Preliminary Construction and
Demolition Management Plan
Dublin Whitewater Course
Georges Dock, Dublin
for
Urban Agency Architect
N17397
January 2019
patrickparsons.co.uk 3.001.1 PPL DMS
Preliminary Construction and Demolition Management Plan
Dublin Whitewater Course
for
Urban Agency Architect
Revision Date of issue Comments Prepared By Checked By
0 05/02/19 Draft issue DSH PVS
1 19/02/19 Amended following design team
feedback DSH PVS
2 10/05/19 Updated to include demolition
considerations DH PVS
3 28/05/19 Referenced Legislation amended and
asbestos information included
DH PVS
4 13/08/19 Issued for Part 8 DH PVS
Should you have any queries relating to this document please contact:
Darren Holmes
Patrick Parsons Limited
Fourth Floor
Central Square
Forth Street
Newcastle upon Tyne
NE1 3PJ
T: +44 (0) 191 691 8175
Preliminary Construction and Demolition Management Plan Dublin Whitewater Course
N17397 patrickparsons.co.uk
Contents
1.0 Introduction ...................................................................................................................... 1
2.0 Material and resource use ................................................................................................ 2
3.0 Environmental effects ...................................................................................................... 3
4.0 Construction phase control measures.............................................................................. 5
5.0 Demolition phase control measures .............................................................................. 11
6.0 Summary ......................................................................................................................... 16
Disclaimer
It should be noted that this document is preliminary and is to be used only for planning
purposes. It is not a substitute for a detailed Construction Management Plan as would
typically be completed by the Main Contractor. This document is for the internal use of the
project design team and for Part 8 planning purposes only, it is not be used by or sent to any
parties external to the appointed design team or Dublin City Councils planning team without
the written permission of Patrick Parsons. This document is not to be used under any
circumstances for tendering or costing purposes. All information is to be read in conjunction
with Patrick Parsons engineering drawings.
Preliminary Construction and Demolition Management Plan Page | 1 Dublin Whitewater Course
N17397 patrickparsons.co.uk
1.0 Introduction
1.1.1 Terms of reference
The CMP describes the proposed programme of the construction works and the key activities
that will be undertaken. The project compromise of two separate entities, construction of a
Whitewater Course within the existing Georges Dock and construction of two Quayside
Buildings in the place of the former DDDA building. It then identifies, in general terms,
potential significant environmental effects associated with the activities and outlines the
proposals for the construction phase control of them. Detailed consideration of effects during
construction and proposed control measures are provided in each associated report
submitted with the planning application. The CMP forms part of the overall Project
Management and as such, activities described would be integrated with other Quality,
Sustainability and Health and Safety management processes.
1.1.2 Programme of works
The construction programme for the Whitewater Course and two Quayside Buildings will span
approximately 18months.
1.1.3 Description of works
The construction activities associated with the Whitewater Course comprises briefly of piling
or raft (enabling works), construction of reinforced concrete structures within Georges Dock
and mechanical and electrical fit out including a canoe conveyor, 4 axial pumps, water
treatment and lighting.
The construction activities associated with the Quayside Buildings building briefly comprises
asbestos removal and demolition of the former DDDA building, piling and or raft (enabling
works), erection of frame, cladding, roofing and glazing and mechanical and electrical fit out.
Preliminary Construction and Demolition Management Plan Page | 2 Dublin Whitewater Course
N17397 patrickparsons.co.uk
2.0 Material and resource use
Plant and Equipment
Consideration has been given to the types of plant that are likely to be used during the
construction works. The plant and equipment associated with each key element and of the
construction process is set out below;
Stage
Enabling works Construction
Tracked/wheeled 360-degree
excavator
* *
Dumpers *
Mobile crane *
Mobile pile rig *
Air compressors *
Power tools including percussion
drills and cutting discs
*
Hand / power tools * *
Wheel washing plant * *
Scaffold *
Mobile access platform *
Delivery trucks * *
Skips and skip trucks *
Concrete pumping apparatus * *
Forklift trucks *
Hours of working
It is anticipated that the normal hours of working for construction will be:
− Weekdays 07.30 to 18.00 hours, and 08.00 to 13.00 hours on Saturdays.
These working arrangements will be agreed with Dublin City Council prior to commencement.
Hours of working will be governed by planning condition, including arrangements for carrying
out specific tasks outside the agreed hours. Night time working will be restricted to
exceptional circumstances. Hours of working will be covered in the Code of Construction
Practice.
Preliminary Construction and Demolition Management Plan Page | 3 Dublin Whitewater Course
N17397 patrickparsons.co.uk
3.0 Environmental effects
A review has been undertaken of the potential environmental issues and adverse effects
associated with the demolition and construction works. This has been undertaken using the
experience of the project team in association with a review of the proposed development.
Environmental effects can arise either from day to day construction operations, or from
individual instances of mishap or accident.
Issue Anticipated
site activities
Potential
effects
Receptor Period of
effects
Noise Construction
traffic, piling
Vehicle
movement and
activity within
site, regrading
of soil and
excavation,
general
building and
construction
activity
Nearby
residential and
business
properties
Short term
Dust/ Air quality Construction
traffic and
operations,
excavations,
materials
handling and
storage,
regarding and
earth moving,
concrete
batching.
Windblown
dust affecting
adjacent
properties.
Effects on air
quality from
airborne
material
Nearby
residential and
business
properties
Short term
Traffic Deliveries to
and from site
Noise and
general
disturbance
Nearby
residential and
business
properties
Short term
Access to adjacent
business and
properties
Material
storage
Hazards from
construction
traffic
and building
operations
Adjacent roads Short term
Hazardous materials Storage of
hazardous
materials on
site
Spill and
general
contamination
hazards
Watercourses/
site
workers
Short term
Preliminary Construction and Demolition Management Plan Page | 4 Dublin Whitewater Course
N17397 patrickparsons.co.uk
Water/Groundwater Excavation and
construction
activities,
vehicle
movements,
human activity
generally
Pollution to
adjacent
watercourse
and
groundwater
Watercourses
&
groundwater
Short term
Asbestos Carryout
asbestos
removal using
approved
cntractors
from the
existing DDDA
building prior
to demolition
Release of
asbestos fibres
into
atmosphere
and exposure
of construction
workers
Public at
nearby
properties and
construction
staff
Short and
Longterm
Preliminary Construction and Demolition Management Plan Page | 5 Dublin Whitewater Course
N17397 patrickparsons.co.uk
4.0 Construction phase control measures
Procedures and code of practice
The following measures will be pursued to eliminate, reduce or offset the potential adverse
environmental effects identified in the table above. Any detrimental or potential adverse
effects will be appropriately mitigated through a variety of procedures and actions that are
set out in this report and in the identified control measures for construction phase activities
set out in individual reports carried out for the benefit of this site.
