PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

33
Geotechnical & Earthquake Engineering Consultants PRELIMINARY GEOTECHNICAL REPORT PROPOSED RESIDENTIAL DEVELOPMENT 607 Second Avenue North Seattle, Washington PROJECT NO. 17-297 October 2017 Prepared for: Enterprise Community Partners, Inc.

Transcript of PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Page 1: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Geotechnical & Earthquake

Engineering Consultants

PRELIMINARY GEOTECHNICAL REPORT

PROPOSED RESIDENTIAL DEVELOPMENT

607 Second Avenue North

Seattle, Washington

PROJECT NO. 17-297

October 2017

Prepared for:

Enterprise Community

Partners, Inc.

Page 2: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

________________________________________________

3213 Eastlake Avenue East, Suite B

Seattle, WA 98102

T. (206) 262-0370

F. (206) 262-0374

Geotechnical & Earthquake

Engineering Consultants

October 30, 2017

PanGEO Project No. 17-297 (REV2)

Mr. Anthony Bridgewater

Enterprise Community Partners, Inc.

2025 1st Avenue, Suite 1250

Seattle, Washington 98121

Subject: Preliminary Geotechnical Report

Proposed Residential Development

607 Second Avenue North, Seattle, Washington

Dear Mr. Bridgewater:

As requested, PanGEO, Inc. is pleased to present this preliminary geotechnical report to

assist the project team with the planning and design of the proposed development at 607

Second Avenue North, Seattle, Washington.

In preparing this report, we observed and logged the drilling of two test borings, reviewed

subsurface information from the site and vicinity, and conducted our engineering

analyses. In summary, the site may be developed generally as planned.

We encountered potentially liquefiable loose to medium dense sand below the site. In

order to mitigate the potential for liquefaction induced settlement, it is our opinion that

building support should be provided using a structural mat foundation or a spread footing

foundation system after a program of ground improvement.

We appreciate the opportunity to be of service. Should you have any questions, please do

not hesitate to call.

Sincerely,

Siew L. Tan, P.E.

Principal Geotechnical Engineer

Page 3: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

17-297 607 2nd Ave N REV2 Page 1 PanGEO, Inc.

TABLE OF CONTENTS

Section Page

1.0 GENERAL .................................................................................................................1 2.0 SITE AND PROJECT DESCRIPTION .....................................................................1 3.0 SUBSURFACE EXPLORATIONS ...........................................................................2

3.1 SITE GEOLOGY ................................................................................................2 3.2 SUBSURFACE EXPLORATION ...........................................................................3 3.3 SOIL CONDITIONS............................................................................................3 3.4 GROUNDWATER ..............................................................................................4

4.0 GEOTECHNICAL RECOMMENDATIONS ...........................................................4 4.1 GENERAL ........................................................................................................4 4.2 SEISMIC DESIGN PARAMETERS ........................................................................5 4.3 BUILDING FOUNDATIONS ................................................................................7

4.3.1 Mat Foundation ..............................................................................7

4.3.2 Conventional Footings on Improved Ground .................................8 4.3.3 Lateral Resistance ...........................................................................8

4.3.4 Perimeter Footing Drains ...............................................................9 4.3.5 Foundation Subgrade Preparation .................................................9

4.4 FLOOR SLABS ..................................................................................................9 4.5 RETAINING WALL DESIGN PARAMETERS ........................................................10

4.5.1 Surcharge ........................................................................................10 4.5.2 Lateral Resistance ...........................................................................10 4.5.3 Wall Drainage .................................................................................11

4.5.4 Wall Backfill....................................................................................11 4.6 PERMANENT CUT AND FILL SLOPES ................................................................11

5.0 EXCAVATIONS AND TEMPORARY SHORING ..................................................11 5.1 TEMPORARY EXCAVATIONS ............................................................................12 5.2 TEMPORARY SHORING ....................................................................................12

5.2.1 Temporary Soldier Pile Shoring Design Parameters .....................12 5.2.2 Wall Design Parameters .................................................................13

5.2.3 Lagging ...........................................................................................13 5.2.4 Baseline Survey and Monitoring .....................................................13

6.0 EARTHWORK CONSIDERATIONS .......................................................................14 6.1 STRUCTURAL FILL AND COMPACTION .............................................................14 6.2 MATERIAL REUSE ...........................................................................................15 6.3 WET WEATHER CONSTRUCTION .....................................................................15 6.4 EROSION CONSIDERATIONS .............................................................................15

7.0 ADDITIONAL SERVICES .......................................................................................16 8.0 CLOSURE .................................................................................................................16 9.0 REFERENCES ...........................................................................................................18

Page 4: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Preliminary Geotechnical Report

607 Second Avenue North, Seattle, Washington

October 30, 2017

17-297 607 2nd Ave N REV2 Page 2 PanGEO, Inc.

ATTACHMENTS:

Figure 1 Vicinity Map

Figure 2 Site and Exploration Location Plan

Figure 3 Geologic Map

Figure 4 Design Lateral Pressures, Soldier Pile Wall Cantilevered or with One

Tieback

Appendix A Boring Logs

Figure A-1 Terms and Symbols for Boring and Test Pit Logs

Figures A-2 and A-3 Logs of Test Borings PG-1 and PG-2

Page 5: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

17-297 607 2nd Ave N REV2 Page 1 PanGEO, Inc.

PRELIMINARY GEOTECHNICAL REPORT

PROPOSED RESIDENTIAL DEVELOPMENT

607 SECOND AVENUE NORTH

SEATTLE, WASHINGTON

1.0 GENERAL

As requested, PanGEO, Inc. is pleased to present this preliminary geotechnical report to assist

the project team with the design and construction of the proposed seven story residential

development planned for 607 Second Avenue North in Seattle, Washington. This study was

performed in general accordance with our mutually agreed scope of services outlined in our

proposal dated September 26, 2017. Our scope of services included reviewing readily available

geologic and geotechnical data, drilling two borings, conducting a site reconnaissance, and

evaluating the feasibility of developing the site as planned.

2.0 SITE AND PROJECT DESCRIPTION

The subject site is located at 607 Second Avenue North, in the northeast corner of the

intersection of Mercer Street and Second Avenue North in Seattle, Washington. The

approximate location of the site is shown on Figure 1, Vicinity Map and Plate 1, below.

Plate 1: Aerial view of site.

Page 6: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Preliminary Geotechnical Report

Proposed Residential Development: 607 Second Avenue North, Seattle, Washington

October 16, 2017

17-297 607 2nd Ave N REV2 Page 2 PanGEO, Inc.

The proposed development area comprises one rectangular lot (Tax Parcel No. 5457800296)

with an area of about 11,000 square feet. The site is bordered to the north by an asphalt paved

parking lot, to the west by Second Avenue North, to the east by a vacant lot, and to the south by

Mercer Street. The layout of the site is shown on Figure 2, Site and Exploration Plan.

The site is currently occupied by a small park and contains paved walking paths around

landscaping beds containing ornamental trees and shrubs. The topography is relatively flat, with

less than five feet of elevation change across the width of the property. Plate 1, above and Plate

2, below illustrate the general site conditions.

Plate 2: View from northeast to southwest showing the general site conditions.

We understand it is planned to develop the site with a seven-story residential building over one

level of below-grade parking. An alternate development proposal is also being considered which

will not include the below-grade parking level.

Page 7: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Geotechnical Report

Proposed Residential Development, 607 Second Avenue North, Seattle, Washington

October 30, 2017

17-297 607 2nd Ave N REV2 Page 2 PanGEO, Inc.

We anticipate the below-grade parking and two lower levels will be of concrete construction,

while the upper five levels of residential space will be of wood frame construction.

If the proposed development will include one level of basement, in order to achieve construction

subgrade elevations for the below grade parking, we anticipate an excavation extending to a

depth of 10 to 12 feet below grade will be needed. The base of the excavation will extend up to

the surrounding property limits as a zero-lot line excavation. Temporary shoring will be used to

support the excavation during construction.

The conclusions and recommendations in this report are based on our understanding of the

proposed development, which is in turn based on the project information provided. If the above

project description is incorrect, or the project information changes, we should be consulted to

review the recommendations contained in this study and make modifications, if needed. In any

case PanGEO should be retained to provide a review of the final design to confirm that our

geotechnical recommendations have been correctly interpreted and adequately implemented in

the construction documents.

3.0 SUBSURFACE EXPLORATIONS

3.1 SITE GEOLOGY

Based on our review of The Geologic Map of Seattle – A Progress Report (Troost, et. al. 2005),

the geologic units in the vicinity of the site consist of Vashon Ice Contact deposits (Geologic

Map Unit Qvi), Lawton Clay (Qvlc) and Vashon Till (Qvt). A portion of the geologic map for

that includes the subject site is included as Figure 3, Geologic Map. Ice Contact Deposits consist

of interlayered till and outwash deposits. The outwash consists of sand and gravel with varying

amounts of silt. These units may or may not have been glacially overridden. Where overridden,

the ice contact deposits are typically dense to very dense. Where they have not been overridden,

the ice contact deposits may range from loose to dense.

