conducted and the result is presented on Drawing 8, with the following fractions:
Sand: 85%
Silt: 14%
Clay: 1%
SILTY SAND TILL: Below upper cohesionless deposits at BH18-1 and below clayey silt till deposit at
BH18-2, silty sand till deposits was encountered and extended to depths ranging from 9.2 to 10.7m
below ground surface. An interbedded wet sand layer was found at a depth of 9.9m in BH18-1. These
deposits were found in a dense to very dense state with, measured SPT ‘N’ values ranging from 46 to
more than 50 blows per 300mm of penetration.
Grain size analysis of one silty sand till sample (BH18-1/SS7) was conducted and the result is
presented in Drawing 8, with the following fractions:
Gravel: 3%
Sand: 43%
Silt: 49%
Clay: 5%
CLAYEY SILT TILL: Below fill material at BH18-2, BH18-3, BH18-5 and BH18-6, clayey silt till deposit
was encountered and extended to depths ranging from 3.5 to 6.1m below ground surface. This
deposit was found generally in a very stiff to hard consistency with occasional firm layers with,
measured SPT ‘N’ values ranging from 8 to more than 50 blows per 300mm of penetration.
Boreholes BH18-3 and BH18-6 were terminated in this deposit.
Grain size analysis of one clayey silt till sample (BH18-2/SS5) was conducted and the result is
presented in Drawing 8, with the following fractions:
Project: 18-701-10
Preliminary Geotechnical Investigation 40-44 Broadway Avenue
Toronto, Ontario 5
DS Consultants Ltd. November 19, 2018
Gravel: 3%
Sand: 33%
Silt: 51%
Clay: 13%
MIDDLE COHESIVE DEPOSITS: Below the upper cohesionless deposits at BH18-1, BH18-2 and BH18-
5, middle cohesive deposits of silty clay to clay silt were encountered and extended to depths
ranging from (10.7m at BH18-5) to (18.3 to 21.3m at BH18-1 and BH18-2). Middle cohesive deposits
were found in a hard consistency with, measured SPT ‘N’ values ranging from 35 to more than 50
blows per 300mm of penetration.
LOWER COHESIONLESS DEPOSITS: Below the middle cohesive deposits at BH18-1, BH18-2 and BH18-
5, lower cohesionless deposits were encountered and extended to the termination depths of the
boreholes. Lower cohesionless deposits were found in a very dense state with, measured SPT ‘N’
values of more than 50 blows per 300mm of penetration. Lower cohesionless deposits were found
wet below depths ranging from 16.8 to 21.3m below ground surface.
Grain size analysis of one sandy silt sample from lower cohesionless deposits (BH18-1/SS19) was
conducted and the result is presented in Drawing 8, with the following fractions:
Sand: 39%
Silt: 57%
Clay: 4%
3.2 Groundwater Conditions
Four Boreholes drilled by DS BH18-1, BH18-1A, BH18-2 and BH18-5 were equipped with monitoring
wells of 50mm dia. to measure the stabilized groundwater. The groundwater level measured at
BH18-1, BH18-1A and BH18-2 was found at depths ranging from 13.5 to 14.3, corresponding to Elev.
148.2 to 151.9m below existing grades. BH18-5 and the monitoring wells installed by TEC (MW1,
MW3, MW5 and MW7) were found dry. Table 1 summarizes the depth and elevation of water level
readings in monitoring wells.
Table 1: Summary of Groundwater Level Measurements
Groundwater Level Measurements in Monitoring Wells Installed by
DS Consultants in Sept. 2018
Depth/Elev. of Screen
inferred (m)
BH No. Ground
Surface
Elevation
(m)
Ground water Depth/Elevation (m)
Oct. 03/18 Oct. 11/18 Nov. 14, 2018
BH18-1 162.4 14.3/148.2 14.3/148.2 13.7/148.8 21.3 – 24.3 (141.2 – 138.2)
BH18-1A 162.5 13.7/148.7 13.6/148.8 13.6/148.8 10.7 – 13.7 (151.8 – 148.8)
BH18-2 165.5 Dry Dry 13.5/151.9 10.7 – 13.7 (154.8 – 151.8)
BH18-5 164.6 Dry Dry Dry 12.2 – 15.2 (152.4 – 149.4)
Groundwater Level Measurements in Monitoring Wells Installed by
TEC in Jan. 2018
Project: 18-701-10
Preliminary Geotechnical Investigation 40-44 Broadway Avenue
Toronto, Ontario 6
DS Consultants Ltd. November 19, 2018
MW1 - Dry 3.4 – 6.4
MW3 - Dry 4.6 – 7.6
MW5 - Dry 3.0 – 6.0
MW7 - Dry 3.0 – 6.0
It should be noted that the groundwater levels can vary and are subject to seasonal fluctuations in
response to major weather events.
4. FOUNDATIONS
It is also understood that the proposed development will consist of a new church and a thirty-five
(35) storey residential building with up to five (5) levels of underground parking below the entire
church and the high-rise building. The P5 level is anticipated to be at about 15m below existing
grade. The footings are expected to be about 1 to 2m below the P5 basement floor.
Based on the information from boreholes, the proposed building with five levels of basement can be
supported by conventional spread and strip footings / mat foundations for a bearing capacity of 600
to 800 kPa at SLS (Serviceability Limit States), and for a factored geotechnical resistance of 900 to
1200 kPa at ULS (Ultimate Limit States) at the anticipated founding levels. The lower value is for 2
levels of basement and the upper value is for 3 or more levels of basement.
Foundations designed to the specified bearing capacity at the Serviceability Limit States (SLS) are
expected to settle less than 25mm total and 19mm differential.
A subgrade reaction coefficient of kt=25 MPa/m can be used for the design of the raft foundation
Where it is necessary to place foundations at different levels, the upper footing must be founded
below an imaginary 10 horizontal to 7 vertical line drawn up from the base of the lower footing. The
lower footing must be installed first to help minimize the risk of undermining the upper footing. In
the vicinity of the existing buried utilities, all footings must be lowered to undisturbed native soils, or
alternatively the services must be structurally bridged.
It should be noted that the recommended bearing capacities have been calculated by DS Consultants
Limited from the borehole information for the preliminary design stage only. The investigation and
comments are necessarily on-going as new information of the underground conditions becomes
available. For example, more specific information is available with respect to conditions between
boreholes when foundation construction is underway. The interpretation between boreholes and
the recommendations of this report must therefore be checked through field inspections provided
by DS Consultants Limited to validate the information for use during the construction stage.
5. FLOOR SLAB AND PERMANENT DRAINAGE
The basement floor can be supported on grade provided the surficially loose/softened soils are
removed and the base thoroughly proof rolled. Any backfill required to raise the grade can consists
of inorganic soil, placed in shallow lifts and compacted to 98 percent of Standard Proctor Maximum
Dry Density (SPMDD).
Project: 18-701-10
Preliminary Geotechnical Investigation 40-44 Broadway Avenue
Toronto, Ontario 7
DS Consultants Ltd. November 19, 2018
A moisture barrier consisting of at least 200mm of 19mm clear crushed stone should be installed
under the floor slab.
A perimeter and underfloor drainage system will be required around the exterior basement walls.
Typical drainage and backfill recommendations are illustrated on Drawing 9.
