PES MD P001_A Draughting Procedure

download PES MD P001_A Draughting Procedure

of 45

description

Draughting Procedure

Transcript of PES MD P001_A Draughting Procedure

  • 2010, ICEPRONAV Form Code PES-AD-T001 Rev. A / May 2010 File name: PES-MD-P001_A - Draughting Procedure.doc

    PROJECT ENGINEERING SYSTEM

    A 2010-10-01 First Issue ABto PNcl PNcl

    Rev. Date Description Performed Checked Approved

    Client:

    ICEPRONAV SA

    Title:

    DRAUGHTING PROCEDURE

    1921 Circular Road, Douglas, Phone: +44-(0)-1624-623-190 Isle of Man, IM11AF British Isles Fax: +44-(0)-1624-628-297 Additional contact information: Phone:+40-(0)-236-415-965 Web: www.icedesign.info Fax: +40-(0)-236-417-836

    Size:

    A4 Project No:

    PES Rev:

    A

    Document No: PES-MD-P001

    Sheet: 1 of 45

    The information and data contained herein are proprietary to International Contract Engineering Ltd and are not to be copied, reproduced, duplicated or disclosed to others, in whole or in part, without prior written consent of International Contract Engineering Ltd.

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 2 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    REVISION HISTORY

    REVISION REVISED CHAPTERS REVISION DESCRIPTION REASON FOR REVISION

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 3 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    TABLE OF CONTENTS

    1 PURPOSE .............................................................................................................................. 5

    2 SCOPE ................................................................................................................................... 5

    3 ABBREVIATIONS .................................................................................................................. 5

    4 REFERENCES ........................................................................................................................ 6

    5 PROCEDURE DESCRIPTION ................................................................................................ 7

    5.1 GENERAL ......................................................................................................................... 7

    5.1.1 Drawing layout ....................................................................................................... 8

    5.1.2 Sheet sizes ............................................................................................................. 9

    5.1.3 Font name and sizes ............................................................................................ 10

    5.2 ADMINISTRATIVE PART LAYOUT ................................................................................. 11

    5.2.1 Property stamp block .......................................................................................... 12

    5.2.2 Title block ............................................................................................................. 13

    5.2.3 Revision status list .............................................................................................. 15

    5.2.4 Sticker / Stamp area ............................................................................................. 16

    5.2.5 Holds block .......................................................................................................... 17

    5.2.6 Notes .................................................................................................................... 18

    5.2.7 List of reference documents ............................................................................... 19

    5.2.8 Key plan ................................................................................................................ 20

    5.2.9 List of materials ................................................................................................... 21

    5.3 DRAWING PART LAYOUT .............................................................................................. 22

    5.3.1 Creating a drawing in Model Space / Paper Space ............................................ 23

    5.3.2 Projection method ............................................................................................... 25

    5.3.3 Scale method ....................................................................................................... 27

    5.3.4 Titles ..................................................................................................................... 28

    5.3.5 Text in Drawing Part Layout ................................................................................ 29

    5.3.6 Dimensions .......................................................................................................... 30

    5.3.7 Sections, Views and Details ................................................................................ 31

    5.3.8 Item Number ......................................................................................................... 32

    5.3.9 Holds indication ................................................................................................... 33

    5.3.10 Revision Indication .............................................................................................. 34

    5.4 CAD DRAWING SPECIFICS ........................................................................................... 35

    5.4.1 Layer arrangements ............................................................................................. 36

    5.4.2 Line types, line styles and colours ..................................................................... 37

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 4 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.4.3 CAD blocks .......................................................................................................... 38

    6 APPENDIX 1 - EXAMPLE OF DRAWING LAYOUT ............................................................. 39

    7 APPENDIX 2 LAYER ARRANGEMENTS .......................................................................... 40

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 5 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    1 PURPOSE

    The purpose of this document is to ensure a consistent and unified company-wide approach in the production of engineering drawings. The intent is to guide the reader through the steps to be taken when producing a drawing. In addition the procedure describes a uniform and logical approach in order to ensure easy-to-read layouts for all CAD drawings.

    2 SCOPE

    This procedure is applicable to all drawings generated within ICE for all types of projects. In addition drawings produced by subcontractors to ICE shall be subject to the same procedure.

    3 ABBREVIATIONS

    CAD Computer Aided Design D&ID Ducting & Instrumentation Diagram P&ID Piping & Instrumentation Diagram

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 6 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    4 REFERENCES

    [1] PES-AD-P001 - Project Document Coding Procedure [2] HR - P 011 - Employees / Subcontractors Name Coding Procedure. [3] ISO 128-20 - Technical drawings -- General principles of presentation -- Part 20: Basic

    conventions for lines [4] ISO 128-22 - Technical drawings -- General principles of presentation -- Part 22: Basic

    conventions and applications for leader lines and reference lines [5] ISO 128-24 - Technical drawings -- General principles of presentation -- Part 24: Lines

    on mechanical engineering drawings [6] ISO 128-25 - Technical drawings -- General principles of presentation -- Part 25: Lines

    on shipbuilding drawings [7] ISO 128-30 - Technical drawings -- General principles of presentation -- Part 30: Basic

    conventions for views [8] ISO 128-34 - Technical drawings -- General principles of presentation -- Part 34: Views

    on mechanical engineering drawings [9] ISO 128-40 - Technical drawings -- General principles of presentation -- Part 40: Basic

    conventions for cuts and sections [10] ISO 128-44 - Technical drawings -- General principles of presentation -- Part 44:

    Sections on mechanical engineering drawings [11] ISO 128-50 - Technical drawings -- General principles of presentation -- Part 50: Basic

    conventions for representing areas on cuts and sections [12] ISO 129-1 - Technical drawings -- Indication of dimensions and tolerances -- Part 1:

    General principles [13] ISO 1101 - Geometrical Product Specifications (GPS) -- Geometrical tolerancing --

    Tolerances of form, orientation, location and run-out - Generalities, definitions, symbols, indications on drawings

    [14] ISO 1302 - Geometrical Product Specifications (GPS) -- Indication of surface texture in technical product documentation

    [15] ISO 2768-1 - General tolerances -- Part 1: Tolerances for linear and angular dimensions without individual tolerance indications

    [16] ISO 3040 - Geometrical product specifications (GPS) -- Dimensioning and tolerancing Cones

    [17] ISO 3098-2 - Technical product documentation Lettering [18] ISO 5455 - Technical drawings Scales [19] ISO 5456-1 - Technical Drawings. Projection methods [20] ISO 5457 - Technical product documentation -- Sizes and layout of drawing sheets [21] ISO 6410 - Technical drawings -- Screw threads and threaded parts [22] ISO 6433 - Technical drawings Item references [23] ISO 7200 - Technical product documentation -- Data fields in title blocks and document

    headers [24] ISO 7573 - Technical product documentation -- Parts lists

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 7 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5 PROCEDURE DESCRIPTION

    5.1 GENERAL

    Drawings must be complete and unambiguous in interpretation. Complete drawings contain or make reference to all data necessary for:

    - fabricating, assembling, installing of the component parts; - testing requirements; - procurement requirements indicating suppliers.

