Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or...

70
June 19, 2012 Local Government Energy Program Energy Audit Final Report Ocean County Vocational Technical School Jackson Center 850 Toms River Road Jackson, NJ 08527 Project Number: LGEA100 Steven Winter Associates, Inc. 293 Route 18 South, Suite 330 Telephone (866) 676-1972 Building Systems Consultants East Brunswick, NJ 08816 Facsimile (203) 852-0741 www.swinter.com

Transcript of Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or...

Page 1: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

June 19, 2012

Local Government Energy Program

Energy Audit Final Report

Ocean County Vocational Technical School Jackson Center

850 Toms River Road Jackson, NJ 08527

Project Number: LGEA100

Steven Winter Associates, Inc. 293 Route 18 South, Suite 330 Telephone (866) 676-1972 Building Systems Consultants East Brunswick, NJ 08816 Facsimile (203) 852-0741 www.swinter.com

Page 2: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 2/70

Table of Contents

EXECUTIVE SUMMARY ................................................................................................................. 3

INTRODUCTION ............................................................................................................................. 5

HISTORICAL ENERGY CONSUMPTION ........................................................................................ 6

EXISTING FACILITY AND SYSTEMS DESCRIPTION .................................................................. 12

PROPOSED ENERGY CONSERVATION MEASURES ................................................................ 25

PROPOSED FURTHER RECOMMENDATIONS ........................................................................... 37

APPENDIX A: EQUIPMENT LIST ................................................................................................. 40

APPENDIX B: JACKSON CENTER FLOOR PLAN ...................................................................... 46

APPENDIX C: LIGHTING STUDY ................................................................................................. 46

APPENDIX D: SOLAR PV SHADING ANALYSIS ......................................................................... 50

APPENDIX E: ENERGYMISER CALCULATIONS ........................................................................ 54

APPENDIX F: COST WORKS COST ESTIMATES ....................................................................... 55

APPENDIX G: UPCOMING EQUIPMENT PHASEOUTS .............................................................. 57

APPENDIX H: THIRD PARTY ENERGY SUPPLIERS .................................................................. 59

APPENDIX I: GLOSSARY AND METHOD OF CALCULATIONS ................................................. 61

APPENDIX J: STATEMENT OF ENERGY PERFORMANCE FROM ENERGY STAR® ............... 65

APPENDIX K: INCENTIVE PROGRAMS ...................................................................................... 66

APPENDIX L: ENERGY CONSERVATION MEASURES .............................................................. 69

APPENDIX M: METHOD OF ANALYSIS ...................................................................................... 70

Page 3: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 3/70

EXECUTIVE SUMMARY The single-story slab on grade 54,000 square feet OCVTS Jackson Center Vocational & Technical School was built in 1971 with an addition built on to the southeast side of the building in 1981. It is a rectangular shaped building layout. The shops are large garage like rooms where students are able to get hands on experience on different technical trades, such as auto mechanics, electrical trades, aviation, cabinetmaking, agriculture, collision repair, plumbing, and cosmetology. Each shop room consists of a bathroom, tool room, locker/dressing area, small classroom, and a small office. In addition to the shop rooms there is a faculty room, main office, nurse’s office, principal’s office, and a computer lab. The building has undergone several renovations since it was built. Such renovations and upgrades include pieces of mechanical equipment, a roof replacement above the 1981 section, new windows, T5 fixture upgrades and installed occupancy sensors. The following chart provides a comparison of the current building energy usage based on the period from January 2011 through December 2011 with the proposed energy usage resulting from the installation of recommended Energy Conservation Measures (ECMs) excluding any renewable energy:

Table 1: State of Building—Energy Usage

Electric Usage

(kWh/yr)

Fuel Oil Usage

(gallons/yr)

Current Annual Cost of

Energy ($)

Site Energy Use Intensity (kBtu/sq. ft.

/yr)

Source Energy Use

Intensity (kBtu/sq. ft.

/yr)

Joint Energy Consumption (MMBtu/yr)

Current 393,453 24,934 $141,766 88.6 147 4,783 Proposed 277,928 21,607 $108,744 75.1 114 4,057 Savings 115,525 3,328 $33,021* 13.5 33 727

% Savings 29.4% 13.3% 23.3% 15.2% 22.6% 15.2% Proposed

Renewable Energy**

162,422 0 $144,485 10.3 10.3 554

*Includes operation and maintenance savings; **Includes SRECS SWA has entered energy information about the Jackson Center facility into the U.S. Environmental Protection Agency’s (EPA) Energy Star Portfolio Manager Energy Benchmarking system. The building has an Energy Star Rating of 34 and a Site Energy Utilization of 89 kBtu/sqft/yr. Recommendations Based on the current state of the building and its energy use, SWA recommends implementing the following Energy Conservation Measures:

Table 2: Energy Conservation Measure Recommendations

ECMs First Year Savings ($)

Simple Payback Period

Initial Investment ($)

CO2 Savings (lbs/yr)

0-5 Year $32,285 1.0 $33,812 235,577 >10 year $736 12.4 $9,100 7,952 Total $33,021 1.3 $42,912 243,528 Proposed Renewable Energy

$144,485 4.6 $670,800 290,817

Energy Conservation Measure Implementation SWA recommends that OCVTS implement the following Energy Conservation Measures using an appropriate Incentive Program for reduced capital cost:

Page 4: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 4/70

Recommended ECMs Incentive Program (APPENDIX K for details)

Retro-commissioning N/A Upgrade 15 incandescent bulbs to CFLs Direct Install, Smart Start Retrofit 1 refrigerated vending machines with VendingMiser™ Devices N/A

Install 39 new occupancy sensors Direct Install, Smart Start Retrofit 20 high pressure sodium parking lot lights with LEDs Smart Start

Retrofit 1 snack vending machines with SnackMiser™ Devices N/A

Install 134 kW Solar Photovoltaic system NJ SREC program Upgrade 13 High Pressure Sodium fixtures to pulse start Metal Halide fixtures Direct Install, Smart Start

Appendix L contains an Energy Conservation Measures table In addition to these ECMs, SWA recommends the following:

• Capital Investment opportunities – measures that would contribute to reducing usage but require significant capital resources as well as long-term financial planning. (Please see Proposed Further Recommendations section of the report for more information)

o Replace roof above original building section o Replace existing hot water heater with two cast iron water heaters o Replace the existing hot water boilers with new cast iron boilers o Replace existing unit ventilators and unit heaters

• Operation and Maintenance (O&M) measures that would contribute to reducing energy

usage at low or no cost: o Check and adjust timers and thermostats monthly o Replace motors with NEMA premium efficiency models o Replace existing thermostats with electronic thermostats o Review VFD installation o Provide water-efficient fixtures and controls o Inspect and replace cracked/ineffective caulk. o Inspect and maintain sealants at all windows for airtight performance. o Inspect and maintain weather-stripping around all exterior doors and roof hatches. o Purchase Energy Star® appliances when available o Use smart power electric strips o Create and energy educational program

There may be energy procurement opportunities for the OCVTS to reduce annual electric costs, which are $1,823 higher, when compared to the average estimated NJ commercial electric rates. SWA recommends further evaluation with energy suppliers, listed in Appendix K. Environmental Benefits SWA estimates that implementing the recommended ECMs is equivalent to removing approximately 20 cars from the roads each year or is equivalent of planting 593 trees to absorb CO2 from the atmosphere.

Page 5: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 5/70

INTRODUCTION Launched in 2008, the Local Government Energy Audit (LGEA) Program provides subsidized energy audits for municipal and local government-owned facilities, including offices, courtrooms, town halls, police and fire stations, sanitation buildings, transportation structures, schools and community centers. The Program will subsidize up to 100% of the cost of the audit. The Board of Public Utilities (BPUs) Office of Clean Energy has assigned TRC Energy Services to administer the Program. Steven Winter Associates, Inc. (SWA) is a 40-year-old architectural/engineering research and consulting firm, with specialized expertise in green technologies and procedures that improve the safety, performance, and cost effectiveness of buildings. SWA has a long-standing commitment to creating energy-efficient, cost-saving and resource-conserving buildings. As consultants on the built environment, SWA works closely with architects, developers, builders, and local, state, and federal agencies to develop and apply sustainable, ‘whole building’ strategies in a wide variety of building types: commercial, residential, educational and institutional. SWA performed an energy audit and assessment for the Jackson Center Vocational & Technical School at 850 Toms River Road, Jackson, NJ. The process of the audit included a facility visit on April 3rd and April 18th, benchmarking and energy bill analysis, assessment of existing conditions, energy conservation measures and other recommendations for improvements. The scope of work includes providing a summary of current building conditions, current operating costs, potential savings, and investment costs to achieve these savings. The facility description includes energy usage, occupancy profiles and current building systems along with a detailed inventory of building energy systems, recommendations for improvement and recommendations for energy purchasing and procurement strategies. The goal of this Local Government Energy Audit is to provide sufficient information to the OCVTS Public School District to make decisions regarding the implementation of the most appropriate and most cost-effective energy conservation measures for the Jackson Center facility.

Page 6: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 6/70

HISTORICAL ENERGY CONSUMPTION

Energy usage, load profile and cost analysis

SWA reviewed utility data from January 2011 through December 2011 that were received from OCVTS with electricity and #2 Fuel Oil. A 12 month period of analysis from January 2011 through December 2011 was used for all calculations and for purposes of benchmarking the building.

Electricity – Jackson Center is currently served by one electric meter. The school currently purchases electricity from Jersey Central Power & Light which is responsible for transmission and distribution. Electricity was purchased at an average aggregated rate of $0.155/kWh and the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows the monthly electric usage and costs. The dashed green line represents the approximate baseload or minimum electric usage required to operate Jackson Center Vocational & Technical School. The baseline usage for the school is approximately 24,541 kWh (average of the three lowest consumption months). As is typical in schools, usage is lower in the summer months, while school is not in session. The low usage in April may be due to estimated billing that may have been corrected or adjusted in the following month of May.

