Overview KANGEAN ENERGY INDONESIA...

10
Overview KANGEAN ENERGY INDONESIA LTD VENDOR’S DAY BERSAMA EAST JAVA 2017 Golden Tulip Hotel, Batu - Malang DIDI BASUKI VP SCM

Transcript of Overview KANGEAN ENERGY INDONESIA...

Page 1: Overview KANGEAN ENERGY INDONESIA LTDscm.phe.pertamina.com/media/0e420c07-8b3e-4365-8c1d-a66f2f1b67be/7. KEI... · 2 OVERVIEW KANGEAN ENERGY INDONESIA LTD DIDI BASUKI VP SCM EAST

Overview KANGEAN ENERGY INDONESIA LTD

Prepared By

INVENTORY & LOGISTIC DIVISION

©2016

VENDORS

Overview

KANGEAN ENERGY INDONESIA LTD

VENDOR’S DAY BERSAMA EAST JAVA 2017

Golden Tulip Hotel, Batu - Malang

DIDI BASUKI

VP SCM

Page 2: Overview KANGEAN ENERGY INDONESIA LTDscm.phe.pertamina.com/media/0e420c07-8b3e-4365-8c1d-a66f2f1b67be/7. KEI... · 2 OVERVIEW KANGEAN ENERGY INDONESIA LTD DIDI BASUKI VP SCM EAST

2

OVERVIEW

KANGEAN ENERGY INDONESIA LTD

DIDI BASUKI

VP SCM

EAST JAVA VENDOR’S DAY , 27 JULY 2017

Golden Tulip Hotel, Batu - Malang

Page 3: Overview KANGEAN ENERGY INDONESIA LTDscm.phe.pertamina.com/media/0e420c07-8b3e-4365-8c1d-a66f2f1b67be/7. KEI... · 2 OVERVIEW KANGEAN ENERGY INDONESIA LTD DIDI BASUKI VP SCM EAST

HISTORY

Page 4: Overview KANGEAN ENERGY INDONESIA LTDscm.phe.pertamina.com/media/0e420c07-8b3e-4365-8c1d-a66f2f1b67be/7. KEI... · 2 OVERVIEW KANGEAN ENERGY INDONESIA LTD DIDI BASUKI VP SCM EAST

4

KEI FIELDS

PAGERUNGAN (PAG)

Production type : Gas & Condensate

Lifespan : 1993 – Now

Cum. Production (1993 – Now)

Gas : 1,191 Bscf

Condensate. : 13.9 MMbbl

TERANG SIRASUN BATUR (TSB)

Production type : Gas

Lifespan : 2012 – Now

Cum. Production : 438 Bscf

Estimated Reserves : 855.1 Bscf

Page 5: Overview KANGEAN ENERGY INDONESIA LTDscm.phe.pertamina.com/media/0e420c07-8b3e-4365-8c1d-a66f2f1b67be/7. KEI... · 2 OVERVIEW KANGEAN ENERGY INDONESIA LTD DIDI BASUKI VP SCM EAST

5

KEI FIELD

PAG

PUO

SED

TSB

PUO

Terang - Sirasun - Batur Area

SEGENTOH

Page 6: Overview KANGEAN ENERGY INDONESIA LTDscm.phe.pertamina.com/media/0e420c07-8b3e-4365-8c1d-a66f2f1b67be/7. KEI... · 2 OVERVIEW KANGEAN ENERGY INDONESIA LTD DIDI BASUKI VP SCM EAST

6

UP COMING PROJECT TSB Phase 2 – Development

• Phase 1

5 subsea completion development wells in Terang gas field had been drilled and completed in the middle of 2011 and started producing gas in May 2012.

• Phase 2

Drilling 4 subsea development wells in Sirasun and Batur gas field is planned to be commenced in March 2018 (Target spud-in) followed by Subsea facility installation.

Target Gas-in : Jan 2019

Page 7: Overview KANGEAN ENERGY INDONESIA LTDscm.phe.pertamina.com/media/0e420c07-8b3e-4365-8c1d-a66f2f1b67be/7. KEI... · 2 OVERVIEW KANGEAN ENERGY INDONESIA LTD DIDI BASUKI VP SCM EAST

LOGISTIC MAP

8

Sirasun-Batur

16

2km

(8

0N

M)

Tanjungwangi Supply Base

Page 8: Overview KANGEAN ENERGY INDONESIA LTDscm.phe.pertamina.com/media/0e420c07-8b3e-4365-8c1d-a66f2f1b67be/7. KEI... · 2 OVERVIEW KANGEAN ENERGY INDONESIA LTD DIDI BASUKI VP SCM EAST

GAS BUYERS

Existing Metering System

New Metering System

80 BBTUD

65 BBTUD

60BBTUD

20BBTUD

TSB Field

Page 9: Overview KANGEAN ENERGY INDONESIA LTDscm.phe.pertamina.com/media/0e420c07-8b3e-4365-8c1d-a66f2f1b67be/7. KEI... · 2 OVERVIEW KANGEAN ENERGY INDONESIA LTD DIDI BASUKI VP SCM EAST

JAKARTA OFFICE

Wisma Mulia Building 25 – 26 Floor Jl. Jend. Gatot Subroto No 42

Jakarta - Indonesia

10

KEI OFFICE

SURABAYA REP OFFICE

Jl Raya Jemursari No 52 Surabaya – East Java

TANJUNGWANGI SHOREBASE

Jl. Raya Situbondo No.44, Desa Ketapang, Kecamatan Kalipuro, Banyuwangi 68451

Page 10: Overview KANGEAN ENERGY INDONESIA LTDscm.phe.pertamina.com/media/0e420c07-8b3e-4365-8c1d-a66f2f1b67be/7. KEI... · 2 OVERVIEW KANGEAN ENERGY INDONESIA LTD DIDI BASUKI VP SCM EAST

Thank You...

Copyright : KEI-SCM 2017