    Drawings must be: - laid out in accordance with this procedure; - complete (unless specifically stated otherwise); - accurate and technically correct; - properly laid out; - easy to read; - unambiguous; - contain all necessary information; - avoid duplication of information; - be checked in accordance with company procedures prior to general issue / distribution; - be approved in accordance with company procedures prior to issue to the client.

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 8 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.1.1 Drawing layout

    A drawing is divided in two parts:

    - an administrative part; - a drawing part.

    G

    1

    H

    32 4 5 6

    F

    E

    G

    7 8 9 10 11 12 A1

    H

    F

    E

    B

    D

    C

    A

    1 32 4 5 6

    B

    D

    C

    7 8 9 10 11

    A

    12

    The information and data contained herein are proprietary to International Contract Engineering Ltd and are not to be copied, reproduced,duplicated or disclosed to others, in whole or in part, without prior written consent of International Contract Engineering Ltd.

    Phone: +44-(0)-1624-623-190Fax: +44-(0)-1624-628-297

    Fax: +40-(0)-236-417-836Phone: +40-(0)-236-415-965

    Isle of Man, IM1 1AF British IslesAdditional contact information:Web: www.icedesign.info

    19-21 Circular Road, Douglas,

    File

    nam

    e:

    Dra

    win

    g6.d

    wg

    The administrative part is located on the right hand side of the drawing, extended from bottom to top, dedicated to the following elements wherever these are applicable: property stamp, title block, revision list, stickers / stamps, holds block, notes, list of reference documents, key plan, list of materials. The administrative part is described in instructions 5.2.1 to 5.2.9 of this document. The drawing part indicates the area upon which arrangements, views, elevations, sections, diagrams, etc. shall be drawn. The standards to be used for the drawing part are described in detail in instructions 5.3.1 to 5.3.9 of this document. The both parts are divided by a vertical line only on first page of drawing. References:

    - None

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 9 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.1.2 Sheet sizes

    The standard sizes of ICE drawing sheets are in accordance with ISO 5457, namely A series, as presented below. The basic size in this series is the A0 size (1189 x 841mm).

    Drawing Sheet Size

    Size [mm]

    ICE Form Code Drawing

    A0 1189 x 841 Form Code Dwg.A0

    A1 841 x 591 Form Code Dwg.A1

    A2 594 x 420 Form Code Dwg.A2

    A3 420 x 297 Form Code Dwg.A3

    A4 297 x 210 Form Code Dwg.A4

    The use of A0 size is to be avoided wherever possible unless it is a specific contract requirement. The preferred size for drawings is A1. A3 and A4 drawings are preferably to be used for drawing packages (e.g. booklets of drawings). A package may consist of a cover sheet, an index sheet (or sheets) and the drawings which make up the package. All drawings within a package shall have the same document number but be identified by unique and consecutive sheet numbers. Drawings are to be produced to the most appropriate scale in order to meet the requirements for the respective type of drawing (concept, basic or detail). This is intended to maintain clarity once all dimensions, symbols, item numbers and miscellaneous details have been included. The originator is responsible for the accuracy and clarity of drawings. It will be for the originator to decide upon the appropriate number of sheets. References:

    - ISO 5457 - Technical product documentation -- Sizes and layout of drawing sheets

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 10 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.1.3 Font name and sizes

    Text used in all ICE drawings must be in font Arial (ISO 3098-2).

    Preferred font sizes are: 2.5, 3.5 and 5. In special cases there will be used sizes: 1.8, 7 and 10. These cases are treated in 5.2.1, 5.3.4.

    Width Factor: 0.8 - 1, as defined in the next chapters.

    Colour:

    Font colour

    Font size Drawing Part Layout Administrative Part

    Layout

    1.8 Red White

    2.5 White White

    3.5 Yellow White

    5 Magenta White

    7 Blue White

    10 Green White

    Notes: o Exceptions: Dimensions text will be red (see chapter 5.3.6), revision indication

    symbol will be red (see chapter 5.3.10); o For background texts, the colour will be grey - 253.

    References:

    - ISO 3098-2 - Technical product documentation -- Lettering

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 11 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.2 ADMINISTRATIVE PART LAYOUT

    The administrative part of the drawing consists of the following sections, extended from bottom to top, in the following order (Appendix 1):

    1. Property stamp block; 2. Title block; 3. Revision status list; 4. Sticker / Stamp area; 5. Holds block; 6. Notes; 7. List of reference documents; 8. Key plan, applicable on structural unit drawings, arrangement and coordination

    drawings; 9. List of materials.

    For multiple page drawings, the administrative part for the pages from the second onward shall include the following sections only:

    1. Property stamp block; 2. Title block; 3. Revision status list; 4. Sticker / Stamp area;

    References:

    - Detailed instructions for above sections are given in instructions 5.2.1 5.2.9.

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 12 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.2.1 Property stamp block

    Property stamp block

    The information and data contained herein are proprietary to International Contract Engineering Ltd and are not to be copied, reproduced,duplicated or disclosed to others, in whole or in part, without prior written consent of International Contract Engineering Ltd.

    is located bottom of title block:

    The information and data contained herein are proprietary to International Contract Engineering Ltd and are not to be copied, reproduced,duplicated or disclosed to others, in whole or in part, without prior written consent of International Contract Engineering Ltd.

    Phone: +44-(0)-1624-623-190Fax: +44-(0)-1624-628-297

    Fax: +40-(0)-236-417-836Phone: +40-(0)-236-415-965

    Isle of Man, IM1 1AF British IslesAdditional contact information:Web: www.icedesign.info

    19-21 Circular Road, Douglas,

    10 11 12 A1

    H

    Font name, size and colour used:

    - Font used: Arial; - Width factor: 0.8; - Colour: white. - Font size: 1.8;

    References:

    - Font name and sizes as per instruction 5.1.3.