Fuel Oil - The school is served Fuel Oil #2 for heating. The Jackson Center currently buys fuel oil at an average aggregated rate of $3.246/gallon and consumed approximately 24,934 gallons, or $80,925 of fuel oil, from January 2011 to December 2011. The chart below shows the monthly fuel oil usage and costs. Since the fuel oil is purchased on an as needed basis, the estimated monthly consumption was calculated based on Heating

Page 7: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 7/70

Degree Days (HDD). HDD is the difference of the average daily temperature and a base temperature of 65°F. Using this method the consumption is highest in the winter months as seen in the graph below due to the higher heating loads.

The chart above shows the monthly fuel oil usage along with the HDD. The heating degree days are zero for the days when the average temperature exceeds the base temperature. SWA’s

Page 8: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 8/70

analysis used a base temperature of 65 degrees Fahrenheit. Since the monthly consumption was calculated based on HDD, the two curves show a very similar profile. The following graphs, pie charts, and table show energy use for the Jackson Center based on utility bills for the 12 month period. Note: electrical cost at $45/MMBtu of energy is nearly 2 times as expensive as Fuel Oil at $24/MMBtu.

Energy Benchmarking

SWA has entered energy information about Jackson Center in the U.S. Environmental Protection Agency’s (EPA) ENERGY STAR® Portfolio Manager energy benchmarking system. This school facility is categorized as a “K-12 School" space type. Based on the data entered into the Portfolio Manager software, the building has an Energy Performance Rating of 34 out of a possible 100 points. For reference, a score of 69 is required for LEED for Existing Buildings

MMBtu $ % $ $/MMBtu

Electric Misc 369 $16,713 12% $45Electric For Cooling 23 $1,062 1% $45Electric For Heating 320 $14,483 10% $45Lighting 631 $28,583 20% $45Domestic Hot Water (Fuel Oil) 128 $3,010 2% $24Building Space Heating (Fuel Oil) 3,313 $77,915 55% $24Totals 4,783 $141,766 100%

Total Electric Usage 1,343 $60,841 43% $45Total Fuel Oil Usage 3,441 $80,925 57% $24Totals 4,783 $141,766 100%

8%

% MMBtu

Annual Energy Consumption / Costs

0.5%7%13%3%69%100%

28%72%100%

Page 9: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 9/70

certification and a score of 75 is required for ENERGY STAR® certification. The Site Energy Utilization Intensity (Site EUI) was calculated to be 89 kBtu/sqft/yr compared to the National Median of 75 kBtu/sqft/yr. This is a 16% difference between the buildings intensity and the national median. See the ECM section for guidance on how to further reduce the building’s energy intensity. The ENERGY STAR® Portfolio Manager uses a national survey conducted by the U.S. Energy Information Administration (EIA). This national survey, known as the Commercial Building Energy Consumption Survey (CBECS), is conducted every four years, and gathers data on building characteristics and energy use from thousands of buildings across the United States. The Portfolio Manager software uses this data to create a database by building type. By entering the building parameters and utility data into the software, Portfolio Manager is able to generate a performance scale from 1-100 by comparing it to similar buildings. This 100 point scale determines how well the building performs relative to other buildings across the country, regardless of climate and other differentiating factors. A score of 34 shows the building performs 16% below the national average.

Per the LGEA program requirements, SWA has assisted the OCVTS Public School District to create an ENERGY STAR® Portfolio Manager account and share the Jackson Center Vocational & Technical School information to allow future data to be added and tracked using the benchmarking tool. SWA has shared this Portfolio Manager account information with the OCVTS Public School District (user name of “OceanCountyBOE” with a password of “ocvtsboe”) and TRC Energy Services (user name of “TRC-LGEA”). SWA has created the Portfolio Manager information for Ocean County Vocational Technical School Board of Education. This information can be accessed at:

Page 10: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 10/70

URL:https://www.energystar.gov/istar/pmpam/ Username: OceanCountyBOE Password: ocvtsboe Tariff analysis

Tariff analysis can help determine if the municipality is paying the lowest rate possible for electric and fuel oil service. Tariffs are typically assigned to buildings based on size and building type. Rate fluctuations are expected during periods of peak usage. Oil prices often increase during winter months since large volumes of oil is needed for heating equipment. Similarly, electricity prices often increase during the summer months when additional electricity is needed for cooling equipment. As part of the utility bill analysis, SWA evaluated the current utility rates and tariffs for Ocean County Vocational and Technical School. The electric use for the building is direct-metered and purchased at a general service rate with an additional charge for electrical demand factored into each monthly bill. The general service rate is a market-rate based on electric usage and electric demand. Demand prices are reflected in the utility bills and can be verified by observing the price fluctuations throughout the year. Energy Procurement strategies

Billing analysis was conducted using an average aggregated rate which is estimated based on the total cost divided by the total energy usage for each utility over a 12 month period. Average aggregated rates do not separate demand charges from usage, and instead provide a metric of inclusive cost per unit of energy. Average aggregated rates are used in order to equitably compare building utility rates to average utility rates throughout the state of New Jersey. The average estimated NJ commercial utility rates for electric are $0.150/kWh, while Jackson Center Vocational & Technical School pays a rate of $0.155/kWh. Jackson Center Vocational & Technical School annual electric utility costs are $1,823 higher, when compared to the average estimated NJ commercial utility rates. Electric bill analysis shows rate fluctuations up to 14% over the most recent 12 month period. Electric rate fluctuations in the winter and spring can be attributed to a combination of demand charges and market rate changes.

Page 11: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 11/70

The average estimated NJ commercial rates for fuel oil are $3.59/gallon, while the Jackson Center pays an average rate of $3.24/gallon. SWA recommends that the Jackson Center Vocational & Technical School further explore opportunities of purchasing electricity from third-party suppliers in order to reduce rate fluctuation and ultimately reduce the annual cost of energy for Jackson Center Vocational & Technical School. Appendix H contains a complete list of third-party energy suppliers for the Ocean County service area.

Page 12: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 12/70

EXISTING FACILITY AND SYSTEMS DESCRIPTION This section gives an overview of the current state of the facility and systems. Please refer to the Proposed Further Recommendations section for recommendations for improvement. Based on visits from SWA on Tuesday, April 3, 2012 and Wednesday, April 18, 2012, the following data was collected and analyzed.

Building Characteristics

The single-story slab on grade 54,000 square feet OCVTS Jackson Center Vocational & Technical School was built in 1971 with an addition built on to the southeast side of the building in 1981. It is a rectangular shaped building layout. The shops are large garage like rooms where students are able to get hands on experience on different technical trades, such as auto mechanics, electrical trades, aviation, cabinetmaking, agriculture, collision repair, plumbing, and cosmetology. Each shop room consists of a bathroom, tool room, locker/dressing area, small classroom, and a small office. In addition to the shop rooms there is a faculty room, main office, nurse’s office, principal’s office, and a computer lab. The building also has a glass window greenhouse for agricultural studies. The building has undergone several renovations since it was built. Such renovations and upgrades include pieces of mechanical equipment being replaced in 1994 and a roof replacement above the 1981 section in 2004. Additionally, soffits, fascia and windows were replaced in 2009. In 2011, T5 fixtures and occupancy sensors were installed in the hallways and administrative offices.

East Façade North Façade

West Façade South Façade

Page 13: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 13/70

Building Occupancy Profiles

The school’s occupancy is approximately 300 students and 25 faculty members from 6:00 AM to 3:30 PM Monday through Friday. The building stays open till 10:00 PM 2 nights per week during the schools regular sessions. The school is closed on Saturdays and Sundays and for the months of June, July, and August. Building Envelope

Due to unfavorable weather conditions, no exterior envelope infrared (IR) images were taken during the field audit. Ideal weather conditions include a minimum indoor/outdoor delta-T of 18°F, and no/low wind.

General Note: All findings and recommendations on the exterior envelope (base, walls, roofs, doors and windows) are based on the energy auditors’ experience and expertise, on construction document reviews and on detailed visual analysis, as far as accessibility and weather conditions allowed at the time of the field audit.

Exterior Walls

The exterior wall envelope is mostly constructed of brick veneer over concrete block with unconfirmed level of masonry concrete block fill insulation. The interior is predominantly painted CMU (Concrete Masonry Units) and painted gypsum board. Note: Wall insulation levels could not be verified in the field or on construction plans, and are based upon similar wall types and time of construction. Exterior and interior wall surfaces were inspected during the field audit. They were found to be in overall good condition with no visible signs of uncontrolled moisture, air-leakage or other energy-compromising issues detected on all facades.

Roof

For both the original section of the school and the addition, the roof is a flat type with no parapet, over steel decking, with a silver-colored EPDM membrane covered by aggregate BUR (loose light-colored gravel stones). The 1981 building addition roof was renovated in 2004 and the original section of the building had the roof replaced in 1996. The roof over the administrative offices is approximately 5’ lower than the main buildings roof. Gravel stops are located along the roofs perimeter to contain the stones. The roof for the original section of the building has been renovated since the building was built. The roof for the buildings addition is still the original roof. There is a metal ribbed fascia board that surrounds the building. Note: Roof insulation levels could not be visually verified in the field by non-destructive methods. Roofs, related flashing, gutters and downspouts were inspected during the field audit. The roofs over the shop rooms and classrooms are in overall fair condition. The lower roof above the administration offices appeared to show signs of aging and deterioration, and may be nearing the end of its useful life. The higher roof above the shop rooms and

Page 14: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 14/70

classrooms had no visible signs of uncontrolled moisture, air-leakage or other energy-compromising issues on any roof areas. The following specific roof problem spots were identified:

The aging roof above the buildings addition. The EPDM shows signs of deterioration.

Base The building’s base is composed of a slab-on-grade floor with a perimeter footing with concrete block foundation walls and no detectable slab edge/perimeter insulation. Slab and perimeter insulation levels could not be verified in the field or on construction plans, and are based upon similar wall types and time of construction. The building’s base and its perimeter were inspected for signs of uncontrolled moisture or water presence and other energy-compromising issues. Overall the base was reported to be in fair condition with no visible signs of uncontrolled moisture, air-leakage and/ or other energy-compromising issues neither visible on the interior nor exterior. Windows

The school underwent a window retrofit in 2009 with more efficient windows. The building contains several different types of windows:

1. Combined fixed and awning type windows with an insulated aluminum frame, low-E,

double glazing and interior mini blinds. The windows are located throughout the building in the classrooms and offices.

2. Fixed type windows with an insulated frame, low-E, double glazing and with no interior or exterior shading devices. The windows are located around the main entrance doors and in some of the shop rooms.

