Office of the Federal Coordinator for Meteorology OFCM Assessment of MPAR Capability to Meet Agency...

16
Federal Coordinator for Meteorology Assessment of MPAR Capability to Meet Agency Needs Jud Stailey, OFCM Executive Secretary, MPAR EC December 14, 2009 1 Multifunction Phased Array Radar (MPAR)

Transcript of Office of the Federal Coordinator for Meteorology OFCM Assessment of MPAR Capability to Meet Agency...

Page 1: Office of the Federal Coordinator for Meteorology OFCM Assessment of MPAR Capability to Meet Agency Needs Jud Stailey, OFCM Executive Secretary, MPAR EC.

Office of the Federal Coordinator for Meteorology OFCM

Assessment of MPAR Capability to Meet Agency

Needs

Jud Stailey, OFCM

Executive Secretary, MPAR EC

December 14, 2009 1

Multifunction Phased Array Radar (MPAR)

Page 2: Office of the Federal Coordinator for Meteorology OFCM Assessment of MPAR Capability to Meet Agency Needs Jud Stailey, OFCM Executive Secretary, MPAR EC.

MPAR Risk-Reduction Strategy

08 09 10 11 12 13 14 15 16 17 18 19 20Fiscal Year

RDT&ENSSL, MIT/LL, others

NWRT

Demo 1Wx

Demo 2Wx/Acft

Algorithm Dev Algorithm & Software Dev

Tradeoff Analyses

Testing

Upgrade to Active Sub-array

Scan Strategies

FAA IOC for Wx &

ASR

RFI

Concept Def3 Contractors, FP

Solicit

Industry Day

AwardRFP

2 Contractors, CPFF

Fly-Off Full

RFP Dev

Solicit

RFP

RFP Dev

Award

Cost-Benefit Study

Pre-Prod Model

RFP Dev

Dev

Limited Prod1 Contractor, CPFF

Solicit

Award

OT&EDT&E

Concept Definition /

System Development

Analysis of Alternatives

Siting/SpectrumSite Surveys

Site Acq & Prep

Spectrum Approvals

Spectrum & Siting Requirements Analysis

Management Approach

Agency InternalTest & Eval Org

Ops Support Org

Program Council Oversight

Joint System Program Office

Ops Concept Development

Reqts Analysis

Reqts Def Definition & Refinement

Employment ConceptRefinement

P3I DevTradeoffs – Design to Budget

Refinement

DOD CPDDOD CDDDOD ICD

DOD FSA DOD POM Bld

DOD DP

DOD DPDOD DP

KDP1 (Def need, priority, and $)

KDP2 (Select design & move to demo/test)

KDP3 (Full Scale Dev)

KDP4(Full Prod)

DOD DP

DOD DP

Mission & Service Needs Analysis andRequirements

BASC Study

Svc Analysis

FAA DPFAA DP

FAA DP

Init Acq Review Wx & Air

Replace ASR-8/9?

Replace 88D?

Page 3: Office of the Federal Coordinator for Meteorology OFCM Assessment of MPAR Capability to Meet Agency Needs Jud Stailey, OFCM Executive Secretary, MPAR EC.

Ops Concept Development

Reqts Analysis

Reqts Def Definition & Refinement

Employment ConceptRefinement

P3I DevTradeoffs – Design to Budget

Refinement

DOD CPDDOD CDDDOD ICD

DOD FSA DOD POM Bld

DOD DP

DOD DPDOD DP

KDP1 (Def need, priority, and $)

KDP2 (Select design & move to demo/test)

KDP3 (Full Scale Dev)

KDP4(Full Prod)

DOD DP

DOD DP

Mission & Service Needs Analysis andRequirements

BASC Study

Svc Analysis

MPAR Risk-Reduction Strategy

08 09 10 11 12 13 14 15 16 17 18 19 20Fiscal Year

RDT&ENSSL, MIT/LL, others

NWRT

Demo 1Wx

Demo 2Wx/Acft

Algorithm Dev Algorithm & Software Dev

Tradeoff Analyses

Testing

Upgrade to Active Sub-array

Scan Strategies

FAA IOC for Wx &

ASR

FAA DPFAA DP

FAA DP

Init Acq Review Wx & Air

Replace ASR-8/9?