− Preparation of procedures which will clearly set out the methods of managing
environmental issues for all involved with the construction works, including supply
chain management
− Requirement to comply with these procedures included as part of the contract
conditions for each element of the work. All contractors tendering for work will be
required to demonstrate that their proposals can comply with the procedures, and
current best practice techniques
− Establishing a dedicated point of contact and responsibility to deal with issues if
they arise. The point of contact will be a named representative from the
construction manager or contractor, part of the professional team (the
Construction Liaison Officer, see below)
− Production of a regular newsletter to be circulated to neighbouring occupiers,
residents and the relevant authorities
− Regular dialogue with Dublin City Council and the local community
The procedures will be set out in the Code of Construction Practice and circulated to Dublin
City Council and other relevant bodies, prior to commencement of the works. It will include
the following:
− The broad plan of the phasing of the works and its context within the whole project
− Baseline levels for noise and dust and details of any monitoring protocols that may
be necessary during the works
− Housekeeping procedures and environmental control measures; Any requirement
for monitoring and record keeping;
− Contact details during normal working hours and emergency details outside
working hours
− Provision for reporting, public liaison, and prior notification
− The mechanism for residents and other members of the public to register
complaints and the procedures for responding to complaints
− Prohibited or restricted operations (location or hours.)
− Details of construction operations highlighting any operations likely to result in
disturbance and/or working hours outside the core working period, with an
indication of the expected duration of key phases and dates
The details of proposed routes for heavy goods vehicles travelling to and from the application
site, and details of all works involving interference (where necessary) with a public highway,
including temporary carriageway/footpath closures, realignment and diversions.
Preliminary Construction and Demolition Management Plan Page | 6 Dublin Whitewater Course
N17397 patrickparsons.co.uk
Management of subcontractors
Individual contracts (for example for groundworks and site preparation) will incorporate
relevant requirements in respect of environmental control, based largely on the standard of
'good working practice' as well as Statutory Requirements. Potential sub-contractors will be
required to demonstrate how they will achieve best practice, how targets will be met and how
potential effects will be minimised.
The following will be put in place to assist the management of sub-contractors:
− Health and Safety Management Plan (HASMP), setting out the construction
methodology and relevant legislation, guidelines and best practice;
− Code of Construction Practice (CCP), which is intended to establish a framework
for the environmental aspects of the HASMP. This document will apply to all
construction work, building site activities, cleaning and maintenance,
transportation of materials and spoil, landscaping activities, and includes both
preventative and construction phase control measures;
Management of construction works
There will be a designated liaison officer (the 'Construction Liaison Officer') who will be in
regular contact with the public, will keep residents informed of progress and will deal with
complaints and enquiries. This nominated individual will be named at the application site
entrance, with a contact number, and will be identified to Dublin City Council and local
resident/community groups, prior to the start of site activities, and whenever a change of
responsibility occurs.
Response to complaints
Any complaints will be logged on site and, where necessary, reported to the relevant
individual within the Local Planning Authority (and vice versa) as soon as practicable.
The procedures will specify the roles and responsibilities of the Construction Liaison Officer
and the Local Planning Authority in respect of breaches and complaints from the public. The
required actions will be different in each specific case, depending on the operation, equipment
or location or applying additional controls (for example screening).
Prior notice of specific activities or operations
In the event of unusual or specific activities and operations that can be anticipated, (e.g.
special large-scale delivery of materials outside normal working hours) such events will be
notified to Dublin City Council and to the relevant property owners or occupiers wherever
possible and neighbours, in advance of the activity. The relevant ‘notifiable’ activities will be determined by agreement with the Local Planning Authority once the detailed programme of
construction is defined and will include:
− Commencement of construction in certain areas;
− Necessary night time, weekend or evening working (outside core areas) of a type
which may affect properties;
− Road or footpath closures/diversions and movements of wide loads; and
− Work on roads affecting land used by others.
Preliminary Construction and Demolition Management Plan Page | 7 Dublin Whitewater Course
N17397 patrickparsons.co.uk
Traffic management
Closures and Diversions - whilst no long-term road closures are envisaged, short term closures
may be required in order to deliver large items of building plant or equipment, or for works to
the highway. If this is required, then consent will be obtained from Dublin City Council.
Notice regarding possible short-term closure or diversion of public rights of way within and/or
adjacent to the application site shall be given by the Contractor/Construction Manager to the
relevant local authorities and to the emergency services in advance of the required closure or
diversion dates.
HGV access to the proposed course area will be from the southern side of the site via Custom
House Quay where the main site access is to be located. There will be specific areas for
construction compounds, designated offloading points, access gates, and security barriers. It
should be noted that the contractor will need to maintain access to adjacent properties
throughout the works. The compound location and preliminary access arrangement is
included in Appendix A. The area designated as the ‘Canoe Polo’ is a flat slab with a large
associated area so may be used as material storage and a temporary compound when
required.
All construction traffic entering and leaving the application site will be closely controlled.
Vehicles making deliveries to the application site or removing spoil or other material, will
travel via designated routes. All HGV movements to and from the site are proposed to be
routed along Custom House Quay. Signs will be placed at the site, and on surrounding roads,
to inform drivers that other routes are not available to construction traffic. The proposed
designated route will be subject to the agreement of the Dublin City Council. Construction
access routes will avoid using any roads that may compromise use of the LUAS Tram.
Deliveries should be phased and controlled on a 'just in time' basis, all being clearly marked to
show their destination. This will minimise travel time around the application site and any
associated noise. All transportation to and from the application site will be on rubber tyre
vehicles. Tracked vehicles will only operate within the site. The timing of deliveries will seek
to avoid the periods of peak traffic flows on the local road network.
