PMI Annual Meeting 2016 REZZATO-DEVNYA 25-11-2015 rev5
-
Upload
matteo-maconi-pmp -
Category
Documents
-
view
250 -
download
0
Transcript of PMI Annual Meeting 2016 REZZATO-DEVNYA 25-11-2015 rev5
PMI EMEA Congress 2011 - Session PRJ11
Generating Opportunities from ConstraintsEthics for Project Success
Michela Ruffa, PMP© - Director at Large – PMI © Northern Italy ChapterStefano Setti, PMP© - Director at Large – PMI © Northern Italy ChapterRezzato and Devnya Projects
Comparison of two success stories with a different Project Management approach
Matteo Maconi PMP® – Direttore Generale CTG Spa (Italcementi Group)
Milano, 29 gennaio 2016
Venti di Futurothe PMI-NIC 20th Anniversary
Assemblea dei Soci 2016
2
Italcementi Group at a glance
The world’s fifth largest cement producer
A worldwide presence in 22 countries
An overall staff of 18,000 people
A consolidated production capacity of approximately 61 million tons
2014 annual sales exceeding 4.1 billion Euro
The first cement company to be listed on the Italian Stock Exchange since 1925
Over 150 years-old successful business strategy implemented by a family-driven company at its fifth
generation
Italcementi Group subsidiary organized into 2
main Divisions
CTG – Centro Tecnico di Gruppo
3
Research&
Development
Technical Operations
Strategic R&D projects: materials, products, solutions,
applications and technologies; environmental impact reduction
and support to the Sustainable Development action plan.
Monitoring of operating plants performance
Operational support and technical assistance to Group Subsidiaries
Management of strategic industrial Investments
4
CONTENTS
Project Context
Project Execution
Conclusions
Rezzato and Devnya ProjectsComparison of two success stories with a different Project Management approach
5
Similar Context for Both the Projects Brownfield projects
Revamping of existing obsolete production lines with marginal capacity increase
Congested areas and complex tie-in with the existing facilities
6
Similar Context for Both the Projects Brownfield projects
Revamping of existing obsolete production lines with marginal capacity increase
Congested areas and complex tie-in with the existing facilities
Similar strategic background Raw material availability Strategic position Reduction of variable costs – readjustment of industrial network substantial reduction of the actual environmental footprint
7
Similar Context for Both the Projects Brownfield projects
Revamping of existing obsolete production lines with marginal capacity increase
Congested areas and complex tie-in with the existing facilities Similar strategic background
Raw material availability Strategic position Reduction of variable costs – readjustment of industrial network substantial reduction of the actual environmental footprint
Complex relation with local community and local authorities Many local constraints superimposed to both the projects Stakeholders management
REZZATO
DEVNYA
8
Similar Context for Both the Projects Brownfield projects
Revamping of existing obsolete production lines with marginal capacity increase
Congested areas and complex tie-in with the existing facilities Similar strategic background
Raw material availability Strategic position Reduction of variable costs – readjustment of industrial network substantial reduction of the actual environmental footprint
Complex relation with local community and local authorities Many local constraints superimposed to both the projects Stakeholders management
Stringent Owner requirements Minimization of the total investment cost within a given target Minimization of production cost Utilization of innovative technical solutions Respect of present BAT being ready for future SD evolution
9
CONTENTS
Project Context
Project Execution
Conclusions
1
REZZATO
Direct Execution with central interface coordination by ITALCEMENTI/CTG
35 main purchase orders with 5 major packages covering 90% of the investment: Detailed Design
[one multidisciplinary Italian contractor] Technology Equipment
[one European supplier selected through competitive bid]
Main Control System Medium Voltage Distribution Construction
[one Italian General Contractor covering the whole construction scope]
EUROPEAN MAIN CONTENT [made in Italy centered]
DEVNYA
Full Scope EPC Contract on Lump Sum Turn Key basis assigned through competitive bid
ITALCEMENTI/CTG Project Management and Supervision
CHINESE MAIN CONTENT
Project Execution Strategy
10
1
REZZATO
Direct control over the planning and execution
Higher flexibility/shorter decision process
Easier communications
DEVNYA
Risk transfer on EPC Contractor Lighter Project Management
Organization Single reference for all Project
aspects with integral responsibility
Higher risk of cost overrun Complex coordination of interfaces Huge organization effort and higher
Project Management cost Complex contract management
Very complex communication (language + cultural background)
Integration of Chinese contractor with local reality (contractors and regulations)