Vashon Till consists of an unsorted deposit (diamict) of clay, silt, sand and gravel that has been

glacially transported and deposited. Vashon Till has been glacially overridden and is typically

dense to very dense.

Lawton Clay consists of a lacustrine silt and clay deposited in a meltwater lake that formed in

front of the Vashon Glacier. This deposit has also been glacially overridden and is typically

hard.

Page 8: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Geotechnical Report

Proposed Residential Development, 607 Second Avenue North, Seattle, Washington

October 30, 2017

17-297 607 2nd Ave N REV2 Page 3 PanGEO, Inc.

3.2 SUBSURFACE EXPLORATION

Two borings (PG-1 and PG-2) were drilled on September 27, 2017. The borings were drilled

using an EC-95 track-mounted drill rig operated by Boretec, Inc. under subcontract to PanGEO

and were logged by an engineer with our firm. The borings were drilled to depths of 41½ and

46½ feet below existing grade. The approximate boring locations were located in the field by

measuring from property corners and site features and are shown on Figure 2, Site and

Exploration Plan.

Standard Penetration Tests (SPT) were performed at 2½- to 5-foot depth intervals using a

standard, 2-inch diameter split-spoon sampler. The sampler was advanced with a 140-pound

drop hammer falling a distance of 30 inches for each strike, in general accordance with ASTM

D-1586, Standard Test Method for Penetration Test and Split Barrel Sampling of Soils.

The soils were logged in general accordance with ASTM D-2487 Standard Practice for

Classification of Soils for Engineering Purposes and the system summarized on Figure A-1,

Terms and Symbols for Boring and Test Pit Logs.

3.3 SOIL CONDITIONS

For a detailed description of the subsurface conditions encountered at each exploration location,

please refer to our boring logs provided in Appendix A. The stratigraphic contacts indicated on

the boring logs represent the approximate depth to boundaries between soil units. Actual

transitions between soil units may be more gradual or occur at different elevations. The

descriptions of groundwater conditions and depths are likewise approximate. The following is a

generalized description of the soils encountered in the borings.

Topsoil: Both borings were located in landscaped areas and encountered a surface layer of

topsoil. The topsoil layer was 6 to 8 inches thick and consisted of silty sand with gravel and

organic material.

Fill: Below the topsoil, we encountered fill. The fill ranged from 8 feet thick at Boring PG-

1 to 9½ feet thick at Boring PG-2. The fill consisted of grey silty fine to medium sand with

gravel and ranged from loose to medium dense. The fill was characterized by its

homogenous to disturbed soil structure, angular gravel, and the presence of organics

including topsoil and fine roots.

Vashon Ice Contact Deposits: Underlying the fill, we encountered an interlayered deposit

of silt, silty clay, sand, and silty sand with varying amounts of gravel. The silt and clay

Page 9: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Geotechnical Report

Proposed Residential Development, 607 Second Avenue North, Seattle, Washington

October 30, 2017

17-297 607 2nd Ave N REV2 Page 4 PanGEO, Inc.

deposits were typically medium stiff while the coarse-grained sand and silty sand deposits

ranged from loose to dense.

We classified these interlayered soils as being consistent with ice contact deposits. The

composition and density of this deposit may vary significantly over a small distance. The

ice contact deposits extended to a depth of about 38 feet below grade in both of our borings.

Pre-Frasier Glaciation Fine-Grained Deposits: Below the ice contact deposits, we

encountered hard grey silt. We identified this soil as consistent with Pre-Frasier Glaciation

Fine-Grained Deposits. This deposit first encountered at about 38 feet deep in both PG-1

and PG-2, and extended to the maximum exploration depth of 46½ feet below grade. A

review of other nearby test borings indicate that this deposit may be significantly shallower

in the southeast and northwest corners of the site.

Our descriptions of subsurface conditions are based on the conditions encountered at the time of

our exploration. Soil conditions between our exploration locations may vary from those

encountered. The nature and extent of variations between our exploratory locations may not

become evident until construction. If variations do appear, PanGEO should be requested to

reevaluate the recommendations in this report and to modify or verify them in writing prior to

proceeding with earthwork and construction.

3.4 GROUNDWATER

Wet to water bearing soils were encountered in both of our borings at about 14 feet below grade

while drilling. Based on the planned one level of below grade parking with a cut of 10 to 12 feet

deep, we do not anticipate groundwater will result in significant construction related issues.

However, there will be fluctuations in seepage depending on the season, amount of rainfall,

surface water runoff, and other factors. Generally, the water level is higher and seepage rates are

greater in the wetter, winter months (typically October through May).

4.0 GEOTECHNICAL RECOMMENDATIONS

4.1 GENERAL

The proposed project will occupy the southwest quadrant of the block defined by Mercer Street

to the south, Second Avenue North to the west, Third Avenue North to the east, and Roy Street

to the north. Another development is planned for the other three quadrants of the block and is

expected to be constructed before the subject site.

Page 10: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Geotechnical Report

Proposed Residential Development, 607 Second Avenue North, Seattle, Washington

October 30, 2017

17-297 607 2nd Ave N REV2 Page 5 PanGEO, Inc.

The adjacent project will include a shored excavation with temporary tiebacks that will extend

below the subject site. The temporary tiebacks will be abandoned in place after the construction

of the adjacent project is completed. If the tiebacks are encountered during excavation at the

subject site, they can be removed (if relatively shallow). Tiebacks that are abandoned below the

elevation of the building at the subject site should not adversely impact the foundation bearing

soils.

The foundation for the subject site will impart a surcharge load on the completed building walls

for the adjacent building. In order to mitigate for the surcharge loads, this project may need to

extend the foundation loads deeper such that they will not impart a surcharge on the adjacent

building. This could be accomplished by stepping the building foundation down or transferring

the building loads down through the use of a deep foundation system. The deep foundation

options will need to be coordinated with tieback locations so that the deep foundation installation

will not encounter the tiebacks. Recommendations for deep foundations, if needed, can be

coordinated during final design.

We recommend coordinating the design and construction of this project with the adjacent project

in order to address potential conflicts from temporary shoring elements and the impacts from

foundation surcharge loads that may affect the constructability of this project.

4.2 SEISMIC DESIGN PARAMETERS

The 2015 International Building Code (IBC) seismic design section provides a basis for seismic

design of structures. Because the some of the sand layers underlying the site are prone to soil

liquefaction, Site Class F should be assumed for the seismic design of the project. With Site

Class F, a site-specific ground response analysis will be required unless the natural period of the

building is less than 0.5 second.

Assuming a building period of less than 0.5 seconds, Table 1 below provides seismic design

parameters for the site that are in conformance with the 2015 IBC, which specifies a design

earthquake having a 2% probability of occurrence in 50 years (return interval of 2,475 years),

and the 2008 USGS seismic hazard maps.

Page 11: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Geotechnical Report

Proposed Residential Development, 607 Second Avenue North, Seattle, Washington

October 30, 2017

17-297 607 2nd Ave N REV2 Page 6 PanGEO, Inc.

Table 1 – Seismic Design Parameters

The spectral response accelerations were obtained from the USGS Earthquake Hazards Program

Interpolated Probabilistic Ground Motion website (2008 data) for the project latitude and

longitude.

For the seismic design of the building, if the fundamental period of the proposed building

exceeds 0.5 seconds (as determined by the structural engineer) and the risk of soil liquefaction is

present, a site-specific ground response analysis will likely be required. PanGEO will be

available to perform the analysis if needed.

Liquefaction Potential: Liquefaction occurs when saturated sands are subjected to cyclic loading

which causes the pore water pressure to increase in the sand thereby reducing the inter-granular

stresses. As the inter-granular stresses are reduced, the shearing resistance of the sand decreases.

If pore pressures develop to the point where the effective stresses acting between the grains

become zero, the soil particles will be in suspension and behave like a viscous fluid. Typically

loose, saturated, clean granular soils, that have a low enough permeability to prevent drainage

during cyclic loading, have the greatest potential for liquefaction, while more dense soil deposits

with higher silt or clay contents have a lesser potential. Potential effects of soil liquefaction

include temporary loss/reduction of foundation capacity and settlement.

Based on the conditions encountered at our boring locations, there is the potential for soil

liquefaction below the site, specifically in the loose to medium dense sand encountered between

20- to 30-feet below grade in Boring PG-1 and between 15- and 20-feet and 30- to 35-feet below

grade in Boring PG-2. We estimate the potential liquefaction induced settlement may be as

much as 5 to 6 inches.

With the plan for one level of below grade parking, the building foundation will be located at

about 10 to 12 feet below grade. As such, the building foundation will be above the potentially

liquefiable soils. In order to mitigate the potential for liquefaction induced settlement damage to

Site

Class

Spectral

Acceleration at

0.2 sec. [g]

SS

Spectral

Acceleration at

1.0 sec. [g]

S1

Site Coefficients Design Spectral

Response Parameters

Control Periods

[sec.]