It is anticipated that a workforce of approximately 100-120 people will be employed, working
for the main contractor, sub-contractors, suppliers and other organisations. Cars and other
vehicles used by workers may have some limited parking available within the site, however
private transport use is to be kept to a minimum and the use of public transport to site
encouraged. Restrictions on parking on neighbouring roads will be strictly enforced.
Monitoring and environmental management of works
The following summarises the construction phase control measures to be adopted in relation
to noise, vibration and air quality issues:
− Contractors must carry out their duties in accordance with the “Air Quality
Monitoring and Noise Control Unit’s Good Practice Guide for Construction and
Demolition” document provided by Dublin City Council. (This document is
appended to the Noise Statement that is issued as part of this application).
Preliminary Construction and Demolition Management Plan Page | 8 Dublin Whitewater Course
N17397 patrickparsons.co.uk
− Designated and supervised areas and compounds for storage of materials, storage
of plant and equipment, site huts and parking of vehicles, storage of building
materials, and locations for loading and unloading of vehicles.
− Agreed construction methodology to minimise generation of noise, vibration and
dust;
− Use of hoardings, where appropriate, to assist acoustic screening;
− Requirement for engines to be switched off on-site when not in use, use of quieter
plant, noise suppression equipment, regular plant maintenance, screening of plant
(if appropriate);
− Spraying of spoil heaps, excavated material and other areas with water when
conditions dictate;
− Effective wheel/body washing facilities to be provided and used as necessary;
− A road sweeper will be used as and when the need for road cleaning arises;
− Vehicles carrying waste material off-site to be sheeted;
− Vibration monitoring will be required for all piling operation;
Waste management, recycling and disposal
Waste will be generated during all stages of the construction works. Major sources of waste
within the construction process are:
− Removal of existing fill material from Georges Dock
− Demolition of existing DDDA building
− Packaging – plastics, pallets, packaging
− Materials generated from site wastage – temporary works, shuttering
All relevant contractors will be required to investigate opportunities to minimise waste
arisings at source and, where such waste generation is unavoidable, to maximise the recycling
and reuse potential of construction materials. Wherever feasible, such arisings will be dealt
with in a manner that reduces environmental impact and maximises potential re-use of
materials. Recycling of materials will largely take place off-site where noise and dust are less
likely to influence the surrounding area to the application site.
Georges Dock is currently filled with what is believed to be demolition rubble, stone and silt
this will need to be excavated to formation level and removed from site. Opportunities to
either encapsulate or reuse should be investigated however due to limited material storage
available this would seem unfeasible. The classification has not yet been proved by material
testing. The formation level is -1.30m and whilst the top level of the demolition rubble varies
it is generally circa 1m. This would mean removal of approximately 18285m³ of material.
The destination of all waste or other materials removed from site will be notified by the
Contractor/Construction Manager for approval (via consultation with the Authorities). Loads
will only be deposited at authorised waste treatment and disposal sites. Deposition will be in
accordance with the requirements of the Environment Protection Agency, the Waste
Management Acts 1996-2003, Waste Management (Licensing) Regulations 2004, Waste
Management (Registration of Broker and Dealers) Regulations 2008, Waste Management
(Collection Permit) Regulations 2007-2008 and Waste Management (Hazardous Waste)
Regulations 1998-2000.
To prove the correct depositing of excavated material and to prevent the occurrence of fly-
tipping, a docket system will be used. The Contractor/Sub-contractor will operate a
Preliminary Construction and Demolition Management Plan Page | 9 Dublin Whitewater Course
N17397 patrickparsons.co.uk
sequentially numbered docket system, to confirm that each load is received at the approved
disposal site. Copies of the dockets are to be provided to the nominated manager, and
available for inspection at the application site. In addition, direct routes via main roads to
designated tips will be agreed with the sub-contractors. No burning of construction waste will
be undertaken on the application site.
It should be noted that during construction no discharge from the construction areas is
permitted to the Liffey or the existing surface water drainage system (which discharges to the
Liffey). If any dewatering of excavations is required water will be required to discharge to the
combined or foul water sewer - the contractor is to be responsible for providing appropriate silt
control measures to the satisfaction of Irish Water. The contractor is to make all necessary
arrangement with Irish Water for temporary connections. All works must comply with the
Greater Dublin Regional Code of Practice for Drainage Works.
The construction of the dismount stairs at the start of the Whitewater facility will require
dewatering of the local section to allow installation of what will be a precast form of
construction.
Temporary Protection
George’s Dock is a Protected Structure including the dock walls. All appropriate measures
must be taken in order to protect historic fabric, protected structures and trees from damage
during the construction phase of the project.
Removal of any fill material from the base of the dock must be carefully undertaken to
minimise damage to the dock walls. Removal of material directly adjacent to the existing
granite walls should be undertaken by hand. Nothing is to be fixed to or placed against the
dock walls during construction. No items which are heavy or may cause damage to the
stonework can be placed upon the granite capstones surrounding the dock throughout
construction. The capping stones should be protected and covered by structural plywood for
the duration of the works.
Protection needs to be provided for the Triumphal Arch during construction. The structure
must be fully hoarded to its full height using a plywood clad timber frame which includes an
access doorway. A low level protective barrier may be needed to avoid potential damage by
vehicles as well as a Heras perimeter fence.
The winch closest to the Triumphal Arch is to be hoarded and retained in position on site
during the works. The Conservation Architect will prepare a photographic record of the winch
prior to its enclosure. Following an assessment of the detailed construction plan provided by
the Appointed Contractor for the works, the risks to the winch will be reviewed. If deemed
necessary by the Conservation Architect, the winch will be temporarily removed and stored
securely on site in a suitable container, being reinstated upon completion of the works. The
winch on the west side of the lock and the crane on the east dock wall are to be protected
through the works with hoarding to the dock side.
The River Liffey quay wall is also to be protected throughout the works similarly to the dock
wall using plywood protection over the capping stones. Following the demolition of the DDDA
building, the existing buttresses of the river wall will be carefully exposed (by hand) to ensure
that the proposed piled foundations and loadings will avoid the buttresses.
Preliminary Construction and Demolition Management Plan Page | 10 Dublin Whitewater Course
N17397 patrickparsons.co.uk
Preliminary Construction and Demolition Management Plan Page | 11 Dublin Whitewater Course
N17397 patrickparsons.co.uk
5.0 Demolition phase control measures
The demolition phase of a project should also be planned and managed to ensure this can be
done safely and with limited impact on the environment.