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 13 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.2.2 Title block

    The title block conveys relevant information about the drawing enabling accurate interpretation, identification and archiving. The default title block to be used in all ICE projects is (ISO 7200):

    File

    nam

    e:

    Dra

    win

    g17.d

    wg

    Phone: +44-(0)-1624-623-190Fax: +44-(0)-1624-628-297

    Fax: +40-(0)-236-417-836Phone: +40-(0)-236-415-965

    Isle of Man, IM1 1AF British IslesAdditional contact information:Web: www.icedesign.info

    19-21 Circular Road, Douglas,

    The information and data contained herein are proprietary to International Contract Engineering Ltd and are not to be copied, reproduced,duplicated or disclosed to others, in whole or in part, without prior written consent of International Contract Engineering Ltd.

    31

    7

    2

    8

    5 9

    6

    4

    Wherein: Item 1 - Project number Item 2 - Drawing number

    Item 3 - Revision status (revision status will be completed for all sheets of the drawing) Item 4 - Client / Third Party or Client Info and logo Item 5 - Main scale of the drawing (e.g. 1:50) Item 6 - Current sheet number out of total number of sheets.

    The typical format to be used is: 1 of 2. Item 7 - Drawing title

    Drawing number and title are to be in accordance with the Project Document Coding Procedure - PES-AD-P001 Font name, sizes, width factor and colour used:

    Item Area

    Font Font Width Font

    Style Size Factor colour

    1 Project Number Arial 2.5 0.8 white

    2 Drawing Number Arial 3.5 0.8 white

    3 Revision1 Arial 3.5 0.8 white

    4 Client

    5 Scale Arial 2.5 0.8 white

    6 Sheet Arial 2.5 0.8 white

    7 Title Arial 3.5 0.8 white

    8 Subtitle Arial 2.5 0.8 white

    9 Size Arial 2.5 0.8 white

    1 Revision status will be completed in all sheets of the drawing.

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 14 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    References: - Document numbering and title as per Project Document Coding Procedure- PES-AD-P001 - Sheet size as per instruction 5.1.2. - Font name and sizes as per instruction 5.1.3. - Revision as per instruction 5.2.3 and 5.3.10. - Projection method as per instruction 5.3.2. - Scale method as per instruction 5.3.3. - ISO 7200 - Technical product documentation -- Data fields in title blocks and document

    headers

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 15 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.2.3 Revision status list

    The revision status list2 to be used is:

    Changes of the contents of the drawing3 shall be marked by clouds around the revised drawing area. Clouds will be used starting with B revision.

    The 1st issue of a drawing is to be identified as revision A. Drawing revisions shall follow the below sequence in alphabetic order:

    If a Revision A drawing is modified, the new drawing showing the latest modifications will have the same drawing number, but its revision status is to be advanced to revision B. Outdated revision A drawings are to be filed and retained within the filing system for historic and back-referencing purposes. Fields Performed, Checked and Approved will be completed with name abbreviation - (according to Employees / Subcontractors Name Coding Procedure). Date format is yyyy.mm.dd. Font name, sizes, width factor and colour used:

    Area Font style Font size Width factor Font colour

    Rev Arial 2.5 0.8 white Date Arial 2.5 0.8 white Description Arial 2.5 0.8 white Performed Arial 2.5 0.8 white Checked Arial 2.5 0.8 white Approved Arial 2.5 0.8 white

    References:

    - Employees / Subcontractors Name Coding Procedure - HR - P - 011 - Font name and sizes as per instruction 5.1.3. - Revision indication in title block as per instruction 5.2.2. - Revision indication on drawing part layout as per instruction 5.3.10.

    2 Status revision list will be placed on each sheet, if the drawing has a lot of sheets.

    3 When a drawing has a lot of sheets, revision cloud an revision status will be placed on the sheet which will be

    modified. Status revision list will be changed in all sheets of the drawing.

    First Issue

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 16 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.2.4 Sticker / Stamp area

    The area located immediately above the revision list is reserved for stickers/stamps, such as IN PROGRESS sticker, CHECK PRINT stamp, etc. Where a drawing has not been finalised for formal delivery but is to be issued to an external party then upon the instruction of the Document Controller it must contain an "IN PROGRESS" indicator as shown below:

    The same indication will also be included for drawings still in progress or submitted for internal checking. Font name, sizes, width factor and colour used:

    Area

    Font Font Width Font

    Style Size Factor colour

    IN PROGRESS Arial 5 0.8 white Date and Time Arial 3.5 0.8 white

    When the drawing is plotted for checking / verification, this area should be kept free for CHECK PRINT stamp to be placed. If necessary, a PRELIMINARY or CONFIDENTIAL INFORMATION sticker will be placed in Administrative Area, as shown below:

    Font name, sizes, width factor and colour used:

    - Font name: Arial; - Font size: 5; - Width factor: 0.8; - Colour: white.

    References:

    - Font name and sizes as per instruction 5.1.3.

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 17 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.2.5 Holds block

    If necessary, holds are to be indicated on the drawing using the following block:

    21

    5

    3

    4

    Font name, sizes, width factor and colour used:

    Item Area

    Font Font Width Font

    Style Size Factor colour

    1 HOLDS Arial 3.5 0.8 white 2 ID Arial 3.5 0.8 white 3 Description Arial 3.5 0.8 white 4 ID number Arial 2.5 0.8 white

    5 Description field Arial 2.5 0.8 white

    References:

    - Font name and sizes as per instruction 5.1.3. - Hold indication on drawing part layout 5.3.9.

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 18 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.2.6 Notes

    The Notes give general information about the parts shown on the drawing concerning materials, welds, treatment, Class Notation, etc. The Notes shall be numbered sequentially for reference purposes. In case a note becomes redundant and will be removed from a subsequent revision, the numbering will not be re-sequenced. CAD coordinators within the various departments are to ensure that the standard of appearance of Notes is consistent throughout all departments. Special care is to be taken in order to ensure that naming conventions and abbreviations are applied consistently. (e.g. use of the abbreviation for

    centreline is CL instead of C.L., etc.). An example of a list of notes is shown below.

    1 Description in 1 Line

    2 Description Starting in First Line andContinued in Second Line

    3

    21

    5

    3

    4

    Font name, sizes, width factor and colour used:

    Item Area

    Font Font Width Font

    Style Size Factor colour

    1 NOTES Arial 3.5 0.8 white 2 ID Arial 3.5 0.8 white 3 Description Arial 3.5 0.8 white 4 ID number Arial 2.5 0.8 white

    5 Description field Arial 2.5 0.8 white

    References:

    - Font name and sizes as per instruction 5.1.3.