3. Combined fixed and awning type windows with a non-insulated frame, single glazing

and with no interior or exterior shading devices. Certain windows have mechanisms to open rows of windows and allow for room ventilation. The windows make up the walls and ceiling for the schools green house.

Windows, shading devices, sills, related flashing and caulking were inspected as far as accessibility allowed for signs of moisture, air-leakage and other energy compromising

Page 15: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 15/70

issues. Overall, the windows were found to be in good age appropriate condition, with no visible signs of uncontrolled moisture, air-leakage and/ or other energy-compromising issues. Exterior doors The buildings contain several different types of exterior doors:

1. Aluminum type exterior doors with single-pane glass panels and a non-insulated frame. They are located at the hallway exits on the exterior side of the vestibules.

2. Fiberglass reinforced polyester type doors with 1” insulated tempered glass. They are located at the emergency exits in shop rooms.

3. Metal doors with an insulated frame. They are located on the interior side of the

hallway exit vestibules.

4. Aluminum non-insulated garage doors. They are located in the shop rooms.

All exterior doors, thresholds, related flashing, caulking and weather-stripping were inspected for signs of moisture, air-leakage and other energy-compromising issues. Overall, the doors were found to be in good condition with a few signs of uncontrolled moisture, air-leakage and/ or other energy-compromising issues. The following specific door problem spots were identified:

Vestibule entrance doors with large gaps and deteriorating

weather stripping

Page 16: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 16/70

Deteriorating weather-stripping on shop room doors

Building air-tightness Overall the field auditors found the building to be reasonably air-tight with only a few areas of suggested improvements, as described in more detail earlier in this chapter.

The air tightness of buildings helps maximize all other implemented energy measures and investments, and minimizes potentially costly long-term maintenance, repair and replacement expenses.

Mechanical Systems

Heating Ventilation Air Conditioning All spaces in Jackson Center Vocational & Technical School are mechanically ventilated, heated and cooled. The school contains one mechanical room which houses boilers, a water heater, pumps, compressors and controls. The heating, ventilation, and air conditioning (HVAC) equipment is described below. Equipment

Heating and ventilation – Two #2 fuel oil fired cast iron hot water boilers, located in the boiler room, are used to provide heating to the entire school. The H.B. Smith 350 Mills boilers both have capacities of 2,352 MBH and were installed in 1971. Hot water is delivered throughout the building to various unit ventilators, unit heaters, and heating and ventilating units, by two 7.5 HP pumps. Hot water baseboard radiators also provide heating to several rooms. The pumps are controlled by a Yaskawa variable frequency drive (VFD) and operate in a lead-lag sequence. Unit ventilators located in the shops and classrooms provide heating and ventilation to the surrounding spaces. Unit ventilators have heating capacities between 4,400 BTU/HR and 145,000 BTU/HR, and flow rates between 750 CFM and 2,000 CFM. Unit heaters provide heat to the corridors, vestibules, and mechanical room, and provide supplemental perimeter heating to shop classes.

Page 17: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 17/70

Two H.B. Smith 350 Mills cast iron boilers

Cooling – All spaces are heated, ventilated and cooled. The building does not contain a central cooling plant and therefore each space is cooled using split direct expansion (DX) cooling units and unit ventilators, with the exception of the administrative offices. Three split-DX units are located on the roof, providing cooling to a classroom, a server room and the computer lab. One packaged roof top unit provides cooling to the administrative offices. Several units which are also used for heating are connected to separate condensing units located throughout the exterior of the building.

Administrative office rooftop unit (L); computer lab condensing unit (R)

Typical heating and ventilating unit (L), and typical planning room unit ventilator (R)

Page 18: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 18/70

Controls Boilers and pumps are controlled by a Honeywell control system. The Honeywell system is located in the boiler room and is capable of monitoring outdoor temperature, controlling season mode, controlling the unit ventilators and the administrative office roof top unit. The boilers do not have outdoor reset.

Honeywell control panel

All unit ventilators and packaged units are controlled by non-programmable thermostats located in the zones they serve. Thermostats are generally set for 69°F during the winter and 72°F during the summer; however, occupants are only capable of adjusting the temperatures. Unit ventilators are also equipped with an on/off switch, which shuts off the units fan.

Domestic Hot Water The water heater is a 260 gallon direct fuel oil-fired shell and tube boiler with a capacity of 420,000 BTU/HR. The heater was installed in 1971. The domestic hot water (DHW) is delivered to bathrooms and classrooms.

Page 19: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 19/70

Patterson Kelley Domestic Hot Water Heater

Electrical systems

Lighting See attached lighting schedule in Appendix C for a complete inventory of lighting throughout the building including estimated power consumption and proposed lighting recommendations. Interior Lighting - The primary interior lighting at the Jackson Center Vocational & Technical School is electronically ballasted T8 lamped fixtures. The hallways currently have linear T5 lamps, while the classrooms have linear T8 fixtures. The hallways, main offices, and faculty room were retrofitted with T5 lighting in 2011. The classrooms consist mainly of ceiling suspended, ceiling mounted, or recessed parabolic T8 lighting. Based on measurements of lighting levels for each space, there are no vastly over-illuminated areas.

Typical entrance hallway T5 lighting (L); and typical shop room T8 lighting (R)

Exit Lights - Exit signs were found to be LED types.

Page 20: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 20/70

Typical LED exit signs

Exterior Lighting - The exterior lighting surveyed during the building audit was found to be a combination of wall pack high pressure sodium and CFL fixtures. Exterior lighting is controlled by both photocells and timers.

Typical recessed CFL and high pressure sodium wall pack fixtures. Note: the CFL

lights are on during the day Appliances and process

SWA has conducted a general survey of larger, installed equipment. Appliances and other miscellaneous equipment account for a significant portion of electrical usage within the building. Typically, appliances are referred to as “plug-load” equipment, since they are not inherent to the building’s systems, but rather plug into an electrical outlet. Equipment such as process motors, computers, computer servers, radio and dispatch equipment, refrigerators, vending machines and printers all create an electrical load on the building that is hard to separate out from the rest of the building’s energy usage based on utility analysis. Installed at the Jackson Center are several refrigerators for food and beverages. The school also has several beverage and snack vending machines.

Page 21: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 21/70

Typical refrigerators

Vending machines

Elevators Jackson Center only has 1 story and does not contain an elevator. Other electrical and fuel oil systems Other significant energy-impacting systems installed at Jackson Center Vocational & Technical School include a 65 kW fuel oil emergency generator located at the exterior of the boiler room. This emergency generator is operated once per week as a functional test for 30 minutes. Additionally, the collision repair shop has three air filters and two oil-fired positive pressure paint booths.

Page 22: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 22/70

65 kW natural fuel oil generator

Page 23: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 23/70

RENEWABLE AND DISTRIBUTED ENERGY MEASURES Renewable energy is defined as any power source generated from sources which are naturally replenished, such as sunlight, wind and geothermal. Technology for renewable energy is improving and the cost of installation is decreasing due to both demand and the availability of government-sponsored funding. Renewable energy reduces the need for using either electricity or fossil fuel, therefore lowering costs by reducing the amount of energy purchased from the utility company. Solar photovoltaic panels and wind turbines use natural resources to generate electricity. Geothermal systems offset the thermal loads in a building by using water stored in the ground as either a heat sink or heat source. Cogeneration or Combined Heat and Power (CHP) allows for heat recovery during electricity generation.

Existing systems Currently there are no renewable energy systems installed in the building. Evaluated Systems Solar Photovoltaic Photovoltaic panels convert light energy received from the sun into a usable form of electricity. Panels can be connected into arrays and mounted directly onto building roofs, as well as installed onto built canopies over areas such as parking lots, building roofs or other open areas. Electricity generated from photovoltaic panels is generally sold back to the utility company through a net meter. Net-metering allows the utility to record the amount of electricity generated in order to pay credits to the consumer that can offset usage and demand costs on the electric bill. In addition to generation credits, there are incentives available called Solar Renewable Energy Credits (SRECs) that are subsidized by the state government. Specifically, the New Jersey State government pays a market-rate SREC to facilities that generate electricity in an effort to meet state-wide renewable energy requirements. Based on utility analysis and a study of roof conditions, the OCVTS Jackson Center facility is a good candidate for a 134 kW Solar Panel installation. See Solar PV ECM. Solar Thermal Collectors Solar thermal collectors are not cost-effective for this building and would not be recommended due to the insufficient and intermittent use of domestic hot water throughout the building to justify the expenditure. Wind

Jackson Center Vocational & Technical School is not a good candidate for wind power generation due to insufficient wind conditions in this area of New Jersey. Geothermal Jackson Center Vocational & Technical School is not a good candidate for geothermal installation since it would require replacement of the entire existing HVAC system, as well as extensive installation of geothermal wells and pumping equipment.

Page 24: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 24/70

Combined Heat and Power Jackson Center Vocational & Technical School is not a good candidate for CHP installation and would not be cost-effective due to the size and operations of the building. Typically, CHP is best suited for buildings with a constant electrical baseload to accommodate the electricity generated, as well as a means for using waste heat generated. Additionally, the seasonal occupancy schedule of the school is not well suited for a CHP installation.

Page 25: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 25/70

PROPOSED ENERGY CONSERVATION MEASURES Energy Conservation Measures (ECMs) are recommendations determined for the building based on improvements over current building conditions. ECMs have been determined for the building based on installed cost, as well as energy and cost-savings opportunities. Recommendations: Energy Conservation Measures

# Energy Conservation Measures ECM 1 Retro-commissioning ECM 2 Upgrade 15 incandescent bulbs to CFLs ECM 3 Retrofit 1 refrigerated vending machines with VendingMiser™ Devices ECM 4 Install 39 new occupancy sensors ECM 5 Retrofit 20 high pressure sodium parking lot lights with LEDs ECM 6 Retrofit 1 snack vending machines with SnackMiser™ Devices ECM 7 Install 134 kW Solar Photovoltaic system ECM 8 Upgrade 13 High Pressure Sodium fixtures to pulse start Metal Halide fixtures

In order to clearly present the overall energy opportunities for the building and ease the decision of which ECM to implement, SWA calculated each ECM independently and did not incorporate slight/potential overlaps between some of the listed ECMs (i.e. lighting change influence on heating/cooling.

