Project Scope Management Based on PMBOK 5th Edition
Waleed El-Naggar, MBA, PMP
https://www.facebook.com/waleed.naggar
![Page 2: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/2.jpg)
Introduction to Project Scope
Plan Scope Management
Collect Requirements
Define Scope
Create WBS
Control Scope
Validate Scope
Agenda
PMP - Project Scope Management 2 https://www.facebook.com/waleed.naggar
![Page 3: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/3.jpg)
Scope refers to all the work involved in creating
the deliverables of the project and the processes
used to create them.
Project scope management includes the
processes required to ensure that the project
includes all the work required, and only the work
required, to complete the project successfully.
What is Project Scope?
PMP - Project Scope Management 3 https://www.facebook.com/waleed.naggar
![Page 4: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/4.jpg)
Product scope: The futures & functions that
characterize the product, service, or result.
Project Scope: The work that needs to be
accomplished to deliver a product, service, or
result with the specified features and
functions.
Product Scope vs. Project Scope
PMP - Project Scope Management 4 https://www.facebook.com/waleed.naggar
![Page 5: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/5.jpg)
PMP - Project Scope Management 5 https://www.facebook.com/waleed.naggar
![Page 6: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/6.jpg)
The process of creating a scope management plan that documents how the project scope will be defined, validated, and controlled.
It provides guidance and direction on scope will be managed.
5.1 Plan Scope Management
PMP - Project Scope Management 6 https://www.facebook.com/waleed.naggar
![Page 7: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/7.jpg)
Plan Scope Management Data Flow
PMP - Project Scope Management 7 https://www.facebook.com/waleed.naggar
![Page 8: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/8.jpg)
1. Project Management Plan: it defines how the
project is executed, monitored, controlled
and closed. It integrates all plan
components.
2. Project Charter
3. Enterprise Environmental Factors
4. Organizational Process Assets
Plan Scope Management: Inputs
PMP - Project Scope Management 8 https://www.facebook.com/waleed.naggar
![Page 9: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/9.jpg)
1. Expert Judgment: knowledgeable and
experiences parties.
2. Meetings.
Plan Scope Management: T & T
PMP - Project Scope Management 9 https://www.facebook.com/waleed.naggar
![Page 10: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/10.jpg)
1. Scope Management Plan. It includes:
Process for preparing a detailed project scope
statement.
Process to enable the creation of WBS
Process to establish how the WBS will be
managed
Define formal acceptance criteria of
deliverables
How change requests will be applied to scope
Plan Scope Management: Output
PMP - Project Scope Management 10 https://www.facebook.com/waleed.naggar
![Page 11: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/11.jpg)
2. Requirements Management Plan: describes how
requirements will be analyzed, documented, and
managed. It includes, but not limited to:
How requirements activities will be planned,
tracked and reported.
Configuration management activities.
Requirements prioritization process.
Product metrics
Traceability structure
Plan Scope Management: Output (2)
PMP - Project Scope Management 11 https://www.facebook.com/waleed.naggar
![Page 12: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/12.jpg)
Which is the BEST description of project scope?
A. All of the features and deliverables your
project will deliver
B. All of the products your project will make
C. All of the people involved in your project
D. All of the work you will do to build the
project deliverables
Quiz
PMP - Project Scope Management 12 https://www.facebook.com/waleed.naggar
![Page 13: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/13.jpg)
The process of determining, documenting and managing stakeholder needs to meet project objectives.
The key benefit is to provide the basis for defining and managing project scope.
Requirements includes the quantified and documented needs and expectations of the sponsor, customer, and other stakeholders.
Requirement must be analyzed and recorded in a clear and detailed way to be measured.
5.2 Collect requirements
PMP - Project Scope Management 13 https://www.facebook.com/waleed.naggar
![Page 14: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/14.jpg)
Requirements can be grouped into classifications including:
Business requirements, describe the high-level needs of
the organization as a whole.
Stakeholder requirements, describe needs of a
stakeholder or stakeholder group.
Solution requirements, describe features, functions and
characteristics of the product, service, or results.
Transition requirements, describe temporary capabilities
such as data conversion & training needs.