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 19 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.2.7 List of reference documents

    The list of reference documents is to contain only those that are directly pertinent to the subject matter contained within the drawing . Reference documents can be:

    - parts list; - drawings with sections or details; - documents referring to the subject drawing; - client drawings; - specifications, calculations, material take-off, etc.

    Referenced documents shall be denoted with:

    - A reference number on the drawing which can be found in the reference list. - A reference list which states the reference number as indicated on the drawing

    followed by document number4 and title.

    Reference document sequence number is unique per sheet. Below, an example of a list of reference documents is given:

    1

    3 4

    6 75

    2

    Font name, sizes, width factor and colour used:

    Item Area

    Font Font Width Font

    Style Size Factor colour

    1 REFERENCE DOCUMENTS Arial 3.5 0.8 white 2 ID Arial 3.5 0.8 white 3 Document number Arial 3.5 0.8 white 4 Title Arial 3.5 0.8 white 5 ID number Arial 2.5 0.8 white

    6 Document number Arial 2.5 0.8 white

    7 Document title Arial 2.5 0.8 white

    References:

    - Document numbering as per Project Document Coding Procedure - PES-AD-P001 - Font name and sizes as per instruction: 5.1.3.

    4 Document number will be recorded without revision.

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 20 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.2.8 Key plan

    A key plan is a small scale representation of the whole ship or object under consideration. The key plan is located within the administrative part of the drawing in the top right hand corner. On the drawing the key plan is located in top right corner of the drawing form. The recommended size of key plan will be 180mm x 70mm. Font name, size, width factor and colour used:

    - Font name: Arial; - Font size for key plan title: 3.5, width factor: 0.8, colour: white; - Font size for other information: 2.5, width factor: 0.8, colour: white.

    Below, is an example of a key plan:

    References:

    - Font name and sizes as per instruction: 5.1.3.

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 21 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.2.9 List of materials

    List of materials (acc. to ISO 7573) will be placed to the top of the Administrative Part. Normally, List of materials is only drawn on Detail Drawings. In this table all positions marked in Drawing Part by Item Number will be detailed.

    2

    9 10

    11 12

    14

    31 4 5 6 713

    8

    Font style, sizes, width factor and colour used:

    Item Field

    Font Font Width Font

    Style Size Factor colour

    1 Item Arial 3.5 0.8 white 2 Description Arial 3.5 0.8 white 3 Dwg. no., Standard or

    Codification Arial 3.5 0.8 white

    4 Pcs. Arial 3.5 0.8 white 5 Material or characteristics Arial 3.5 0.8 white 6 Remarks Arial 3.5 0.8 white 7 Weight kg/pc. Arial 3.5 0.8 white 8 Item number Arial 3.5 0.8 white

    9 Description: e.g. Screw M8x10-1 line

    Arial 2.5 0.8 white

    10 Standard: e.g. ISO EN 4815 Arial 2.5 0.8 white

    11 Pieces: e.g. 40 Arial 2.5 0.8 white

    12 Material or characteristics: e.g. St.37.3

    Arial 2.5 0.8 white

    13 Remarks: e.g. Cd5Fl Arial 2.5 0.8 white

    14 Weight per pc. Arial 2.5 0.8 white

    Once a drawing has been itemised ( see 5.3.8 ) then the list of materials is to be filled in accordingly with item number, description, etc. References:

    - Font name and sizes as per instruction: 5.1.3. - Item number as per instruction: 5.3.8. - ISO 7573 - Technical product documentation -- Parts lists

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 22 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.3 DRAWING PART LAYOUT

    This area of a drawing sheet is designated solely for graphical representations such as plan views, elevations, sections, details, diagrams, schematics, etc. It is vitally important that views must always be laid out in a logical, consistent and easy-to-read manner in accordance with the following rules:

    - the frame numbering (frame ruler) of one view is to align with the frame numbering of others; - section views are to be aligned and laid out such that they are in a logical numeric sequence; - datums (e.g. centrelines, baseline) are to align from one view to another; - details are to be identified and positioned in a logical alphanumeric sequence; - plan views of decks must be tiered one above the other in sequence with the lowermost deck

    at the bottom of the drawing area and the uppermost deck at the top of the drawing area. Only under exceptional and agreed circumstances are these rules to be infringed. Further information regarding projection methods, scales, titles, dimensioning, referencing, etc. are given in instruction parts 5.3.1 to 5.3.9 of this document.

    G

    1

    H

    32 4 5 6

    F

    E

    G

    7 8 9 10 11 12 A1

    H

    F

    E

    B

    D

    C

    A

    1 32 4 5 6

    B

    D

    C

    7 8 9 10 11

    A

    12

    The information and data contained herein are proprietary to International Contract Engineering Ltd and are not to be copied, reproduced,duplicated or disclosed to others, in whole or in part, without prior written consent of International Contract Engineering Ltd.

    Phone: +44-(0)-1624-623-190Fax: +44-(0)-1624-628-297

    Fax: +40-(0)-236-417-836Phone: +40-(0)-236-415-965

    Isle of Man, IM1 1AF British IslesAdditional contact information:Web: www.icedesign.info

    19-21 Circular Road, Douglas,

    File

    nam

    e:

    Dra

    win

    g6.d

    wg

    References:

    - none

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 23 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.3.1 Creating a drawing in Model Space / Paper Space

    Model Space is an environment in which all drawing components are drawn at a scale one to one, and millimetre is the preferred measurement unit. The drawings must be positioned versus the defined coordinate system. This will enable an accurate integration / superimposition between various drawings. Paper Space / Layout is an environment enabling the creation of sheet layouts for plotting purposes. Paper Space is not intended to be used for full scale drawings. A drawing may be created in one of two ways:

    - Inside Model Space: views, cross-sections, details, dimensions, different types of blocks (revision clouds, item number, weld symbols, etc.) at a scale 1:1, and inside Paper Space: Administrative Part and viewports.

    - Entirely within the Model Space when the previous method proves to be troublesome. In this case the main view is created at a scale of 1:1. All entities consisting of plan views, elevations, sections, details, text, dimensions, title block, border, etc are to be scaled to suit the intended drawing plot size.

    Steps for producing a drawing:

    - Creating a model. - Creating a Paper space Lay-out; - Creating Viewports; - Sizing / dimensioning and inserting symbols, item numbers and text.