Page 26: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 26/70

ECM #1: Retro-commissioning Retro-commissioning, or existing building commissioning, is a systematic building investigation process for improving and optimizing a building’s operation and maintenance. The process focuses on the building’s energy consumption by analyzing equipment such as the HVAC mechanical equipment, related controls and consumption patterns derived from utility and other usage information. Retro-commissioning may not necessarily emphasize bringing the building back to its original intended design specifications if the retro-commissioning team finds that the original specifications no longer apply to existing equipment or building needs. The process may result in recommendations for capital improvements, but its primary intent is to optimize the building systems by equipment tune-up, improved operation and maintenance, and diagnostic testing. The retro-commissioning process involves obtaining documentation about the facility equipment and its current operation as well as multiple site visits for further review of operating parameters and conditions with the maintenance staff. All major energy consuming systems are diagnosed to determine system operation. The retro-commissioning process can also identify potential capital intensive improvements that can be made to further reduce energy usage and utility cost. Often, the savings associated with the low cost improvements can be used to lower the implementation cost associated with the capital-intensive measures and make the overall package more economically viable. The goals of RCx include:

• Finding opportunities to reduce energy costs through readily implemented changes to the operation of the building.

• Evaluating set points of equipment and systems with the intent of bringing them to a proper operational state.

• Improving indoor environmental quality (IEQ) thereby reducing occupant complaints and reducing staff time spent on complaint calls.

• Improving equipment reliability through enhanced operation and maintenance procedures. Project cost: Estimated project cost: $10,800 Source of cost estimate: Similar projects Economics:

net e

st. E

CM

cos

t with

in

cent

ives

, $

kWh,

1st

yr s

avin

gs

kW, d

eman

d re

duct

ion/

mo

ther

ms,

1st

yr s

avin

gs

kBtu

/sq.

ft.,

1st y

r sav

ings

est.

oper

atin

g co

st, 1

st y

r sa

ving

s, $

tota

l 1st

yr s

avin

gs, $

life

of m

easu

re, y

rs.

est.

lifet

ime

cost

sav

ings

, $

sim

ple

payb

ack,

yrs

.

lifet

ime

retu

rn o

n in

vest

men

t, %

annu

al re

turn

on

inve

stm

ent,

%

inte

rnal

rate

of r

etur

n, %

net p

rese

nt v

alue

, $

CO

2 re

duce

d, lb

s/yr

$10,800 69,843 0 3,328 10.6 $0 $21,600 3 $64,800 1 500% 167% 192% $48,511 161,735

Page 27: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 27/70

Assumptions: SWA calculated the estimated ECM cost at $0.20/sqft, which is typical of buildings of this size and type. Rebates/financial incentives: • There currently are no incentives for this measure at this time.

Please see APPENDIX K for more information on Incentive Programs.

Page 28: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 28/70

ECM #2: Upgrade 15 incandescent bulbs to CFLs

The existing lighting contains inefficient incandescent lamps. SWA recommends that each incandescent lamp is replaced with a more efficient, Compact Fluorescent Lamp (CFL). CFLs are capable of providing equivalent or better light output while using less power when compared to incandescent, halogen and Metal Halide fixtures. CFL bulbs produce the same lumen output with less wattage than incandescent bulbs and last up to five times longer. The labor for the recommended installations is evaluated using prevailing electrical contractor wages. The building owner may decide to perform this work with in-house resources from the Maintenance Department on a scheduled, longer timeline than otherwise performed by a contractor. (Add any ECM specifics)

Installation cost: Estimated installed cost: $140 (includes $60 of labor) Source of cost estimate: RS Means, Published and established costs, NJ Clean Energy Program Economics:

net e

st. E

CM

cos

t with

in

cent

ives

, $

kWh,

1st

yr s

avin

gs

kW, d

eman

d re

duct

ion/

mo

ther

ms,

1st

yr s

avin

gs

kBtu

/sq.

ft.,

1st y

r sav

ings

est.

oper

atin

g co

st, 1

st y

r sa

ving

s, $

tota

l 1st

yr s

avin

gs, $

life

of m

easu

re, y

rs.

est.

lifet

ime

cost

sav

ings

, $

sim

ple

payb

ack,

yrs

.

lifet

ime

retu

rn o

n in

vest

men

t, %

annu

al re

turn

on

inve

stm

ent,

%

inte

rnal

rate

of r

etur

n, %

net p

rese

nt v

alue

, $

CO

2 re

duce

d, lb

s/yr

$140 1,117 0 0 0.1 $47 $220 5 $1,100 1 686 137 156 $835 2,000

Assumptions: SWA calculated the savings for this measure using measurements taken the days of the field visits and using the billing analysis. Rebates/financial incentives: There are currently no incentives for this measure at this time.

Page 29: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 29/70

ECM #3: Retrofit 1 refrigerated vending machines with VendingMiser™ Devices

The school currently has one beverage machine which is located in the faculty room. VendingMiser devices are available for conserving energy used by beverage vending machines and coolers. Purchasing new machines is not necessary to reduce operating costs and greenhouse gas emissions. When equipped with the VendingMiser devices, refrigerated beverage vending machines use less energy and are comparable in daily energy performance to new ENERGY STAR qualified machines. VendingMiser devices incorporate innovative energy-saving technology into small plug-and-play devices that installs in minutes, either on the wall or on the vending machine. Vending miser devices use a Passive Infrared Sensor (PIR) to: Power down the machine when the surrounding area is vacant; Monitor the room's temperature; Automatically repower the cooling system at one- to three-hour intervals, independent of sales; ensure the product stays cold. The school should request permission to install the devices if the machines are leased.

Installation cost: Estimated installed cost: $199 (includes $20 of labor) Source of cost estimate: www.usatech.com and established costs Economics:

net e

st. E

CM

cos

t with

in

cent

ives

, $

kWh,

1st

yr s

avin

gs

kW, d

eman

d re

duct

ion/

mo

ther

ms,

1st

yr s

avin

gs

kBtu

/sq.

ft.,

1st y

r sav

ings

est.

oper

atin

g co

st, 1

st y

r sa

ving

s, $

tota

l 1st

yr s

avin

gs, $

life

of m

easu

re, y

rs.

est.

lifet

ime

cost

sav

ings

, $

sim

ple

payb

ack,

yrs

.

lifet

ime

retu

rn o

n in

vest

men

t, %

annu

al re

turn

on

inve

stm

ent,

%

inte

rnal

rate

of r

etur

n, %

net p

rese

nt v

alue

, $

CO

2 re

duce

d, lb

s/yr

$199 1,525 0 0 0.1 $0 $236 12 $2,830 1 1,322% 110% 118% $2,055 2,731

Assumptions: SWA calculated the savings for this measure using measurements taken on the day of the field visit and using the billing analysis. SWA determined energy savings based on modeling calculator found at www.usatech.com or http://www.usatech.com/energy_management/energy_calculator.php. See APPENDIX E for savings calculations. Rebates/financial incentives: • This measure does not qualify for a rebate or other financial incentives at this time.

Please see APPENDIX K for more information on Incentive Programs.

Page 30: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 30/70

ECM #4: Install 39 new occupancy sensors

On the days of the site visits, SWA completed a lighting inventory of the Jackson Center (see Appendix C). The building contains several areas that could benefit from the installation of occupancy sensors. These areas consisted of various storage rooms, bathrooms and offices that are used sporadically throughout the day and could show energy savings by having the lights turn off after a period of no occupancy. Typically, occupancy sensors have an adjustable time delay that shuts down the lights automatically if no motion is detected within a set time period. Advanced ultra-sonic lighting sensors include sound detection as a means to controlling lighting operation. Installation cost: Estimated installed cost: $7,800 (includes $1,980 of labor) Source of cost estimate: RS Means; Published and established costs, NJ Clean Energy Program Economics:

net e

st. E

CM

cos

t with

in

cent

ives

, $

kWh,

1st

yr s

avin

gs

kW, d

eman

d re

duct

ion/

mo

ther

ms,

1st

yr s

avin

gs

kBtu

/sq.

ft.,

1st y

r sav

ings

est.

oper

atin

g co

st, 1

st y

r sa

ving

s, $

tota

l 1st

yr s

avin

gs, $

life

of m

easu

re, y

rs.

est.

lifet

ime

cost

sav

ings

, $

sim

ple

payb

ack,

yrs

.

lifet

ime

retu

rn o

n in

vest

men

t, %

annu

al re

turn

on

inve

stm

ent,

%

inte

rnal

rate

of r

etur

n, %

net p

rese

nt v

alue

, $

CO

2 re

duce

d, lb

s/yr

$7,800 26,481 6 0 1.7 $0 $4,104 15 $61,560 2 689% 46% 53% $39,236 47,414

Assumptions: SWA calculated the savings for this measure using measurements taken the days of the field visits and using the billing analysis. Rebates/financial incentives: • NJ Clean Energy – SmartStart – Wall-mounted Occupancy Sensors ($20 per control)

o Maximum Incentive Amount: $660 • NJ Clean Energy – Direct Install (Up to 70% of installed costs)

Please see APPENDIX K for more information on Incentive Programs.

Page 31: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 31/70

ECM #5: Retrofit 20 high pressure sodium parking lot lights with LEDs

The exterior lighting is made up of inefficient metal halide fixtures. Aside from having higher energy consumption, these fixtures require frequent lamp and ballast replacements. SWA is recommending LED lamps replacement lamps. For the proposed retrofit, the scope of work involves removing the existing light and ballast and replacing with an LED lamp and ballast. The existing poles and fixtures would be left in tact at the same quantity and height. By retrofitting the existing fixtures, the cost of materials and labor can be reduced. LED technology has advanced greatly in the past 10 years and has long operating lifespans. LED lighting uses considerably less energy than metal halide lights. Installation cost: Estimated installed cost: $14,692 (includes $5,692 of labor) Source of cost estimate: RS Means; Published and established costs, NJ Clean Energy Program Economics:

net e

st. E

CM

cos

t with

in

cent

ives

, $

kWh,

1st

yr s

avin

gs

kW, d

eman

d re

duct

ion/

mo

ther

ms,

1st

yr s

avin

gs

kBtu

/sq.

ft.,

1st y

r sav

ings

est.

oper

atin

g co

st, 1

st y

r sa

ving

s, $

tota

l 1st

yr s

avin

gs, $

life

of m

easu

re, y

rs.

est.

lifet

ime

cost

sav

ings

, $

sim

ple

payb

ack,

yrs

.

lifet

ime

retu

rn o

n in

vest

men

t, %

annu

al re

turn

on

inve

stm

ent,

%

inte

rnal

rate

of r

etur

n, %

net p

rese

nt v

alue

, $

CO

2 re

duce

d, lb

s/yr

$14,693 11,752 2 0 0.7 $4,247 $6,069 5 $30,345 2 107 21 30 $12,542 21,042

Assumptions: SWA calculated the savings for this measure using measurements taken the days of the field visits and using the billing analysis. Rebates/financial incentives: There are currently no incentives for this measure at this time.