Fa Fv SDS SD1 TO TS

D 1.343 0.521 1.000 1.500 0.895 0.521 0.116 0.582

Page 12: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Geotechnical Report

Proposed Residential Development, 607 Second Avenue North, Seattle, Washington

October 30, 2017

17-297 607 2nd Ave N REV2 Page 7 PanGEO, Inc.

the structure we recommend a program of ground improvement with aggregate piers (eg,

Geopiers, etc) or supporting the building on a relatively stiff structural mat foundation.

4.3 BUILDING FOUNDATIONS

Based on our understanding of the proposed development, the project will include one level of

below grade parking with a foundation subgrade elevation of about 10 to 12 feet below grade.

An alternate development plan is also being considered, which will not include the below grade

parking. Based on the conditions encountered in our borings, the ice contact deposits below the

site contain loose to medium dense water bearing sand lenses that may be susceptible to

liquefaction induced settlement.

In order to mitigate the impacts from liquefaction, it is our opinion one of the following options

should be used for supporting the proposed building:

• Mat Foundation: With this option, the building foundation would be supported on a

structural may bearing on the medium dense to dense ice contact deposits underlying the

below the fill..

• Conventional Foundation on Improved Ground: This option would consist of mitigating

the liquefaction potential using ground improvement, such as aggregate piers. The

building can then be supported on a conventional foundation bearing on the improved

soils.

Due to the presence of 8 to 9½ feet of loose fill underlying the site, the mat foundation option

would not be applicable for the development option that will not include a below grade parking

level. If the option without below grade parking is pursued, it should be planned to support the

building on conventional foundations after ground improvement.

4.3.1 Mat Foundation

With this option, building support can be provided using a structural mat foundation bearing on

the ice-contact deposits that should be encountered 10 to 12 feet below grade. The ice-contact

deposits may consist of medium dense to dense sand, and medium stiff to stiff silt and clay. The

existing fill, which was about 8 to 9 feet thick at our test boring locations, are not suitable for

supporting the mat foundation.

The structural mat foundation should be designed so that is sufficiently stiff to spread the

concentrated column loads out over a wide area. The mat foundation can be evaluated using a

Page 13: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Geotechnical Report

Proposed Residential Development, 607 Second Avenue North, Seattle, Washington

October 30, 2017

17-297 607 2nd Ave N REV2 Page 8 PanGEO, Inc.

modulus of subgrade reaction of 150 pounds per cubic inch (pci). Local bearing pressures

below concentrated loads can be evaluated using an allowable soil bearing pressure of 3,000 psf.

We estimate total settlement of the mat foundation due to dead plus live loads will be about 1-

inch, with differential settlement of ½-inch.

We estimate total liquefaction induced settlements could be on the order of 5 to 6 inches.

However, because the site soils in our test borings are quite uniform, it is our opinion the

settlement from the potential soil liquefaction will likely be generally uniform across the site,

and the potential differential settlements will likely be less than half of the estimated total

settlement. Some architectural or structural damage could occur as a result of the settlement,

however, from a life safety standpoint, the structure would not collapse and entrance or egress

from the building should not be significantly impeded.

4.3.2 Conventional Footings on Improved Ground

A commonly-used ground improvement method in the local area is aggregate piers, such as

Geopiers or stone columns. This type of ground improvement would consist of compacting

columns of well-graded crushed rock to increase the bearing capacity of the loose, potentially

liquefiable soils and reduce the potential for settlement. After the aggregate piers are installed,

spread footings and slab-on-grade floors can be supported directly on the improved ground.

Because aggregate piers are a proprietary system, the installation contractor is responsible for the

design of the aggregate piers, based on the performance criteria provided by the structural

engineer. Based on the performance criteria provided, the aggregate pier contractor will

determine the allowable bearing pressures, improved soil characteristics and anticipated

settlements.

4.3.3 Lateral Resistance

Lateral loads on the structure may be resisted by passive earth pressure developed against the

embedded portion of the foundation and by frictional resistance between the bottom of the

foundation and the supporting subgrade soils. For footings bearing on the medium dense to

dense sand and silty sand, a frictional coefficient of 0.35 may be used to evaluate sliding

resistance developed between the concrete and the subgrade soil. Passive soil resistance may be

calculated using an equivalent fluid weight of 300 pcf assuming foundations are backfilled with

structural fill. The above values include a factor of safety of 1.5. Unless covered by pavements

or slabs, the passive resistance in the upper 12 inches of soil should be neglected.

Page 14: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Geotechnical Report

Proposed Residential Development, 607 Second Avenue North, Seattle, Washington

October 30, 2017

17-297 607 2nd Ave N REV2 Page 9 PanGEO, Inc.

4.3.4 Perimeter Footing Drains

Footing drains should be installed around the perimeter of the at-grade portion of the building, at

or just below the invert of the footings. Under no circumstances should roof downspout drain

lines be connected to the footing drain systems. Roof downspouts must be separately tightlined

to appropriate discharge locations. Cleanouts should be installed at strategic locations to allow

for periodic maintenance of the footing drain and downspout tightline systems.

4.3.5 Foundation Subgrade Preparation

The foundation subgrade soils should be in a firm and unyielding condition prior to setting forms

and placing reinforcing steel. If loose soils are encountered at the foundation subgrade elevation,

the loose soils should be removed from the footing excavations and replaced with structural fill.

4.4 FLOOR SLABS

Floor slabs with the ground improvement option may be constructed using conventional concrete

slab-on-grade floor construction. The floor slabs should be supported on competent native soil

or on structural fill. Any overexcavation, if needed, should be backfilled with structural fill.

If heated space or spaces that are sensitive to moisture intrusion are planned for the parking

garage level, the concrete floors should be underlain by a capillary break meeting the gradational

requirements provided in Table 2, below.

The capillary break material should meet the gradational requirements provided in Table 2,

below.

Table 2 – Capillary Break Gradation

Sieve Size Percent Passing

¾-inch 100

No. 4 0 – 10

No. 100 0 – 5

No. 200 0 – 3

The capillary break should be placed on subgrade soils that have been compacted to a dense and

unyielding condition.

Page 15: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Geotechnical Report

Proposed Residential Development, 607 Second Avenue North, Seattle, Washington

October 30, 2017

17-297 607 2nd Ave N REV2 Page 10 PanGEO, Inc.

A 10-mil polyethylene vapor barrier should also be placed directly below the slab. Construction

joints should be incorporated into the floor slab to control cracking.

4.5 RETAINING WALL DESIGN PARAMETERS

Cast-in-place concrete retaining and basement walls should be designed to resist the lateral earth

pressures exerted by the soils behind the wall. Proper drainage provisions should also be

provided to intercept and remove groundwater that may be present behind the walls.

Cantilever walls should be designed for an equivalent fluid pressure of 35 pcf for a level backfill

condition and assuming the walls are free to rotate. If the walls are restrained at the top from

free movement, such as basement walls with a floor diaphragm, an equivalent fluid pressure of

45 pcf should be used for a level backfill condition behind the walls. Permanent walls should be

designed for an additional uniform lateral pressure of 7H psf for seismic loading, where H

corresponds to the height of the buried depth of the wall.

The recommended lateral pressures assume the backfill behind the walls consists of free draining

and properly compacted fill with adequate drainage provisions.

4.5.1 Surcharge

Surcharge loads, where present, should also be included in the design of retaining walls. We

recommend that a lateral load coefficient of 0.3 be used to compute the lateral pressure on the

wall face resulting from surcharge loads located within a horizontal distance of one-half the wall

height.

4.5.2 Lateral Resistance

Lateral forces from seismic loading and unbalanced lateral earth pressures may be resisted by a

combination of passive earth pressures acting against the embedded portions of the foundations

and by friction acting on the base of the wall foundation. Passive resistance values may be

determined using an equivalent fluid weight of 300 pcf. This value includes a factor of safety of

1.5, assuming the footing is backfilled with structural fill. A friction coefficient of 0.30 may be

used to determine the frictional resistance at the base of the footings. The coefficient includes a

factor of safety of 1.5.

Page 16: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Geotechnical Report

Proposed Residential Development, 607 Second Avenue North, Seattle, Washington

October 30, 2017

17-297 607 2nd Ave N REV2 Page 11 PanGEO, Inc.

4.5.3 Wall Drainage

Provisions for wall drainage should consist of a 4-inch diameter perforated drainpipe placed

behind and at the base of the wall footings, embedded in 12 to 18 inches of clean crushed rock or

pea gravel wrapped with a layer of filter fabric. A minimum 18-inch wide zone of free draining

granular soils (i.e. pea gravel or washed rock) is recommended to be placed adjacent to the wall

for the full height of the wall. Alternatively, a composite drainage material, such as Miradrain

6000, may be used in lieu of the clean crushed rock or pea gravel. The drainpipe at the base of

the wall should be graded to direct water to a suitable outlet.