Wherever the exposed subgrade consists of cohesionless soils below the water table; all openings
including the subgrade must be covered or wrapped with filter fabric, typically a Class II non-woven
textile with a filtration opening size (F.O.S.) of 50 to 100 μm.
6. ELEVATOR AND SUMP PITS
For elevator and sump pits be installed in sandy and silty deposits, below groundwater table,
drainage systems at the base level of the elevator pits are not recommended, due to the concern of
loss of fines. The elevator pits can be designed as water-tight structures, and water pressure on the
pit walls and the slab should be considered, assuming the water table at about 0.3m below the
adjacent basement floor.
7. FROST PROTECTION
All footings exposed to seasonal freezing conditions must have at least 1.2 metres of soil cover for
frost protection.
There is no official rule governing the required founding depth for footings below unheated
basement floors. Certainly, it will not be greater than the 1.2 m required in Southern Ontario for
exterior footings. Un-monitored experience indicates that a shallower depth ranging from 0.82 to
0.9 m for interior column footings and 0.4 m for wall footings has been successful where 2 or more
basement levels apply. The 0.82 m depth is believed to be close to the minimum structural
requirement for interior column footings. Adjacent to air shafts and entrance and exit doors, a
footing depth of 1.2 m below floor level is required or, alternatively, insulation protection must be
provided.
It is also emphasized that underfloor drainage and/or an adequate free draining gravel base is
required to minimize the risk of floor dampness. Floor dampness could lead to temporary icing and
the risk of accidents.
8. EARTH AND WATER PRESSURES
The lateral earth pressures acting on foundation walls may be calculated from the following
expression:
p = K(γ h +q)
where, p = Lateral earth pressure in kPa acting at depth h
K = Earth pressure coefficient, assumed to be 0.40 for vertical walls
and horizontal backfill for permanent construction
γ = Unit weight of backfill, a value of 21 kN/m3 may be assumed
Project: 18-701-10
Preliminary Geotechnical Investigation 40-44 Broadway Avenue
Toronto, Ontario 8
DS Consultants Ltd. November 19, 2018
h = Depth to point of interest in metres
q = Equivalent value of surcharge on the ground surface in kPa
The above expression assumes that the perimeter drainage system prevents the build-up of any
hydrostatic pressure behind the wall.
9. EXCAVATION AND GROUNDWATER CONTROL
Excavation can be carried out with heavy hydraulic backhoe. Any excavation below wet sandy
deposits (below elevations of 151.9m and 148.8m) will require positive dewatering using well
points/eductors; otherwise it will result in an unstable base and flowing sides. The groundwater
table must be lowered to at least 1.0m below the deepest excavation. A contractor specializing in
dewatering should be retained to design the dewatering systems. At other locations groundwater
can be controlled using pumping from sumps. DS is carrying out a hydrogeological study at the
subject site and more comments regarding the type and extent of groundwater control required will
be addressed in the hydrogeology report.
It should be noted that the till is a non-sorted sediment and therefore may contain boulders.
Provisions must be made in the excavation contract for the removal of possible boulders in the till or
obstructions in the fill material.
All temporary excavations must be carried out in accordance with the most recent Occupational
Health and Safety Act (OHSA). In accordance with OHSA, the fill material and cohesionless sandy and
silty soils can be classified as Type 3 Soil above groundwater and Type 4 Soil below groundwater
table. The very stiff to hard clayey silt till can be classified as Type 2 soil above groundwater table.
The select inorganic fill and native soils free from topsoil and organics can be used as general
construction backfill where it can be compacted with sheep's foot type compactors. Loose lifts of
soil, which are to be compacted, should not exceed 200 mm.
Imported Granular 'B' fill is recommended in areas where free draining material is required, i.e.
backfill behind foundation walls and in footing trenches.
Imported granular fill, which can be compacted with hand held equipment, should be used in
confined areas.
Depending on the time of construction and weather, some excavated material may be too wet to
compact and will require aeration prior to its use.
It should be noted that the excavated soils are subject to moisture content increase during wet
weather which would make these materials too wet for adequate compaction. Stockpiles should
therefore be compacted at the surface or be covered with tarpaulins to help minimize moisture
uptake.
Project: 18-701-10
Preliminary Geotechnical Investigation 40-44 Broadway Avenue
Toronto, Ontario 9
DS Consultants Ltd. November 19, 2018
10. EARTHQUAKE CONSIDERATIONS
Based on the existing borehole information and according to Table 4.1.8.4.A of OBC 2012, the
subject site for the proposed development building with five levels of basement can be classified as
“Class C” for seismic site response
11. TEMPORARY SHORING
It is understood that the proposed excavations may be supported by a temporary shoring system
consisting of timber lagging and soldier piles. A caisson wall may be required to support adjacent
structures. The requirement for caisson walls is given on Drawings 10 and 11. A continuous caisson
wall may be required if excavation exceeds below 13.5m.
The shoring system must be designed in accordance with the Fourth Edition of the Canadian
Foundation Engineering Manual. The soil parameters estimated to be applicable for this design are
as follows:
1) Earth Pressure Coefficients
(a) where movement must be minimal
K0=0.50 for shoring near TTC structures
K=0.45 for shoring not within influence of the TTC structures
(b) where minor movement (.002H) can be tolerated K=0.28
(c) passive earth pressure for soldier piles (unfactored) Kp=4
(d) where minor movement (.002H) can be tolerated K= 0.25
(e) passive earth pressure for soldier piles (unfactored) Kp=4 for very dense soils
2) For stability check
φ= 32°
c= 0
γ = 21 kN/m3
Surcharge is to be determined by shoring contractor.
3) For earth anchors
An allowable bond value of 50 kPa is suggested; this value depends on anchor installation methods
and grouting procedures. Gravity poured concrete can result in low bond values while pressure
grouted anchors will give higher values and produce a more satisfactory anchor.
The top anchor must not be placed lower than 3.0 metres below the top of level ground surface.
Anchors will require casing when penetrating through wet sand and silt layers. The bond value of 50
KPa is suggested but this value is arbitrary since the contractor’s installation procedures will
determine the actual soil to concrete bond value. Hence, the contractor must decide on a capacity
Project: 18-701-10
Preliminary Geotechnical Investigation 40-44 Broadway Avenue
Toronto, Ontario 10
DS Consultants Ltd. November 19, 2018
and confirm its availability. All anchors must be tested as indicated in the Foundation Manual, 4th
edition.
The soldier piles should be installed in pre-augered holes taken below the deepest excavation. The
holes should be filled with concrete below the excavation level and half bag mix above the base of
the excavation. The concrete strength must be specified by the shoring designer. Temporary liners
will be required to help prevent the sand deposits from caving during the installation period.
Positive measures may be required to prevent the loss of soil through the spaces between the
lagging boards. This could probably be achieved by placing well-graded sand and gravel behind the
lagging boards or by installing a geotextile filter cloth.
Soil anchors will be required to support the shoring. The anchors must be of a length that meets the
Canadian Foundation Manual recommendations. It is important to note that the minimum length
lies beyond the 45 - φ/2 + .15H line drawn from the base of the soldier pile and the overall stability of
the system must be checked at each anchor level.
Adhesion on the buried caisson shaft or behind the shoring system must be neglected when
designing this shoring system.
