Outline
description
Transcript of Outline
Prototype flex hybrid and module designs for the ATLAS Inner Detector Upgrade
Ashley Greenall
The University of Liverpool
On behalf of the ATLAS Tracker Silicon Strip Upgrade Stave Programme
Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009 1
2
Outline
Introduction to the Stave (2009) concept Geometry and components
Stave flex hybrid, first steps Build considerations - preparing for mass production Prototype flex, a test vehicle for the 0.25µm ABCN-25 ASIC
Electrical performance (using untested ABCN-25) Short strip module demonstrator using ATLAS07 large area sensor (10cm x 10cm)
Bridged Hybrid Hybrid directly glued onto sensor
Summary
First stave module, a substrate-less and connector-less module Module concept and flex build
Current substrate-less hybrids Substrate-less stave hybrids and industrialisation Stave Readout architecture A first look at module integration onto a stave
Conclusions
Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
Stave 2009 – Geometry and components
Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
~ 1.2m (1200mm)
Bus cable
HybridsCarbon honeycomb
Carbon fiberfacing
Readout IC’s
P-type 4 segment crystals (10cm x 10cm) ABCN-25 readout ASIC
40 per module 960 per stave (>120k channels)
Kapton hybrid Auxiliary BCC asic (digital I/O) Serial Power protection
Embedded bus cable End of stave card Stave mechanical core
Coolant tube structure
3
Single flex Module with 2 x flex
120mm
Sensor
12 modules/side of stave
Stave flex hybrid – Build considerations
Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009 4
Hybrid layout is driven by minimising material Keep the area small! Engage ASIC and sensor designers to achieve this.
Eventually we will want to source in excess of 10000 pieces (for Barrel short-strip layers) Yield and reliability has to be taken into account from the outset Don’t push the limits on design rules (pertinent to feature size) Repeatability becomes problematic for non-standard capability – limits vendor choice
Manufacturability, feedback from UK (flex) manufacturers: Keep to standard 100µm track and gap routing to maintain yield Identified via lands (for plated-through holes) as critical, need to be >300µm
Ref: CMS had many problems with micro-vias (had to increase to 320µm to recover yield/stability) Settled on 375µm via lands with 150µm laser drilled holes
Kapton carrier (dielectric) should be no thinner than 50µm – handling issues during manufacture
Will be a staged design First stage – very cautious, new ASICs and sensors to be evaluated THIS IS WHERE WE ARE
Flex build is electrically ‘robust’ – maximal power planes and supply decoupling Second more aggressive stage – comes much later,
Reduction in hybrid mass (removal of non-critical passives, power plane reduction etc.)
S
M: Master (Legacy mode)
Mm: Master (Legacy mode + MCC I/O)
S: Slave
Common Bus serving 20 x ABCN-25
Primary Data O/P
Redundant Data O/P
MCC I/O (Data + Token)
Connector
Consists of 2 columns of ABCN-25s with a services connector
Readout Architecture is made up of
Single TTC Bus (BCOClk, Com, L1, DataClk)
Power Control Bus for serial powering circuitry
Auxiliary Analogue Supply routed to front-end of ABCN-25s
Alternatively make use onboard regulator for the front-end
Common Digital Supply provided for ABCN-25s
Legacy data paths at top and bottom of each column (maintains compatibility with existing DAQ)
Bi-directional data paths within columns can be exercised
Data & Token I/O for 2 leading ABCN-25s for use with an upgraded DAQ (if desired)
Column 0 Column 1
Prototype flex topology
Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009 5
S
S
S
S
S
S
S
Mm
M
S
S
S
S
S
S
S
S
Mm
M
ASIC – Sensor Detail
<16° bond angle
Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
Dialogue with designers
4.1mm
Se
nso
r b
on
d p
ad
s
Front-end Decoupling Capacitor
Early dialogue with ASIC and sensor designers lead to modifications to increase manufacturability and reduce mass...