4.5.4 Wall Backfill

Wall backfill should consist of free draining granular material. The site soils are relatively silty

and would not meet the requirements for wall backfill. We recommend importing a free draining

granular material, such as Gravel Borrow as defined in Section 9-03.14(1) of the WSDOT

Standard Specifications for Road, Bridge, and Municipal Construction (WSDOT, 2016). In

areas where space is limited between the wall and the face of excavation, pea gravel may be used

as backfill without compaction.

Wall backfill should be moisture conditioned to near optimum moisture levels, placed in loose,

horizontal lifts less than 8 inches in thickness, and systematically compacted to a dense and

relatively unyielding condition and to at least 95 percent of the maximum dry density, as

determined using test method ASTM D-1557 (Modified Proctor). Within 5 feet of the wall, the

backfill should be compacted with hand-operated equipment to at least 90 percent of the

maximum dry density.

4.6 PERMANENT CUT AND FILL SLOPES

Permanent cut and fill slopes should be inclined no steeper than 2H:1V. Permanently exposed

slopes should be seeded with an appropriate species of vegetation to reduce erosion and improve

stability of the surficial layer of soil.

5.0 EXCAVATIONS AND TEMPORARY SHORING

In order to achieve construction subgrade elevations for the below grade parking level, we

anticipate an excavation extending to a depth of 10 to 12 feet below grade is planned. The

planned excavation will extend up the site boundaries as a zero lot line excavation. The

Page 17: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Geotechnical Report

Proposed Residential Development, 607 Second Avenue North, Seattle, Washington

October 30, 2017

17-297 607 2nd Ave N REV2 Page 12 PanGEO, Inc.

excavation will be accomplished using a combination of open cuts with temporary slopes and

vertical cuts supported with temporary shoring.

5.1 TEMPORARY EXCAVATIONS

Temporary excavations should be constructed in accordance with Part N of WAC (Washington

Administrative Code) 296-155. The contractor is responsible for maintaining safe excavation

slopes and/or shoring.

Based on the soil conditions encountered in the test borings, it is our opinion that temporary

excavations may be cut at a maximum 1H:1V inclination. If sufficient space is not available,

temporary excavation shoring will be needed.

Temporary excavations should be evaluated in the field during construction based on actual

observed soil conditions. If seepage is encountered, excavation slope inclinations may need to

be reduced. During wet weather, the cut slopes may need to be flattened to reduce potential

erosion or should be covered with plastic sheeting.

5.2 TEMPORARY SHORING

Where there is not sufficient room to make conventional open cuts temporary shoring will be

needed. In our opinion, temporary shoring consisting of a soldier pile wall with timber lagging is

likely the most cost-effective shoring option.

The shoring system should be designed to provide adequate protection for the workers, adjacent

structures, utilities, and other facilities. Excavations should be performed in accordance with the

current requirements of WISHA. Construction should proceed as rapidly as feasible, to limit the

time temporary excavations are open.

5.2.1 Temporary Soldier Pile Shoring Design Parameters

A soldier pile wall consists of vertical steel beams, typically spaced from 6 to 8 feet apart along

the proposed excavation wall, spanned by timber lagging. Prior to the start of excavation, the

steel beams are installed into holes drilled to a design depth and then backfilled with lean mix or

structural concrete. As the excavation proceeds downward and the steel piles are subsequently

exposed, timber lagging is installed between the flanges of the piles to further stabilize the walls

of the excavation.

Page 18: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Geotechnical Report

Proposed Residential Development, 607 Second Avenue North, Seattle, Washington

October 30, 2017

17-297 607 2nd Ave N REV2 Page 13 PanGEO, Inc.

5.2.2 Wall Design Parameters

The earth pressures depicted on Figure 4, Design Lateral Pressures, Soldier Pile Wall,

Cantilevered be used for design of soldier pile walls for this project. Our shoring design

parameters assume the excavation is fully dewatered and do not include hydrostatic pressures

from groundwater.

5.2.3 Lagging

Lagging design recommendations for general conditions are presented on Figure 4. Lagging

located within 10 feet of the top of the shoring which may be subjected to surcharge loads from

construction equipment or material storage should be designed for an additional uniform lateral

surcharge pressure of 200 psf. This pressure approximately corresponds to a vertical uniform

surcharge load of 500 psf at the top of the wall for general construction surcharge. Point loads

located close to the top of the wall, such as outriggers of heavy cranes, may apply additional

loads to the lagging. These loads may need to be individually analyzed. However, lagging

designed for a uniform load of 600 psf in the top 10 feet of the wall should be able to

accommodate most crane outrigger loads.

We recommend voids behind the lagging be backfilled with CDF.

The lagging will be faced by the permanent basement walls of the buildings. In order to

maintain drainage, a continuous layer of a geocomposite drainage, such as Miradrain 6000,

should be placed between the lagging and basement walls. The geocomposite drainage should

be connected to a tightline collection pipe on the interior of the building.

5.2.4 Baseline Survey and Monitoring

Ground movements may be experienced as a result of excavation activities. As such, ground

surface elevations of the adjacent properties and city streets should be documented prior to

commencing earthwork to provide baseline data. As a minimum, optical survey points should be

established at the following locations:

• The top of every other soldier pile. These monitoring points should be monitored

twice a week. The monitoring frequency may be reduced based on the monitoring

results.

• Adjacent structures located within 25 feet of the shoring walls.

Page 19: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Geotechnical Report

Proposed Residential Development, 607 Second Avenue North, Seattle, Washington

October 30, 2017

17-297 607 2nd Ave N REV2 Page 14 PanGEO, Inc.

• The curbs and the centerlines of adjacent streets should be monitored by establishing a

set of baseline point spaced no more than 20 feet apart. These monitoring points

should not need to be regularly surveyed after the baseline is established unless the

soldier pile wall monitoring indicates deflections exceeding one inch.

The monitoring program should include monitoring for changes in both the horizontal (x and y

directions) and vertical deformations. The monitoring should be performed by the contractor or

the project surveyor, and the results should be promptly submitted to PanGEO for review. The

results of the monitoring will allow the design team to confirm design parameters, and for the

contractor to make adjustments if necessary.

We also recommend the existing conditions along the public right-of-way and the adjacent

private properties be photo-documented prior to commencing earthwork at the site.

6.0 EARTHWORK CONSIDERATIONS

6.1 STRUCTURAL FILL AND COMPACTION

Structural fill, if needed, should consist of City of Seattle Type 17, crushed surfacing base course

as specified in WSDOT Section 9-03.9(3) (WSDOT 2014), or an approved similar material.

Structural fill should be moisture conditioned to within about 3 percent of optimum moisture

content, placed in loose, horizontal lifts less than 8 inches in thickness, and compacted to at least

95 percent maximum density, determined using ASTM D-1557 (Modified Proctor). The

procedure to achieve proper density of a compacted fill depends on the size and type of

compacting equipment, the number of passes, thickness of the lifts being compacted, and certain

soil properties. If the excavation to be backfilled is constricted and limits the use of heavy

equipment, smaller equipment can be used, but the lift thickness will need to be reduced to

achieve the required relative compaction.

Generally, loosely compacted soils are a result of poor construction technique or improper

moisture content. Soils with high fines contents are particularly susceptible to becoming too wet

and coarse-grained materials easily become too dry, for proper compaction. Silty or clayey soils

with a moisture content too high for adequate compaction should be dried as necessary, or

moisture conditioned by mixing with drier materials, or other methods.

Page 20: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Geotechnical Report

Proposed Residential Development, 607 Second Avenue North, Seattle, Washington

October 30, 2017

17-297 607 2nd Ave N REV2 Page 15 PanGEO, Inc.

6.2 MATERIAL REUSE

The native soils underlying the site are moisture sensitive, and will become disturbed and soft

when exposed to inclement weather conditions. We do not recommend reusing the native soils

as structural fill. If it is planned to use the native soil in non-structural areas, the excavated soil

should be stockpiled and protected with plastic sheeting to prevent it from becoming saturated by

precipitation or runoff.

6.3 WET WEATHER CONSTRUCTION

General recommendations relative to earthwork performed in wet weather or in wet conditions

are presented below. The following procedures are best management practices recommended for

use in wet weather construction:

• Earthwork should be performed in small areas to minimize subgrade exposure to wet

weather. Excavation or the removal of unsuitable soil should be followed promptly

by the placement and compaction of clean structural fill. The size and type of

construction equipment used may have to be limited to prevent soil disturbance.

• During wet weather, the allowable fines content of the structural fill should be

reduced to no more than 5 percent by weight based on the portion passing the 0.75-

inch sieve. The fines should be non-plastic.

• The ground surface within the construction area should be graded to promote run-off

of surface water and to prevent the ponding of water.

• Geotextile silt fences should be installed at strategic locations around the site to

control erosion and the movement of soil.

• Excavation slopes and soils stockpiled on site should be covered with plastic

sheeting.