Page 32: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 32/70

ECM #6: Retrofit 1 snack vending machines with SnackMiser™ Devices

SnackMiser devices are now available for conserving energy used by vending machines. Purchasing newer equipment is not necessary to reduce operating costs and greenhouse gas emissions. When equipped with the snack miser devices, vending machines use less energy and are comparable in daily energy performance to new ENERGY STAR qualified machines. SnackMiser devices can be used on snack vending machines to achieve maximum energy savings that result in reduced operating costs and decreased greenhouse gas emissions with existing machines. Snack vending miser devices also use a Passive Infrared Sensor (PIR) to determine if there is anyone within 25 feet of the machine. It waits for 15 minutes of vacancy, then powers down the machine. If a customer approaches the machine while powered down, the snacks vending miser will sense the presence and immediately power up. The school should request permission to install the devices if the machines are leased. Installation cost: Estimated installed cost: $180 (includes $20 of labor) Source of cost estimate: www.usatech.com and established costs Economics:

net e

st. E

CM

cos

t with

in

cent

ives

, $

kWh,

1st

yr s

avin

gs

kW, d

eman

d re

duct

ion/

mo

ther

ms,

1st

yr s

avin

gs

kBtu

/sq.

ft.,

1st y

r sav

ings

est.

oper

atin

g co

st, 1

st y

r sa

ving

s, $

tota

l 1st

yr s

avin

gs, $

life

of m

easu

re, y

rs.

est.

lifet

ime

cost

sav

ings

, $

sim

ple

payb

ack,

yrs

.

lifet

ime

retu

rn o

n in

vest

men

t, %

annu

al re

turn

on

inve

stm

ent,

%

inte

rnal

rate

of r

etur

n, %

net p

rese

nt v

alue

, $

CO

2 re

duce

d, lb

s/yr

$180 366 0 0 0.0 $0 $52 12 $627 3.4 248% 21% 27% $324 655

Assumptions: SWA calculated the savings for this measure using measurements taken on the day of the field visit and using the billing analysis. SWA assumes energy savings based on modeling calculator found at www.usatech.com or http://www.usatech.com/energy_management/energy_calculator.php. See APPENDIX E for savings calculations. Rebates/financial incentives: • This measure does not qualify for a rebate or other financial incentives at this time.

Please see APPENDIX K for more information on Incentive Programs.

Page 33: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 33/70

ECM #7: Install 134 kW Solar Photovoltaic system Currently, Jackson Center Vocational & Technical School does not use any renewable energy systems. Renewable energy systems such as photovoltaic (PV) panels can be mounted on the building roof facing south which can offset a portion of the purchased electricity for the building. Power stations generally have two separate electrical charges: usage and demand. Usage is the amount of electricity in kilowatt-hours that a building uses from month to month. Demand is the amount of electrical power that a building uses at any given instance in a month period. During the summer periods, electric demand at a power station is high, due to the amount of air conditioners, lights, and other equipment being used within the region. Demand charges increase to offset the utility’s cost to provide enough electricity at that given time. Photovoltaic systems offset the amount of electricity used by a building and help to reduce the building’s electric demand, resulting in a higher cost savings. Installing a PV system will offset electric demand and reduce annual electric consumption, while utilizing available state incentives. PV systems are modular and readily allow for future expansions. The size of the system was determined considering the available roof surface area, without compromising service space for roof equipment and safety, as well as the facilities’ annual base load and mode of operation. A commercial multi-crystalline panel has 17.1 square feet of surface area (providing 12.2 watts per square foot). A 134 kW system needs approximately 645 panels which would take up 11,025 square feet. Additionally, PV system installations should be accompanied by an evaluation of the roof’s structural stability. A PV system would reduce the building's electric load and allow more capacity for surrounding buildings as well as serve as an example of energy efficiency for the community. The building is not eligible for a residential 30% federal tax credit. The building owner may want to consider applying for a grant and / or engage a PV generator / leaser who would install the PV system and then sell the power at a reduced rate. Utility companies in New Jersey buy Solar Renewable Energy Credits (SRECs) at the best market rate. In addition to selling electricity generated by the solar PV system, SRECs are earned every time that 1 MWh or 1,000 kWh are generated from the renewable system. Based on the cumulative weighted average of SRECs sold in NJ in 2012, SRECs are currently conservatively valued at $145/MWh.

The red rectangle above represents potential space for a PV system installation.

Page 34: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 34/70

Installation cost: Net estimated installed cost: $670,800 Source of cost estimate: RS Means; Published and established costs; Similar projects Economics:

net e

st. E

CM

cos

t with

in

cent

ives

, $

kWh,

1st

yr s

avin

gs

kW, d

eman

d re

duct

ion/

mo

ther

ms,

1st

yr s

avin

gs

kBtu

/sq.

ft.,

1st y

r sav

ings

est.

oper

atin

g co

st, 1

st y

r sa

ving

s, $

tota

l 1st

yr s

avin

gs, $

life

of m

easu

re, y

rs.

est.

lifet

ime

cost

sav

ings

, $

sim

ple

payb

ack,

yrs

.

lifet

ime

retu

rn o

n in

vest

men

t, %

an

nual

retu

rn o

n in

vest

men

t, %

inte

rnal

rate

of r

etur

n, %

net p

rese

nt v

alue

, $

CO

2 re

duce

d, lb

s/yr

$670,800 162,422 134.2 0 0.0 $1,442 $47,285 25 956,023 14.2 43 2 3 15,019 290,817

Annual Solar PV Cost Savings Breakdown Rated Capacity (kW) 134.2 Rated Capacity (kWh) 158,309 Annual Capacity Loss 0%

Year kWh Capacity

Installation/Maintenance Cost SRECs Savings ($)

0 $670,800 $0 1 162,422 $1,442 $23,551 $47,285 2 162,422 $1,442 $23,551 $47,285 3 162,422 $1,442 $23,551 $47,285 4 162,422 $1,442 $23,551 $47,285 5 162,422 $1,442 $23,551 $47,285 6 162,422 $1,442 $23,551 $47,285 7 162,422 $1,442 $23,551 $47,285 8 162,422 $1,442 $23,551 $47,285 9 162,422 $1,442 $23,551 $47,285

10 162,422 $1,442 $23,551 $47,285 11 162,422 $1,442 $23,551 $47,285 12 162,422 $1,442 $23,551 $47,285 13 162,422 $1,442 $23,551 $47,285 14 162,422 $1,442 $23,551 $47,285 15 162,422 $1,442 $23,551 $47,285 16 162,422 $1,442 $0 $24,675 17 162,422 $1,442 $0 $24,675 18 162,422 $1,442 $0 $24,675 19 162,422 $1,442 $0 $24,675 20 162,422 $1,442 $0 $24,675 21 162,422 $1,442 $0 $24,675 22 162,422 $1,442 $0 $24,675 23 162,422 $1,442 $0 $24,675 24 162,422 $1,442 $0 $24,675

Page 35: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 35/70

25 162,422 $1,442 $0 $24,675 kWh Cost Saving

Lifetime Total 4,060,551 ($706,851) $353,268 $956,023

Table of 12 SREC Values EY2012 SACP=$658 SREC Quantity Monthly Cumulative

Month Year Active kW DC

Issued in

Month Traded

in Month High

($/MWh) Low

($/MWh) # of

SRECs Traded

Weighted Avg Price ($/MWh)

Sept 2012 Aug 2012 Jul 2012 Jun 2012 May 2012 Apr 2012 Mar 2012 668,643 60,685 50,701 $635 $100 309,381 $342.56 Feb 2012 629,664 43,636 37,581 $650 $112 258,680 $361.67 Jan 2012 521,987 42,745 50,186 $669 $115 221,099 $373.75 Dec 2011 488,357 40,592 52,716 $658 $115 170,913 $369.46 Nov 2011 443,654 36,897 52,024 $650 $100 118,197 $353.21 Oct 2011 425,798 34,467 34,724 $658 $120 66,173 $403.07 Sept 2011 413,889 45,941 18,412 $675 $50 31,449 $401.90 Aug 2011 395,919 48,535 12,252 $665 $100 13,037 $410.48

July 2011 362,871 37,738 785

Due to low trade volume, the July trades are reported with the cumulative pricing data

starting in August. Total 391,236 309,381

*The cumulative weighted average price takes into account all of the SRECs that have been traded for all of the months reported. This number can be used to reflect pricing trends. It is calculated based on [(number of SRECs sold at Price A * price A)+(number of SRECs sold at Price B * price B)+...] www.njcleanenergy.com/renewable-

energy/project-activity-reports/srec-pricing/srec-pricing

Assumptions: SWA estimated the cost and savings of the system based on past PV projects. Installed costs were estimated at $5/Watt installed. SRECs are currently evaluated at $145/MWh based on the lowest monthly averages in the past 12 month period PV systems are sized based on 134 kW and physical dimensions for an array will differ with the efficiency of a given solar panel (W/sq. ft.). Rebates/financial incentives:

• NJ Clean Energy - Solar Renewable Energy Certificate Program. Each time a solar electric system generates 1,000kWh (1MWh) of electricity, a SREC is issued which can then be sold or traded separately from the power. The buildings must also become net-metered in order to earn SRECs as well as sell power back to the electric grid. A total of $23,551/year, based on $145/SREC, has been incorporated in the above costs for a period of 15 years; however it requires proof of performance, application approval and negotiations with the utility.