    Creating a model It is important that the model is created in a logical and orderly manner, so it will be clear to anyone who uses the drawing as an eXternal-Reference. When attaching reference files, the path to this file should only be named as No Path. Set Reference Type on Overlay:

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 24 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    Creating a Paper space Layout From Model space switch to Paper Space environment. Page Setup Manager will be selected, and then Paper Size will be set to A1, Plot Scale to 1:1 and Plot Area to Layout. The drawing border, title block and other administrative blocks are then superimposed. Creating Viewports As a standard, a layer is made with the name Viewport. Otherwise this layer should be created. The existing viewport must be produced at a desired scale (i.e. 1:50) and then be locked. The viewport will be sized and positioned upon the drawing area. Any other necessary viewport is to be created, scaled and sited as above. References:

    - None

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 25 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.3.2 Projection method

    The method shown by Reference Arrows is mainly used for ship work rather than the First Angle Projection Method. The ICE projection method used is the European projection - first angle projection (ISO 5456-1).

    If the use of European projection method is not suitable due the lack of space in the drawing format, then another possibility for representation of projections is by using Reference Arrows:

    Principal view

    Principal view

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 26 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    Projections A and B (view from A or view from B) can be placed below principal view in a single row. Sections parallel with A or B will be subject to the same treatment. Projections C and D (view from C or view from D) can be placed in the same row with the principal view in the right side. Sections parallel with C or D will be subject to the same treatment. Naming conventions for views are as follows:

    profile view meaning projection looking from starboard to port; plan view on main deck - meaning looking vertically downwards on main deck; plan view on platform - meaning looking vertically downwards on platform; plan view on tank top - meaning looking vertically downwards on tank top; section view at frame, e.g. Fr.100 - meaning cross-section (at Fr 100) looking from aft to

    forward. General projection method can be summarised as:

    - Looking from aft to forward5; - Looking vertically downwards; - Looking from starboard to port;

    In general, the principal view should be the most informative, being the most recognisable during manufacture or use.

    References: - ISO 5456-1 - Technical Drawings. Projection methods.

    5 By exception and only when necessary, section views looking from forward to aft may of necessity have to

    be used for the sake of clarity. In these circumstances such views will be clearly identified as looking aft.

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 27 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.3.3 Scale method

    Drawings shall be to scale, except for diagrams and sketches. The main scale is indicated in box position 5 of the title block. Deviating scales are mentioned below the title of the relevant views, sections or details. Whenever a drawing refers to a diagram or a sketch, NTS (not to scale) will be written in box position 5 of the title block. Standard scales (ISO 5455), to be used:

    1:1; 1:2; 1:5; 1:10; 1:20; 1:50; 1:75; 1:100; 1:200; 1:500; 1: 750; 1:1000

    However, in exceptional circumstances it may be necessary to use the following scales:

    (1:2.5); (1:25); (1:150); (1:250); References:

    - Title block as per instruction 5.2.2. - Sections, views and details as per instruction 5.3.7. - ISO 5455 - Technical drawings -- Scales

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 28 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.3.4 Titles

    Title descriptions for views are to be written above the view, located centrally wherever possible. Font name, size and width factor:

    - Font used: Arial underlined, uppercase; - Font size for Title: 5; Font colour: Magenta; Layer: _G Text 0.50;

    (Font size 7 or 10 can be used for Safety Plan and Fire Control Plan and font colour: blue and green respectively)

    - Font size for Subtitle or other information: 3.5, uppercase; Font colour: Yellow; Layer: _G Text 0.35;

    - Font size for Scale: 2.5; Font colour: White; Layer: _G Text 0.25; - Width factor: 1.

    SECTION ON B-B

    SIMILAR IN 8 POSITIONSSCALE 1:5

    2

    3

    Resilient Mount

    4

    5

    14

    Flat Bar 50x5

    Daming Foam 50x20

    References:

    - Font name and size as per instruction 5.1.3. - Symbols as per instruction 5.3.7.

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 29 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.3.5 Text in Drawing Part Layout

    For all text situated within the Drawing Part Layout other than as previously described for view Titles (see 5.3.4), the font style, size and width factor is to be as indicated below:

    - Font used: Arial; - Font size: 2.5; - Font colour: White; - Width factor: 1; - Layer: _G Text 0.25.

    References:

    - Font name and size as per instruction 5.1.3.

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 30 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.3.6 Dimensions

    Drawings must include the minimum number of dimensions required for accurate manufacture:

    - describing the form or shape of the component, usually by using orthographic and sometimes pictorial views;

    - giving actual dimensions of all features of the geometry; - giving information about any special manufacturing processes and materials required.

    General rules for dimensioning (ISO 129):

    - Company accepted standards and conventions must be followed; - Dimensions must be placed on drawings so that they may be easily read; - Drawings must include only the minimum number of dimensions required for accurate

    manufacture; - A dimension is not to be stated more than once, unless it aids communication; - It should not be necessary for the operator manufacturing or assembling the

    component to need to calculate any dimension(s). All dimensions are in metric units, unless otherwise indicated. Font name, sizes, width factor and colour used:

    - Font name: Arial. - Dimension lines: 0.18 mm. - Font size for dimensions text: 2.5. - Width factor: 1. - Colour: text, lines, arrows - by layer (red). - Layer: _G Dimensioning.

    References:

    - Font size as per instruction 5.1.3. - ISO 129 - Technical drawings -- Indication of dimensions and tolerances -- Part 1:

    General principles

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 31 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.3.7 Sections, Views and Details

    For sections, views and details (ISO 128-34), the following symbols are to be used for:

    Section indication and presentation:

    SECTION A-A SCALE 1:10

    SECTION B-B SCALE 1:10

    View indication and presentation:

    PLAN VIEW ON A SCALE 1:10

    Detail indication and presentation:

    DETAIL A SCALE 1:10

    Font name, sizes, width factor and colour used:

    - Font name: Arial. - Font size: 5. - Width of lines: 0.25 mm - Width factor: 1. - Colour: by layer. - Layer for section, view and detail symbol: _G Symbols

    References:

    - Font name and size as per instruction 5.1.3. - ISO 128-34 - Technical drawings -- General principles of presentation -- Part 34: Views

    on mechanical engineering drawings

    See Detail A

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 32 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.3.8 Item Number

    The following symbol will be used in drawing area:

    Item number indication

    Case a Case b

    Font name, sizes, width factor and colour used:

    - Font name: Arial. - Width of lines: 0.25 mm. - Font size for text: 5. - Width factor: 1. - Colour: by layer. - Later: _G Item Number.

    References:

    - Font name and size as per instruction 5.1.3.