Replace 88D?

Page 4: Office of the Federal Coordinator for Meteorology OFCM Assessment of MPAR Capability to Meet Agency Needs Jud Stailey, OFCM Executive Secretary, MPAR EC.

MPAR Risk-Reduction Strategy

08 09 10 11 12 13 14 15 16 17 18 19 20Fiscal Year

RDT&ENSSL, MIT/LL, others

NWRT

Demo 1Wx

Demo 2Wx/Acft

Algorithm Dev Algorithm & Software Dev

Tradeoff Analyses

Testing

Upgrade to Active Sub-array

Scan Strategies

RFI

Concept Def3 Contractors, FP

Solicit

Industry Day

AwardRFP

2 Contractors, CPFF

Fly-Off Full

RFP Dev

Solicit

RFP

RFP Dev

Award

Cost-Benefit Study

Pre-Prod Model

RFP Dev

Dev

Limited Prod1 Contractor, CPFF

Solicit

Award

OT&EDT&E

Concept Definition /

System Development

Analysis of Alternatives

Siting/SpectrumSite Surveys

Site Acq & Prep

Spectrum Approvals

Spectrum & Siting Requirements Analysis

Management Approach

Agency InternalTest & Eval Org

Ops Support Org

Program Council Oversight

Joint System Program Office

FAA DPFAA DP

FAA DP

Init Acq Review Wx & Air

Replace ASR-8/9?

Replace 88D?FAA IOC for Wx &

ASR

Ops Concept Development

Reqts Analysis

Reqts Def Definition & Refinement

Employment ConceptRefinement

P3I DevTradeoffs – Design to Budget

Refinement

DOD CPDDOD CDDDOD ICD

DOD FSA DOD POM Bld

DOD DP

DOD DPDOD DP

KDP1 (Def need, priority, and $)

KDP2 (Select design & move to demo/test)

KDP3 (Full Scale Dev)

KDP4(Full Prod)

DOD DP

DOD DP

Mission & Service Needs Analysis andRequirements

BASC Study

Svc Analysis

Page 5: Office of the Federal Coordinator for Meteorology OFCM Assessment of MPAR Capability to Meet Agency Needs Jud Stailey, OFCM Executive Secretary, MPAR EC.

Office of the Federal Coordinator for Meteorology OFCM

5

Assessment of MPAR Capability

BackgroundWG/MPAR challenges to establishing requirements:

•Number of agencies and relationship•Different agency definitions and processes•Different potential role of MPAR in terms of meeting discrete versus broad needs

•Different level of understanding of potential MPAR capabilities

•Lack of the right resources to do the work

Page 6: Office of the Federal Coordinator for Meteorology OFCM Assessment of MPAR Capability to Meet Agency Needs Jud Stailey, OFCM Executive Secretary, MPAR EC.

Office of the Federal Coordinator for Meteorology OFCM

6

Assessment of MPAR Capability

BackgroundAction Item from MPAR Symposium II:

•Mission needs assessment• Identify current radar-related shortfalls and

needed improvements• Consider both technology / equipment and

services

Page 7: Office of the Federal Coordinator for Meteorology OFCM Assessment of MPAR Capability to Meet Agency Needs Jud Stailey, OFCM Executive Secretary, MPAR EC.

Office of the Federal Coordinator for Meteorology OFCM

7

Assessment of MPAR Capability

Approach

Start with potentially easier to define needs:

•FAA Replacement of ASRs and TDWR•Replacement of long range radars (?)

Page 8: Office of the Federal Coordinator for Meteorology OFCM Assessment of MPAR Capability to Meet Agency Needs Jud Stailey, OFCM Executive Secretary, MPAR EC.