Movement of the shoring system is inevitable. Vertical movements will result from the vertical load
on the soldier piles resulting from the inclined tiebacks and inward horizontal movement results
from earth and water pressures. The magnitude of this movement can be controlled by sound
construction practices, and it is anticipated that the horizontal movement will be in the range of 0.1
to 0.25%H.
To ensure that movements of the shoring are within an acceptable range, monitoring must be
carried out. Vertical and horizontal targets on the soldier piles must be located and surveyed before
excavation begins. Weekly readings during excavation should show that the movements will be
within those predicted; if not, the monitoring results will enable directions to be given to improve
the shoring.
12. GENERAL COMMENTS AND LIMITATIONS OF REPORT
DS Consultants Limited (DSCL) should be retained for a general review of the final design and
specifications to verify that this report has been properly interpreted and implemented. If not
accorded the privilege of making this review, DSCL will assume no responsibility for interpretation of
the recommendations in the report.
This report is intended solely for the Client named. The material in it reflects our best judgment in
light of the information available to DSCL at the time of preparation. Unless otherwise agreed in
writing by DSCL, it shall not be used to express or imply warranty as to the fitness of the property for
a particular purpose. No portion of this report may be used as a separate entity, it is written to be
read in its entirety.
The conclusions and recommendations given in this report are based on information determined at
the test hole locations. The information contained herein in no way reflects on the environment
aspects of the project, unless otherwise stated. Subsurface and groundwater conditions between
Project: 18-701-10
Geotechnical Investigation 40-44 Broadway Avenue
Toronto, Ontario 12
DS Consultants Ltd. November 19, 2018
Drawings
Project No.: 18-701-10
Drawing 1A: Notes On Sample Descriptions
1. All sample descriptions included in this report generally follow the Unified Soil Classification. Laboratory grain size
analyses provided by DSCL also follow the same system. Different classification systems may be used by others, such
as the system by the International Society for Soil Mechanics and Foundation Engineering (ISSMFE). Please note that,
with the exception of those samples where a grain size analysis and/or Atterberg Limits testing have been made, all
samples are classified visually. Visual classification is not sufficiently accurate to provide exact grain sizing or precise
differentiation between size classification systems.
ISSMFE SOIL CLASSIFICATION CLAY SILT SAND GRAVEL COBBLES BOULDERS FINE MEDIUM COARSE FINE MEDIUM COARSE FINE MEDIUM COARSE
0.002 0.006 0.02 0.06 0.2 0.6 2.0 6.0 20 60 200
EQUIVALENT GRAIN DIAMETER IN MILLIMETRES
CLAY (PLASTIC) TO FINE MEDIUM CRS. FINE COARSE SILT (NONPLASTIC) SAND GRAVEL
UNIFIED SOIL CLASSIFICATION
2. Fill: Where fill is designated on the borehole log it is defined as indicated by the sample recovered during the boring
process. The reader is cautioned that fills are heterogeneous in nature and variable in density or degree of
compaction. The borehole description may therefore not be applicable as a general description of site fill materials.
All fills should be expected to contain obstruction such as wood, large concrete pieces or subsurface basements,
floors, tanks, etc., none of these may have been encountered in the boreholes. Since boreholes cannot accurately
define the contents of the fill, test pits are recommended to provide supplementary information. Despite the use of
test pits, the heterogeneous nature of fill will leave some ambiguity as to the exact composition of the fill. Most fills
contain pockets, seams, or layers of organically contaminated soil. This organic material can result in the generation
of methane gas and/or significant ongoing and future settlements. Fill at this site may have been monitored for the
presence of methane gas and, if so, the results are given on the borehole logs. The monitoring process does not
indicate the volume of gas that can be potentially generated nor does it pinpoint the source of the gas. These
readings are to advise of the presence of gas only, and a detailed study is recommended for sites where any explosive
gas/methane is detected. Some fill material may be contaminated by toxic/hazardous waste that renders it
unacceptable for deposition in any but designated land fill sites; unless specifically stated the fill on this site has not
been tested for contaminants that may be considered toxic or hazardous. This testing and a potential hazard study
can be undertaken if requested. In most residential/commercial areas undergoing reconstruction, buried oil tanks are
common and are generally not detected in a conventional preliminary geotechnical site investigation.
3. Till: The term till on the borehole logs indicates that the material originates from a geological process associated with
glaciation. Because of this geological process the till must be considered heterogeneous in composition and as such
may contain pockets and/or seams of material such as sand, gravel, silt or clay. Till often contains cobbles (60 to 200
mm) or boulders (over 200 mm). Contractors may therefore encounter cobbles and boulders during excavation, even
if they are not indicated by the borings. It should be appreciated that normal sampling equipment cannot
differentiate the size or type of any obstruction. Because of the horizontal and vertical variability of till, the sample
description may be applicable to a very limited zone; caution is therefore essential when dealing with sensitive
excavations or dewatering programs in till materials.
161.7
160.0
158.7
157.9
151.8
49
14
FILL: sand & gravel, grey, moist,compact
FILL: limestone screenings, grey,moist, loose50mm thick silty clay, trace organicslayer at 0.9m
FILL: silty clay mixed withlimestone screening, grey to brown,moist, soft to firm
SILTY FINE SAND: trace clay,brown, moist, compact
SILTY SAND TILL: trace clay,trace gravel, brown to grey, moist towet, dense to very dense
layer of silty clay at 9.1m
layer of wet sand at 9.9m
SAND: trace silt, grey, wet, verydense
3
0.8
2.5
3.8
4.6
10.7
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
1
2
3
4
5
6
7
8
9
10
11
12
43
85
16
7
4
4
5
15
46
68
59
50/150mm
50/150mm
92/275mm
5
1
Continued Next Page
1 OF 3
20 40 60 80 100GR
OU
ND
WA
TE
R
CO
ND
ITIO
NS
"N"
B
LOW
S
0.3
m
DESCRIPTION
GR
REF. NO.: 18-701-10
ENCL NO.: 2
1
2
3
4
5
6
7
8
9
10
11
12
13
Numbers referto Sensitivity
w
WATER CONTENT (%)
wP
DEPTH
SA
1st 2nd 4th3rdGROUNDWATER ELEVATIONS
(kN
/m3)
DRILLING DATA
Method: Hollow Stem Augers
Diameter: 200mm
Date: Sep-24-2018
PROJECT: Geotechnical Investigation- Proposed High-rise Building
CLIENT: Collecdev
PROJECT LOCATION: 40-44 Broadway Avenue in Toronto, Ontario
DATUM: Geodetic
BH LOCATION: See Drawing 1
SOIL PROFILE
ELE
VA
TIO
N
20 40 60 80 100
QUICK TRIAXIAL
SHEAR STRENGTH (kPa)
TY
PE
,3
CL
=3%Strain at Failure
Measurement
(Cu)
(kP
a)(m)
ST
RA
TA
PLO
T
LAB VANE
:
10 20 30
REMARKS
AND
GRAIN SIZE
DISTRIBUTION
(%)
NATURALMOISTURECONTENT
3
SI
GRAPHNOTES
LIQUIDLIMIT
SAMPLES
NU
MB
ER
162
161
160
159
158
157
156
155
154
153
152
151
150
NA
TU
RA
L U
NIT
WT
PO
CK
ET
PE
N.