6.4 EROSION CONSIDERATIONS

Surface runoff can be controlled during construction by careful grading practices. Typically, this

includes the construction of shallow, upgrade perimeter ditches or low earthen berms in

conjunction with silt fences to collect runoff and prevent water from entering excavations or to

prevent runoff from the construction area leaving the immediate work site. Temporary erosion

control may require the use of hay bales on the downhill side of the project to prevent water from

leaving the site and potential storm water detention to trap sand and silt before the water is

Page 21: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Geotechnical Report

Proposed Residential Development, 607 Second Avenue North, Seattle, Washington

October 30, 2017

17-297 607 2nd Ave N REV2 Page 16 PanGEO, Inc.

discharged to a suitable outlet. All collected water should be directed under control to a positive

and permanent discharge system.

Permanent control of surface water should be incorporated in the final grading design. Adequate

surface gradients and drainage systems should be incorporated into the design such that surface

runoff is collected and directed away from the structure to a suitable outlet. Potential issues

associated with erosion may also be reduced by establishing vegetation within disturbed areas

immediately following grading operations.

7.0 ADDITIONAL SERVICES

To confirm that our recommendations are properly incorporated into the design and construction

of the proposed development, PanGEO should be retained to conduct a review of the final

project plans and specifications, and to monitor the construction of geotechnical elements. The

City of Seattle, as part of the permitting process, will also require geotechnical construction

inspection services. PanGEO can provide you a cost estimate for construction monitoring

services at a later date.

8.0 CLOSURE

We have prepared this report for Enterprise Community Partners, Inc. and the project design

team. Recommendations contained in this report are based on a site reconnaissance, a subsurface

exploration program, review of pertinent subsurface information, and our understanding of the

project. The study was performed using a mutually agreed-upon scope of services.

Variations in soil conditions may exist between the locations of the explorations and the actual

conditions underlying the site. The nature and extent of soil variations may not be evident until

construction occurs. If any soil conditions are encountered at the site that are different from

those described in this report, we should be notified immediately to review the applicability of

our recommendations. Additionally, we should also be notified to review the applicability of our

recommendations if there are any changes in the project scope.

The scope of our work does not include services related to construction safety precautions. Our

recommendations are not intended to direct the contractors’ methods, techniques, sequences or

procedures, except as specifically described in our report for consideration in design.

Additionally, the scope of our services specifically excludes the assessment of environmental

characteristics, particularly those involving hazardous substances. We are not mold consultants

Page 22: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Geotechnical Report

Proposed Residential Development, 607 Second Avenue North, Seattle, Washington

October 30, 2017

17-297 607 2nd Ave N REV2 Page 17 PanGEO, Inc.

nor are our recommendations to be interpreted as being preventative of mold development. A

mold specialist should be consulted for all mold-related issues.

This report has been prepared for planning and design purposes for specific application to the

proposed project in accordance with the generally accepted standards of local practice at the time

this report was written. No warranty, express or implied, is made.

This report may be used only by the client and for the purposes stated, within a reasonable time

from its issuance. Land use, site conditions (both off and on-site), or other factors including

advances in our understanding of applied science, may change over time and could materially

affect our findings. Therefore, this report should not be relied upon after 24 months from its

issuance. PanGEO should be notified if the project is delayed by more than 24 months from the

date of this report so that we may review the applicability of our conclusions considering the

time lapse.

It is the client’s responsibility to see that all parties to this project, including the designer,

contractor, subcontractors, etc., are made aware of this report in its entirety. The use of

information contained in this report for bidding purposes should be done at the contractor’s

option and risk. Any party other than the client who wishes to use this report shall notify

PanGEO of such intended use and for permission to copy this report. Based on the intended use

of the report, PanGEO may require that additional work be performed and that an updated report

be reissued. Noncompliance with any of these requirements will release PanGEO from any

liability resulting from the use this report.

Sincerely,

PanGEO, Inc.

Scott D. Dinkelman, LEG, LHG Siew L Tan, P.E.

Senior Engineering Geologist Principal Geotechnical Engineer

Page 23: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Geotechnical Report

Proposed Residential Development, 607 Second Avenue North, Seattle, Washington

October 30, 2017

17-297 607 2nd Ave N REV2 Page 18 PanGEO, Inc.

9.0 REFERENCES

City of Seattle, 2011, Standard Specifications for Road, Bridges, and Municipal Construction.

International Code Council, 2015, International Building Code (IBC), 2012.

Post Tensioning Institute (PTI), 2004, Recommendations for Pre-Stressed Rock and Soil

Anchors.

Troost, K.G., Booth, D. B., Wisher, A. P., Shimmel, S. A., 2005, The Geologic Map of Seattle-A

Progress Report, Seattle, Washington – U. S. Geological Survey Open File Report 2005-

1252, scale 1:24,000.

United States Geological Survey, Earthquake Hazards Program, Interpolated Probabalisitic

Ground Motion for the Conterminous 48 States by Latitude and Longitude, 2008 Data,

accessed via:

http://earthquake.usgs.gov/designmaps/us/application.php

WSDOT, 2016, Standard Specifications for Road, Bridge and Municipal Construction, M 41-

10.

Page 24: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

-122.365 -122.360 -122.355 -122.350 -122.345 -122.340

47.630

47.625

47.620

47.615

47.610

-122.365 -122.360 -122.355 -122.350 -122.345 -122.340

47.630

47.625

47.620

47.615

47.610

I N C O R P O R A T E D

17-297

1

VICINITY MAP

PROJECT

LOCATION

Proposed Residential Development

607 2nd Avenue N Seattle, Washington

1000'500' 0 500'

Approximate Scale: 1" = 1000'