Procedures and code of practice
The environmental effects identified in the table in Section 3.0 of this report will also apply to
the demolition phase of the project. The following measures will be pursued to eliminate,
reduce or offset the potential adverse environmental effects identified in Section 3.0. Any
detrimental or potential adverse effects will be appropriately mitigated through a variety of
procedures and actions that are set out in this report and in the identified control measures
for demolition phase activities set out in individual reports carried out for the benefit of this
site.
− Preparation of procedures which will clearly set out the methods of managing
environmental issues for all involved with the demolition works, including supply
chain management
− Requirement to comply with these procedures included as part of the contract
conditions for each element of the work. All contractors tendering for work will be
required to demonstrate that their proposals can comply with the procedures, and
current best practice techniques
− Establishing a dedicated point of contact and responsibility to deal with issues if
they arise. The point of contact will be a named representative from the demolition
manager or contractor, part of the professional team (the Construction Liaison
Officer, see below)
− Production of a regular newsletter to be circulated to neighbouring occupiers,
residents and the relevant authorities
− Regular dialogue with Dublin City Council and the local community
The procedures will be set out in the Code of Construction Practice and circulated to Dublin
City Council and other relevant bodies, prior to commencement of the works. It will include
the following:
− The broad plan of the phasing of the demolition works and its context within the
whole project
− Baseline levels for noise and dust and details of any monitoring protocols that may
be necessary during the demolition works
− Housekeeping procedures and environmental control measures; Any requirement
for monitoring and record keeping;
− Contact details during normal working hours and emergency details outside
working hours
− Provision for reporting, public liaison, and prior notification
− The mechanism for residents and other members of the public to register
complaints and the procedures for responding to complaints
− Prohibited or restricted operations (location or hours.)
− Details of demolition operations highlighting any operations likely to result in
disturbance and/or working hours outside the core working period, with an
indication of the expected duration of key phases and dates
Preliminary Construction and Demolition Management Plan Page | 12 Dublin Whitewater Course
N17397 patrickparsons.co.uk
The details of proposed routes for heavy goods vehicles travelling to and from the application
site, and details of all works involving interference (where necessary) with a public highway,
including temporary carriageway/footpath closures, realignment and diversions.
Management of subcontractors
Individual contracts will incorporate relevant requirements in respect of environmental
control, based largely on the standard of 'good working practice' as well as Statutory
Requirements. Potential sub-contractors will be required to demonstrate how they will
achieve best practice, how targets will be met and how potential effects will be minimised.
The following will be put in place to assist the management of sub-contractors:
− Health and Safety Management Plan (HASMP), setting out the demolition
methodology and relevant legislation, guidelines and best practice;
− Code of Construction Practice (CCP), which is intended to establish a framework
for the environmental aspects of the HASMP. This document will apply to all
demolition work.
Asbestos Removal
Dublin City Council commissioned an asbestos survey and report for the former DDDA
building which was undertaken in March 2019. Asbestos was found to be present I the form
of bitumen adhesive on the floor beneath the screed in a vacant office. As the building is still
extensively used, intrusive access was limited and therefore asbestos may be present in
other parts of the building. As recommended in the report, a full survey should take place
after the building has been vacated. The full survey should be used to plan and manage
asbestos removal which will need to be completed prior to demolition and in accordance
with Safety, Health and Welfare at Work (Exposure to Asbestos) Regulations 2006.
Management of demolition works
There will be a designated liaison officer (the 'Construction Liaison Officer') who will be in
regular contact with the public, will keep residents informed of progress and will deal with
complaints and enquiries. This nominated individual will be named at the application site
entrance, with a contact number, and will be identified to Dublin City Council and local
resident/community groups, prior to the start of site activities, and whenever a change of
responsibility occurs.
Response to complaints
Any complaints will be logged on site and, where necessary, reported to the relevant
individual within the Local Planning Authority (and vice versa) as soon as practicable.
The procedures will specify the roles and responsibilities of the Construction Liaison Officer
and the Local Planning Authority in respect of breaches and complaints from the public. The
required actions will be different in each specific case, depending on the operation, equipment
or location or applying additional controls (for example screening).
Preliminary Construction and Demolition Management Plan Page | 13 Dublin Whitewater Course
N17397 patrickparsons.co.uk
Prior notice of specific activities or operations
In the event of unusual or specific activities and operations that can be anticipated, (e.g.
special large-scale removal of materials outside normal working hours) such events will be
notified to Dublin City Council and to the relevant property owners or occupiers wherever
possible and neighbours, in advance of the activity. The relevant ‘notifiable’ activities will be determined by agreement with the Local Planning Authority once the detailed programme of
construction is defined and will include:
− Commencement of demolition in certain areas;
− Necessary night time, weekend or evening working (outside core areas) of a type
which may affect properties;
− Road or footpath closures/diversions and movements of wide loads; and
− Work on roads affecting land used by others.
Traffic management
Closures and Diversions - whilst no long-term road closures are envisaged, short term closures
may be required in order to remove large items of building plant or materials. If this is
required, then consent will be obtained from Dublin City Council.
Notice regarding possible short-term closure or diversion of public rights of way within and/or
adjacent to the application site shall be given by the Contractor/demolition Manager to the
relevant local authorities and to the emergency services in advance of the required closure or
diversion dates.
HGV access will be from the southern side of the site via Custom House Quay where the main
site access would be located. There will be specific areas for site compounds, designated
loading points, access gates, and security barriers.
All demolition traffic entering and leaving the application site will be closely controlled.
Vehicles removing spoil or other material, will travel via designated routes. All HGV
movements to and from the site are proposed to be routed along Custom House Quay. Signs
will be placed at the site, and on surrounding roads, to inform drivers that other routes are
not available to demolition traffic. The proposed designated route will be subject to the
agreement of the Dublin City Council. Demolition access routes will avoid using any roads that
may compromise use of the LUAS Tram.
Deliveries should be phased and controlled on a 'just in time' basis, all being clearly marked to
show their destination. This will minimise travel time around the application site and any
associated noise. All transportation to and from the application site will be on rubber tyre
vehicles. Tracked vehicles will only operate within the site. The timing of deliveries will seek
to avoid the periods of peak traffic flows on the local road network.