162.5
PLASTICLIMIT
FIELD VANE& Sensitivity
ELEV
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
wL
0.0
UNCONFINED
LOG OF BOREHOLE BH18-1D
S S
OIL
LO
G 1
8-70
1-10
- 4
0-44
BR
OA
DW
AY
, TO
RO
NT
O.G
PJ
DS
.GD
T 1
8-11
-21
Bentonite Grout
145.4
144.2
142.7
137.5
57
SAND: trace silt, grey, wet, verydense(Continued)
SILT TO CLAYEY SILT: tracegravel, grey, wet, hard
SILT: trace to some clay, tracesand, grey, wet, very dense
SANDY SILT: trace clay, grey, wet,very dense
frequent sand seams below 24m
END OF BOREHOLENotes:1) 50mm dia. monitoring wellinstalled in the borehole uponcompletion.
17.1
18.3
19.8
25.0
SS
SS
SS
SS
SS
SS
SS
SS
13
14
15
16
17
18
19
20
39
90
50/150mm
74
50/125mm
50/150mm
50/150mm
86
74
4
Continued Next Page
2 OF 3
20 40 60 80 100GR
OU
ND
WA
TE
R
CO
ND
ITIO
NS
"N"
B
LOW
S
0.3
m
DESCRIPTION
GR
REF. NO.: 18-701-10
ENCL NO.: 2
14
15
16
17
18
19
20
21
22
23
24
25
Numbers referto Sensitivity
w
WATER CONTENT (%)
wP
DEPTH
SA
1st 2nd 4th3rdGROUNDWATER ELEVATIONS
(kN
/m3)
DRILLING DATA
Method: Hollow Stem Augers
Diameter: 200mm
Date: Sep-24-2018
PROJECT: Geotechnical Investigation- Proposed High-rise Building
CLIENT: Collecdev
PROJECT LOCATION: 40-44 Broadway Avenue in Toronto, Ontario
DATUM: Geodetic
BH LOCATION: See Drawing 1
SOIL PROFILE
ELE
VA
TIO
N
20 40 60 80 100
QUICK TRIAXIAL
SHEAR STRENGTH (kPa)
TY
PE
,3
CL
=3%Strain at Failure
Measurement
(Cu)
(kP
a)(m)
ST
RA
TA
PLO
T
LAB VANE
:
10 20 30
REMARKS
AND
GRAIN SIZE
DISTRIBUTION
(%)
NATURALMOISTURECONTENT
3
SI
GRAPHNOTES
LIQUIDLIMIT
SAMPLES
NU
MB
ER
149
148
147
146
145
144
143
142
141
140
139
138
NA
TU
RA
L U
NIT
WT
PO
CK
ET
PE
N.PLASTIC
LIMIT
FIELD VANE& Sensitivity
ELEV
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
wL
UNCONFINED
LOG OF BOREHOLE BH18-1D
S S
OIL
LO
G 1
8-70
1-10
- 4
0-44
BR
OA
DW
AY
, TO
RO
NT
O.G
PJ
DS
.GD
T 1
8-11
-21
Filter pack
Slotted Pipe
W. L. 148.8 mNov 14, 2018
2) Water Level ReadingsDate Water Depth (mbgs)Nov. 14, 2018 13.7Oct. 11, 2018 14.3Oct 03, 2018 14.3
3 OF 3
20 40 60 80 100GR
OU
ND
WA
TE
R
CO
ND
ITIO
NS
"N"
B
LOW
S
0.3
m
DESCRIPTION
GR
REF. NO.: 18-701-10
ENCL NO.: 2
Numbers referto Sensitivity
w
WATER CONTENT (%)
wP
DEPTH
SA
1st 2nd 4th3rdGROUNDWATER ELEVATIONS
(kN
/m3)
DRILLING DATA
Method: Hollow Stem Augers
Diameter: 200mm
Date: Sep-24-2018
PROJECT: Geotechnical Investigation- Proposed High-rise Building
CLIENT: Collecdev
PROJECT LOCATION: 40-44 Broadway Avenue in Toronto, Ontario
DATUM: Geodetic
BH LOCATION: See Drawing 1
SOIL PROFILE
ELE
VA
TIO
N
20 40 60 80 100
QUICK TRIAXIAL
SHEAR STRENGTH (kPa)
TY
PE
,3
CL
=3%Strain at Failure
Measurement
(Cu)
(kP
a)(m)
ST
RA
TA
PLO
T
LAB VANE
:
10 20 30
REMARKS
AND
GRAIN SIZE
DISTRIBUTION
(%)
NATURALMOISTURECONTENT
3
SI
GRAPHNOTES
LIQUIDLIMIT
SAMPLES
NU
MB
ER
NA
TU
RA
L U
NIT
WT
PO
CK
ET
PE
N.PLASTIC
LIMIT
FIELD VANE& Sensitivity
ELEV
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
wL
UNCONFINED
LOG OF BOREHOLE BH18-1D
S S
OIL
LO
G 1
8-70
1-10
- 4
0-44
BR
OA
DW
AY
, TO
RO
NT
O.G
PJ
DS
.GD
T 1
8-11
-21
Staright augered to 13.7m withoutsoil sampling and a 50mm dia.monitoring well installed
Continued Next Page
1 OF 2
20 40 60 80 100GR
OU
ND
WA
TE
R
CO
ND
ITIO
NS
"N"
B
LOW
S
0.3
m
DESCRIPTION
GR
REF. NO.: 18-701-10
ENCL NO.: 2A
1
2
3
4
5
6
7
8
9
10
11
12
13
Numbers referto Sensitivity
w
WATER CONTENT (%)
wP
DEPTH
SA
1st 2nd 4th3rdGROUNDWATER ELEVATIONS
(kN
/m3)
DRILLING DATA
Method: Hollow Stem Augers
Diameter: 200mm
Date: Sep-25-2018
PROJECT: Geotechnical Investigation- Proposed High-rise Building
CLIENT: Collecdev
PROJECT LOCATION: 40-44 Broadway Avenue in Toronto, Ontario
DATUM: Geodetic
BH LOCATION: See Drawing 1
SOIL PROFILE
ELE
VA
TIO
N
20 40 60 80 100
QUICK TRIAXIAL
SHEAR STRENGTH (kPa)
TY
PE
,3
CL
=3%Strain at Failure
Measurement
(Cu)
(kP
a)(m)
ST
RA
TA
PLO
T
LAB VANE
:
10 20 30
REMARKS
AND
GRAIN SIZE
DISTRIBUTION
(%)
NATURALMOISTURECONTENT
3
SI
GRAPHNOTES
LIQUIDLIMIT
SAMPLES
NU
MB
ER
162
161
160
159
158
157
156
155
154
153
152
151
150
NA
TU
RA
L U
NIT
WT
PO
CK
ET
PE
N.