ELLIOTT

BAY

Source: Open Street Map

AutoCAD SHX Text
5
AutoCAD SHX Text
5
AutoCAD SHX Text
5
AutoCAD SHX Text
520
AutoCAD SHX Text
WY S
AutoCAD SHX Text
WY SW
AutoCAD SHX Text
SW
AutoCAD SHX Text
AV
AutoCAD SHX Text
35
AutoCAD SHX Text
NE 145 ST
AutoCAD SHX Text
5TH AV NE
AutoCAD SHX Text
N 45 ST
AutoCAD SHX Text
N
AutoCAD SHX Text
WY
AutoCAD SHX Text
STONE
AutoCAD SHX Text
MERCER ST
AutoCAD SHX Text
VIADUCT
AutoCAD SHX Text
ALASKAN WAY
AutoCAD SHX Text
S DEARBORN ST
AutoCAD SHX Text
E MARGINAL
AutoCAD SHX Text
S MICHIGAN
AutoCAD SHX Text
SW
AutoCAD SHX Text
WAY
AutoCAD SHX Text
AVALON
AutoCAD SHX Text
MYERS WY S
AutoCAD SHX Text
LAKE
AutoCAD SHX Text
GREEN
AutoCAD SHX Text
UNION
AutoCAD SHX Text
LAKE
AutoCAD SHX Text
WASHINGTON
AutoCAD SHX Text
LAKE
AutoCAD SHX Text
ELLIOTT BAY
AutoCAD SHX Text
S CLOVERDALE ST
AutoCAD SHX Text
S OTHELLO ST
AutoCAD SHX Text
S ORCAS ST
AutoCAD SHX Text
S LUCILE ST
AutoCAD SHX Text
SW HOLDEN ST
AutoCAD SHX Text
SW THISTLE ST
AutoCAD SHX Text
SW BARTON ST
AutoCAD SHX Text
SW ROXBURY ST
AutoCAD SHX Text
AV S
AutoCAD SHX Text
RENTON
AutoCAD SHX Text
JR WY S
AutoCAD SHX Text
M L KING
AutoCAD SHX Text
W MARGINAL
AutoCAD SHX Text
SW
AutoCAD SHX Text
DR
AutoCAD SHX Text
BEACH
AutoCAD SHX Text
16 AV SW
AutoCAD SHX Text
9 AV SW
AutoCAD SHX Text
AIRPORT
AutoCAD SHX Text
4 AV S
AutoCAD SHX Text
DELRIDGE WY SW
AutoCAD SHX Text
35 AV SW
AutoCAD SHX Text
WY SW
AutoCAD SHX Text
FAUNTLEROY
AutoCAD SHX Text
CALIFORNIA AV SW
AutoCAD SHX Text
1 AV S
AutoCAD SHX Text
6 AV S
AutoCAD SHX Text
15 AV S
AutoCAD SHX Text
LAKE
AutoCAD SHX Text
WASHINGTON
AutoCAD SHX Text
BLVD S
AutoCAD SHX Text
BROADWAY
AutoCAD SHX Text
23 AV E
AutoCAD SHX Text
15 AV E
AutoCAD SHX Text
10 AV E
AutoCAD SHX Text
AV E
AutoCAD SHX Text
EASTLAKE
AutoCAD SHX Text
AV N
AutoCAD SHX Text
WESTLAKE
AutoCAD SHX Text
QUEEN ANNE AV N
AutoCAD SHX Text
10 AV W
AutoCAD SHX Text
15 AV W
AutoCAD SHX Text
W
AutoCAD SHX Text
28 AV
AutoCAD SHX Text
34 AV W
AutoCAD SHX Text
ALKI AV SW
AutoCAD SHX Text
BEACON AV S
AutoCAD SHX Text
RAINIER AV S
AutoCAD SHX Text
E MADISON ST
AutoCAD SHX Text
ELLIOTT AV
AutoCAD SHX Text
ADMIRAL WY
AutoCAD SHX Text
SW GENESEE ST
AutoCAD SHX Text
S GENESEE ST
AutoCAD SHX Text
S SPOKANE ST
AutoCAD SHX Text
S MCCLELLAN ST
AutoCAD SHX Text
E YESLER WY
AutoCAD SHX Text
E CHERRY ST
AutoCAD SHX Text
E UNION ST
AutoCAD SHX Text
DENNY WY
AutoCAD SHX Text
MAGNOLIA BR
AutoCAD SHX Text
W MCGRAW ST
AutoCAD SHX Text
W DRAVUS ST
AutoCAD SHX Text
W EMERSON ST
AutoCAD SHX Text
W NICKERSON ST
AutoCAD SHX Text
NW MARKET ST
AutoCAD SHX Text
NW 65 ST
AutoCAD SHX Text
N 40
AutoCAD SHX Text
SAND
AutoCAD SHX Text
POINT WY
AutoCAD SHX Text
AURORA AV N
AutoCAD SHX Text
N 50 ST
AutoCAD SHX Text
NE 45 ST
AutoCAD SHX Text
NE 55 ST
AutoCAD SHX Text
NE 65 ST
AutoCAD SHX Text
NW 80 ST
AutoCAD SHX Text
NW 85 ST
AutoCAD SHX Text
N 105 ST
AutoCAD SHX Text
RD NW
AutoCAD SHX Text
HOLMAN
AutoCAD SHX Text
NE 75 ST
AutoCAD SHX Text
NE 95 ST
AutoCAD SHX Text
NE 125 ST
AutoCAD SHX Text
NE NORTHGATE WY
AutoCAD SHX Text
N 130 ST
AutoCAD SHX Text
WY NE
AutoCAD SHX Text
LAKE CITY
AutoCAD SHX Text
WY NW
AutoCAD SHX Text
LEARY
AutoCAD SHX Text
NE
AutoCAD SHX Text
15 AV NE
AutoCAD SHX Text
ROOSEVELT WY NE
AutoCAD SHX Text
AURORA AV N
AutoCAD SHX Text
GREENWOOD AV N
AutoCAD SHX Text
3 AV NW
AutoCAD SHX Text
8 AV NW
AutoCAD SHX Text
15 AV NW
AutoCAD SHX Text
24 AV NW
AutoCAD SHX Text
32 AV NW
AutoCAD SHX Text
90
AutoCAD SHX Text
WASHINGTON
AutoCAD SHX Text
LAKE
AutoCAD SHX Text
ST
AutoCAD SHX Text
WY S
AutoCAD SHX Text
ST
AutoCAD SHX Text
p
AutoCAD SHX Text
p
AutoCAD SHX Text
p
AutoCAD SHX Text
p
AutoCAD SHX Text
BLUE
AutoCAD SHX Text
RIDGE
AutoCAD SHX Text
NORTHGATE
AutoCAD SHX Text
HILL
AutoCAD SHX Text
GREENWOOD
AutoCAD SHX Text
LAKE CITY
AutoCAD SHX Text
VICTORY
AutoCAD SHX Text
HEIGHTS
AutoCAD SHX Text
VIEW
AutoCAD SHX Text
RIDGE
AutoCAD SHX Text
WINDERMERE
AutoCAD SHX Text
LAURELHURST
AutoCAD SHX Text
RAVENNA
AutoCAD SHX Text
MAPLE
AutoCAD SHX Text
LEAF
AutoCAD SHX Text
WEDGEWOOD
AutoCAD SHX Text
SUNSET
AutoCAD SHX Text
HILL
AutoCAD SHX Text
BALLARD
AutoCAD SHX Text
FREMONT
AutoCAD SHX Text
WALLING-
AutoCAD SHX Text
FORD
AutoCAD SHX Text
LAWTON
AutoCAD SHX Text
UNIVERSITY
AutoCAD SHX Text
MAGNOLIA
AutoCAD SHX Text
INTERBAY
AutoCAD SHX Text
QUEEN
AutoCAD SHX Text
ANNE
AutoCAD SHX Text
MADISON
AutoCAD SHX Text
PARK
AutoCAD SHX Text
MONTLAKE
AutoCAD SHX Text
CAPITOL
AutoCAD SHX Text
HILL
AutoCAD SHX Text
CENTRAL
AutoCAD SHX Text
BUSINESS
AutoCAD SHX Text
DISTRICT
AutoCAD SHX Text
MADRONA
AutoCAD SHX Text
HARBOR
AutoCAD SHX Text
ISLAND
AutoCAD SHX Text
ALKI
AutoCAD SHX Text
WEST
AutoCAD SHX Text
SEATTLE
AutoCAD SHX Text
MT BAKER
AutoCAD SHX Text
RAINIER
AutoCAD SHX Text
VALLEY
AutoCAD SHX Text
GEORGETOWN
AutoCAD SHX Text
COLUMBIA
AutoCAD SHX Text
SEWARD
AutoCAD SHX Text
PARK
AutoCAD SHX Text
BRIGHTON
AutoCAD SHX Text
DUNLAP
AutoCAD SHX Text
BEACON HILL
AutoCAD SHX Text
SOUTH
AutoCAD SHX Text
SEATTLE
AutoCAD SHX Text
SOUTH
AutoCAD SHX Text
PARK
AutoCAD SHX Text
HIGHLAND
AutoCAD SHX Text
PARK
AutoCAD SHX Text
WHITE CENTER
AutoCAD SHX Text
FAUNTLEROY
AutoCAD SHX Text
ARROYO
AutoCAD SHX Text
CROWN
AutoCAD SHX Text
SOUND
AutoCAD SHX Text
PUGET
AutoCAD SHX Text
SOUND
AutoCAD SHX Text
PUGET
AutoCAD SHX Text
WASHINGTON
AutoCAD SHX Text
LAKE
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
DRAWN BY:
AutoCAD SHX Text
CHECKED BY:
AutoCAD SHX Text
PROJECT NO.
AutoCAD SHX Text
FIGURE NO.
AutoCAD SHX Text
10/2/2017
AutoCAD SHX Text
SLT
AutoCAD SHX Text
NTW
AutoCAD SHX Text
Z:\Projects\2017 Projects\17-297 607 2nd Ave N\Report + Figures\Figures\CADDVicinity Map.dwg
Page 25: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

MERCER STREET

ROY STREET

2N

D A

VE

N

3R

D A

VE

N

PG-2

PG-1

I N C O R P O R A T E D

2

SITE AND EXPLORATION PLAN

17-297

50'50'

scale in feet

0 25'

Scale: 1" = 50'

1. Aerial imagery & topography obtained from Seattle DPD GIS website.

GIS features are provided for relative information only and are not substitution for field survey.

2. Location of borings are approximate and based on the relative locations of known site features.

3. Vertical Datum: NAVD '88

NOTES

PROJECT

LOCATION

LEGEND

Proposed Development 607 2nd Avenue N

Seattle, Washington

1

1

0

f

t

1

2

0

f

t

1

2

0

f

t

1

3

0

f

t

1

2

0

ft

1

3

0

f

t

1

4

0

f

t

1

2

0

f

t

1

5

0

f

t

Soil Boring by PanGEO, Inc. (2017 - Appendix A)PG-#

AutoCAD SHX Text
PROJECT NO.
AutoCAD SHX Text
FIGURE NO.
AutoCAD SHX Text
CHECKED BY:
AutoCAD SHX Text
DRAWN BY:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
10/3/2017
AutoCAD SHX Text
SLT
AutoCAD SHX Text
NTW
AutoCAD SHX Text
Z:\Projects\2017 Projects\17-297 607 2nd Ave N\Report + Figures\Figures\CADD\Site and Exploration Plan.dwg
Page 26: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

I N C O R P O R A T E D

17-297

3

GEOLOGIC MAP

1500'750' 0 750'

Approximate Scale: 1" = 1500'

GEOLOGIC UNITS NOTES

1. Derived from the Geologic Map of Seattle (Troost, et. al. 2005)

2. Detailed descriptions of the geologic units can be found in the

text of the report.

3. Only the applicable geologic units are listed.

Ql Lake deposits

Qvr Vashon recessional outwash deposits

Qvrl Vashon recessional lacustrine deposits

Qvi Vashon ice-conctact deposits

Qvt Vashon glacial till

Qva Vashon advance outwash deposits

Qvlc Vashon lawton clay deposits

Qpf Pre-Fraser glaciation age deposits

Qpfn Pre-Fraser, nonglacial deposits

PROJECT

LOCATION

Qob Olympia beds

Qpo Deposits of pre-olympia age

MERCER ST

Qvt

ROY ST

2ND AVE N

Qva

Qvlc

Qpf

Qvrl

Queen Anne Ave N

Q

p

f

Qvt

ELLIOTT

BAY

Proposed Residential Development

607 2nd Avenue N Seattle, Washington

AutoCAD SHX Text
DATE:
AutoCAD SHX Text
DRAWN BY:
AutoCAD SHX Text
CHECKED BY:
AutoCAD SHX Text
PROJECT NO.
AutoCAD SHX Text
FIGURE NO.
AutoCAD SHX Text
10/2/2017
AutoCAD SHX Text
SLT
AutoCAD SHX Text
NTW
AutoCAD SHX Text
Z:\Projects\2017 Projects\17-297 607 2nd Ave N\Report + Figures\Figures\CADD\Geologic Map.dwg
Page 27: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Project No. Figure No.