Monitoring and environmental management of works
The following summarises the demolition phase control measures to be adopted in relation
to noise, vibration and air quality issues:
− Contractors must carry out their duties in accordance with the “Air Quality
Monitoring and Noise Control Unit’s Good Practice Guide for Construction and
Preliminary Construction and Demolition Management Plan Page | 14 Dublin Whitewater Course
N17397 patrickparsons.co.uk
Demolition” document provided by Dublin City Council. (This document is
appended to the Noise Statement that is issued as part of this application).
− Designated and supervised areas and compounds for storage of materials, storage
of plant and equipment, site huts and parking of vehicles, storage of building
materials, and locations for loading and unloading of vehicles.
− Agreed demolition methodology to minimise generation of noise, vibration and
dust;
− Use of hoardings, where appropriate, to assist acoustic screening;
− Requirement for engines to be switched off on-site when not in use, use of quieter
plant, noise suppression equipment, regular plant maintenance, screening of plant
(if appropriate);
− Spraying of spoil heaps, excavated material and other areas with water when
conditions dictate;
− Effective wheel/body washing facilities to be provided and used as necessary;
− A road sweeper will be used as and when the need for road cleaning arises;
− Vehicles carrying waste material off-site to be sheeted;
Waste management, recycling and disposal
Waste will be generated during all stages of the demolition works. Major sources of waste
within the demolition process are:
− Removal of Asbestos from the DDDA building
− Demolition of the DDDA building
All relevant contractors will be required to investigate opportunities to minimise waste
arisings at source and, where such waste generation is unavoidable, to maximise the recycling
and reuse potential of construction materials. Wherever feasible, such arisings will be dealt
with in a manner that reduces environmental impact and maximises potential re-use of
materials. Recycling of materials will largely take place off-site where noise and dust are less
likely to influence the surrounding area to the application site.
The destination of all waste or other materials removed from site will be notified by the
Contractor/Demolition Manager for approval (via consultation with the Authorities). Loads
will only be deposited at authorised waste treatment and disposal sites. Deposition will be in
accordance with the requirements of the Environment Protection Agency, the Waste
Management Acts 1996-2003, Waste Management (Licensing) Regulations 2004, Waste
Management (Registration of Broker and Dealers) Regulations 2008, Waste Management
(Collection Permit) Regulations 2007-2008 and Waste Management (Hazardous Waste)
Regulations 1998-2000.
To prove the correct depositing of excavated material and to prevent the occurrence of fly-
tipping, a docket system will be used. The Contractor/Sub-contractor will operate a
sequentially numbered docket system, to confirm that each load is received at the approved
disposal site. Copies of the dockets are to be provided to the nominated manager, and
available for inspection at the application site. In addition, direct routes via main roads to
designated tips will be agreed with the sub-contractors. No burning of construction waste will
be undertaken on the application site.
It should be noted that during demolition no discharge from the demolition areas is permitted
to the Liffey or the existing surface water drainage system (which discharges to the Liffey). If
Preliminary Construction and Demolition Management Plan Page | 15 Dublin Whitewater Course
N17397 patrickparsons.co.uk
any dewatering of excavations is required water will be required to discharge to the combined
or foul water sewer - the contractor is to be responsible for providing appropriate silt control
measures to the satisfaction of Irish Water. The contractor is to make all necessary
arrangement with Irish Water for temporary connections. All works must comply with the
Greater Dublin Regional Code of Practice for Drainage Works.
Demolition must be carried out without damage to protected structures including the original
dock walls, lock gate, quay wall and triumphed arch. The lock gates are to be carefully removed
and stored off site for use elsewhere by Dublin City Council.
Careful attention should be made to the proposed construction details which include a layer
of protection between the reinforced concrete walls of the course and the existing dock walls.
This detail is to allow the removal of the proposed concrete sides if the watercourse ever
needs to be removed without impacting on the dock walls behind.
Preliminary Construction and Demolition Management Plan Page | 16 Dublin Whitewater Course
N17397 patrickparsons.co.uk
6.0 Summary
The construction programme will span approximately 18 months, and it is envisaged that the
development will be completed in two main phases; enabling works and construction.
The initial phase of the development will be involving excavation works, demolition and slab
construction.
Plant and equipment to be used during construction has been identified.
Potential effects arising from construction and demolition activities have been identified and
control measures are identified in this CMP report and in other relevant reports submitted to
support the planning application. A Code of Construction Practice will be written by the main
contractor upon appointment and submitted to Dublin City Council and other relevant
organisations to set out the agreed procedures and ‘best practice’ on construction operations, and in accordance with relevant legislative requirements. Likely significant adverse effects will
be appropriately mitigated.
Management of subcontractors will be through procurement procedures and an agreed
commitment to the Code of Construction Practice. A designated liaison officer will be in
regular contact with the public, will keep residents informed of all relevant matters, and will
deal with complaints and inquiries. Monitoring of construction activities will be reported back
to the local authority on a regular basis.
The comments stated above are based on information received from other consultees, and
this report is based upon the recommendations stated within these reports. This report is
intended for the use of the project design team in support of the planning application for the
site only.