162.5
PLASTICLIMIT
FIELD VANE& Sensitivity
ELEV
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
wL
0.0
UNCONFINED
LOG OF BOREHOLE BH18-1AD
S S
OIL
LO
G 1
8-70
1-10
- 4
0-44
BR
OA
DW
AY
, TO
RO
NT
O.G
PJ
DS
.GD
T 1
8-11
-21
Bentonite Grout
Filter pack
Slotted Pipe
148.8
Staright augered to 13.7m withoutsoil sampling and a 50mm dia.monitoring well installed(Continued)
END OF BOREHOLENotes:1) BH18-1A was drilled adjacent toBH18-1 and a 50mm dia.monitoring well installed.2) Water Level ReadingsDate Water Depth (mbgs)Nov. 14, 2018 13.6Oct. 11, 2018 13.6Oct 03, 2018 13.7
13.7
2 OF 2
20 40 60 80 100GR
OU
ND
WA
TE
R
CO
ND
ITIO
NS
"N"
B
LOW
S
0.3
m
DESCRIPTION
GR
REF. NO.: 18-701-10
ENCL NO.: 2A
Numbers referto Sensitivity
w
WATER CONTENT (%)
wP
DEPTH
SA
1st 2nd 4th3rdGROUNDWATER ELEVATIONS
(kN
/m3)
DRILLING DATA
Method: Hollow Stem Augers
Diameter: 200mm
Date: Sep-25-2018
PROJECT: Geotechnical Investigation- Proposed High-rise Building
CLIENT: Collecdev
PROJECT LOCATION: 40-44 Broadway Avenue in Toronto, Ontario
DATUM: Geodetic
BH LOCATION: See Drawing 1
SOIL PROFILE
ELE
VA
TIO
N
20 40 60 80 100
QUICK TRIAXIAL
SHEAR STRENGTH (kPa)
TY
PE
,3
CL
=3%Strain at Failure
Measurement
(Cu)
(kP
a)(m)
ST
RA
TA
PLO
T
LAB VANE
:
10 20 30
REMARKS
AND
GRAIN SIZE
DISTRIBUTION
(%)
NATURALMOISTURECONTENT
3
SI
GRAPHNOTES
LIQUIDLIMIT
SAMPLES
NU
MB
ER
149
NA
TU
RA
L U
NIT
WT
PO
CK
ET
PE
N.PLASTIC
LIMIT
FIELD VANE& Sensitivity
ELEV
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
wL
UNCONFINED
LOG OF BOREHOLE BH18-1AD
S S
OIL
LO
G 1
8-70
1-10
- 4
0-44
BR
OA
DW
AY
, TO
RO
NT
O.G
PJ
DS
.GD
T 1
8-11
-21
W. L. 148.9 mNov 14, 2018
165.5165.2165.0
164.7
164.0
159.4
156.3
154.8
51
ASPHALTIC CONCRETE 60mmGRANULAR BASE: 200mmFILL: silt to clayey silt mixed withtopsoil & organics, trace brickfragements, brown, wet, looseFILL: sand, trace silt, brown, moist,looseFILL: silt to clayey silt, tracetopsoil, trace gravel, brown, moist,looseCLAYEY SILT TILL: trace gravel,sandy with seams of sand, brown,moist, stiff to hard
SILTY SAND TILL: trace gravel,trace to some clay, seams of sand,brown, moist, very dense
SAND AND GRAVEL: trace silt,brown, moist, very dense
SAND: trace to some silt, brown,moist, very dense
3
0.1
0.30.5
0.8
1.5
6.1
9.2
10.7
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
1
2
3
4
5
6
7
8
9
10
11
33
4
5
8
85
83/275mm
72
57
56
50/150mm
50/150mm
50/150mm
13
Continued Next Page
1 OF 3
20 40 60 80 100GR
OU
ND
WA
TE
R
CO
ND
ITIO
NS
"N"
B
LOW
S
0.3
m
DESCRIPTION
GR
REF. NO.: 18-701-10
ENCL NO.: 3
1
2
3
4
5
6
7
8
9
10
11
12
13
Numbers referto Sensitivity
w
WATER CONTENT (%)
wP
DEPTH
SA
1st 2nd 4th3rdGROUNDWATER ELEVATIONS
(kN
/m3)
DRILLING DATA
Method: Solid Stem Augers
Diameter: 150mm
Date: Sep-25-2018
PROJECT: Geotechnical Investigation- Proposed High-rise Building
CLIENT: Collecdev
PROJECT LOCATION: 40-44 Broadway Avenue in Toronto, Ontario
DATUM: Geodetic
BH LOCATION: See Drawing 1
SOIL PROFILE
ELE
VA
TIO
N
20 40 60 80 100
QUICK TRIAXIAL
SHEAR STRENGTH (kPa)
TY
PE
,3
CL
=3%Strain at Failure
Measurement
(Cu)
(kP
a)(m)
ST
RA
TA
PLO
T
LAB VANE
:
10 20 30
REMARKS
AND
GRAIN SIZE
DISTRIBUTION
(%)
NATURALMOISTURECONTENT
3
SI
GRAPHNOTES
LIQUIDLIMIT
SAMPLES
NU
MB
ER
165
164
163
162
161
160
159
158
157
156
155
154
153
NA
TU
RA
L U
NIT
WT
PO
CK
ET
PE
N.
165.5
PLASTICLIMIT
FIELD VANE& Sensitivity
ELEV
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
wL
0.0
UNCONFINED
LOG OF BOREHOLE BH18-2D
S S
OIL
LO
G 1
8-70
1-10
- 4
0-44
BR
OA
DW
AY
, TO
RO
NT
O.G
PJ
DS
.GD
T 1
8-11
-21
Bentonite Grout
Filter pack
Slotted Pipe
145.7
144.2
142.6
140.7
SAND: trace to some silt, brown,moist, very dense(Continued)
SILT TO CLAYEY SILT: tracesand, grey, moist, hard
SAND: trace silt, grey, wet, verydense
SILT TO SANDY SILT: trace sand,trace clay, grey, wet, very dense
END OF BOREHOLENotes:1) 50mm dia. monitoring wellinstalled in the borehole uponcompletion.2) Water Level Readings
19.8
21.3
22.9
24.8
SS
SS
SS
SS
SS
SS
SS
SS
12
13
14
15
16
17
18
19
50/150mm
50/100mm
94/250mm
50/150mm
50/150mm
50/150mm
89/275mm
84
Continued Next Page
2 OF 3
20 40 60 80 100GR
OU
ND
WA
TE
R
CO
ND
ITIO
NS
"N"
B
LOW
S
0.3
m
DESCRIPTION
GR
REF. NO.: 18-701-10
ENCL NO.: 3
14
15
16
17
18
19
20
21
22
23
24
Numbers referto Sensitivity
w
WATER CONTENT (%)
wP
DEPTH
SA
1st 2nd 4th3rdGROUNDWATER ELEVATIONS
(kN
/m3)
DRILLING DATA
Method: Solid Stem Augers
Diameter: 150mm
Date: Sep-25-2018
PROJECT: Geotechnical Investigation- Proposed High-rise Building
CLIENT: Collecdev