Please see APPENDIX K for more information on Incentive Programs.

Page 36: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 36/70

ECM #8: Upgrade 13 High Pressure Sodium fixtures to pulse start Metal Halide fixtures The existing exterior lighting contains standard probe start High Pressure Sodium (HPS) lamps. SWA recommends replacing the higher wattage HPS fixtures with pulse start MH lamps which produce higher light output both initially and over time, operate more efficiently, produce whiter light, and turn on and re-strike faster. Due to these characteristics, energy savings can be realized via one-to-one substitution of lower-wattage systems, or by taking advantage of higher light output and reducing the number of fixtures required in the space. The labor for the recommended installations is evaluated using prevailing electrical contractor wages. The building owner may decide to perform this work with in-house resources from the Maintenance Department on a scheduled, longer timeline than otherwise performed by a contractor. Installation cost: Estimated installed cost: $14,692 (includes $5,692 of labor) Source of cost estimate: RS Means; Published and established costs, NJ Clean Energy Program Economics:

net e

st. E

CM

cos

t with

in

cent

ives

, $

kWh,

1st

yr s

avin

gs

kW, d

eman

d re

duct

ion/

mo

ther

ms,

1st

yr s

avin

gs

kBtu

/sq.

ft.,

1st y

r sav

ings

est.

oper

atin

g co

st, 1

st y

r sa

ving

s, $

tota

l 1st

yr s

avin

gs, $

life

of m

easu

re, y

rs.

est.

lifet

ime

cost

sav

ings

, $

sim

ple

payb

ack,

yrs

.

lifet

ime

retu

rn o

n in

vest

men

t, %

annu

al re

turn

on

inve

stm

ent,

%

inte

rnal

rate

of r

etur

n, %

net p

rese

nt v

alue

, $

CO

2 re

duce

d, lb

s/yr

$9,100 4,441 1 0 0.3 $48 $736 15 $11,040 12 21 1 3 -$426 7,952

Assumptions: SWA calculated the savings for this measure using measurements taken the days of the field visits and using the billing analysis. Rebates/financial incentives: NJ Clean Energy - SmartStart - Metal Halide with pulse start $25 per fixture - Maximum incentive amount is $325 Please see APPENDIX K for more information on Incentive Programs.

Page 37: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 37/70

Proposed Further Recommendations Capital Improvements Capital Improvements are recommendations for the building that may not be cost-effective at the current time, but that could yield a significant long-term payback. Capital improvements may also constitute equipment that is currently being operated beyond its useful lifetime. These recommendations should typically be considered as part of a long-term capital improvement plan. Capital improvements should be considered if additional funds are made available. SWA recommends the following capital improvements for the OCVTS Jackson Center.

• Replace roof above original building section – The Jackson Center roof is made up of a light-

colored EPDM membrane covered by aggregate BUR (loose light-colored gravel stones). The roof is nearing the end of its useful life, as it was last replaced in 1996. Based on similar roof types, this roof surface is beyond the manufacturer’s warranty and is recommended to be replaced. SWA recommends upgrading the existing roof with a roof with high solar reflectance and increased insulation. Replacing the roof will result in some energy savings; however, due to the high capital cost, this measure will not be justified based on energy savings alone. The roof should be replaced prior to installing a PV system. Accurate energy savings calculations would require the use of advanced building modeling software, which is outside the scope of this project. SWA estimates the roof replacement to cost $186,137 based on the total footprint of the building.

• Replace existing hot water heater with two cast iron water heaters – During the field audit, SWA

inspected the existing Domestic Hot Water (DHW) heater. There is currently one fuel oil heater that produces DHW for the entire building. The expected service life of a DHW heater is 20 years, which the existing heater has exceeded. Consideration should be given to replace the heater with more efficient type and tank as part of a capital improvement plan. The associated pump appears to be operating adequately and has fractional horsepower, so replacement would not yield significant energy savings or an attractive payback period. SWA recommends replacing the existing water heater with two appropriately sized heaters with sufficient capacity for the entire building. New energy-efficient water heaters are a good, cost-effective replacement option for old water heaters. They have higher levels of insulation around the tank and one-way valves where pipes connect to the tank, substantially reducing standby heat loss. For safety as well as energy efficiency, fuel-burning water heaters should be installed with sealed combustion ("direct-vented" or "power-vented). Sealed combustion means that outside air is brought in directly to the water heater and exhaust gases are vented directly outside, keeping combustion totally separate from the house air. SWA estimates the removal of the old heater, and installation of two condensing boilers to be $31,425. The combined capacity of the two condensing boilers is assumed to be equivalent to the existing water heater.

• Replace the existing hot water boilers with new cast iron boilers – During the field audit, SWA inspected the existing heating equipment, which consists of two cast iron boilers. The expected service life of a hot water boiler is 20 years, which the existing boilers have exceeded. SWA recommends replacing the existing boilers with newer energy efficient models. The demolition and installation costs are estimated to be $107,252. Due to the high replacement costs, the increased efficiency will not provide an attractive payback.

• Replace existing unit ventilators and unit heaters – The existing unit ventilators have reached their end of useful life. Some unit ventilators are rarely turned on, due to the loud fan noise and

Page 38: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 38/70

damaged fins on the heating coils. SWA recommends replacing the existing unit ventilators and heaters which would provide more comfort to each space they serve, and would operate more efficiently. Accurate energy savings calculations would require the use of advanced building modeling software, which is outside the scope of this project. Implementation costs and units to be replaced are presented below:

Replacement Component Installed Cost

Replacement of ten 750 CFM unit ventilators $54,675 Replacement of four 1500 CFM unit ventilators $34,075 Replacement of ten 2000 CFM unit ventilators $112,636

Replacement of two 20 MBH cabinet unit heaters $2,101 Replacement of seven 16 MBH unit heaters $4,027 Replacement of two 36.5 MBH unit heaters $10,676

Replacement of one 47 MBH unit heater $840 Demolition of existing unit ventilators and heaters $15,308

Total Replacement Costs $234,338 Operations and Maintenance Operations and Maintenance measures consist of low/no cost measures that are within the capability of the current building staff to handle. These measures typically require little investment, and they yield a short payback period. These measures may address equipment settings or staff operations that, when addressed will reduce energy consumption or costs. • Check and adjust timers and time clocks monthly – During the site visit, several exterior lights

were observed to be left on during the day due to incorrect timer settings. In addition to exterior lights, several time clocks that control HVAC equipment were also left on due to incorrect time settings. During power surges or outages, digital clocks are reset and require setting to ensure that timers remain accurate.

• Replace motors with NEMA premium efficiency models – SWA observed several motors for hot water distribution that were not NEMA premium efficiency models and are beyond their useful lifetime. Operating non-NEMA premium efficiency motors with a VFD can shorten the life of the motor. Since these motors have been maintained well, SWA recommends replacing them with high efficiency models as part of routine O&M the next time that they fail.

• Replace existing thermostats with electronic thermostats – The existing thermostats are non-

programmable or electronic. SWA recommends replacing the thermostats with electronic or programmable models, capable of limiting zone temperature by +/- 2°F. By limiting the temperature control, employees will not be able to create drastic temperature variations between each zone.

• Review VFD installation – At the time of the visit, SWA was not able to verify if unit ventilators,

and heating and ventilation units were equipped with two-way valves. Based on the building drawings, the units are equipped with three-way valves. VFDs are capable of saving energy by varying the motor speed, provided that the system is equipped with two-way valves. SWA recommends the OCVTS Jackson Center review the installation of the VFD and the valves at the heating equipment. This review can be conducted as part of retro-commissioning as recommended earlier in this report.

Page 39: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 39/70

• Unclog and maintain all roof drains/scuppers.

• Provide water-efficient fixtures and controls – Adding controlled on/off timers on all lavatory faucets is a cost-effective way to reduce domestic hot water demand and save water. Building staff can also easily install faucet aerators and/or low-flow fixtures to reduce water consumption. There are many retrofit options, which can be installed now or incorporated as equipment is replaced. Routine maintenance practices that identify and quickly address water leaks are a low-cost way to save water and energy. Retrofitting with more efficient water-consumption fixtures/appliances will reduce energy consumption for water heating, while also decreasing water/sewer bills.

• Inspect and replace cracked/ineffective caulk. • Inspect and maintain sealants at all windows for airtight performance.

• Inspect and maintain weather-stripping around all exterior doors and roof hatches.

• SWA recommends that the building considers purchasing the most energy-efficient equipment,

including ENERGY STAR® labeled appliances, when equipment is installed or replaced. More information can be found in the “Products” section of the ENERGY STAR® website at: http://www.energystar.gov.

• Use smart power electric strips - in conjunction with occupancy sensors to power down

computer equipment when left unattended for extended periods of time.

• Create an energy educational program - that teaches how to minimize energy use. The U.S. Department of Energy offers free information for hosting energy efficiency educational programs and plans. For more information please visit: http://www1.eere.energy.gov/education/.