DESIGN LATERAL PRESSURESSOLDIER PILE WALL

CANTILEVERED

17-297 4

file.

grf w

/ fil

e.da

t 1

0/13

/17

(14:

50) T

EA2

Notes:1. Minumum embedment should be at least 10 feet below bottom of excavation.2. A factor of safety of 1.5 has been applied to the recommended passive pressure values.

No factor of safety has been applied to the recommended active earth pressure values.3. Active pressures should be applied over the full width of the pile spacing above the

base of the excavation, and over one pile diameter below the base of the excavation.4. Surcharge pressures should be applied over the entire length of the loaded area.5. Passive pressure should be applied to two times the diameter of the soldier piles.6. Use 50% of the active and surcharge pressures for lagging design with soldier piles spaced

at 8' or less.7. Refer to report text for additional discussions.

Base of Excavation

Soldier Pile Wall withTimber Lagging

H

Passive PressureActive Pressure

FootingSurcharge = q

175 pcf1

40 pcf (1H:1V backslope)35 pcf (level backslope)

1

Bf

1

1 1H:1V Temporary Cut(if applicable)

Level Backslope

X

Apply only to abovebottom of excavation

0.4(1 - X/H) q

3Bf

Street traffic surcharge:80 psf uniform pressure

x

Apply only to abovebottom of excavation

Proposed Residential Development

607 Second Ave N Seattle, Washington

15 fe

et m

ax

Groundwater at 14 feetbelow grade.

Page 28: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

APPENDIX A

BORING LOGS

Page 29: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

MOISTURE CONTENT

2-inch OD Split Spoon, SPT(140-lb. hammer, 30" drop)

3.25-inch OD Spilt Spoon(300-lb hammer, 30" drop)

Non-standard penetrationtest (see boring log for details)

Thin wall (Shelby) tube

Grab

Rock core

Vane Shear

Dusty, dry to the touch

Damp but no visible water

Visible free water

Terms and Symbols forBoring and Test Pit Logs

Density

SILT / CLAY

GRAVEL (<5% fines)

GRAVEL (>12% fines)

SAND (<5% fines)

SAND (>12% fines)

Liquid Limit < 50

Liquid Limit > 50

Breaks along defined planes

Fracture planes that are polished or glossy

Angular soil lumps that resist breakdown

Soil that is broken and mixed

Less than one per foot

More than one per foot

Angle between bedding plane and a planenormal to core axis

Very Loose

Loose

Med. Dense

Dense

Very Dense

SPTN-values

Approx. Undrained ShearStrength (psf)

<4

4 to 10

10 to 30

30 to 50

>50

<2

2 to 4

4 to 8

8 to 15

15 to 30

>30

SPTN-values

Units of material distinguished by color and/orcomposition from material units above and below

Layers of soil typically 0.05 to 1mm thick, max. 1 cm

Layer of soil that pinches out laterally

Alternating layers of differing soil material

Erratic, discontinuous deposit of limited extent

Soil with uniform color and composition throughout

Approx. RelativeDensity (%)

Gravel

Layered:

Laminated:

Lens:

Interlayered:

Pocket:

Homogeneous:

Highly Organic Soils

#4 to #10 sieve (4.5 to 2.0 mm)

#10 to #40 sieve (2.0 to 0.42 mm)

#40 to #200 sieve (0.42 to 0.074 mm)

0.074 to 0.002 mm

<0.002 mm

UNIFIED SOIL CLASSIFICATION SYSTEM

MAJOR DIVISIONS GROUP DESCRIPTIONS

Notes:

MONITORING WELL

<15

15 - 35

35 - 65

65 - 85

85 - 100

GW

GP

GM

GC

SW

SP

SM

SC

ML

CL

OL

MH

CH

OH

PT

TEST SYMBOLS

50%or more passing #200 sieve

Groundwater Level at time of drilling (ATD)Static Groundwater Level

Cement / Concrete Seal

Bentonite grout / seal

Silica sand backfill

Slotted tip

Slough

<250

250 - 500

500 - 1000

1000 - 2000

2000 - 4000

>4000

RELATIVE DENSITY / CONSISTENCY

Fissured:

Slickensided:

Blocky:

Disrupted:

Scattered:

Numerous:

BCN:

COMPONENT DEFINITIONS

Dry

Moist

Wet

1. Soil exploration logs contain material descriptions based on visual observation and field tests using a systemmodified from the Uniform Soil Classification System (USCS). Where necessary laboratory tests have beenconducted (as noted in the "Other Tests" column), unit descriptions may include a classification. Please refer to thediscussions in the report text for a more complete description of the subsurface conditions.

2. The graphic symbols given above are not inclusive of all symbols that may appear on the borehole logs.Other symbols may be used where field observations indicated mixed soil constituents or dual constituent materials.

COMPONENT SIZE / SIEVE RANGE COMPONENT SIZE / SIEVE RANGE

SYMBOLSSample/In Situ test types and intervals

Silt and Clay

Consistency

SAND / GRAVEL

Very Soft

Soft

Med. Stiff

Stiff

Very Stiff

Hard

Phone: 206.262.0370

Bottom of BoringBoulder:

Cobbles:

Gravel

Coarse Gravel:

Fine Gravel:

Sand

Coarse Sand:

Medium Sand:

Fine Sand:

Silt

Clay

> 12 inches

3 to 12 inches

3 to 3/4 inches

3/4 inches to #4 sieve

Atterberg Limit Test

Compaction Tests

Consolidation

Dry Density

Direct Shear

Fines Content

Grain Size

Permeability

Pocket Penetrometer

R-value

Specific Gravity

Torvane

Triaxial Compression

Unconfined Compression

Sand50% or more of the coarsefraction passing the #4 sieve.Use dual symbols (eg. SP-SM)for 5% to 12% fines.

for In Situ and Laboratory Testslisted in "Other Tests" column.

50% or more of the coarsefraction retained on the #4sieve. Use dual symbols (eg.GP-GM) for 5% to 12% fines.

DESCRIPTIONS OF SOIL STRUCTURES

Well-graded GRAVEL

Poorly-graded GRAVEL

Silty GRAVEL

Clayey GRAVEL

Well-graded SAND

Poorly-graded SAND

Silty SAND

Clayey SAND

SILT

Lean CLAY

Organic SILT or CLAY

Elastic SILT

Fat CLAY

Organic SILT or CLAY

PEAT

ATT

Comp

Con

DD

DS

%F

GS

Perm

PP

R

SG

TV

TXC

UCC

LOG

KE

Y

09-1

18 L

OG

.GP

J P

AN

GE

O.G

DT

11/

12/1

3

Figure A-1

Page 30: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

[LANDSCAPING / BARK TOPSOIL] Approximately 8-inch thicklayer of landscaping bark and organic rich topsoil.

UNIT 1: FILL / MODIFIED LAND Medium dense, grey, silty fine to medium SAND with scatteredsubangular to subrounded gravel; dry, non-plastic fines.

-- becomes loose, grey with faint bands of iron-oxide staining, silty fineSAND with scattered fine to coarse roots; dry to damp, non-plasticfines, poorly graded sand fraction, homogeneous soil structure.

-- becomes grey, slight increase in fine fraction and moisture content.Observed an approximately 0.1-inch thick layer of black, organicmaterial mid-sample.

UNIT 2: VASHON ICE-CONTACT DEPOSITS Medium stiff, grey with black and rust colored mottling, silty CLAY withscattered one-inch thick layers of silty sand; moist, low to mediumplasticity, disrupted and blocky soil texture.

Medium dense, grey, fine to coarse SAND with gravel to poorlygraded, sandy Gravel; wet, subangular to subrounded fine to coarsegravel.

Medium dense, dark grey with light bluish cast, silty SAND withabundant fine subangular gravel and scattered coarse gravel; wet,non-plastic fines, homogenous color.

Medium dense, grey, poorly graded, medium to coarse SAND; wet,trace silt, homogenous color and soil structure.

S-1

S-2

S-3

S-4

S-5

S-6

101613

323

333

234

2511

1058

Remarks: EC-95 track-mounted drill rig. Standard Penetration Test (SPT) sampler drivenwith a 140 lb. safety hammer. Hammer operated with a rope an cathead mechanism.Surface elevation estimated based on a City of Seattle's GIS Website. This information isprovided for relative information only and is not a substitution for field survey. VerticalDatum: NAVD88

0

5

10

15

20

25

The stratification lines represent approximate boundaries. The transition may be gradual.

