Oerview of Procurement and Materials Management in Contracts

download Oerview of Procurement and Materials Management in Contracts

of 30

Transcript of Oerview of Procurement and Materials Management in Contracts

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    1/30

    OVERVIEW OF PROCUREMENT AND

    MATERIALS MANAGEMENT IN CONTRACTS

    By

    Dr. S.S.Seehra

    Additional Director (Highways)

    Intercontinental Consultants and Technocrats Pvt. Ltd. &

    Former Director Grade Scientist & Head,

    Rigid Pavements Division,

    Central Road Research Institute, New Delhi.

    Intercontinental Consultants & Technocrats Pvt Ltd.

    New Delhi

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    2/30

    GENERAL Project overruns attributable to delay in the supply ofcritical equipment and materials are very common in

    India.

    Delayed delivery, manufacturing defects, incorrect

    specifications, belated replacements, pilferage, shortage,etc., are common problems in almost all projects.

    Very early supply of some items also, with resultant longstorage, leading to deterioration, is not uncommon.

    A vigilant project management can ward of much of theseproblems by proper planning and control of procurementand efficient post procurement materials management.

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    3/30

    PROCUREMENT MATERIALSCHEDULING AND COVERING

    Critical equipment and bulk materials

    Mechanical

    Electrical

    Instruments

    Refractories

    Construction equipments

    Civil Engineering materials and other bulk materials

    Project Consumables

    Raw materials and feed back

    Lubricants, spares and manufacturing consumables

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    4/30

    PROCUREMENT PLANNING ANDCOVERING

    Indenting

    Buy or make decision

    Bid documents preparation

    Asking for bids/quotations

    Bids evaluation

    Acceptance and approval

    Ordering

    Vendors confirmation

    Inspection, testing and quality assurance

    Expediting

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    5/30

    contd . . . Risk-purchase and contingency plans

    Ex-factory delivery

    Packing and despatching

    Insurance

    Transport and clearances

    Receipt, checking and tallying

    Transit damage/shortage reports

    Replacement supplies

    Logistics planning

    Procurement budgeting

    Implementation of the plans

    A purchase function assisted by finance department

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    6/30

    MATERIALS MANAGEMENT (MM) MM covers storage and control of the flow of materials

    from the on-site delivery point to the sites of consumptionor use or incorporation.

    Procurement and MM are the interface between thedemand and supply of materials to ensure success of theproject.

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    7/30

    PROCUREMENT OF MATERIALS CLASSIFICATION OF PROCUREMENT

    Bought-out equipment and components designed byvendors for any particular project such as boilers, pumps,motors, valves, etc.

    Equipment by turnkey contractors as a part of their totalpackage

    Designed and ordered by the enterprise

    Bulk materials like sand, bricks, pebbles, cements, steel,lime wood, piping, insulation materials and cables basedon engineering drawings for all the work segmentstogether.

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    8/30

    Contd . . .

    Consumables and loose tools specifically needed in theconstruction such as binding wires, nails, screws, bolts,

    nuts, washers, gas, electrodes, cutting and grindingwheels, petrol, oil, lubricants, cotton waste, etc. and toolsother than construction equipment. Depending on theapproach to be adopted for construction, these may ormay not form part of the contractors obligations.

    Construction equipment like cranes, derricks, winches,shovels, dumpers, trucks, tractors, trailers, compressors,welding equipments, fabrication and machine shopequipment, etc.

    Administration equipment and materials like motorvehicles, air conditioners, refrigerators, office equipment,etc. for facilitating administration work. Printing andstationery also might be bracketed with this class.

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    9/30

    PROCUREMENT ORGANIZATION ANDUSE OF PROCUREMENT AGENTS

    Whether project procurement should be under the projectmanager (PM), or be independent of him, is a matter forthe top management to decide on the considerations ofefficiency.

    In projects where procurement is complex, if the owner orthe turnkey contractor does not have the necessaryorganization to handle it, procurement agents may beemployed.

    Procurements agents are generally well-versed in nationaland international procurement in line with the WorldBank guidelines. Documentation and clearances are also

    handled by them.

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    10/30

    MATERIALS SCHEDULING The first step in materials scheduling is listing. This is

    done by project Engineer (PE) on the basis of drawings orother engineering details.

    Materials scheduling which follows the listing is donewith reference to on-site delivery times to suit the work

    schedule

    All key materials shall be scheduled in the form ofnetwork manually or on computer to facilitate timelyaction.

    Delivery scheduling of materials is purely a PM functionbut procurement scheduling is a purchase function.

    In Indian conditions it is presently too much to expect ajust-in-time delivery of materials that will straightway gointo the work.

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    11/30

    PROCUREMENT PLANNING

    In the detailed procurement planning, every action step isnecessary to deliver all materials on the site as perschedule of the orders of PM.