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 33 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.3.9 Holds indication

    The following symbol is to be used within the Drawing Area in order to highlight those parts of a drawing that are on-hold. Hold numbers are to correspond with the number listed in the table of Holds where the description of the hold point will be made also.

    HOLDS indication and presentation:

    HOLD 1

    All indications in drawing area and the corresponding HOLDS table details (see. 5.2.5) will be deleted after the hold status is resolved. Font name, sizes, width factor and colour used:

    - Font name: Arial; - Width of lines: 0.35 mm; - Font size for text: 5; - Width factor: 1; - Colour: by layer; - Layer: _G Holds.

    References:

    - Font name and size as per instruction 5.1.3. - HOLDS table will be completed, see 5.2.5.

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 34 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.3.10 Revision Indication

    Modifications for new revisions are indicated by a Cloud around the revised part(s). Clouds are only shown for the latest (actual) revision and only when the revision status is updated.

    View on design fields

    A

    Title block and revision list will be completed in all sheets of the drawing, see 5.2.2. One specific layer will be defined for each revision status. When a new revision occurs, the previous revision clouds and symbols remain on their specific layers which are switched off. In this way the revision history is kept. Font name, sizes, width factor and colour used:

    - Font name: Arial. - Width of lines: 0.35 mm. - Font size for text: 5. - Width factor: 1. - Colour: by layer. - Layer: _G REVISION-X6

    References:

    - Font type and size as per instruction 5.1.3. - Revision status from title block as per instruction 5.2.2. - Status revision list as per instruction 5.2.3.

    6 X means revision status. Will be a layer for each revision.

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 35 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.4 CAD DRAWING SPECIFICS

    Preparation of CAD drawings will entail specific procedures and the use of tailor-made provisions, such as reference files, layer arrangements, blocks, AutoCAD Auto lisp, Visual Basic programs and commands. Recording and filing of CAD drawings differs from those directly draughted by means of non-CAD methods such as hand-draughted/non CAD produced drawings. CAD drawings are to be prepared in such a way that they are compatible with, and easily converted to, the various other CAD systems that may be in use. References:

    - Essential features of CAD drawings are given in the instruction 5.4.1 5.4.3 of this document.

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 36 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.4.1 Layer arrangements

    Different items of a CAD drawing are drawn on layers. The layer classification is dependent on the type of drawing. The following types of drawing are set:

    - General; - Structure construction - Arrangements; - Piping and ducting layouts and schematics P&ID etc. - Electrical layouts, cables, etc. - Fire and Safety

    For the various drawing types, the layer classifications are as given in Appendix 2. Each type of drawing will be built onto one or more specific layers. Entities such as electric cable, hull, etc. can be used as background for other drawings. Attributes such as colour and line width, for all entities pertaining to the background will be set to grey (253) and, respectively 0.18 mm. References:

    - None

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 37 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.4.2 Line types, line styles and colours

    The following rules (ISO 128-20) are applicable for lines attributes - colour, width (line thickness) and style:

    LINE STYLE TABLE

    LINE STYLE ACAD Line Type

    Name Line pattern

    Continuous Continuous

    Dots Dot .

    Small dashes (hidden lines) Hidden _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

    Dashes Dashed

    Dash - dot DashDot2 _____ . _____ . _____ . _____ . _____ . _____ . ___

    Dash - dot - dot Phantom2 ____ _ _ ____ _ _ ____ _ _ ____ _ _ _____ _ _ ___

    For details of line types, lineweights, colour and application domain used see Appendix 2 LAYER ARRANGEMENTS. For specific hull drawings the line style and the rules for application are according to ISO 128-25. References:

    - Symbols as per instruction 5.3.6. - ISO 128-20 - Technical drawings -- General principles of presentation -- Part 20: Basic

    conventions for lines - ISO 128-24 - Technical drawings -- General principles of presentation -- Part 24: Lines

    on mechanical engineering drawings - ISO 128-25 - Technical drawings -- General principles of presentation -- Part 25: Lines

    on shipbuilding drawings

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 38 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    5.4.3 CAD blocks

    Blocks (for AutoCAD) are displays of standard elements, such as symbols, equipment, outfitting and auxiliary structures. Blocks are discipline related and maintenance of the block library is consequently allocated to the appropriate departmental CAD coordinator, under global responsibility of the CAD coordinator, who is also responsible for the maintenance of the blocks for general use. The structure for organizing block libraries is as follows: O:\ICE Standards\PROJECT SYSTEMS\

    - ICE Menu - Library

    - Symbols; - Models;

    - Lisp (CAD commands) - Menu (pull-down menus) - Template (different templates)

    Notes:

    1. For some projects, specific blocks are created; those blocks (not belonging to the blocks for a certain discipline or for a specific client) are stored in project libraries (and will be stored in the computer backup for that order).

    2. In order to create a new block in the project library, the following steps are to be used: - the entities must be drawn in layer 0. The entities will be drawn with colour, line type

    and line weight attributes set BY LAYER. If necessary, these characteristics will be changed according to drawing standards.

    - upon block completion, it will be saved by using WBLOCK command, into the folder corresponding with block destination or will be sent to CAD coordinator to do this operation.

    References:

    - None

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 39 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    6 Appendix 1 - EXAMPLE OF DRAWING LAYOUT

    File

    nam

    e:

    A$C

    66B

    C45A

    F.D

    WG

    Phone: +44-(0)-1624-623-190Fax: +44-(0)-1624-628-297

    Fax: +40-(0)-236-417-836Phone: +40-(0)-236-415-965

    Isle of Man, IM1 1AF British IslesAdditional contact information:Web: www.icedesign.info

    19-21 Circular Road, Douglas,

    The information and data contained herein are proprietary to International Contract Engineering Ltd and are not to be copied, reproduced,duplicated or disclosed to others, in whole or in part, without prior written consent of International Contract Engineering Ltd.

