Planning & Designing for Green Infrastructure

37
Planning & Designing for Green Infrastructure: Implementation in the Public Right-of-way

Transcript of Planning & Designing for Green Infrastructure

Page 1: Planning & Designing for Green Infrastructure

Planning & Designing for Green Infrastructure:

Implementation in the Public Right-of-way

Page 2: Planning & Designing for Green Infrastructure

Presenters

Terra Ishee, Acting Director, Pedestrian Projects Group, NYC DOT Rosanna Collars, Urban Planner & Designer, Arup

SENY Conference 2015 2 NYC DOT | Arup

Page 3: Planning & Designing for Green Infrastructure

Learning Objectives

Understanding how NYC DOT’s policy and planning measures can be used to accommodate pedestrian needs and achieve safety benefits within the framework of NYC DEP’s green infrastructure implementation goals.

SENY Conference 2015 3 NYC DOT | Arup

Page 4: Planning & Designing for Green Infrastructure

Agenda

1.  Overview: NYC DEP GI Program 2.  Program History 3.  Concept to Construction 4.  Green Infrastructure: Siting & ROWB Design 5.  Designing Stormwater Greenstreets 6.  Key Questions

SENY Conference 2015 4 NYC DOT | Arup

Page 5: Planning & Designing for Green Infrastructure

NYC Green Infrastructure Plan

GI Plan will achieve better water quality and sustainability benefits than all-Grey strategy by: •  Reducing CSO volume by addition

3.8 billion gallons per year •  Capturing rainfall from 10% of

impervious surfaces through GI and other source controls

•  Providing substantial, quantifiable sustainability benefits

•  Cooling the city •  Reducing energy use •  Increasing property values •  Cleaning the air

SENY Conference 2015 5 NYC DOT | Arup

Page 6: Planning & Designing for Green Infrastructure

Right-of-way bioswales (ROWB): Planted into sidewalk with curb cuts to let water in. Stormwater greenstreets (SGS): Planted in roadbed, change street geometry

SENY Conference 2015 6 NYC DOT | Arup

GI in NYC

Page 7: Planning & Designing for Green Infrastructure

Program History

SENY Conference 2015 7 NYC DOT | Arup

Page 8: Planning & Designing for Green Infrastructure

Program History

SENY Conference 2015 8 NYC DOT | Arup

DOT Review of GI •  Before 2012: “Greenstreets”

•  Dept. of Parks & Rec in lead •  Approx. 20 projects per year •  Various funding sources

•  2012-2013: 1st Phase ROWBs •  DPR managed design/

construction •  Approx. 20 projects per year •  DEP funding

Page 9: Planning & Designing for Green Infrastructure

Program History

SENY Conference 2015 9 NYC DOT | Arup

DOT Review of GI •  2014-present, Full Program

•  DEP in lead, with up to 10 consultants managing design

•  Approx. 1,000 projects per year •  DEP funding

Page 10: Planning & Designing for Green Infrastructure

SENY Conference 2015 10 NYC DOT | Arup

Concept to Construction

Page 11: Planning & Designing for Green Infrastructure

Concept to Construction

SENY Conference 2015 11 NYC DOT | Arup

Agency Interaction •  NYC DEP

•  Manage contract areas •  Decide how many/where •  Prepare design/construction

documents •  Maintain GI

•  NYC DOT •  Provide guidance on siting/design •  Review/approve locations

•  NYC DPR •  Provide input on trees/plantings

Page 12: Planning & Designing for Green Infrastructure

SENY Conference 2015 12 NYC DOT | Arup

Original NYC DEP Green Infrastructure Standards

Page 13: Planning & Designing for Green Infrastructure

SENY Conference 2015 13 NYC DOT | Arup

Walkthrough Design Approval Build Maintain

DEP uses: -DOT GI Siting Guidelines

DEP uses: -DOT GI Submission Requirements -DOT GI Design Guidelines

DOT reviews at 10%, 60%, 90%, and 100%

Page 14: Planning & Designing for Green Infrastructure

SENY Conference 2015 14 NYC DOT | Arup

Page 15: Planning & Designing for Green Infrastructure

SENY Conference 2015 15 NYC DOT | Arup

Walkthrough Design Approval Build Maintain

DEP uses: -DOT GI Siting Guidelines

DEP uses: -DOT GI Submission Requirements -DOT GI Design Guidelines

DOT units review at 10%, 60%, 90%, and 100%

Borough Commissioner Offices Capital Program Management Bridges Street Furniture Wayfinding Accessibility Programs Sidewalk Inspection & Management Roadway Repair & Maintenance Traffic & Planning Parking Public Spaces & Urban Design Project Development Pedestrian & Bicycle Programs RIS Street Lighting Signals Operations Geometric Design Borough Engineering OCMC / Permits