PROJECT LOCATION: 40-44 Broadway Avenue in Toronto, Ontario
DATUM: Geodetic
BH LOCATION: See Drawing 1
SOIL PROFILE
ELE
VA
TIO
N
20 40 60 80 100
QUICK TRIAXIAL
SHEAR STRENGTH (kPa)
TY
PE
,3
CL
=3%Strain at Failure
Measurement
(Cu)
(kP
a)(m)
ST
RA
TA
PLO
T
LAB VANE
:
10 20 30
REMARKS
AND
GRAIN SIZE
DISTRIBUTION
(%)
NATURALMOISTURECONTENT
3
SI
GRAPHNOTES
LIQUIDLIMIT
SAMPLES
NU
MB
ER
152
151
150
149
148
147
146
145
144
143
142
141
NA
TU
RA
L U
NIT
WT
PO
CK
ET
PE
N.PLASTIC
LIMIT
FIELD VANE& Sensitivity
ELEV
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
wL
UNCONFINED
LOG OF BOREHOLE BH18-2D
S S
OIL
LO
G 1
8-70
1-10
- 4
0-44
BR
OA
DW
AY
, TO
RO
NT
O.G
PJ
DS
.GD
T 1
8-11
-21
W. L. 152.0 mNov 14, 2018
Date Water Depth (mbgs)Nov. 14, 2018 13.5Oct. 11, 2018 DryOct 03, 2018 Dry
3 OF 3
20 40 60 80 100GR
OU
ND
WA
TE
R
CO
ND
ITIO
NS
"N"
B
LOW
S
0.3
m
DESCRIPTION
GR
REF. NO.: 18-701-10
ENCL NO.: 3
Numbers referto Sensitivity
w
WATER CONTENT (%)
wP
DEPTH
SA
1st 2nd 4th3rdGROUNDWATER ELEVATIONS
(kN
/m3)
DRILLING DATA
Method: Solid Stem Augers
Diameter: 150mm
Date: Sep-25-2018
PROJECT: Geotechnical Investigation- Proposed High-rise Building
CLIENT: Collecdev
PROJECT LOCATION: 40-44 Broadway Avenue in Toronto, Ontario
DATUM: Geodetic
BH LOCATION: See Drawing 1
SOIL PROFILE
ELE
VA
TIO
N
20 40 60 80 100
QUICK TRIAXIAL
SHEAR STRENGTH (kPa)
TY
PE
,3
CL
=3%Strain at Failure
Measurement
(Cu)
(kP
a)(m)
ST
RA
TA
PLO
T
LAB VANE
:
10 20 30
REMARKS
AND
GRAIN SIZE
DISTRIBUTION
(%)
NATURALMOISTURECONTENT
3
SI
GRAPHNOTES
LIQUIDLIMIT
SAMPLES
NU
MB
ER
NA
TU
RA
L U
NIT
WT
PO
CK
ET
PE
N.PLASTIC
LIMIT
FIELD VANE& Sensitivity
ELEV
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
wL
UNCONFINED
LOG OF BOREHOLE BH18-2D
S S
OIL
LO
G 1
8-70
1-10
- 4
0-44
BR
OA
DW
AY
, TO
RO
NT
O.G
PJ
DS
.GD
T 1
8-11
-21
164.7164.4
164.0
163.3
163.0
161.1
ASPHALTIC CONCRETE :110mmGRANULAR BASE: 250mmFILL: sand, trace gravel, trace silt,brown, moist, looseFILL: clayey silt, traceorganics/topsoil, brown to grey, verymoist, looseFILL: silty clay, sandy, trace gravel,brown, moist, stiffCLAYEY SILT TILL: sandy, tracegravel, brown, moist, stiff to hard
END OF BOREHOLENotes:1) Borehole dry upon completion
0.1
0.4
0.8
1.5
1.8
3.7
SS
SS
SS
SS
SS
1
2
3
4
5
6
3
8
41
60
1 OF 1
20 40 60 80 100GR
OU
ND
WA
TE
R
CO
ND
ITIO
NS
"N"
B
LOW
S
0.3
m
DESCRIPTION
GR
REF. NO.: 18-701-10
ENCL NO.: 4
1
2
3
Numbers referto Sensitivity
w
WATER CONTENT (%)
wP
DEPTH
SA
1st 2nd 4th3rdGROUNDWATER ELEVATIONS
(kN
/m3)
DRILLING DATA
Method: Solid Stem Augers
Diameter: 150mm
Date: Sep-27-2018
PROJECT: Geotechnical Investigation- Proposed High-rise Building
CLIENT: Collecdev
PROJECT LOCATION: 40-44 Broadway Avenue in Toronto, Ontario
DATUM: Geodetic
BH LOCATION: See Drawing 1
SOIL PROFILE
ELE
VA
TIO
N
20 40 60 80 100
QUICK TRIAXIAL
SHEAR STRENGTH (kPa)
TY
PE
,3
CL
=3%Strain at Failure
Measurement
(Cu)
(kP
a)(m)
ST
RA
TA
PLO
T
LAB VANE
:
10 20 30
REMARKS
AND
GRAIN SIZE
DISTRIBUTION
(%)
NATURALMOISTURECONTENT
3
SI
GRAPHNOTES
LIQUIDLIMIT
SAMPLES
NU
MB
ER
164
163
162
NA
TU
RA
L U
NIT
WT
PO
CK
ET
PE
N.
164.8
PLASTICLIMIT
FIELD VANE& Sensitivity
ELEV
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
wL
0.0
UNCONFINED
LOG OF BOREHOLE BH18-3D
S S
OIL
LO
G 1
8-70
1-10
- 4
0-44
BR
OA
DW
AY
, TO
RO
NT
O.G
PJ
DS
.GD
T 1
8-11
-21
164.3164.0
162.3
ASPHALTIC CONCRETE: 100mmGRANULAR BASE: 300mmFILL: sand and gravel, someconcrete fragments, trace asphalt &brick fragments, brown, moist,loose to dense
END OF BOREHOLE:Notes:1) BH moved 1.5m Northwest dueto the concrete pieces and augerrefusal at 0.8m2) BH moved 1.0m Southeast of firstBH. Auger refusal at 2.1m
0.1
0.4
2.1
SS
SS
SS
1
2
3
14
8
32
1 OF 1
20 40 60 80 100GR
OU
ND
WA
TE
R
CO
ND
ITIO
NS
"N"
B
LOW
S
0.3
m
DESCRIPTION
GR
REF. NO.: 18-701-10
ENCL NO.: 5
1
2
Numbers referto Sensitivity
w
WATER CONTENT (%)
wP
DEPTH
SA
1st 2nd 4th3rdGROUNDWATER ELEVATIONS
(kN
/m3)
DRILLING DATA
Method: Hollow Stem Augers
Diameter: 200mm
Date: Sep-27-2018
PROJECT: Geotechnical Investigation- Proposed High-rise Building
CLIENT: Collecdev
PROJECT LOCATION: 40-44 Broadway Avenue in Toronto, Ontario
DATUM: Geodetic
BH LOCATION: See Drawing 1
SOIL PROFILE
ELE
VA
TIO
N
20 40 60 80 100
QUICK TRIAXIAL
SHEAR STRENGTH (kPa)
TY
PE
,3
CL
=3%Strain at Failure
Measurement
(Cu)
(kP
a)(m)
ST
RA
TA
PLO
T
LAB VANE
:
10 20 30
REMARKS
AND
GRAIN SIZE
DISTRIBUTION
(%)
NATURALMOISTURECONTENT
3
SI
GRAPHNOTES
LIQUIDLIMIT
SAMPLES
NU
MB
ER
164
163
NA
TU
RA
L U
NIT
WT
PO
CK
ET
PE
N.