5.2 Collect requirements (2)
PMP - Project Scope Management 14 https://www.facebook.com/waleed.naggar
![Page 15: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/15.jpg)
PMP - Project Scope Management 15 https://www.facebook.com/waleed.naggar
Co
llec
t R
equ
irem
ents
Da
ta F
low
![Page 16: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/16.jpg)
1. Project Scope Management Plan
2. Requirements Management Plan
3. Stakeholder Management Plan
4. Project Charter
5. Stakeholder Register
Collect Requirements: Inputs
PMP - Project Scope Management 16 https://www.facebook.com/waleed.naggar
![Page 17: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/17.jpg)
1. Interviews: meeting the stakeholders to ask
prepared and spontaneous question &
recording the responses.
Collect Requirements: T & T (1)
PMP - Project Scope Management 17 https://www.facebook.com/waleed.naggar
![Page 18: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/18.jpg)
2. Focus groups: bring together stakeholders
and subject matter experts to learn about
their expectations and attitudes about a
proposed product,
service or result.
Collect Requirements: T & T (1)
PMP - Project Scope Management 18 https://www.facebook.com/waleed.naggar
![Page 19: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/19.jpg)
3. Facilitated Workshops: Focused session with
key cross-functional stakeholders to define
product requirements.
4. Group Creativity Techniques:
Brainstorming
Nominal Group
Idea/Mind Mapping
Affinity Diagram
Multi-criteria decision analysis
Collect Requirements: T & T (2)
PMP - Project Scope Management 19 https://www.facebook.com/waleed.naggar
![Page 20: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/20.jpg)
Mind Map
PMP - Project Scope Management 20 https://www.facebook.com/waleed.naggar
![Page 21: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/21.jpg)
Affinity Diagram
PMP - Project Scope Management 21 https://www.facebook.com/waleed.naggar
![Page 22: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/22.jpg)
5. Group Decision Making Techniques
Unanimity
Majority
Plurality
Dictatorship
6. Questionnaire and Surveys
7. Observations
8. Prototypes
Collect Requirements: T & T (3)
PMP - Project Scope Management 22 https://www.facebook.com/waleed.naggar
![Page 23: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/23.jpg)
9. Benchmarking
10.Context Diagrams
11. Document Analysis
Collect Requirements: T & T (4)
PMP - Project Scope Management 23 https://www.facebook.com/waleed.naggar
![Page 24: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/24.jpg)
1. Requirements Document
Business Requirements
Stakeholder requirements
Solution requirements
Project requirements
Transition requirements
2. Requirements Traceability Matrix
Collect Requirements: Outputs
PMP - Project Scope Management 24 https://www.facebook.com/waleed.naggar
![Page 25: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/25.jpg)
Sample Requirements Traceability Matrix
PMP - Project Scope Management 25 https://www.facebook.com/waleed.naggar
![Page 26: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/26.jpg)
The best tool in collecting requirements for a
cross-functional project is:
A. Facilitated Workshops
B. Interviews
C. Surveys
D. Brainstorming
Quiz
PMP - Project Scope Management 26 https://www.facebook.com/waleed.naggar
![Page 27: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/27.jpg)
The process of developing a detailed description
of the project and product.
5.3 Define Scope
PMP - Project Scope Management 27 https://www.facebook.com/waleed.naggar
![Page 28: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/28.jpg)
Define Scope Data Flow
PMP - Project Scope Management 28 https://www.facebook.com/waleed.naggar
![Page 29: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/29.jpg)
1. Scope Management Plan
2. Project charter
3. Requirements Document
4. Organizational Process Assets
Procedures & Templates
Historical Data
Lessons learned from old Projects
Define Scope: Inputs
PMP - Project Scope Management 29 https://www.facebook.com/waleed.naggar
![Page 30: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/30.jpg)
1. Expert Judgment
2. Product Analysis
3. Alternatives Identification
4. Facilitated workshops
Define Scope: T & T
PMP - Project Scope Management 30 https://www.facebook.com/waleed.naggar
![Page 31: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/31.jpg)
1. Scope Statement: describes project’s
deliverables and the work required to create
those deliverables. It includes
Product scope description
Deliverables’ Acceptance Criteria
Project Deliverables
Project Exclusion
Project Assumptions
Constraints
Define Scope: Outputs (1)
PMP - Project Scope Management 31 https://www.facebook.com/waleed.naggar
![Page 32: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/32.jpg)
PMP - Project Scope Management 32 https://www.facebook.com/waleed.naggar
Elements of
Project
Charter and
Scope
Statement
![Page 33: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/33.jpg)
2. Project Documents Updates: may include,
but not limited to:
Stakeholder register
Requirements Documents
Requirements Traceability Matrix
Define Scope: Outputs (2)
PMP - Project Scope Management 33 https://www.facebook.com/waleed.naggar
![Page 34: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/34.jpg)
Why would you consider the scope statement so important
in your project management methodology?