Preliminary Construction and Demolition Management Plan Page | 17 Dublin Whitewater Course
N17397 patrickparsons.co.uk
Appendix A
Site Compound Plan
Wa
ll
Wall
EBOX
EBOX
EBOX
FHFH
FH
GY
FH
FH FH
Kerb Top
Kerb Top
Kerb Top
Fence
Gate
Bu
ildin
g
Wa
llB
uild
ing
LPLP
RS
SV
SV
SVSV
SV
BDBDBDBDBDBDBDBDBD
LP
LP
LP
LPV
V
V
LP
LP
LP
LP
LP
SV
SV
BD
BD
BD
BDBD
BDBD
BD BDBD
V
SV
SV
SV
SVSV
LP
V
LP
LP
BD
BD
BD
BD
BD
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
V
EV
EV
APX
APX
APX
EV
EV
PAR
PAR
EV
ICIC
IC
MH
MHMH
MHIC
ICIC
IC
ICIC
ICMH
IC
ICICTIC
IC
IC
ICT
IC
IC
IC
IC
IC
IC
IC
IC
MH
MH
IC
IC
ICIC
ICIC
MH
MH
IC
IC
IC
ICT
IC
IC
IC
IC
MH
MH
MH
IC
IC
IC
MH
MH
ICMH
11.60
16.07
4.1
9 4.30
4.5
34.2
5
4.61
CL 4.51CL 4.52
CL 4.54
CL 4.57
CL 4.57CL 4.59
CL 4.74CL 4.74
CL 4.82CL 4.81
CL 4.81
CL 4.83CL 4.81
CL 4.77CL 4.76
CL 4.71
4.52CL 4.53CL 4.47
CL 4.45
CL 4.47
CL 4.48
CL 4.51
CL 4.51
CL 4.84
CL 4.43
CL 4.42
CL 4.76
CL 4.73
CL 4.41
CL 4.43
CL 4.48
CL 4.52
CL 4.36
CL 4.42
CL 4.79CL 4.91
CL 4.92CL 4.87
CL 4.89
CL 4.53
CL 4.49
CL 4.46
CL 4.46
CL 4.47
CL 4.59
CL 4.58
CL 4.56
CL 4.48
4.59
4.50 4.54
4.3
5
4.4
5
4.3
8
4.3
7
4.3
2
4.4
7
4.62
4.69
4.39
4.94
4.71
4.32
4.424.36
4.4
3
4.36
4.42
4.42
4.4
2
4.97
4.4
5
4.49
4.434.42
4.4
2
4.39 4.47
4.44
4.3
9
CL 4.34
CL 4.31
CL 4.31
CL 4.36
CL 4.38
CL 4.41
4.3
6
4.34
CL 4.39
CL 4.39
CL 4.38CL 4.41
GY
GY
Building
Bu
ildin
g
GY
GY
GY
Bridge Deck
Railing
Wall
Footpath
Footpath
GY
FH
FH
FH
GY
GY
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
SV SV
BDBDBDBDBDBD
SV
SV
SV
PolePole
Pole
Pole
LP
BDBDBDBDBD
BDBD
LP
LP
BD
LP
V
LP
LP
BD
IC
MH
MH
MH
MH
MH
IC
MH
MH
MH
MH
IC
MH
MH
IC
MH
MH
IC
IC
MH
IC
ICIC
MH
MH
MH
IC
MH
IC
MH
IC
IC
MH
4.36
4.31
CL 4.40
CL 4.41
CL 4.53
CL 4.45
CL 4.60
CL 4.68
CL 4.40
CL 4.52
CL 4.73
CL 4.62
CL 4.64
CL 4.66
CL 4.68
CL 4.63
CL 4.65
CL 4.63
CL 3.95
3.94
CL 4.08
CL 4.27
CL 4.32
CL 4.11
CL 4.13CL 4.29
4.41
CL 4.43
CL 4.34
4.2
94.29
4.31
4.3
2
4.3
6
CL 4.31
4.18 4.14
4.37
4.40
4.37
4.32
4.24
4.23
4.21
4.21
4.23
4.13
CL 4.18
4.10
CL 4.29
CL 4.32
4.2
4
4.16
4.22
4.27
CL 4.35
4.34
4.30
CL 4.31
CL 4.32
CL 2.19
lock positions
lock positions
Hoarding
Building
Buildin
g
Kerb Top
Kerb Top
Fen
ce
EBOX
FH
EBOXEBOX
FH
WM
Wall
Ga
te
Hoarding
Gate
LP
LP
LP
LP
LP
LP
LP
LP
LP
LPTL
TLTL
BS
TLTL
BDBD
BDBD
BDBDBD
BDBDBDBDBDBDBDBDBDBDBD
BDBD
BD
LP
LP
POST
V
V
EV
IC
IC
IC MH
IC
MHMH
IC IC
IC
IC
IC
IC
IC
IC
MHIC
IC
IC
MH
MHICT
MH
ICICTC
IC
MH
3.34
3.53
3.38
3.2
1
3.38
3.1
0
CL 3.99
CL 3.90
CL 3.79 CL 3.70
CL 3.51
CL 3.45CL 3.45
CL 3.59 CL 3.51
CL 3.57
CL 3.72
CL 3.61
CL 3.36
CL 3.34
CL 3.373.37
CL 3.39CL 3.34
CL 3.38
CL 3.37
CL 3.43
CL 3.51CL 3.50
CL 3.51
CL 3.55CL 3.58
CL 3.55
CL 3.48
RS
RS
RS
Bicycle Vending Machine
POSTRS
Wa
ll
Wall
EBOX
EBOX
EBOX
FHFH
FH
GY
FH
FH FH
Kerb Top
Kerb Top
Kerb Top
Fence
Gate
Bu
ildin
g
Wa
llB
uild
ing
LPLP
RS
SV
SV
SVSV
SV
BDBDBDBDBDBDBDBDBD
LP
LP
LP
LPV
V
V
LP
LP
LP
LP
LP
SV
SV
BD
BD
BD
BDBD
BDBD
BD BDBD
V
SV
SV
SV
SVSV
LP
V
LP
LP
BD
BD
BD
BD
BD
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
V
EV
EV
APX
APX
APX
EV
EV
PAR
PAR
EV
ICIC
IC
MH
MHMH
MHIC
ICIC
IC
ICIC
ICMH
IC
ICICTIC
IC
IC
ICT
IC
IC
IC
IC
IC
IC
IC
IC
MH
MH
IC
IC
ICIC
ICIC
MH
MH
IC
IC
IC
ICT
IC
IC
IC
IC
MH
MH
MH
IC
IC
IC
MH
MH
ICMH
11.60
16.07
4.1
9 4.30
4.5
34.2
5
4.61
CL 4.51CL 4.52
CL 4.54
CL 4.57
CL 4.57CL 4.59