164.4
PLASTICLIMIT
FIELD VANE& Sensitivity
ELEV
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
wL
0.0
UNCONFINED
LOG OF BOREHOLE BH18-4D
S S
OIL
LO
G 1
8-70
1-10
- 4
0-44
BR
OA
DW
AY
, TO
RO
NT
O.G
PJ
DS
.GD
T 1
8-11
-21
164.5
163.8
162.3
160.0
158.5
157.0
155.5
153.9
ASPHALT SLAB: 120mmGRANULAR BASE: 700mm
FILL: clayey silt, trace gravel,sandy, brown, moist, loose
trace brick fragements below 1.5 m
CLAYEY SILT TILL: trace gravel,sandy, moist, brown, very stiff tohard
SAND: seams of silt, brown, moist,dense
SILTY SAND TILL: trace gravel,trace clay, brown, very moist, dense
SANDY SILT: seams of silty clay,brown to grey, moist, very dense
SILTY CLAY: seams of sand,grey, moist
SAND: trace silt, brown, moist tovery moist, very dense
0.1
0.8
2.3
4.6
6.1
7.6
9.1
10.7
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
1
2
3
4
5
6
7
8
9
10
11
11
6
4
24
43
42
42
53
35
50/150mm
50/125mm
Continued Next Page
1 OF 2
20 40 60 80 100GR
OU
ND
WA
TE
R
CO
ND
ITIO
NS
"N"
B
LOW
S
0.3
m
DESCRIPTION
GR
REF. NO.: 18-701-10
ENCL NO.: 6
1
2
3
4
5
6
7
8
9
10
11
12
13
Numbers referto Sensitivity
w
WATER CONTENT (%)
wP
DEPTH
SA
1st 2nd 4th3rdGROUNDWATER ELEVATIONS
(kN
/m3)
DRILLING DATA
Method: Solid Stem Augers
Diameter: 150mm
Date: Sep-27-2018
PROJECT: Geotechnical Investigation- Proposed High-rise Building
CLIENT: Collecdev
PROJECT LOCATION: 40-44 Broadway Avenue in Toronto, Ontario
DATUM: Geodetic
BH LOCATION: See Drawing 1
SOIL PROFILE
ELE
VA
TIO
N
20 40 60 80 100
QUICK TRIAXIAL
SHEAR STRENGTH (kPa)
TY
PE
,3
CL
=3%Strain at Failure
Measurement
(Cu)
(kP
a)(m)
ST
RA
TA
PLO
T
LAB VANE
:
10 20 30
REMARKS
AND
GRAIN SIZE
DISTRIBUTION
(%)
NATURALMOISTURECONTENT
3
SI
GRAPHNOTES
LIQUIDLIMIT
SAMPLES
NU
MB
ER
164
163
162
161
160
159
158
157
156
155
154
153
152
NA
TU
RA
L U
NIT
WT
PO
CK
ET
PE
N.
164.6
PLASTICLIMIT
FIELD VANE& Sensitivity
ELEV
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
wL
0.0
UNCONFINED
LOG OF BOREHOLE BH18-5D
S S
OIL
LO
G 1
8-70
1-10
- 4
0-44
BR
OA
DW
AY
, TO
RO
NT
O.G
PJ
DS
.GD
T 1
8-11
-21
Bentonite Grout
Filter pack
146.0
SAND: trace silt, brown, moist tovery moist, very dense(Continued)
some silt, trace clay, grey, wetbelow 16.8 m
END OF BOREHOLENotes:1) 50mm dia. monitoring wellinstalled in the borehole uponcompletion.2) Water Level ReadingsDate Water Depth (mbgs)Nov. 14, 2018 DryOct. 11, 2018 DryOct 03, 2018 Dry
18.6
SS
SS
SS
SS
12
13
14
15
50/125mm
50/125mm
56
50/150mm
2 OF 2
20 40 60 80 100GR
OU
ND
WA
TE
R
CO
ND
ITIO
NS
"N"
B
LOW
S
0.3
m
DESCRIPTION
GR
REF. NO.: 18-701-10
ENCL NO.: 6
14
15
16
17
18
Numbers referto Sensitivity
w
WATER CONTENT (%)
wP
DEPTH
SA
1st 2nd 4th3rdGROUNDWATER ELEVATIONS
(kN
/m3)
DRILLING DATA
Method: Solid Stem Augers
Diameter: 150mm
Date: Sep-27-2018
PROJECT: Geotechnical Investigation- Proposed High-rise Building
CLIENT: Collecdev
PROJECT LOCATION: 40-44 Broadway Avenue in Toronto, Ontario
DATUM: Geodetic
BH LOCATION: See Drawing 1
SOIL PROFILE
ELE
VA
TIO
N
20 40 60 80 100
QUICK TRIAXIAL
SHEAR STRENGTH (kPa)
TY
PE
,3
CL
=3%Strain at Failure
Measurement
(Cu)
(kP
a)(m)
ST
RA
TA
PLO
T
LAB VANE
:
10 20 30
REMARKS
AND
GRAIN SIZE
DISTRIBUTION
(%)
NATURALMOISTURECONTENT
3
SI
GRAPHNOTES
LIQUIDLIMIT
SAMPLES
NU
MB
ER
151
150
149
148
147
NA
TU
RA
L U
NIT
WT
PO
CK
ET
PE
N.PLASTIC
LIMIT
FIELD VANE& Sensitivity
ELEV
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
wL
UNCONFINED
LOG OF BOREHOLE BH18-5D
S S
OIL
LO
G 1
8-70
1-10
- 4
0-44
BR
OA
DW
AY
, TO
RO
NT
O.G
PJ
DS
.GD
T 1
8-11
-21
Slotted Pipe
Sand
165.5165.3
163.8
162.0
ASPHALT SLAB: 60mmGRANULAR BASE: 150mmFILL: silty sand, trace gravel,brown, moist, loose
CLAYEY SILT TILL: sandy, tracegravel, brown, moist, very stiff tohard
END OF BOREHOLE
0.10.2
1.7
3.5
SS
SS
SS
SS
SS
1
2
3
4
5
7
7
26
54
78
1 OF 1
20 40 60 80 100GR
OU
ND
WA
TE
R
CO
ND
ITIO
NS
"N"
B
LOW
S
0.3
m
DESCRIPTION
GR
REF. NO.: 18-701-10
ENCL NO.: 7
1
2
3
Numbers referto Sensitivity
w
WATER CONTENT (%)
wP
DEPTH
SA
1st 2nd 4th3rdGROUNDWATER ELEVATIONS
(kN
/m3)
DRILLING DATA
Method: Solid Stem Augers
Diameter: 150mm
Date: Sep-26-2018
PROJECT: Geotechnical Investigation- Proposed High-rise Building
CLIENT: Collecdev
PROJECT LOCATION: 40-44 Broadway Avenue in Toronto, Ontario
DATUM: Geodetic
BH LOCATION: See Drawing 1
SOIL PROFILE
ELE
VA
TIO
N
20 40 60 80 100
QUICK TRIAXIAL
SHEAR STRENGTH (kPa)
TY
PE
,3
CL
=3%Strain at Failure
Measurement
(Cu)
(kP
a)(m)
ST
RA
TA
PLO
T
LAB VANE
:
10 20 30
REMARKS
AND
GRAIN SIZE
DISTRIBUTION
(%)
NATURALMOISTURECONTENT
3
SI
GRAPHNOTES
LIQUIDLIMIT
SAMPLES
NU
MB
ER
165
164
163
NA
TU
RA
L U
NIT
WT
PO
CK
ET
PE
N.