Wire bond pad locations and ASIC size/placement fixed to allow for direct ASIC-to-sensor wire bonding
Pitch adaptors are no longer requiredLess mass and wire bonds
ASIC bond pads re-located:Inter-chip communication now provided by
wire bonds and not traces on the flex.Front-end decoupling capacitor positioned
for shortest bond length.
6
Vias
Flex build details4 layer build designed to qualify components i.e. ASICs and sensors and to prove signalling quality as fast as possible
Layer 1 & 2: SignalLayer3: Analogue and Digital PowerLayer4: Common Ground
Flex manufactured by Stevenage Circuits Ltd UK100µm track and gap375µm via lands with 150µm laser drilled holes50µm Kapton (polyimide) dielectrics
Digital Power
Analogue Power
Common Ground
Component Layer
Solder Resist (25µm)5µm Cu foil carrier + Ni/Au plating (5µm)Bond ply (50µm)Cu (18µm)Kapton (50µm)
Predicted build thickness is ~260µm, actual is ~280µm(uncertainty arises due to plating of outer layers)
Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009 7
Digital Bus
Hybrid Stuffed with Passives and 6 x ABCN-25s
Inter-chip bondingNeighbouring ABCN-25s wire bonded
7.5mm 7.5mm2.1mm
Flex Weight ≤2g (unpopulated)
Fully populated hybrid
24mm
8Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
Hybrid realisation
100
mm
Distributed decoupling capacitors adjacent to the ASICs for power supply decoupling - capacitance increases whilst inductance reduces (improves high frequency decoupling)
Sensor HV filter with guard ring
Transmission of fast LVDS signals (expected to be 160MHz for next generation ASICs), need to account Use of thin dielectrics for flex build, results in a high capacitance (~25pF on a 100m trace) further loading the bus Bus loading (up to 20 ASICs max)
Trace impedance set by width, thickness of dielectric and dielectric constant. Hybrid topology makes use of embedded edge-strip geometry for LVDS transmission. For proposed build using 100µm track and gap with 50µm dielectrics, ZDIFF ~ 71Ω.
But this does not take into account asic receiver loading (see plot below). 20 ASICs on bus reduces impedance to <50Ω.
Trace Impedance, Zdiff as function of 10 & 20 ASIC loading
0
10
20
30
40
50
60
70
80
1 2 3 4 5 6 7 8 9 10 11 12
Asic drops
Imp
edan
ce (
Oh
ms)
10 ASICs
20 ASICs
Unloaded Bus Loaded Bus
80Mbs PRBS
43Ω end termination
(2ns/div, 50mV/div)
160Mbs PRBS
43Ω end termination
(2ns/div, 50mV/div)
Electrical Performance – Signal Propagation
9Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
Eye diagrams for 20 ASIC Loading
•Hybrid tested at both 40MHz and 80MHz data rates (maximum that ABCN-25 operates at)•All 4 data paths from hybrid work - confirming ABCN-25 bi-directional I/O functions correctly
40MHz data readout
Gain: 105mV/fC
Input Noise: ≤400e ENC
Threshold variation:5.5mV before trimming, 1mV after trimming
Noise Occupancy
Electrical Performance – Hybrid results
10Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
80MHz data readout
After trimming
ASICs and hybrids working extremely well with high yield
Channel threshold spread
Channel threshold spread
ENC vs ChannelENC vs Channel
ENC vs Channel
Occupancy vs Channel
ATLAS Tracker Upgrade Week, 23rd-27th Feb 09
Short-strip module demonstrator with 10x10cm sensor
11Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
Overview
Al plate with machined bridge legs and cooling pipe (10°C glycol + water)
Sensor glued directly to fixture 2 layers of 75µm thick kapton
between Al plate and sensor HV connection through tab to
backplane Al plate referenced to ground of hybrid First hybrid bridged with 1mm thick Al
2mm air gap between hybrid and sensor
Second hybrid directly glued to sensor
Objective
Test the functionality of the ABCN-25 in a 20 ASIC hybrid bonded to a full size ATLAS07 sensorUsing untested ASICs
Check the noise performance and occupancyStability at low threshold of 0.5fC
ATLAS Tracker Upgrade Week, 23rd-27th Feb 09