    The lowest bid gets the order Vendors confirmation of the order

    Expediting by the owners buyers

    Manufacturing by the vendor

    Quality control and inspection

    Packing of materials to the site

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    12/30

    Contd . . .

    Risk of the neglecting vendor risk purchase clausegives the owner the right to get the order executed byothers at the cost and risk of neglecting vendor.

    Procurement budget and cost control

    Procurement through turnkey contract covering the

    composite responsibility of engineering, design,manufacturing and/or supply of materials, constructionand commissioning.

    Logistics planning it is a major planning of project

    activity loading, transport, port clearance unloading,storage facilities and site transportation, etc.

    The turnkey contractor may take the responsibility ofocean/inland transport of materials loading and

    unloading depending upon the contract conditions.

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    13/30

    LEGAL ASPECTS OF PURCHASINGCONTRACTS

    Every purchase order is a contract involving several legalprovisions.

    Every bit of it should be legally worded

    The procurement department has to handle customs,excise, sales, tax claims against the enterprise and disputesraised by the vendors. The department should, therefore,have a legal cell.

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    14/30

    MATERIALS MANAGEMENT (MM) MM is strictly a part of construction management

    Poor MM delays the projects and leads to even costoverruns.

    Checking of materials on arrival

    Recording the receipts in the engineering documents.

    Storage on site, handling and retrieval

    Risk management

    Rectifications, repairs and replacements at site.

    Inventory control

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    15/30

    Contd

    Wastage and damage during usage/erection

    Owners supplies to Contractors

    Transfers to general maintenance stock

    The project manager (MM) and chief materials manager(CMM) should have thorough knowledge of the presentand future supply vis--vis the demand of the project.

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    16/30

    CONTRACTING AND CONSTRUCTIONMANAGEMENT (CCM)

    Contracting is the process of establishing a relationbetween the owner and the contractors to execute theproject work, mainly construction.

    It has many legal and commercial facets, and, therefore, itshandling calls for specialized knowledge and practicalexperience more importantly in the following:

    Indian Contract Act, 1872

    Indian Arbitration Act, 1940

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    17/30

    TYPES OF CONTRACTS

    The popular types of contracts are:

    Turnkey contract

    Measurement contract

    Lumpsum works contract

    Item rate contract

    Piece rate work

    Labour supply contract

    Hybrid contract

    Fixed price and variable price contract

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    18/30

    CONTRACTING PROCEDURE

    Contracting procedure is more or less the same asprocurement procedure. The usual steps in contractingare the following:

    Work packaging

    Preparation of tender documents Determination of the contractors; qualifications to

    undertake the work package

    Pre-qualification of contractors

    Tender invitation

    Tender submission

    Tender opening

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    19/30

    Contd. . .

    Evaluation and recommendations

    Approval of contract

    Award of contract

    Signing of agreement with detailed contract conditions

    Drawings, bills of quantities and technical specifications

    Schedule of rates

    General conditions of contract

    Special conditions of contract

    Specimens of bank guarantees

    Size of the contract package should be neither too largenor too small for one or more reputed contractors to

    handle.

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    20/30

    CONCLUSIONS

    Efficient procurement and materials management lead to

    project success.

    Timely on-site delivery of materials to suit theconstruction schedule will greatly avoid time overruns

    By proper planning and vigilant follow-up actions, this

    should be made possible

    Procurement of materials should be planned with prefectintegration into the engineering and constructionschedules.

    As approximately 60% of the project cost is spent onmaterials, close control on procurement cost is necessaryfor controlling the overall project cost.

    Management of materials after their on-site delivery isimportant project activity.

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    21/30

    Contd . . .

    Storage and control of the flow of materials from the on-site delivery points to the sites of incorporation/use needvigilant attention by the project team and the materialsdepartment, so that every piece of materials is availablewhen required at project site.

    In projects there is a need for a good inventory control,which will result in preventing long storage time, massivestock, storage risks and above all, will ensure the timelysupply of the required items for an efficient projectimplementation.

    A just-in-time (JIT) supply and inventory controltechnique is not workable in the Indian projects.

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    22/30

    Contd

    In variable price contract the prices are subject to

    variations according to the rate of inflation in the country,on some agreed formula. In fixed price contract, the pricesremain fixed throughout the contract period except forfluctuations in taxes, duties and statutory levels.

    In long-term contracts normally no contractor would agreeto the fixed price condition, especially in an inflationaryeconomic situation.

    Contract for every package must be awarded sufficientlyin advance of the starting date of the work so that thecontractor is able to mobilize his resources and move inbefore the starting date.

    Crisis situations should be avoided at every step in theinterest of overall efficiency of the project.

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    23/30

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    24/30

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    25/30

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    26/30

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    27/30

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    28/30

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    29/30

  • 7/28/2019 Oerview of Procurement and Materials Management in Contracts

    30/30

    THANK YOU