165.5
PLASTICLIMIT
FIELD VANE& Sensitivity
ELEV
DYNAMIC CONE PENETRATIONRESISTANCE PLOT
wL
0.0
UNCONFINED
LOG OF BOREHOLE BH18-6D
S S
OIL
LO
G 1
8-70
1-10
- 4
0-44
BR
OA
DW
AY
, TO
RO
NT
O.G
PJ
DS
.GD
T 1
8-11
-21
0
10
20
30
40
50
60
70
80
90
100
0.001 0.01 0.1 1 10 100
PE
RC
EN
T P
AS
SIN
G (
%)
GRAIN SIZE (MM)
BH18-1 SS7
BH18-1 SS12
BH18-1 SS19
BH18-2 SS5
Particle Size Distribution (ASTM-D421/D422)
0.0
75
0.4
25
0.8
5
0.2
5
2 4.7
5
9.5
19
25 37
.5
50
75
20
0
Coarse
Silt and Clay
Clay Silt Medium FineCoarse
Sand Gravel Cobble +
Fine
Specification and Comments:
Project:
Client:
Location:
Project No.:
Date:
Drawing No.:
0.1
5
0.1
06
(#2
00
)
(#4
0)
(#1
0)
(#4
)
(#1
00
)
40-44 Broadway Ave. 18-701-10
Collecdev
40-44 Broadway Ave. , Toronto 8
Oct-17-2018
DRAINAGE AND BACKFILL RECOMMENDATIONSBasement with Underfloor Drainage
(not to scale)
Project: 18-701-10 Drawing No. 9
Notes 1. Drainage tile to consist of 100 mm (4") diameter weeping tile or equivalent perforated pipe leading to a positive sump or outlet. 2. 20 mm (3/4") clear stone - 150 mm (6") top and side of drain. If drain is not on footing, place100 mm (4 inches) of stone below drain . 3. Wrap the clear stone with an approved filter membrane (Terrafix 270R or equivalent). 4. Free Draining backfill - OPSS Granular B or equivalent compacted to the specified density. Do not use heavy compaction equipment within 450 mm (18") of the wall. Use hand controlled light compaction equipment within 1.8 m (6') of wall. The minimum width of the Granular 'B' backfill must be 1.0 m. 5. Impermeable backfill seal - compacted clay, clayey silt or equivalent. If original soil is free-draining, seal may be omitted. Maximum thickness of seal to be 0.5 m. 6. Do not backfill until wall is supported by basement and floor slabs or adequate bracing. 7. Moisture barrier to be at least 200 mm (8") of compacted clear 20 mm (3/4") stone or equivalent free draining material. A vapour barrier may be required for specialty floors. 8. Basement wall to be damp proofed /water proofed. 9. Exterior grade to slope away from building.10. Slab on grade should not be structurally connected to the wall or footing.11. Underfloor drain invert to be at least 300 mm (12") below underside of floor slab.12. Drainage tile placed in parallel rows 6 to 8 m (20 to 25') centers one way. Place drain on 100 mm (4") clear stone with 150 mm (6") of clear stone on top and sides. Enclose stone with filter fabric as noted in (3). 13. The entire subgrade to be sealed with approved filter fabric (Terrafix 270R or equivalent) if non-cohesive (sandy) soils below ground water table encountered. 14. Do not connect the underfloor drains to perimeter drains.15. Review the geotechnical report for specific details.
Exterior Grade (9)
Impermeable Seal (5)
On-Site Materialif Approved (4) Free Draining Backfill (4)
Basement Wall (8)
20 mm Clear Stone (2)
Floor Slab (6)
Slab on Grade(10)
Moisture Barrier (7)
20 mm Clear Stone (2)
Drainage Tile (1, 11, 12)
EXTERIOR FOOTING
Drainage Tile (1)
Approved Filter Membrane (3)
1.0 m (min.)
Approved Filter Membrane (3)
Approved Filter Fabric Blanket (13)
DRAINAGE RECOMMENDATIONSShored Basement wall with Underfloor Drainage System
(not to scale)
Project: 18-701-10 Drawing No. 10
Notes 1. Drainage tile to consist of 100 mm (4") diameter weeping tile or equivalent perforated pipe leading to a positive sump or outlet, spaced between columns. 2. 20 mm (3/4") clear stone - 150 mm (6") top and side of drain. If drain is not on footing, place100 mm (4 inches) of stone below drain . 3. Wrap the clear stone with an approved filter membrane (Terrafix 270R or equivalent). 4. Moisture barrier to be at least 200 mm (8") of compacted clear 20 mm (3/4") stone or equivalent free draining material. A vapour barrier may be required for specialty floors. 5. Slab on grade should not be structurally connected to the wall or footing. 6. Underfloor drain invert to be at least 300 mm (12") below underside of floor slab. Drainage tile placed in parallel rows 6 to 8 m (20 to 25') centers one way. Place drain on 100 mm (4") clear stone with 150 mm (6") of clear stone on top and sides. Enclose stone with filter fabric as noted in (3). 7. Do not connect the underfloor drains to perimeter drains. 8. Solid discharge pipe located at the middle of each bay between the solider piles, approximate spacing 2.5 m, outletting into a solid pipe leading to a sump. 9. Vertical drainage board mira-drain 6000 or eqivalent with filter cloth should be continous from bottom to 1.2 m below exterior finished grade. 10. The entire subgrade to be sealed with approved filter fabric (Terrafix 270R or equivalent) if non-cohesive (sandy) soils below ground water table encountered. 11. The basement walls must be water proofed using bentonite or equivalent water-proofing system.12. Review the geotechnical report for specific details. Final detail must be approved before system is considered acceptable.
EXTERIOR FOOTING
Floor Slab
Slab on Grade(5)
Moisture Barrier (4)
20 mm Clear Stone (2)
Drainage Tile (1, 6)
Approved Filter Fabric (3)Solid discharge pipe (8)
Water Proofing (11)
Caisson Wall
Vertical Drainage Board (9)
Sealant
Approved Filter Fabric Blanket (10)
Project: 18-701-10 Drawing 11
Guidelines for Underpinning in Soil and Excavation Support
Existing foundations located within Zone A normally require underpinning, especially for heavy structures. For some foundations in Zone A, it may be possible to eliminate underpinning and control foundation movement by tightly braced excavation walls, such as caisson walls. 2 1 TIGHTLY BRACED/TIED 1 EXCAVATION WALL A 1 B BASE OF EXCAVATION C 0.6 m
Zone A Foundations located within this zone normally require underpinning. Horizontal and vertical pressures on the excavation wall of non underpinned foundations must be considered Zone B Foundations located within this zone normally do not require underpinning. Horizontal and vertical pressures on the excavation wall of non underpinned foundations must be considered Zone C Underpinning to structures is normally founded in this zone. Lateral pressure from underpinning is not normally considered
(Reference: Figure 26.27 from Canadian Foundation Engineering Manual, 4th Edition)
Project: 18-701-10
Preliminary Geotechnical Investigation 40-44 Broadway Avenue
Toronto, Ontario 13
DS Consultants Ltd. November 19, 2018
Appendix A Trafalgar Environmental Consultant (TEC’s)
Borehole Logs of Monitoring Wells MW1, MW3, MW5 and MW7