    G

    1

    H

    32 4 5 6

    F

    E

    G

    7 8 9 10 11 12 A1

    H

    F

    E

    B

    D

    C

    A

    1 32 4 5 6

    B

    D

    C

    7 8 9 10 11

    A

    12

    PLAN VIEW

    LONGITUDINAL SECTION

    CROSS SECTION

    Full dimensioning in this section

    For dimensioning in remaining sectionsrefer to the first section

    DETAILS

    For general details refer toseparate details drawing

    If port and starboard side are identical,half sections may be used

    CROSS SECTION

    CROSS SECTION

    LONGITUDINAL SECTION

    LONGITUDINAL SECTION

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 40 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    7 Appendix 2 LAYER ARRANGEMENTS

    General

    Name Colour

    (By Layer) Line Type (By Layer)

    Lineweight (By Layer)

    Description

    _G Text 0.18 Red CONTINUOUS 0.18 Used to write texts with font height = 1.8 mm

    _G Text 0.25 white CONTINUOUS 0.25 Used to write texts with font height = 2.5 mm

    _G Text 0.35 yellow CONTINUOUS 0.35 Used to write texts with font height = 3.5 mm

    _G Text 0.50 magenta CONTINUOUS 0.50 Used to write texts with font height = 5 mm

    _G Text 0.70 Blue CONTINUOUS 0.70 Used to write texts with font height = 7 mm

    _G Text 1.0 green CONTINUOUS 1.00 Used to write texts with font height = 10 mm

    _G Ad-tive white CONTINUOUS 0.25

    Borders; Title Block; Revision Blocks; Note; External References; Property Stamp; Key Plan; Legend; List of Materials

    _G Ruler Red CONTINUOUS 0.18 Used to draw CL and BL.

    _G Centrelines red CENTER2 0.18 CentreLine and frames in each view from drawing

    _G Tank lines 211 CENTER2 0.18 Tanks delimitation

    _G Symbols white CONTINUOUS 0.18

    Used to store blocks of drawing: tolerance, weld, roughness, section symbol, etc

    _G Dimensioning Red CONTINUOUS 0.18 Used to draw the dimensions

    _G Item Number white CONTINUOUS 0.25 Used for storing item number blocks

    _G Revision - X7 Red CONTINUOUS 0.35

    Used for storing the revision symbols

    _G Holds Red CONTINUOUS 0.35 Used for storing the hold symbols

    _G Break_Line white PHANTOM2 0.25 Used for plotting the drawing of break lines

    _G Hatch red CONTINUOUS 0.18 Used to show hatched areas within the design field when plotting drawings

    _G Viewports magenta CONTINUOUS 0.25 Used to draw on the viewport line layout aids work;

    _General White CONTINUOUS 0.25

    7 X means revision status. A layer is to be created for each revision.

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 41 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    Hull

    Name Colour

    (By Layer) Line Type (By Layer)

    Width (By Layer)

    Description

    H Stiffeners green CONTINUOUS 0.25 Draughting of stiffeners;

    H Stiffeners Hidden I green DASHED 0.25 Draughting of stiffeners

    (opposite);

    H Stiffeners Hidden II green

    DASHED2 0.25 Draughting of stiffeners

    (opposite);

    H Web frame green CONTINUOUS 0.50 Draughting of web frame;

    H Web frame Hidden green

    CENTER 0.50 Draughting of web frame

    (opposite);

    H Edge green CONTINUOUS 0.25 Draughting of edge;

    H Visible WT Bulkhead

    green CONTINUOUS 0.50

    Draughting of visible watertight bulkhead;

    H WT Bhd Hidden Double

    green CONTINUOUS 0.25

    Draughting of invisible watertight bulkhead (double line menu draw multiline);

    H WT Bhd Hidden Simple

    green HIDDEN 0.35

    Draughting of invisible watertight bulkhead (simple

    line);

    H Visible NWT Bulkhead

    green CONTINUOUS 0.50

    Draughting of visible non-watertight bulkhead;

    H NWT Bhd Hidden green

    DASHEDX2 0.50 Draughting of visible non-

    watertight bulkhead (opposite);

    H Pillars green CONTINUOUS 0.25 Draughting of pillars;

    H Shell green CONTINUOUS 0.50 Draughting of shell;

    H Stairwell Manholes Hatch openings

    red CONTINUOUS 0.25 Draughting of holes;

    H Plate Seams red CONTINUOUS 0.25 Draughting of plate seams;

    H Knuckle Lines green DASHDOT 0.25 Draughting of knuckle lines;

    H Additional Structure cyan

    CONTINUOUS 0.18

    Draughting of additional

    structure;

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 42 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    Arrangements

    Name Colour

    (By Layer) Line Type (By Layer)

    Width (By Layer)

    Description

    A WT Bulkhead magenta CONTINUOUS 0.5 Draughting of visible watertight bulkhead in arrangement drawings;

    A WT Bulkhead hidden

    magenta DASHED 0.35 Draughting of hidden watertight bulkhead in arrangement drawings;

    A NWT Bulkhead 40 CONTINUOUS 0.5 Draughting of visible non-watertight bulkhead in arrangement drawings;

    A NWT Bulkhead hidden

    41 DASHED 0.35 Draughting of hidden non-watertight bulkhead in arrangement drawings;

    A Stairwell Manholes Hatch openings

    yellow CONTINUOUS 0.25 Draughting of stairwell/ manhole/hatch openings

    A Stairwell Manholes Hatch openings above

    yellow CENTER2 0.25 Draughting of stairwell/ manhole/hatch openings above the current deck

    A Stairs Platforms Walkways Railing

    160 CONTINUOUS 0.25 Draughting railings

    A Doors Portholes Windows

    yellow CONTINUOUS 0.25 Draughting of windows and portholes

    A Lining Ceiling and Partition Bulkheads

    80 CONTINUOUS 0.25 Draughting of lining, ceiling and partition bulkheads

    A Insulation white CONTINUOUS 0.25 Draughting of insulation

    A Furniture 131 CONTINUOUS 0.25 Draughting of furniture

    A Sanitary 131 CONTINUOUS 0.25 Draughting of sanitary cabins

    A Stair Indication white CONTINUOUS 0.18 Draughting of stairs indication symbols

    A Foundation & support

    41 CONTINUOUS 0.50 Draughting of foundation and supports

    A Manholes Hatch yellow CONTINUOUS 0.50 Draughting of hatches and manholes

    A Floor & Deck Covering

    white CONTINUOUS 0.25 Draughting of floor and deck covering

    A Propulsion (thrusters etc)

    yellow CONTINUOUS 0.25 Draughting of propulsion equipment

    A Manoeuvring Equipment

    yellow CONTINUOUS 0.50 Draughting of Rudder, Steering Gear, Stabilizers, dynamic positioning system

    A Deck Equipment yellow CONTINUOUS 0.25 Draughting deck equipment

    A Electrical Equipment yellow CONTINUOUS 0.25 Draughting electrical equipment

    A Navigation Searching Communication Equip.

    white Continuous 0.5 Draughting of Radar plants, GPS, GMDSS, EPIRBS, VHF/UHF, etc.