Office of the Federal Coordinator for Meteorology OFCM

8

Assessment of MPAR Capability

Approach (Cont’d)Address more complex needs:

•NWS weather surveillance• CORL & Weather Radar 20-Year Vision Planning

Report• Weather Service Improvements diagram

•Homeland/National Defense Air Surveillance:• IS CONOPS, NORAD input, other available data• Air Surveillance Service Improvements diagram

Page 9: Office of the Federal Coordinator for Meteorology OFCM Assessment of MPAR Capability to Meet Agency Needs Jud Stailey, OFCM Executive Secretary, MPAR EC.

Office of the Federal Coordinator for Meteorology OFCMMultifunction Phased Array Radar9

Page 10: Office of the Federal Coordinator for Meteorology OFCM Assessment of MPAR Capability to Meet Agency Needs Jud Stailey, OFCM Executive Secretary, MPAR EC.

Office of the Federal Coordinator for Meteorology OFCM10

Page 11: Office of the Federal Coordinator for Meteorology OFCM Assessment of MPAR Capability to Meet Agency Needs Jud Stailey, OFCM Executive Secretary, MPAR EC.

Office of the Federal Coordinator for Meteorology OFCM

Assessment of MPAR Capability

11

FAA ASR & TDWR Needs

DoD LRR Needs

NWS Weather Observing

Needs (CORL)

DHS Surveillance

Needs

Page 12: Office of the Federal Coordinator for Meteorology OFCM Assessment of MPAR Capability to Meet Agency Needs Jud Stailey, OFCM Executive Secretary, MPAR EC.

Office of the Federal Coordinator for Meteorology OFCM

Assessment of MPAR Capability

12

FAA ASR TDWR Needs

DoD LRR Needs

NWS Weather Observing

Needs (CORL)

DHS Surveillance

Needs

MPAR Capabilities

Page 13: Office of the Federal Coordinator for Meteorology OFCM Assessment of MPAR Capability to Meet Agency Needs Jud Stailey, OFCM Executive Secretary, MPAR EC.

Office of the Federal Coordinator for Meteorology OFCM

Assessment of MPAR Capability

13

FAA ASR TDWR Needs

DoD LRR Needs

NWS Weather Observing

Needs (CORL)

DHS Surveillance

Needs

MPAR Capabilities

Page 14: Office of the Federal Coordinator for Meteorology OFCM Assessment of MPAR Capability to Meet Agency Needs Jud Stailey, OFCM Executive Secretary, MPAR EC.

Office of the Federal Coordinator for Meteorology OFCM14

Approach• Not creating a programmatic document

• Every agency has a different acquisition system

• May not have the same documents• Even if they have the same documents, the

requirements for those documents will not be the same

• Avoid using a standard name for product• Could follow an agency’s template

Assessment of MPAR Capability

Page 15: Office of the Federal Coordinator for Meteorology OFCM Assessment of MPAR Capability to Meet Agency Needs Jud Stailey, OFCM Executive Secretary, MPAR EC.

Office of the Federal Coordinator for Meteorology OFCM15

Approach (Cont’d)•At some point a program office will get agency agreement on a procurement model

•At this point we should create documentation that meets our needs

• Understanding what agencies need• Helping define technical challenges and prioritize

work (input to R&D Plan)• Educating decision makers on what needs MPAR

can meet

Assessment of MPAR Capability

Page 16: Office of the Federal Coordinator for Meteorology OFCM Assessment of MPAR Capability to Meet Agency Needs Jud Stailey, OFCM Executive Secretary, MPAR EC.

Office of the Federal Coordinator for Meteorology OFCM16

Recommendation Task WG/MPAR to

• Consider and define the potential applications for needs assessment

• Determine the type of needs information that would suit those applications

• Gather the needs information

• Assess the capability of MPAR to meet the multi-agency needs

Assessment of MPAR Capability