CL 4.74CL 4.74
CL 4.82CL 4.81
CL 4.81
CL 4.83CL 4.81
CL 4.77CL 4.76
CL 4.71
4.52CL 4.53CL 4.47
CL 4.45
CL 4.47
CL 4.48
CL 4.51
CL 4.51
CL 4.84
CL 4.43
CL 4.42
CL 4.76
CL 4.73
CL 4.41
CL 4.43
CL 4.48
CL 4.52
CL 4.36
CL 4.42
CL 4.79CL 4.91
CL 4.92CL 4.87
CL 4.89
CL 4.53
CL 4.49
CL 4.46
CL 4.46
CL 4.47
CL 4.59
CL 4.58
CL 4.56
CL 4.48
4.59
4.50 4.54
4.3
5
4.4
5
4.3
8
4.3
7
4.3
2
4.4
7
4.62
4.69
4.39
4.94
4.71
4.32
4.424.36
4.4
3
4.36
4.42
4.42
4.4
2
4.97
4.4
5
4.49
4.434.42
4.4
2
4.39 4.47
4.44
4.3
9
CL 4.34
CL 4.31
CL 4.31
CL 4.36
CL 4.38
CL 4.41
4.3
6
4.34
CL 4.39
CL 4.39
CL 4.38CL 4.41
GY
GY
Building
Bu
ildin
g
GY
GY
GY
Bridge Deck
Railing
Wall
Footpath
Footpath
GY
FH
FH
FH
GY
GY
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
SV SV
BDBDBDBDBDBD
SV
SV
SV
PolePole
Pole
Pole
LP
BDBDBDBDBD
BDBD
LP
LP
BD
LP
V
LP
LP
BD
IC
MH
MH
MH
MH
MH
IC
MH
MH
MH
MH
IC
MH
MH
IC
MH
MH
IC
IC
MH
IC
ICIC
MH
MH
MH
IC
MH
IC
MH
IC
IC
MH
4.36
4.31
CL 4.40
CL 4.41
CL 4.53
CL 4.45
CL 4.60
CL 4.68
CL 4.40
CL 4.52
CL 4.73
CL 4.62
CL 4.64
CL 4.66
CL 4.68
CL 4.63
CL 4.65
CL 4.63
CL 3.95
3.94
CL 4.08
CL 4.27
CL 4.32
CL 4.11
CL 4.13CL 4.29
4.41
CL 4.43
CL 4.34
4.2
94.29
4.31
4.3
2
4.3
6
CL 4.31
4.18 4.14
4.37
4.40
4.37
4.32
4.24
4.23
4.21
4.21
4.23
4.13
CL 4.18
4.10
CL 4.29
CL 4.32
4.2
4
4.16
4.22
4.27
CL 4.35
4.34
4.30
CL 4.31
CL 4.32
CL 2.19
lock positions
lock positions
Hoarding
Building
Buildin
g
Kerb Top
Kerb Top
Fen
ce
EBOX
FH
EBOXEBOX
FH
WM
Wall
Ga
te
Hoarding
Gate
LP
LP
LP
LP
LP
LP
LP
LP
LP
LPTL
TLTL
BS
TLTL
BDBD
BDBD
BDBDBD
BDBDBDBDBDBDBDBDBDBDBD
BDBD
BD
LP
LP
POST
V
V
EV
IC
IC
IC MH
IC
MHMH
IC IC
IC
IC
IC
IC
IC
IC
MHIC
IC
IC
MH
MHICT
MH
ICICTC
IC
MH
3.34
3.53
3.38
3.2
1
3.38
3.1
0
CL 3.99
CL 3.90
CL 3.79 CL 3.70
CL 3.51
CL 3.45CL 3.45
CL 3.59 CL 3.51
CL 3.57
CL 3.72
CL 3.61
CL 3.36
CL 3.34
CL 3.373.37
CL 3.39CL 3.34
CL 3.38
CL 3.37
CL 3.43
CL 3.51CL 3.50
CL 3.51
CL 3.55CL 3.58
CL 3.55
CL 3.48
RS
RS
RS
Bicycle Vending Machine
POSTRS
Wa
ll
Wall
EBOX
EBOX
EBOX
FHFH
FH
GY
FH
FH FH
Kerb Top
Kerb Top
Kerb Top
Fence
Gate
Bu
ildin
g
Wa
llB
uild
ing
LPLP
RS
SV
SV
SVSV
SV
BDBDBDBDBDBDBDBDBD
LP
LP
LP
LPV
V
V
LP
LP
LP
LP
LP
SV
SV
BD
BD
BD
BDBD
BDBD
BD BDBD
V
SV
SV
SV
SVSV
LP
V
LP
LP
BD
BD
BD
BD
BD
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
V
EV
EV
APX
APX
APX
EV
EV
PAR
PAR
EV
ICIC
IC
MH
MHMH
MHIC
ICIC
IC
ICIC
ICMH
IC
ICICTIC
IC
IC
ICT
IC
IC
IC
IC
IC
IC
IC
IC
MH
MH
IC
IC
ICIC
ICIC
MH
MH
IC
IC
IC
ICT
IC
IC
IC
IC
MH
MH
MH
IC
IC
IC
MH
MH
ICMH
11.60
16.07
4.1
9 4.30
4.5
34.2
5
4.61
CL 4.51CL 4.52
CL 4.54
CL 4.57
CL 4.57CL 4.59
CL 4.74CL 4.74
CL 4.82CL 4.81
CL 4.81
CL 4.83CL 4.81
CL 4.77CL 4.76
CL 4.71
4.52CL 4.53CL 4.47
CL 4.45
CL 4.47
CL 4.48
CL 4.51
CL 4.51
CL 4.84
CL 4.43
CL 4.42
CL 4.76
CL 4.73
CL 4.41
CL 4.43
CL 4.48
CL 4.52
CL 4.36
CL 4.42
CL 4.79CL 4.91
CL 4.92CL 4.87
CL 4.89
CL 4.53
CL 4.49
CL 4.46
CL 4.46
CL 4.47
CL 4.59
CL 4.58
CL 4.56
CL 4.48
4.59
4.50 4.54
4.3
5
4.4
5
4.3
8
4.3
7
4.3
2
4.4
7
4.62
4.69
4.39
4.94
4.71
4.32
4.424.36
4.4
3
4.36
4.42
4.42
4.4
2
4.97
4.4
5
4.49
4.434.42
4.4
2
4.39 4.47
4.44
4.3
9
CL 4.34
CL 4.31
CL 4.31
CL 4.36
CL 4.38
CL 4.41
4.3
6
4.34
CL 4.39
CL 4.39
CL 4.38CL 4.41
GY
GY
Building
Bu
ildin
g
GY
GY
GY
Bridge Deck
Railing
Wall
Footpath
Footpath
GY
FH
FH
FH
GY
GY
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
LP
SV SV
BDBDBDBDBDBD