Page 40: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 40/70

APPENDIX A: EQUIPMENT LIST Inventory

Building System Description Location Model# Fuel Space served

Year Equip

Installed

Remaining useful life

%

Heating

H.B. Smith 350 Mills Hot Water Boiler, 2,352 MBH Input, SV Capacity 2,900

MBH

Mechanical Room Serial #06508 Fuel Oil Mechanical

Room 1971 0%

Heating

H.B. Smith 350 Mills Hot Water Boiler, 2,352 MBH Input, SV Capacity 3,184

MBH

Mechanical Room Serial #06507 Fuel Oil Mechanical

Room 1971 0%

Domestic Hot

Water

DHW, 420,000 BTU/HR, 260 Gallon

Mechanical Room

The Patterson Kelley Co - 300-

3/2T, Serial #NB24858

Fuel Oil Whole Building 1971 0%

Heating

Hot Water Distribution Pump, 7.5 HP, 3 Phase,

1750 RPM

Mechanical Room

Century, Model #SC-254U-KAA 6-305494-01, Serial

#5K

Electric Whole Building N/A N/A

Heating

Hot Water Distribution Pump, 7.5 HP, 3 Phase,

1750 RPM

Mechanical Room

Century, Model #SC-254U-KAA 6-305494-01, Serial

#5K

Electric Whole Building N/A N/A

Heating

Horizontal Unit Heater, 36.3 MBH,

3.5 GPM, 1100 CFM, 1550 RPM,

1/8 HP

Recreational Vehicle

Repair 15 Trane, Model #705 Fuel Oil

Recreational Vehicle Repair

15 1979 0%

Heating

Horizontal Unit Heater, 36.3 MBH,

3.5 GPM, 1100 CFM, 1550 RPM,

1/8 HP

Recreational Vehicle

Repair 15 Trane, Model #705 Fuel Oil

Recreational Vehicle Repair

15 1979 0%

Heating

Horizontal Unit Heater, 36.3 MBH,

3.5 GPM, 1100 CFM, 1550 RPM,

1/8 HP

Recreational Vehicle

Repair 15 Trane, Model #705 Fuel Oil

Recreational Vehicle Repair

15 1979 0%

Heating

Horizontal Unit Heater, 36.3 MBH,

3.5 GPM, 1100 CFM, 1550 RPM,

1/8 HP

Recreational Vehicle

Repair 15 Trane, Model #705 Fuel Oil

Recreational Vehicle Repair

15 1979 0%

Heating

Heating & Ventilating Unit, 7000 CFM, 800 RPM, 1 HP, Ent

Temp 190°F, 226.8 MBH Heating, 15

GPM

Recreational Vehicle

Repair 15 Trane, Catalog #14 Fuel

Oil/Electric

Recreational Vehicle Repair

15 1979 0%

Page 41: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 41/70

Cooling Condensing Unit, R-22, 2.5 ton, 1/8 HP Exterior

Model #2TTA0030A3000A

A, Serial #30142MB3F

Electric Planning Room 16 2003 55%

Heating/Cooling

Vertical Unit Ventilator, 750 CFM

supply, 115 CFM O.A., 12.5 MBH

Heating, 19.2 MBH Cooling, DX cooling

Recreational Vehicle

Repair 15 Trane, Model #07 Fuel

Oil/Electric Planning Room

16 1979 0%

Heating

Horizontal Unit Heater, 36.3 MBH,

3.5 GPM, 1100 CFM, 1550 RPM,

1/8 HP

Masonry Trades 22 Trane, Model #705 Fuel Oil Masonry Trades

22 1979 0%

Heating

Horizontal Unit Heater, 36.3 MBH,

3.5 GPM, 1100 CFM, 1550 RPM,

1/8 HP

Masonry Trades 22 Trane, Model #705 Fuel Oil Masonry Trades

22 1979 0%

Heating/Cooling

Heating & Ventilating Unit, 5100 CFM, 700

RPM, 3/4 HP, Ent Temp 190°F, 165.2 MBH Heating, 11

GPM

Masonry Trades 22 Trane, Catalog #9 Fuel

Oil/Electric Masonry Trades

22 1979 0%

Heating/Cooling

Vertical Unit Ventilator, 750 CFM

supply, 115 CFM O.A., 12.5 MBH

Heating, 19.2 MBH Cooling, DX cooling

Planning Room 28 Trane, Model #07 Fuel

Oil/Electric Planning Room

28 1979 0%

Cooling Condensing Unit, R-22, 2.5 ton, 1/8 HP Exterior

Model #2TTA0030A3000A

A, Serial #3035TL23F

Electric Planning Room 28 2003 55%

Heating

Horizontal Unit Heater, 36.3 MBH,

3.5 GPM, 1100 CFM, 1550 RPM,

1/8 HP

Agriculture 6 Trane, Model #705 Fuel Oil Agriculture 6 1979 0%

Heating

Horizontal Unit Heater, 36.3 MBH,

3.5 GPM, 1100 CFM, 1550 RPM,

1/8 HP

Agriculture 6 Trane, Model #705 Fuel Oil Agriculture 6 1979 0%

Heating

Horizontal Unit Heater, 36.3 MBH,

3.5 GPM, 1100 CFM, 1550 RPM,

1/8 HP

Agriculture 6 Trane, Model #705 Fuel Oil Agriculture 6 1979 0%

Heating/Cooling

Vertical Unit Ventilator, 750 CFM

supply, 115 CFM O.A., 4.4 MBH

Heating, 20.3 MBH Cooling, DX cooling

Planning Room 13 Trane, Model #07 Fuel

Oil/Electric Planning Room

13 1979 0%

Page 42: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 42/70

Cooling Condensing Unit, R-22, 25.5 BTU/HR, 2 HP, 1 fan, 1/3 HP

Agriculture 6-Exterior

Trane, Catalog #RAUC-256 Electric Planning Room

13 1979 0%

Heating

Heating & Ventilating Unit, 7000 CFM, 800 RPM, 1 HP, Ent

Temp 190°F, 151.2 MBH Heating, 10

GPM

Agriculture 6 Trane, Catalog #14 Fuel Oil/Electric Agriculture 6 1979 0%

Heating/Cooling

Vertical Unit Ventilator, 750 CFM

supply, 130 CFM O.A., 5.6 MBH

Heating, 24.8 MBH Cooling, DX cooling

Storage 5 Trane, Model #07 Fuel Oil/Electric Storage 5 1979 0%

Cooling Condensing Unit, R-22, 25.5 BTU/HR, 2 HP, 1 fan, 1/3 HP

Storage 5 Trane, Catalog #RAUC-256 Electric Storage 5 1979 0%

Heating

Horizontal Unit Heater, 36.3 MBH,

3.5 GPM, 1100 CFM, 1550 RPM,

1/8 HP

Storage 5 Trane, Model #705 Fuel Oil Storage 5 1979 0%

Heating

Heating & Ventilating Unit, 1900 CFM, 900 RPM, 1 HP, Ent

Temp 190°F, 73.8 MBH Heating, 5

GPM

Auto Body Shop Trane, Catalog #3 Fuel

Oil/Electric Auto Body Shop 1979 0%

Heating

Horizontal Unit Heater, 36.3 MBH,

3.5 GPM, 1100 CFM, 1550 RPM,

1/8 HP

Auto Body Shop Trane, Model #705 Fuel Oil Auto Body Shop 1979 0%

Heating/Cooling

Vertical Unit Ventilator, 750 CFM

supply, 115 CFM O.A., 4.4 MBH

Heating, 20.3 MBH Cooling, DX cooling

Greenhouse Trane, Model #07 Fuel Oil/Electric Greenhouse 1979 0%

Heating

Horizontal Unit Heater, 36.3 MBH,

3.5 GPM, 1100 CFM, 1550 RPM,

1/8 HP

Greenhouse Trane, Model #705 Fuel Oil Greenhouse 1979 0%

Heating

Cabinet Unit Heater, 20.2 MBH, 3.0 GPM,

200 CFM, 7000 RPM, 1/30 HP

Corridor 17 Trane, Model #03 Fuel Oil Corridor 17 1979 0%

Heating

Cabinet Unit Heater, 20.2 MBH, 3.0 GPM,

200 CFM, 7000 RPM, 1/30 HP

Corridor 17 Trane, Model #03 Fuel Oil Corridor 17 1979 0%

Heating Unit Heater, 1004, 1550 RPM, 1/8 HP,

40.4 MBH

Auto Mechanics 40

Trane, Model #70-WF Fuel Oil Auto Mechanics

40 1971 0%

Page 43: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 43/70

Heating

Unit Ventilator, 2000 CFM, 145,000

BTUH Heating, 1/3 HP

Auto Mechanics 40 Trane, Model #20 Fuel Oil Auto Mechanics

40 1971 0%

Heating

Unit Ventilator, 2000 CFM, 145,000

BTUH Heating, 1/3 HP

Auto Mechanics 40 Trane, Model #20 Fuel Oil Auto Mechanics

40 1971 0%

Heating Unit Ventilator, 750 CFM, 29,000 BTUH

Heating, 1/6 HP

Planning Room 41 Trane, Model #07 Fuel Oil Planning Room

41 1971 0%

Heating Unit Ventilator, 750 CFM, 29,000 BTUH

Heating, 1/6 HP

Planning Room 41 Trane, Model #07 Fuel Oil Planning Room

41 1971 0%

Heating Unit Heater, 200,

1100 RPM, 100 W, 15 MBH

Corridor 70 Trane, Model E46-AO-04 Fuel Oil Corridor 70 1971 0%

Heating Unit Heater, 200,

1100 RPM, 100 W, 15 MBH

Corridor 70 Trane, Model E46-AO-04 Fuel Oil Corridor 70 1971 0%

Heating Unit Heater, 200,

1100 RPM, 100 W, 15 MBH

Corridor 70 Trane, Model E46-AO-04 Fuel Oil Corridor 70 1971 0%

Heating Unit Heater, 200,

1100 RPM, 100 W, 15 MBH

Corridor 70 Trane, Model E46-AO-04 Fuel Oil Corridor 70 1971 0%

Heating Unit Heater, 1004, 1550 RPM, 1/8 HP,

40.4 MBH Auto Body 49 Trane, Model #70-

WF Fuel Oil Auto Body 49 1971 0%

Heating Unit Ventilator, 1500 CFM, 75,000 BTUH

Heating, 1/6 HP Auto Body 49 Trane, Model #15 Fuel Oil Auto Body 49 1971 0%

Heating

Unit Ventilator, 2000 CFM, 125,000

BTUH Heating, 1/3 HP

Auto Body 49 Trane, Model #20 Fuel Oil Auto Body 49 1971 0%

Heating Unit Ventilator, 750 CFM, 29,000 BTUH

Heating, 1/6 HP

Planning Room 50 Trane, Model #07 Fuel Oil Planning Room

