Parking Forest Materials
-
Upload
maria-cahill -
Category
Design
-
view
95 -
download
0
description
Transcript of Parking Forest Materials
The Parking Forest:
Linear Tree Well Design Using Structural Soil
Sustainability for all the places between the buildings
503.334.8634www.greengirlpdx.com
[email protected] certified women business enterprise
The Parking Forest
An Assembly of Common Materials
The Parking Forest
A Close Up
THPRD in Plan
Structural Soil
Our “Secret Weapon”
Source: Cornell University – CU Structural Soil - http://www.hort.cornell.edu
How do we know it works?
Olympia Results 8 Years Later
Control Trees Planted in Compacted Native Soil
Trees Planted in Structural Soil
Assembly Procedure
Assembly Procedure
Assembly Procedure
Assembly Procedure
Assembly Procedure
Assembly Procedure
Assembly Procedure
Assembly Procedure
Sunset Swim Center Parking Lot Construction Expenses
Item Cost
Porous Concrete $200,000
Drain Rock $62,000
Excavation $35,000
Mobilization $30,000
Curbs/Sidewalk $26,000
Landscaping $23,500
Soil/Structural Soil/Installation $18,000
Demolition/Removal $11,000
Striping/Wheel Stops/Signs $10,000
French Drain / Drain Pipe $3,000
12 Trees for Linear Well $1,600
Other Stuff $8,500
TOTAL CONSTRUCTION $427,600
Why these materials?
• Structural soil
• Amended Native Soil
• Trees
• Wheel stops
• Crush rock (in landscape area)
Why these materials?
Structural Soil
• Structural soil versus structural supports
Why these materials?
Proprietary mix versus mixed by contractor
Mixing Structural Soil
Photo Source: www.greelysand.com/cu-soil.html
Olympia Soil Recipe
4 cubic yards Crushed Rock ¾”-1¼”
+ 1 cubic yard Loam/organic topsoil
+ 1 pound Soil Binder “Stabilizer”
+ 46 gallons water__________
Makes 4.6 cubic yards Structural Soil
Structural Soil Costs - Olympia
“The price to supply, deliver and install the structural soil material per
cubic yard ranged from $19 to $85 with an average bid of $42, the median
price was $39.50.
The city paid $24 per cubic yard for the structural soil material to the low
bidder.
This compare to a price quote we received for the supply of CU structural
soil at $65 per cubic yard plus delivery. The source was over an hour’s drive
away and delivery charges were $85 per hr with a truck and trailer hauling 22
cubic yard. The expected cost delivered was $72 per cubic yard.”
Excerpted from “Structural Soil Demonstration Project”
http://olympiawa.gov/~/media/Files/CPD/Urban%20Forestry/Forms/StructuralSoil.as
hx
Source: City of Olympia -Structural Soil Demonstration Project
Why these materials?
Amended native soil
Amended native soil versus faster draining “3-way” mix
Why these materials?
Trees
Trees versus only shrubs &/or groundcover:
• Interception & evaporation
• Evapotranspiration
• Heat island effect
Why these materials?
Wheel stops
Wheel stops versus curbs
Why these materials?
Crushed rock
¼”x 10 crushed rock versus rounded rock or pavers
Siting Criteria
• Site is suitable for infiltration
• Non-expansive soils
• Soils should infiltrate at least 0.2 inches/hour*. Clay soils are OK!
*Based on 2ft of structural soil, 25% void ratio, facility empty in 30 hours to be ready for the next Type IA storm
The Other Project
PCC Sylvania Lot 10
• THPRD Sunset Swim Center = Redevelopment that manages rainfall
• PCC Sylvania Lot 10 = Retrofit that manages runoff
The Parking Forest Retrofit
at PCC Sylvania Lot 10
Ignore the piles of dirt. They’re
gone.
Design Differences at PCC Sylvania Lot 10
Left most of the parking lot unmodified/ impervious
Installed an impervious liner adjacent to impervious
asphalt
Installed an impervious liner adjacent to impervious
asphalt
Stakeholders chose a native
conifer
Water quality and quantity monitoring
Design Differences at PCC Sylvania Lot 10
Straight head-in parking
Donated “old school” solid bottom wheel
stops = not ideal
Just trees
Erosive forces
are an issue at PCC
Non-attentive forces
are an issue at PCC
Thank You!
Siting Criteria at PCC
• Site is suitable for infiltration
• Non-expansive soils
• Soils should infiltrate at least 0.2 inches/hour*. Clay soils are OK!
*Based on 2ft of structural soil, 25% void ratio, facility empty in 30 hours to be ready for the next Type IA storm
www.parkingforest.org