SV
SV
SV
PolePole
Pole
Pole
LP
BDBDBDBDBD
BDBD
LP
LP
BD
LP
V
LP
LP
BD
IC
MH
MH
MH
MH
MH
IC
MH
MH
MH
MH
IC
MH
MH
IC
MH
MH
IC
IC
MH
IC
ICIC
MH
MH
MH
IC
MH
IC
MH
IC
IC
MH
4.36
4.31
CL 4.40
CL 4.41
CL 4.53
CL 4.45
CL 4.60
CL 4.68
CL 4.40
CL 4.52
CL 4.73
CL 4.62
CL 4.64
CL 4.66
CL 4.68
CL 4.63
CL 4.65
CL 4.63
CL 3.95
3.94
CL 4.08
CL 4.27
CL 4.32
CL 4.11
CL 4.13CL 4.29
4.41
CL 4.43
CL 4.34
4.2
94.29
4.31
4.3
2
4.3
6
CL 4.31
4.18 4.14
4.37
4.40
4.37
4.32
4.24
4.23
4.21
4.21
4.23
4.13
CL 4.18
4.10
CL 4.29
CL 4.32
4.2
4
4.16
4.22
4.27
CL 4.35
4.34
4.30
CL 4.31
CL 4.32
CL 2.19
lock positions
lock positions
Hoarding
Building
Buildin
g
Kerb Top
Kerb Top
Fen
ce
EBOX
FH
EBOXEBOX
FH
WM
Wall
Ga
te
Hoarding
Gate
LP
LP
LP
LP
LP
LP
LP
LP
LP
LPTL
TLTL
BS
TLTL
BDBD
BDBD
BDBDBD
BDBDBDBDBDBDBDBDBDBDBD
BDBD
BD
LP
LP
POST
V
V
EV
IC
IC
IC MH
IC
MHMH
IC IC
IC
IC
IC
IC
IC
IC
MHIC
IC
IC
MH
MHICT
MH
ICICTC
IC
MH
3.34
3.53
3.38
3.2
1
3.38
3.1
0
CL 3.99
CL 3.90
CL 3.79 CL 3.70
CL 3.51
CL 3.45CL 3.45
CL 3.59 CL 3.51
CL 3.57
CL 3.72
CL 3.61
CL 3.36
CL 3.34
CL 3.373.37
CL 3.39CL 3.34
CL 3.38
CL 3.37
CL 3.43
CL 3.51CL 3.50
CL 3.51
CL 3.55CL 3.58
CL 3.55
CL 3.48
RS
RS
RS
Bicycle Vending Machine
POSTRS
LUASBRIDGE
GEORGE'S
DOCK
EAST
QUAYSIDE
WEST
QUAYSIDE
SOUTH
QUAYSIDE
CHQ
STACK B
IFSC HOUSE
LA TOUCHE
HOUSE
MUNCHIES
IFSCSPAR IFSC
JP MORGAN
HOUSE
2 HARBOUR
MASTER
1 HARBOUR
MASTER
GEORGE'S
DOCK
HOUSE
WHITEWATER
COURSE
QUAYSIDE BUILDINGS
SCHERZERBRIDGE
CUSTOM HOUSE QUAY
GEORGES DOCK
SITE COMPOUND FOR
WHITEWATER COURSE
STACK B
CAR PARK
SITE
COMPOUND
FOR DDDA
BUILDING
CURRENT ROUTE TO
STACK B CAR PARK
ASSUMED SITE
GATE LOCATION
RIVER LIFFEY
TRIUMPHAL ARCH TO REMAIN
AND TO BE PROTECTED
EXISTING
COFFERDAM
CRANE TO BE
PROTECTED
WINCH TO BE TEMPORARILY
REMOVED IS ADEQUATE
PROTECTION CAN NOT BE
GUARANTEED THROUGH THE
WORKS
WINCH TO BE PROTECTED
EXISTING
COFFERDAM
PUBLIC
CARPARK
HOTEL
G
G
MH
ENTRANCE LOCKBRIDGE
TIMBER AND IRON LOCK GATES
TO BE CAREFULLY REMOVED AND
STORED FOR RE-USE
ELSEWHERE BY DCC
TREES TO BE
REMOVED
EXISTING BRICK CULVERT IN THIS AREA
TO BE PROTECTED DURING THE WORKS
REFERENCE MUST BE MADE TO HOWLEY HAYES
CONSERVATION REPORT BEFORE COMMENCING WORKS
1.3. LOCATIONS OF ALL EXISTING SERVICES ON-SITE TO
BE CONFIRMED & PROVIDED TO THE ENGINEER
PRIOR TO COMMENCEMENT OF WORKS.
1.4. THIS DRAWING IS TO BE READ IN CONJUNCTION
WITH ALL RELEVANT PATRICK PARSONS LTD
DRAWINGS & SPECIFICATIONS.
Revisions
Rev. Amendments
GENERAL NOTES
1.1. THIS DRAWING IS COPYRIGHT AND SHOULD NOT BE
REPRODUCED IN WHOLE OR PART WITHOUT THE WRITTEN
CONSENT OF PATRICK PARSONS LTD.
1.2 DO NOT SCALE FROM THIS DRAWING.
A3At original size
Date ChkDrg
P2 AMENDED FOLLOWING DESIGN
TEAM COMMENTS
19.02.19 DSH PVS
Drawing No.
Drawn byDate
Scales
Checked by
Client
Status
Drawing
Project
T. +44 (0)191 261 9000
Central Square
Forth Street
Fourth Floor
Newcastle upon Tyne
W. www.patrickparsons.co.uk
Rev.
NE1 3PJ UK
URBAN AGENCY ARCHITECTS
DUBLIN WHITEWATER COURSE
PRELIMINARY SITE COMPOUND
LOCATION PLAN
1:1000
FEB 19DSH PVS
PRELIMINARY
N17397-260 P6
P3 SITE PLAN UPDATED 13.05.19 DH PVS
P4 PROTECTED STRUCTURES SHOWN 28.05.19 DH PVS
P5 ISSUED FOR PART 8 05.06.19 DH PVS
P6 REVISED AND ISSUED FOR PART 8 13.08.19 DH PVS
UK locations:
Newcastle upon Tyne
London
Manchester
Glasgow
Huddersfield
Chester
Birmingham
Guildford