MATERIAL DESCRIPTION

Figure A-2

Oth

er T

ests

Sam

ple

No.

Completion Depth:Date Borehole Started:Date Borehole Completed:Logged By:Drilling Company:

Dep

th,

(ft)

607 2nd Ave N

17-297

607 2nd Ave N, Seattle, Washington

Northing: 47.624936, Easting: -122.352369

46.5ft9/27/179/27/17N. WeikelBortec 1, Inc.

Sheet 1 of 2

Project:

Job Number:

Location:

Coordinates:

Sym

bol

Sam

ple

Typ

e

Blo

ws

/ 6

in.

122.0ft

n/a

6-in. Hollow Stem Auger

SPT

Surface Elevation:

Top of Casing Elev.:

Drilling Method:

Sampling Method:

LOG OF TEST BORING PG-1

N-Value

0

Moisture LL

50

PL

RQD Recovery

100

Page 31: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Medium dense, grey, poorly graded, medium to coarse SAND; wet,trace silt, homogenous color and soil structure. (Continued)

Medium dense brownish-grey, silty very fine to fine SAND; wet,non-plastic to low plasticity fines, homogenous color and soil structure.

Medium dense, light grey, poorly graded medium to coarse SAND;wet, homogenous color and soil structure.-- observed sampler bouncing on gravel while sampling. Blowcountsmay be overstated due to the presence of gravel. Sample descriptionbased on recovered material.-- driller reports it feels like the soil is squeezing against the outside ofthe augers while advancing the augers between 30 to 35 feet bgs.However, the inside of the hollow stem augers appeared to remainopen and no heaving was observed.

Medium dense, fine to coarse SAND with some silt; wet, non-plasticfines, homogenous color and soil structure.

UNIT 3: Pre-Fraser Glaciation Fine-grained Deposits Hard, grey, SILT; moist, non-plastic to low plasticity fines, finelybedded, massive.

-- same as above.

Boring terminated approximately 46.5 feet below the surface.

Groundwater was encountered approximately 14-ft below the groundsurface.

S-7

S-8

S-9

S-10

S-11

558

50/5

81214

81424

101518

Remarks: EC-95 track-mounted drill rig. Standard Penetration Test (SPT) sampler drivenwith a 140 lb. safety hammer. Hammer operated with a rope an cathead mechanism.Surface elevation estimated based on a City of Seattle's GIS Website. This information isprovided for relative information only and is not a substitution for field survey. VerticalDatum: NAVD88

25

30

35

40

45

50

The stratification lines represent approximate boundaries. The transition may be gradual.

MATERIAL DESCRIPTION

Figure A-2

Oth

er T

ests

Sam

ple

No.

Completion Depth:Date Borehole Started:Date Borehole Completed:Logged By:Drilling Company:

Dep

th,

(ft)

607 2nd Ave N

17-297

607 2nd Ave N, Seattle, Washington

Northing: 47.624936, Easting: -122.352369

46.5ft9/27/179/27/17N. WeikelBortec 1, Inc.

Sheet 2 of 2

Project:

Job Number:

Location:

Coordinates:

Sym

bol

Sam

ple

Typ

e

Blo

ws

/ 6

in.

122.0ft

n/a

6-in. Hollow Stem Auger

SPT

Surface Elevation:

Top of Casing Elev.:

Drilling Method:

Sampling Method:

LOG OF TEST BORING PG-1

N-Value

0

Moisture LL

50

PL

RQD Recovery

100

>>

Page 32: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

[LANDSCAPING / BARK TOPSOIL] Approximately 6-inch thicklayer of landscaping bark and organic rich topsoil.

UNIT 1: FILL / MODIFIED LAND Very loose, grey, silty fine to medium SAND with subangular tosubrounded gravel; dry, non-plastic fines.

-- poor recovery. Soil description based on visual observation of soilcuttings.

-- becomes intermixed grey and brown, silty fine SAND with scatteredfine gravel; very moist, disrupted soil structure.

-- becomes grey with faint iron-oxide staining, moist, slight increase infines fraction, scattered fine rootlets.

Medium stiff, very dark grey, sandy SILT with organics; very moist,non-plastic fines, strong organic odor.

UNIT 2: VASHON ICE-CONTACT DEPOSITS Medium stiff, grey with black and rust colored mottling, silty CLAY;moist, low to medium plasticity, disrupted and blocky soil texture.

Loose, grey with a bluish cast, very silty, very fine to medium SANDwith scattered subangular to subrounded gravel; wet, non-plastic tolow plasticity fines, homogenous color.

Dense, grey, medium to coarse SAND with scattered subangulargravel; wet, trace silt, poorly graded, homogenous color and soilstructure.

-- observed sampler bouncing on gravel while sampling. Blowcountsmay be overstated due to the presence of gravel..

Dense, grey with strong uniform iron-oxide staining, silty fine tomedium SAND; wet, homogenous soil structure.

S-1

S-2

S-3

S-4

S-5

S-6

2013

411

212

224

436

123423

Remarks: EC-95 track-mounted drill rig. Standard Penetration Test (SPT) sampler drivenwith a 140 lb. safety hammer. Hammer operated with a rope an cathead mechanism.Surface elevation estimated based on a City of Seattle's GIS Website. This information isprovided for relative information only and is not a substitution for field survey. VerticalDatum: NAVD88

0

5

10

15

20

25

The stratification lines represent approximate boundaries. The transition may be gradual.

MATERIAL DESCRIPTION

Figure A-3

Oth

er T

ests

Sam

ple

No.

Completion Depth:Date Borehole Started:Date Borehole Completed:Logged By:Drilling Company:

Dep

th,

(ft)

607 2nd Ave N

17-297

607 2nd Ave N, Seattle, Washington

Northing: 47.624761, Easting: -122.352535

41.5ft9/27/179/27/17N. WeikelBortec 1, Inc.

Sheet 1 of 2

Project:

Job Number:

Location:

Coordinates:

Sym

bol

Sam

ple

Typ

e

Blo

ws

/ 6

in.

121.0ft

n/a

6-in. Hollow Stem Auger

SPT

Surface Elevation:

Top of Casing Elev.:

Drilling Method:

Sampling Method:

LOG OF TEST BORING PG-2

N-Value

0

Moisture LL

50

PL

RQD Recovery

100

Page 33: PRELIMINARY GEOTECHNICAL REPORT PROPOSED …

Dense, grey with strong uniform iron-oxide staining, silty fine tomedium SAND; wet, homogenous soil structure. (Continued)-- observed sampler bouncing on gravel while sampling. Blowcountsmay be overstated due to the presence of gravel..

Medium dense, light grey, poorly graded medium to coarse SAND;wet, homogenous color and soil structure.-- observed sampler bouncing on gravel while sampling. Blowcountsmay be overstated due to the presence of gravel. Sample descriptionbased on recovered material.-- driller reports it feels like the soil is squeezing against the outside ofthe augers while advancing the augers between 30 to 35 feet bgs.However, the inside of the hollow stem augers appeared to remainopen and no heaving was observed.-- becomes loose, grey, very silty, very fine SAND with numerous fineangular gravel; wet, homogenous soil structure. Observed anapproximately 4-inch thick layer of grey, non-plastic SILT mid-sample.-- driller reports increased drilling effort below 30 feet bgs.

Medium dense brownish-grey, silty very fine to fine SAND; wet,non-plastic to low plasticity fines, homogenous color and soil structure.

UNIT 3: Pre-Fraser Glaciation Fine-grained Deposits Hard, grey, SILT; moist, non-plastic to low plasticity fines, finelybedded, massive.

-- same as above.

Boring terminated approximately 41.5 feet below the surface.

Groundwater was encountered approximately 14-ft below the groundsurface.

S-7

S-8

S-9

S-10

132224

445

121421

111515

Remarks: EC-95 track-mounted drill rig. Standard Penetration Test (SPT) sampler drivenwith a 140 lb. safety hammer. Hammer operated with a rope an cathead mechanism.Surface elevation estimated based on a City of Seattle's GIS Website. This information isprovided for relative information only and is not a substitution for field survey. VerticalDatum: NAVD88

25

30

35

40

45

50

The stratification lines represent approximate boundaries. The transition may be gradual.

MATERIAL DESCRIPTION

Figure A-3

Oth

er T

ests

Sam

ple

No.

Completion Depth:Date Borehole Started:Date Borehole Completed:Logged By:Drilling Company:

Dep

th,

(ft)

607 2nd Ave N

17-297

607 2nd Ave N, Seattle, Washington

Northing: 47.624761, Easting: -122.352535

41.5ft9/27/179/27/17N. WeikelBortec 1, Inc.

Sheet 2 of 2

Project:

Job Number:

Location:

Coordinates:

Sym

bol

Sam

ple

Typ

e

Blo

ws

/ 6

in.

121.0ft

n/a

6-in. Hollow Stem Auger

SPT

Surface Elevation:

Top of Casing Elev.:

Drilling Method:

Sampling Method:

LOG OF TEST BORING PG-2

N-Value

0

Moisture LL

50

PL

RQD Recovery

100