First tests – Bridged hybrid
12Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
Bridge grounded to plate Thermal grease applied to cooling
points Hybrid operating at 40°C i.e. 30° above
coolant temperature (coolant at 10°C) Peak currents >4A during readout Token passing non-functioning between
chips 5 and 6 (damaged bond pad) All chips work BUT only able to
readout 15 chips at a time
Noise Slope
• Able to join 2.5cm segments of sensor to single ABCN-25 e.g. 2.5cm, 5cm and 7cm strip lengths
• Also have bare hybrid plus 1cm silicon strip measurement
• Sensor design provides 1pF/cm load
2.5cm
5cm
7.5cm
ATLAS Tracker Upgrade Week, 23rd-27th Feb 09
Preliminary Noise slope
13Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
With separate analogue/digital power
With analogue regulator
Bare Hybrid
400-450 e- 400-450 e-
1 pF 525 e-
2.5 pF 605 e- 575 e-
5 pF 986 e- 952 e-
7.5 pF 1364 e- 1313 e-
Noise prediction from ASIC designers with no detector leakage
Measured noise is slightly higher than that expected from simulation – especially above 2.5pF load
ATLAS Tracker Upgrade Week, 23rd-27th Feb 09
Bridged Hybrid Electrical Performance
14Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
Module tested with front-end regulator enabledSingle Digital power feed to all ASICs
Input Noise is as expected at ~600e-
Open circuit channels are due to wire-bonding problems Al plate hybrid is mounted on is not rigid enough – makes it difficult to bond
Noise Occupancy at 1fC is <10-6
Shows a very regular uniform profile across all channelsClearly shows the 5 ASICs we are unable to readout
Noise Occupancy
ENC vs Channel
Occupancy vs Channel
ATLAS Tracker Upgrade Week, 23rd-27th Feb 09
Directly Glued Hybrid on to Sensor
15Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
p- bulk p-spray/stop
Passivation
Hybrid
Kapton (75 m)
Kapton (150 m)Copper (75 m)
Glue(~20 m)
Hybrid was not designed to be glued directly to sensor Vias go right through the flex circuit – results in a perforated ground plane No shielding of the digital bus is provided
Copper shield added between hybrid and sensor Insulated from hybrid and sensor Can be referenced to hybrid ground if desired
Hybrid operates at 24°C during readout (compare with the bridged hybrid of 40°C)
Glue was only applied on passivated regions of sensor, maintaining a clearance of 5mm from the guard-rings.
ATLAS Tracker Upgrade Week, 23rd-27th Feb 09
Glued Hybrid Electrical Performance
16Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
With the screen connectedTo either module ground or HVretChannels towards the edges of the ASICs
have elevated noiseInput noise is ~650e-
With the screen floatingNoise profile is flatInput noise is ≤600e-
Performance is comparable to Bridged Hybrid
Shield Connected Shield Open Circuit
Occupancy vs Channel
ENC vs Channel ENC vs Channel
ATLAS Tracker Upgrade Week, 23rd-27th Feb 09
Glued Hybrid Electrical Performance – Low Threshold Stability
17Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
Scurves at 0.5fC threshold show no instability with 2.5cm sensor strips bonded
Scurve distortion is due to wire-bonding (see next slide)
ATLAS Tracker Upgrade Week, 23rd-27th Feb 09
Wire-Bonding Problems
18Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
• Identified that glued hybrid is 400µm off centre w.r.t. sensor
• Results in increased bond-angle from ASIC to chip
• Bonds at chip-edges are at 12-21° angle• Anything >16° is at risk of shorting to
neighbouring bond pads on ABCN-25• This is what we see on the noise plots
• Problem with bonding of front-end ground pads • Wire bonds are orthogonal to pad
• Pad is too narrow for the bond foot• Adhesion of bonds is not so good
• Revised layout of flex will correct for this
ATLAS Tracker Upgrade Week, 23rd-27th Feb 09
Prototype flex/module Summary
19Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