A. Mandatory to consult the plan before accepting change.
B. Project managers must document any changes before
approving or declining them.
C. The project scope serves as a reference for all future
project decisions.
D. The scope statement is the base of WBS creation
Quiz
PMP - Project Scope Management 34 https://www.facebook.com/waleed.naggar
![Page 35: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/35.jpg)
Subdividing the project deliverables and
project work into smaller and more
manageable components.
The work breakdown structure is a
deliverable-oriented hierarchical
decomposition of project work.
5.4 Create WBS
PMP - Project Scope Management 35 https://www.facebook.com/waleed.naggar
![Page 36: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/36.jpg)
Create WBS Data Flow
PMP - Project Scope Management 36 https://www.facebook.com/waleed.naggar
![Page 37: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/37.jpg)
Sample WBS
PMP - Project Scope Management 37 https://www.facebook.com/waleed.naggar
![Page 38: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/38.jpg)
Sample WBS
PMP - Project Scope Management 38 https://www.facebook.com/waleed.naggar
![Page 39: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/39.jpg)
Sample
WBS
PMP - Project Scope Management 39 https://www.facebook.com/waleed.naggar
![Page 40: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/40.jpg)
1. Scope Management Plan
2. Project Scope Statement
3. Requirements Document
4. Enterprise Environmental Factors
5. Organizational Process Assets
Create WBS: Inputs
PMP - Project Scope Management 40 https://www.facebook.com/waleed.naggar
![Page 41: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/41.jpg)
1. Decomposition: The subdivision of project
deliverables into smaller, more manageable
components. The work package level is the
lowest level in the WBS, and is the point at
which the cost an activity durations can be
reliably estimated and managed. The level of
detail for work packages will vary with the size
and complexity of the project.
2. Expert Judgment
Create WBS: T & T
PMP - Project Scope Management 41 https://www.facebook.com/waleed.naggar
![Page 42: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/42.jpg)
1. Scope Baseline
Project Scope Statement
WBS
WBS Dictionary
2. Project Documents updates
Create WBS: Outputs
PMP - Project Scope Management 42 https://www.facebook.com/waleed.naggar
![Page 43: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/43.jpg)
WBS Dictionary may include (but not limited to) Code of Account Identifier
Description of work
Assumptions and Constraints
Schedule Milestone
Resource required
Cost Estimate
Acceptance criteria
Quality Requirements
Create WBS: Outputs (2)
PMP - Project Scope Management 43 https://www.facebook.com/waleed.naggar
![Page 44: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/44.jpg)
Control
Accounts,
Work
Packages
and
Activities
PMP - Project Scope Management 44 https://www.facebook.com/waleed.naggar
![Page 45: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/45.jpg)
A work breakdown structure numbering system allows
project staff to:
A. Systematically estimate costs of work breakdown
structure elements.
B. Provide project justification
C. Identify the level at which individual elements are
found
D. Use it in project management software
Quiz
PMP - Project Scope Management 45 https://www.facebook.com/waleed.naggar
![Page 46: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/46.jpg)
Which of the following documents contain detailed
descriptions of work packages?
A. Work breakdown structure (WBS) dictionary
B. Activity list
C. Preliminary project scope statement
D. Project scope management plan
Quiz
PMP - Project Scope Management 46 https://www.facebook.com/waleed.naggar
![Page 47: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/47.jpg)
The work breakdown structure can best be thought of
as an effective aid for ___________ communication
A. Team
B. PMO
C. Customer
D. Stakeholders
Quiz
PMP - Project Scope Management 47 https://www.facebook.com/waleed.naggar
![Page 48: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/48.jpg)
Formalizing acceptance of the completed
project deliverables.