Page 16: Planning & Designing for Green Infrastructure

GI: Siting & ROWB Design

SENY Conference 2015 16 NYC DOT | Arup

Page 17: Planning & Designing for Green Infrastructure

NYC DEP GI Siting Process

•  Contract area based on CSO outflow point

SENY Conference 2015 17 NYC DOT | Arup

NYC DEP Office of Green Infrastructure, Area-wide Contracts

Page 18: Planning & Designing for Green Infrastructure

NYC DEP GI Siting Process

•  Stormwater capture needs based on block-level analysis

SENY Conference 2015 18 NYC DOT | Arup

Tributary Drainage Area (TDA) analysis

Page 19: Planning & Designing for Green Infrastructure

NYC DOT Siting Guidelines

•  Comprehensive field guidelines for walkthrough team

•  First distributed in 2011/2012 •  Re-issued many times

•  Iterative, learning process for agencies and units involved

•  Balance of technical requirements, engineering analysis and existing context

SENY Conference 2015 19 NYC DOT | Arup

NYC DOT Green Infrastructure Siting Guidelines

Page 20: Planning & Designing for Green Infrastructure

SENY Conference 2015 20 NYC DOT | Arup

Key Issues in R.O.W. •  Pedestrian volumes

•  Dictated by land use: residential, commercial, industrial

•  Available sidewalk (before and after installation)

•  Pedestrian desire lines Requirements for Implementation

•  Adequate room for mobility •  Access to street

Siting & Design: Pedestrian Mobility

Low volume residential

High volume commercial

Low volume industrial

Page 21: Planning & Designing for Green Infrastructure

SENY Conference 2015 21 NYC DOT | Arup

Siting & Design: Pedestrian Mobility

NYC DOT Green Infrastructure Siting Guidelines

Constructed ROWB, Queens

Vertical element

Pedestrian clear path

Required pedestrian path

Page 22: Planning & Designing for Green Infrastructure

SENY Conference 2015 22 NYC DOT | Arup

Multi-agency walkthrough

Siting & Design: Pedestrian Mobility

Wide existing tree line

Total sidewalk width Pedestrian clear

path

Vertical element

Page 23: Planning & Designing for Green Infrastructure

SENY Conference 2015 23 NYC DOT | Arup

Siting & Design: Access to Curb

NYC DOT GI Siting Guidelines

Key Issues •  Loading & drop off •  Parking •  Garbage pick up

Page 24: Planning & Designing for Green Infrastructure

Pedestrian path provides path for parking, loading,

and garbage

SENY Conference 2015 24 NYC DOT | Arup

Sample page, NYC DOT Green Infrastructure Design Guidelines

Constructed ROWB, Queens

Allows for parking along

curb

Access to entrances, vaults

and gates

Siting & Design: Access to Curb

Page 25: Planning & Designing for Green Infrastructure

SENY Conference 2015 25 NYC DOT | Arup

Siting & Design: Visibility

Key Issues •  Maximum height of plantings •  Tree distance from

intersection

Plant heights should not

obstruct visibility

Trees should not obstruct visibility

Page 26: Planning & Designing for Green Infrastructure

Designing Stormwater Greenstreets

SENY Conference 2015 26 NYC DOT | Arup

Page 27: Planning & Designing for Green Infrastructure

Designing Stormwater Greenstreets

SENY Conference 2015 27 NYC DOT | Arup

SGS Background •  Sited where ROWBs do not fit in

sidewalk Key Considerations:

•  Curb alignments •  Signs/object markers/markings •  FDNY requirements •  Pedestrian facilities/mobility •  Car turning movements •  Accessibility •  Plant heights •  Tree locations

Page 28: Planning & Designing for Green Infrastructure

SENY Conference 2015 28 NYC DOT | Arup

NYC DOT Green Infrastructure Design Guidelines

Required minimum

projection into roadbed

Tree guard

Correct curb radius

Page 29: Planning & Designing for Green Infrastructure

GI: Potential for Co-Benefits

SENY Conference 2015 29 NYC DOT | Arup

•  Vision zero objectives •  Neighborhood beautification •  Improving pedestrian access

Page 30: Planning & Designing for Green Infrastructure

DOT-Pedestrian Projects Group Goals

SENY Conference 2015 30 NYC DOT | Arup

Street Improvement Goals •  Shorten pedestrian crossing

distances •  Align pedestrian access with

the “desire line” •  Reduce pedestrian/vehicle

conflicts

Co-benefits: Provides shorter ped crossing distance and space

for GI

Page 31: Planning & Designing for Green Infrastructure

SENY Conference 2015 31 NYC DOT | Arup

*Preferred option

SGS Designs (contingent upon catch basin & street conditions)

Page 32: Planning & Designing for Green Infrastructure

SENY Conference 2015 32 NYC DOT | Arup

Preferred option Alternative

T-intersection designs

Page 33: Planning & Designing for Green Infrastructure

SENY Conference 2015 33 NYC DOT | Arup

Existing 102nd Street and 63rd Road

SGS – Alternative Designs

Page 34: Planning & Designing for Green Infrastructure

SENY Conference 2015 34 NYC DOT | Arup

Proposed 102nd Street and 63rd Road

SGS – Alternative Designs

Page 35: Planning & Designing for Green Infrastructure

Questions

1.  What is the first step in analyzing locations for green infrastructure in NYC?

2.  What are two pedestrian requirements for GI implementation in the public right-of-way?

3.  What are the two concerns for visibility?

SENY Conference 2015 35 NYC DOT | Arup

Page 36: Planning & Designing for Green Infrastructure

Answers

1.  What is the first step in analyzing locations for green infrastructure in NYC? 1.  Tributary drainage analysis

2.  What are two pedestrian requirements for GI implementation in the public right-of-way? 1.  Adequate room for mobility 2.  Access to the street

3.  What are the two concerns for visibility? 1.  Plant height 2.  Distance of trees to intersections

SENY Conference 2015 36 NYC DOT | Arup

Page 37: Planning & Designing for Green Infrastructure

SENY Conference 2015 37 NYC DOT | Arup

Thank you!