First batch of flexes arrived towards the end of last year – 36 totalYield of 89% was achievedShould increase to ≥98% during production run (achieved by process tuning)Yield enhancement is part of the design stage – high yield translates into a reliable
object
Hybrid performs as expected – untested ASICsHybrids have been successfully used at 4 different sitesWire-bonded at 2 sites with no problems
For the module, bridged and glued hybrids have similar electrical performanceBoth stable at 0.5fC thresholdNoise is higher than predicted from simulation
No show stoppers identified for Stave hybrid
ATLAS Tracker Upgrade Week, 23rd-27th Feb 09
Stave Module Concept
20Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
•Flex circuit is designed at the outset for direct gluing to the sensor•Core of the circuit (trace routing, component placement remains as prototype) – it works•But will have to revise the flex build to take into account additional shield layer
•Sensor provides mechanical support and thermal management
•Prior to gluing the flex circuit to the sensor the flex is not rigid•Need to stuff with passives/ASICs and then test before gluing on to the sensor
Furthermore
•Have to take into account integration of the module on to a stave
•Stave design calls for a connector-less system•All connectivity is made by wire-bonds to/from a bus cable•Bus cable is a single-layer design – results in connections at opposing ends of flex
•Would like to maintain maximum flexibility for stave module – especially true for powering•Default powering is serial •But power/protection board has provision for auxiliary plug-in boards (for DC-DC, etc/)
•Also start looking at industrialisation of flexes•Component stuffing and testing
Sensor
ATLAS Tracker Upgrade Week, 23rd-27th Feb 09
Stave Module Layout
21Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
Flex is a 4+1 layer build (4 electrical + shield layer)
Layer 1 Signal Layer 2-3 Signal/Power Layer 4 Non-split Ground Layer 5 Shield (single-point contact with option
to connect to module ‘ground’ or leave open)
Inner layer Cu thickness is 18µm Top layer is 5µm Cu with Ni/Au plating Shield is 5µm Cu Kapton dielectric thickness is 50µm
Total build thickness is ~300µm
Power/Protection Board
‘M’ Shunt Regulation Control Circuit
Digital I/O - BCC
97.6mm
5mm
6.2mm
6.2mm
5mm
24mm
TTC & Data Bus
Serial Power, Control & Sensor Bias
Sensor HV Filter Circuit +Power In/Out to flex
AB
CN
-25
fle
x
AB
CN
-25
fle
x
Stave 2009 – Readout Architecture
Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009 22
Module 1 Module 2 Module 12
TTC
Data
PwrIn
PwrOut
TTC (L1, Command and 40MHz clock) is broadcast as multi-drop LVDS to all modules 24 drops in total with ac-coupled receivers Non-balanced data transmission
2 data output links per module, 1 per flex Point-to-point LVDS Up to 160Mbs data rate AC-coupled, non-balanced data transmission
Default powering scheme is serial Flexes sat at differing voltage potentials (2.5V per flex, 60V total across a stave) Parallel (DC-DC) powering is also provided for
Independent parallel sensor biasing (12 x HVbias + return) Single NTC thermistor per flex for temperature monitoring
BufferControlChip provides digital I/O
Serial powering
Digital I/O
Sensor bias
ATLAS Tracker Upgrade Week, 23rd-27th Feb 09
How to make a substrate-less hybrid
23Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
Flex circuit composed of 2 components
1. Main active circuit (non-glued)
2. Sacrificial ends which are glued to FR4
Circuit sits flat on a rigid FR4 base
Drilled for vacuuming down
Sacrificial ends
Main circuit
I/O bond pads
Step 1
Step 2 Step 3
Final step, circuit + sensor removed
Sacrificial ends (retained)
Initiated a program to investigate working with substrate-less hybridsTry to learn as much as possible from the pixel community
Kindly sent jigs to show steps involved in their module construction (see below)Dialogue set up with both flex and circuit population companies.