    A Special Equipment white Continuous 0.5 Draughting of Drilling, Dredging, Diving, De-icing, Seismic, Laboratory equip.

    A Machinery Equipment

    grey Continuous 0.5 Draughting of equipment in machinery rooms

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 43 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    Piping & Ducting

    Name Colour

    (By Layer) Line Type (By Layer)

    Width (By Layer)

    Description

    P Chilled Water 31 Continuous 0.5 Chilled water

    P Sanitary supply 182 Continuous 0.5 Sanitary supply

    P Sanitary discharge 211 Continuous 0.5 Sanitary discharge

    P Fuel Oil 41 Continuous 0.5 Fuel oil

    P Waste oil 242 Continuous 0.5 Waste oil

    P Lube Oil 40 Continuous 0.5 Lube oil

    P Sea Water Blue Continuous 0.5 Sea water

    P Cooling Water-HT 166 Continuous 0.5 HT Cooling water

    P Cooling-Water-LT 74 Continuous 0.5 LT Cooling water

    P Fresh Water Cyan Continuous 0.5 Fresh water

    P Starting Air 254 Continuous 0.5 Starting air

    P Service & Control Air

    70 Continuous 0.5 Service & Control Compressed Air

    P Exhaust 33 Continuous 0.5 Exhaust gas

    P Steam Condensate & Feed Water

    Grey Continuous 0.5 Steam condensate and feed water

    P Distilled Fresh water storage

    202 Continuous 0.5 Distilled fresh water

    P Pneum. Valves Remote Control

    32 Continuous 0.5 Pneumatic valve remote control

    P Ballast 121 Continuous 0.5 Ballast system

    P Bilge 123 Continuous 0.5 Bilge system

    P Scupper Pipes 80 Continuous 0.5 Scupper system

    P Fire water Red Continuous 0.5 Fire fighting with water

    P Fire CO2 245 Continuous 0.5 Fire fighting with CO2

    P Fire Foam White Continuous 0.5 Fire fighting with Foam

    P Air and Sounding 30 Continuous 0.5 Overflow Pipes Systems;

    P Hydraulic 251 Continuous 0.5

    P Thermal Oil White Continuous 0.5

    Heating Oil Treatment Systems; Heating Oil distribution Systems for ER and Outside ER

    P Air Conditioning

    - blue for supply air; - green for exhaust air; - red for return air.

    Continuous 0.5 Air Conditioning ducts

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 44 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    P Ventilation accommodation

    - green for exhaust air;

    Continuous 0.5 Ventilation in accommodation

    P Ventilation holds technical

    - blue for supply air; - green for exhaust air;

    Continuous 0.5 Ventilation in holds and technical spaces

    P Ventilation Machinery

    - blue for supply air; - green for exhaust air; - red for return air.

    Continuous 0.5 Ventilation in machinery rooms

    P Heating White Continuous 0.5 Heating system

    P Process systems 200 Continuous 0.5 Process systems

    Electrical

    Name Colour

    (By Layer) Line Type

    (By Layer) Width

    (By Layer) Description

    E Automation Systems for Machinery

    blue Continuous 0.5

    Main and Maneuvre consoles; Common Automation Equipment Engine Room Alarm Systems; Automation Equipment for Boilers, Motor / turbo Aggregates, other Machinery Components; etc

    E Fire Detection and Alarm

    green Continuous 0.5 Electric Devices: Detectors, Manual Call Point, etc.

    E Common electric and Electronic

    white Continuous 0.5 Common computer Systems

    E Electric Power Supply

    cyan Continuous 0.5

    Generators / Alternators; Transformers; Battery and Chargers; Rectifiers and Converters; Electric Shore Supply Systems;

    E Common Electric Distribution

    white Continuous 0.5

    Main Switchboards; Emergency Switchboards; Distribution panels and Boards; Group Starters;

    E Cable Trays - Power 132 Continuous 0.5 Cable trays for power system

    E Cable Trays - Low voltage

    Magenta Continuous 0.5 Low voltage cable trays

    E Cable Trays - High voltage

    Red Continuous 0.5 High voltage cable trays

    E Cable Trays - control & instrumentation

    Yellow Continuous 0.5 Control and instrumentation cable trays/lines

    E Electric Consumer Systems

    White Continuous 0.5

    Electric Lighting Systems for Engine and Boiler room, Accommodation, Deck and Cargo Holds

  • Project Name: PROJECT ENGINEERING SYSTEM Sheet

    Title: DRAUGHTING PROCEDURE 45 of 45

    Document No: PES-MD-P001 Rev A

    2010, ICEPRONAV

    Form Code PES-AD-T001 Rev. A / May 2010

    File name: PES-MD-P001_A - Draughting Procedure.doc

    Fire & Safety

    Name Colour

    (By Layer) Line Type (By Layer)

    Width (By Layer)

    Description

    FS F & S Symbols white CONTINUOUS 0.18 Fire & Safety

    FS Rating A60 240 CONTINUOUS 0.5 Fire & Safety

    FS Rating A30 90 CONTINUOUS 0.5 Fire & Safety

    FS Rating A0 magenta CONTINUOUS 0.5 Fire & Safety

    FS Rating B15 52 CONTINUOUS 0.5 Fire & Safety

    FS Rating B0 40 CONTINUOUS 0.5 Fire & Safety

    1 PURPOSE2 SCOPE3 ABBREVIATIONS4 REFERENCES5 PROCEDURE DESCRIPTION5.1 GENERAL5.1.1 Drawing layout5.1.2 Sheet sizes5.1.3 Font name and sizes

    5.2 ADMINISTRATIVE PART LAYOUT5.2.1 Property stamp block5.2.2 Title block5.2.3 Revision status list5.2.4 Sticker / Stamp area5.2.5 Holds block5.2.6 Notes5.2.7 List of reference documents5.2.8 Key plan5.2.9 List of materials

    5.3 DRAWING PART LAYOUT5.3.1 Creating a drawing in Model Space / Paper Space5.3.2 Projection method5.3.3 Scale method5.3.4 Titles5.3.5 Text in Drawing Part Layout5.3.6 Dimensions5.3.7 Sections, Views and Details5.3.8 Item Number5.3.9 Holds indication5.3.10 Revision Indication

    5.4 CAD DRAWING SPECIFICS5.4.1 Layer arrangements5.4.2 Line types, line styles and colours5.4.3 CAD blocks

    6 Appendix 1 - EXAMPLE OF DRAWING LAYOUT7 Appendix 2 LAYER ARRANGEMENTS