Reduced control and visibility over decisional process
Strength/weakness of the two approaches
11
REZZATO
Common reference on EU standards
DEVNYA
Single point of responsibility on the EPC contractor
Complex coordination of several subcontractors
Management of congested areas (due to local lay-out constraints) and concurrent operation of existing plant
Communication Gap between Chinese and European
standards Difficult interface with local
bureaucracy Big effort from owner Project
Management team to ensure proper working conditions
12
Health, Safety and Environment
REZZATO
Direct control over the engineering execution
Familiarity with EU standards and local norms
Easier inspection and quality control
DEVNYA
Single point of responsibility on the EPC contractor
Owner direct responsibility in front of the Construction Contractor
Complex interface management between vendors and construction
Very complex communication due to different techincal approach and geographical distance
Difficult and time consuming management of the local content (“bulgarization” of the design through local engineering companies)
Limited control on expediting and inspection of the material and quality control
13
Engineering and Supply
REZZATO
General Contractor representing a single point of responsibility for all the construction disciplines (integrated approach)
Strict control on planning and progress and wider room for owner direct intervention
DEVNYA
Experienced Chinese manpower installing “their own” equipment (high productivity)
Integrated management and responsibility over the supply chain
Complex contract management Owner direct responsibility to grant
the availability of engineering and equipment
Lack of “cement experienced” subcontractors (learning curve)
Limited possibility to import Chinese manpower
Complex management of local subcontractors
Difficult integration of Chinese manpower with local sub-contractors (language and cultural background gap)
14
Construction
Some Snapshots from the Jobsites…
15
REZZATO
16
DEVNYASome Snapshots from the Jobsites…
1
RAW GRINDING + BURNING LINE COST
NOMINAL ANNUAL CLINKER PRODUCTION
COMPARISON OF UNITARY RATES FOR MAIN COST VOICESDEVNYA REZZATO
[ratio vs. DEVNYA]
Unit Rates for Civil Construction (Euro/m3 materials + manpower)
557 1305[2,34]
Unit rates for equipment (Euro/kg) 4,6 7,1[1,54]
Unit rates for structural steel(Euro/kg)
1,6 2,7[1,69]
Labor Cost “all in” (Euro/MHR) 19,5 50,4[2,58]
Erection Productivity (hours/ton steel) 74,3 41,7[0,56]
Erection unit rate(Euro/kg steel)
1,4 2,1[1,5]
DEVNYA = 82,2 €/Ton
REZZATO = 111,8 €/Ton [1,36 x Devnya]
Costs
17
1
REZZATO PROJECT COMPLETED IN LINE WITH THE BASELINE SCHEDULE [start up 25 months from equipment purchase order]
DEVNYA PROJECT CUMULATED 5 MONTHS OVERALL DELAY AGAINST THE CONTRACTUAL BASELINE [baseline = 26 months from Contract – Actual duration = 31 months from Contract signature]
Difficult start up - excellent respect of the updated forecast since May 2013
Substantial respect of the baseline with few minor adjustments along the execution – progress gap in the close out mainly due to postponement of ancillary activities after start up
18
Time
REZZATO
NEED OF VERY ACCURATE BASIC DESIGN AND MANAGEMENT TOOLS: Positive return on the approach provided that a very accurate and detailed preparation and planning is carried out before the start of the execution phase
Packaged approach is a winning strategy BUT maximum attention to the RISK OF FORCING SUPPLIERS OUT OF THEIR “USUAL” SCOPE LIMITS
DEVNYA
Ensure the IN DEEP UNDERSTANDING OF THE PROJECT CONTEXT by the EPC contractor through the definition of pre-agreements with local contractors
INVEST IN COMMUNICATION SKILLS through cultural mediators able to facilitate the mutual understanding
Detailed verification and joint review of the project schedule before the signature of the contract to ensure ADEQUATE CONTROL TOOLS ARE IN PLACE SINCE DAY 1
19
Lessons learnt
20
CONTENTS
Project Context
Project Execution
Conclusions
2121
Conclusions The correct choice of the purchasing and execution strategy in addition
to a very strict control of engineering, construction and commissioning is fundamental to respect time and costs
The projects of the new line in Rezzato and Devnya represent a strong effort to arrange technological innovation, sustainability and project execution proceeding at the same pace for the success of the initiative
The Project context plays a key role in the definition of the Project Execution Strategy
Adoption of Chinese contractors requires an additional Project Management effort and wider time contingencies usually not properly taken into account in the selection process and cost comparison
Virtuous integration of Chinese and European content is possible provided that adequate preparation work is carried out
For innovative technology applications and complex revamping/brownfield works, European/Italian suppliers/contractors do have a significant advantage vs. low cost countries competitors