ATLAS Tracker Upgrade Week, 23rd-27th Feb 09
Stave substrate-less hybrids and industrialisation
24Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
Flexi-rigid construction with flexes selectively glued to a FR4 Panel.8 flexes per panel.Panel is 300mm x 200mm.Matches up to auto-placement machine (passive stuffing geared for industry)Various hole detail shown are used for wire-bonding and module assembly jigs
Panel designed so that flexes can be electrically tested as 1 to 8 items (using legacy or future DAQ)
Active part of flex – not glued to FR4
Score line is used as guide for cutting out of flexes
Sacrificial ends of flex, cut off during flex removal (beyond score line)
DAQ Connector(s)
Power
Bond pads
ATLAS Tracker Upgrade Week, 23rd-27th Feb 09
Stave Integration – Bus Cable Detail
25Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
Bus Detail (100µm track & gap)Segmented Shield Detail
(showing break between adjacent modules) Continuous Shield
Serial Power Return (7mm width)
TTC multi-drop Busand Module Data
Power, Control & Sensor Bias
Plots courtesy of Carl Haber & Roy Wastie
1200mm
120mm
Bond Pads
Flexes are DC connected to their respective shield
Flexes are AC connected to the
shield
• Modules (sensor + flex) glued onto stave – embedded bus cable sits between stave core and module• Bus cable used to distribute services to module(s) – digital I/O, power, sensor bias etc. – connections made by wire-bonds• Cable build is single layer Cu Kapton + Al shield on top layer (2 flavours of shield, segmented and continuous to be evaluated)
ATLAS Tracker Upgrade Week, 23rd-27th Feb 09
Conclusions
26Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
For the ATLAS Inner Detector and the large number of circuits required, it is important to plan at the outset for manufacturability and reliability.
Dialogue should be set up during the design phase between ASIC, hybrid and sensor designers.This is also true for industrial partners
Hybrid operation has shown nothing untoward – performance is as expected!
Module demonstrator has also been shown to perform wellFirst time an ATLAS07 large area sensor has been bonded to full 20 x ABCN-25 readoutNoise is slightly higher than expectedBUT no show stoppers as yet identified
Have now migrated to ‘next generation’ hybrid designed for integration onto a stave.
Submission took place over the summer and flexes are due imminent.If no problems identified expect flex passive/ASIC stuffing and testing in the near future.
Furthermore module integration onto a stave structure is well understood – now awaiting modulesBus cables have been received and are ready for assembly on to a stave.
ATLAS Tracker Upgrade Week, 23rd-27th Feb 09
Backup
27Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
Sensor biasing and gluing
28Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
Concerns about gluing hybrid assembly directly to the sensorIs there a risk of damaging the sensor – especially the sensitive guard ring structure
Limited maximum sensor bias to 200VReduces the risk of micro-discharge
Before assembly sensor current is 0.8µAAfter gluing to Al fixture 0.8µAAfter wire-bonding of front-end of bridged hybrid 3.1µAAfter directly gluing of hybrid to sensor 2.9µAAfter wire-bonding of front-end of glued hybrid 3.0µA
Some slight damage occurred during the wire-bonding of the bridged hybrid to the sensor
Otherwise no effect observed due to gluing of hybrid to sensor
Before Irradiation, 20°C
2 Epolite glued miniature sensors were irradiated at CERN PS to 9.3×1014 neq cm-2. Before irradiation, W17-BZ3-P15 showed some breakdown above 950 V before gluing (blue circles). W31-BZ3-P9 goes to 1000V.
After irradiation, W17-BZ3-P15 shows breakdown above 1000 V. W31-BZ3-P9 goes to 1100 V. The currents are consistent with the expected fluence.
No measurable effects from the epoxy on the surface
After Irradiation, -25 C
24 GeV Proton Irradiation Results
29Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
Irradiated to 1.5×1015 p cm-2 at CERN (9.3×1014 neq cm-2)No measurable effect of glue relative to similar irradiations
Using fit of clustered charge, efficiency at 500 V near 100% at threshold of 1 fC for 1×1 cm2. Would expect 0.75 fC needed for 2.5 cm strips.
30Topical Workshop on Electronics for Particle Physics Paris, September 21-25, 2009
24 GeV Proton Irradiation Results (2)