Includes reviewing deliverables with the client
and obtaining formal acceptance of deliverables.
Scope verification is concerned with acceptance
of deliverables while quality control is
concerned with correctness of the deliverables
and meeting quality requirements.
5.5 Validate Scope
PMP - Project Scope Management 48 https://www.facebook.com/waleed.naggar
![Page 49: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/49.jpg)
Validate Scope: Data Flow Diagram
PMP - Project Scope Management 49 https://www.facebook.com/waleed.naggar
![Page 50: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/50.jpg)
1. Project Management Plan
2. Requirements Documentation
3. Requirements Traceability Matrix
4. Validated Deliverables
5. Work Performance Data
Validate Scope: Inputs
PMP - Project Scope Management 50 https://www.facebook.com/waleed.naggar
![Page 51: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/51.jpg)
1. Inspection: measuring, examining, and
validating to determine whether work and
deliverables meet requirements and product
acceptance criteria. Inspections may be called
reviews, audits, and walkthroughs.
2. Group Decision Making Techniques
Validate Scope: T & T
PMP - Project Scope Management 51 https://www.facebook.com/waleed.naggar
![Page 52: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/52.jpg)
1. Accepted Deliverables
2. Change Requests
3. Work Performance Information
4. Project Document Updates
Validate Scope: Outputs
PMP - Project Scope Management 52 https://www.facebook.com/waleed.naggar
![Page 53: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/53.jpg)
Which of the following is an output of scope
verification?
A. WBS template
B. Rework
C. Formal acceptance
D. SOW acceptance
Quiz
PMP - Project Scope Management 53 https://www.facebook.com/waleed.naggar
![Page 54: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/54.jpg)
Monitoring the status of the project &
products scope
Managing changes to scope baseline
Ensure all requested changes and
recommended corrective or preventive actions
are processed through the “Perform Integrated
Change Control” process.
Uncontrolled changes are often referred to as
project scope creep.
5.6 Control Scope
PMP - Project Scope Management 54 https://www.facebook.com/waleed.naggar
![Page 55: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/55.jpg)
Control
Scope
Data
Flow
PMP - Project Scope Management 55 https://www.facebook.com/waleed.naggar
![Page 56: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/56.jpg)
1. Project Management Plan
Scope baseline
Scope management plan
Change management plan
Configuration management plan
Requirements management plan
2. Requirements Documentation
Control Scope: Inputs (1)
PMP - Project Scope Management 56 https://www.facebook.com/waleed.naggar
![Page 57: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/57.jpg)
3. Requirements Traceability Matrix
4. Work Performance Data
5. Organizational Process Assets
Control Scope: Inputs (2)
PMP - Project Scope Management 57 https://www.facebook.com/waleed.naggar
![Page 58: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/58.jpg)
1. Variance Analysis
Analyze performance measurements to assess
the variation from the baseline scope. Analysis
should determine the cause and degree of
variance.
Control Scope: T & T
PMP - Project Scope Management 58 https://www.facebook.com/waleed.naggar
![Page 59: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/59.jpg)
1. Work Performance Information
2. Change Requests
3. Project Management Plan Updates
4. Project Document Updates
5. Organizational Process Asset Updates
Control Scope: Outputs
PMP - Project Scope Management 59 https://www.facebook.com/waleed.naggar
![Page 60: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/60.jpg)
During a project team meeting, a team member suggests
an enhancement to the scope that is beyond the scope of
the project charter. The project manager points out that
the team needs to concentrate on completing all the work
and only the work required. This is an example of:
A. Change management process.
B. scope management.
C. quality analysis.
D. scope decomposition.
Quiz
PMP - Project Scope Management 60 https://www.facebook.com/waleed.naggar
![Page 61: PMP 02 Project Scope Management - PMBOK 5th Edition](https://reader035.fdocuments.net/reader035/viewer/2022081719/5442970bb1af9f410a8b46dd/html5/thumbnails/61.jpg)
Which of the following is the KEY attribute of scope
validation?
A. More complete project scope management plan
B. Customer acceptance of project deliverables
C. Improved schedule estimates
D. An improved project management information
system.
Quiz