50 1971 0%

Heating

Unit Ventilator, 2000 CFM, 143,000

BTUH Heating, 1/3 HP

A/C & Heating 56 Trane, Model #20 Fuel Oil A/C & Heating 56 1971 0%

Heating Unit Ventilator, 750 CFM, 29,000 BTUH

Heating, 1/6 HP

Planning Room 57 Trane, Model #07 Fuel Oil Planning Room

57 1971 0%

Heating

Unit Ventilator, 2000 CFM, 143,000

BTUH Heating, 1/3 HP

Appliance Services Trane, Model #20 Fuel Oil Appliance

Services 1971 0%

Heating Unit Ventilator, 750 CFM, 29,000 BTUH

Heating, 1/6 HP

Appliance Services Trane, Model #07 Fuel Oil Appliance

Services 1971 0%

Heating

Unit Ventilator, 2000 CFM, 143,000

BTUH Heating, 1/3 HP

Electrical Trades Trane, Model #20 Fuel Oil Electrical Trades 1971 0%

Page 44: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 44/70

Heating Unit Ventilator, 750 CFM, 29,000 BTUH

Heating, 1/6 HP

Planning Room 27 Trane, Model #07 Fuel Oil Planning Room

27 1971 0%

Heating

Unit Ventilator, 2000 CFM, 145,000

BTUH Heating, 1/3 HP

Building Trades Trane, Model #20 Fuel Oil Building Trades 1971 0%

Heating

Unit Ventilator, 2000 CFM, 145,000

BTUH Heating, 1/3 HP

Building Trades Trane, Model #20 Fuel Oil Building Trades 1971 0%

Heating Unit Heater, 1004, 1550 RPM, 1/8 HP,

40.4 MBH

Building Trades

Trane, Model #70-WF Fuel Oil Building Trades 1971 0%

Heating/Cooling

Unit Ventilator, 750 CFM, 29,000 BTUH

Heating, 1/6 HP

Planning Room 64 Trane, Model #07 Fuel Oil Planning Room

64 1971 0%

Heating Unit Heater, 200,

1100 RPM, 100 W, 15 MBH

Gallery 1 Trane, Model E46-AO-04 Fuel Oil Gallery 1 1971 0%

Heating Unit Heater, 200,

1100 RPM, 100 W, 15 MBH

Gallery 1 Trane, Model E46-AO-04 Fuel Oil Gallery 1 1971 0%

Heating/Cooling

Unit Ventilator, 1500 CFM, 74,000 BTUH

Heating, 1/6 HP

Beauty Culture 20 Trane, Model #15 Fuel Oil Beauty Culture

20 1971 0%

Heating/Cooling

Unit Ventilator, 1500 CFM, 74,000 BTUH

Heating, 1/6 HP

Beauty Culture 20 Trane, Model #15 Fuel Oil Beauty Culture

20 1971 0%

Heating Unit Heater, 200,

1100 RPM, 100 W, 15 MBH

Corridor Trane, Model E46-AO-04 Fuel Oil Corridor 1971 0%

Heating/Cooling

Unit Ventilator, 1500 CFM, 52,000 BTUH

Heating, 1/6 HP

Health Assistant 16 Trane, Model #15 Fuel Oil Health Assistant

16 1971 0%

Heating/Cooling

Unit Ventilator, 1500 CFM, 52,000 BTUH

Heating, 1/6 HP

Health Assistant 16 Trane, Model #15 Fuel Oil Health Assistant

16 1971 0%

Heating

Pump motor, 1 1/2 HP, 1725 RPM, NEMA Nom. Eff.

78.5%

Mechanical Room

Baldor, Cat. #UM3154, Spec.

35B15-372 Electric Boilers 1971 0%

Heating

Pump motor, 1 1/2 HP, 1725 RPM, NEMA Nom. Eff.

78.5%

Mechanical Room

Baldor, Cat. #UM3154, Spec.

35B15-372 Electric Boilers 1971 0%

Cooling Indoor Unit, 0.4A motor load, switch

capacity 20A Server Room

Sanyo, Model #KS1251, Serial

#0260432 Electric Server Room 2003 55%

Cooling Outdoor Unit, 11,800 BTU/HR Roof

Sanyo, Model #CL1251, Serial

#0053434 Electric Server Room 2003 55%

Cooling Indoor Unit, 0.4A motor load, switch

capacity 15A Server Room

Sanyo, Model #KS3682, Serial

#0070304 Electric Planning Room

64 2010 90%

Page 45: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 45/70

Cooling Outdoor Unit, R-410A, 11,800

BTU/HR, SEER 16 Roof

Sanyo, Model #C3682, Serial

#0071712 Electric Planning Room

64 2011 95%

Cooling Outdoor Unit,

100,000 BTU/HR Heating,

Roof

Model #.RRNA-B036JK10E, Serial #2G7287ADAAF43

0707869

Electric Computer Lab 2007 75%

Heating/Cooling

Rooftop Unit, R-22, 2 compressors, 7.5

ton, 13 SEER Roof

Model #PAB090N2HA RAMA75H001A

Electric Administrative Office 1994 10%

Cooling Condensing Unit, R-22, 3.5 ton, 1/6 HP Exterior

Model #2TTA2042A300A

A, Serial #2355X6K3F

Electric Health Assistant 16 2002 50%

Cooling Condensing Unit, R-22, 3.5 ton, 1/6 HP Exterior

Model #2TTR2042A1000

AA, Serial #2291M5W2F

Electric Health Assistant 16 2002 50%

Cooling Condensing Unit, R-22, 4 ton, 1/6 HP Exterior

Model #2TTA2048A3000A

A, Serial #2364NXW3F

Electric Beauty Culture 20 2002 50%

Cooling Condensing Unit, R-22, 4 ton, 1/6 HP Exterior

Model #2TTA2048A3000A

, Serial #2364NUP3F

Electric Beauty Culture 20 2002 50%

Note: The remaining useful life of a system (in %) is an estimate based on the system date of built and existing conditions derived from visual inspection.

Page 46: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Appendix B: Jackson Center Floor Plan

Appendix C: Lighting Study

Page 47: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 47/70

Mar

ker

Floo

r

Room

Iden

tific

atio

n

Fixt

ure

Type

Balla

st

Lam

p Ty

pe

# of

Fix

ture

s

# of

Lam

ps p

er

Fixt

ure

Wat

ts p

er L

amp

Cont

rols

Ope

ratio

nal H

ours

pe

r Day

Ope

ratio

nal D

ays

per

Year

Balla

st W

atta

ge

Tota

l Wat

ts

Ener

gy U

se

kWh/

year

Cate

gory

Fixt

ure

Type

Lam

p Ty

pe

Balla

st

Cont

rols

# of

Fix

ture

s

# of

Lam

ps p

er

Fixt

ure

Wat

ts p

er L

amp

Ope

ratio

nal H

ours

pe

r Day

Ope

ratio

nal D

ays

per

Year

Balla

st W

atts

Tota

l Wat

ts

Ener

gy U

se

kWh/

year

Fixt

ure

Savi

ngs

(kW

h)

Cont

rols

Sav

ings

(k

Wh)

Tota

l Sav

ings

(kW

h)

1 1 Fac. Rm (J5A ) Recessed Parabolic E 4'T5 5 2 28 OS 8 261 8 320 668 N/A Recessed Parabolic 4'T5 E OS 5 2 28 8 261 8 320 668 0 0 02 1 Fac. Bathroom (J5) Recessed Parabolic E 2'T5 1 2 14 OS 8 261 4 32 67 N/A Recessed Parabolic 2'T5 E OS 1 2 14 8 261 4 32 67 0 0 03 1 Fac. Bathroom (J5B) Recessed Parabolic E 2'T5 1 2 14 OS 8 261 4 32 67 N/A Recessed Parabolic 2'T5 E OS 1 2 14 8 261 4 32 67 0 0 04 1 Office (J1) Recessed Parabolic E 4'T5 10 2 28 OS 8 261 8 640 1,336 N/A Recessed Parabolic 4'T5 E OS 10 2 28 8 261 8 640 1336 0 0 05 1 Office Nurse (J3) Recessed Parabolic E 4'T5 8 2 28 Sw 8 261 8 512 1,069 N/A Recessed Parabolic 4'T5 E Sw 8 2 28 8 261 8 512 1069 0 0 06 1 Principal (J2) Recessed Parabolic E 4'T5 4 2 28 OS 8 261 8 256 534 N/A Recessed Parabolic 4'T5 E OS 4 2 28 8 261 8 256 534 0 0 07 1 Office Bathroom Recessed Parabolic E 2'T5 1 2 14 OS 8 261 4 32 67 N/A Recessed Parabolic 2'T5 E OS 1 2 14 8 261 4 32 67 0 0 08 1 Guidance (J4) Recessed Parabolic E 4'T5 2 2 28 OS 8 261 8 128 267 N/A Recessed Parabolic 4'T5 E OS 2 2 28 8 261 8 128 267 0 0 09 1 Vesibule Recessed Parabolic E 2'T5 3 2 14 Sw 8 261 4 96 200 N/A Recessed Parabolic 2'T5 E Sw 3 2 14 8 261 4 96 200 0 0 010 1 Hallway A Recessed Parabolic E 4'T5 12 2 28 Sw 8 261 8 768 1,603 N/A Recessed Parabolic 4'T5 E Sw 12 2 28 8 261 8 768 1603 0 0 011 1 Hallway B Recessed Parabolic E 4'T5 22 2 28 Sw 8 261 8 1,408 2,940 N/A Recessed Parabolic 4'T5 E Sw 22 2 28 8 261 8 1408 2940 0 0 012 1 Hallway B Exit Sign S LED 1 1 5 N 24 365 1 6 48 N/A Exit Sign LED S N 1 1 5 24 365 1 6 48 0 0 013 1 Boiler Room (J9 ) Ceiling Suspended E 4'T8 11 2 32 Sw 8 261 10 814 1,700 N/A Ceiling Suspended 4'T8 E Sw 11 2 32 8 261 10 814 1700 0 0 014 1 Hair Salon (J8) Ceiling Mounted E 4'T8 36 2 32 Sw 8 261 10 2,664 5,562 C Ceiling Mounted 4'T8 E OS 36 2 32 6 261 10 2664 4172 0 1391 139115 1 Locker Rm (J8B) Ceiling Mounted E 4'T8 1 2 32 Sw 8 261 10 74 155 N/A Ceiling Mounted 4'T8 E Sw 1 2 32 8 261 10 74 155 0 0 016 1 Locker Rm (J8A) Ceiling Mounted E 4'T8 4 2 32 Sw 8 261 10 296 618 N/A Ceiling Mounted 4'T8 E Sw 4 2 32 8 261 10 296 618 0 0 017 1 Locker Rm (J8A) Ceiling Mounted E 4'T8 3 2 32 Sw 8 261 10 222 464 N/A Ceiling Mounted 4'T8 E Sw 3 2 32 8 261 10 222 464 0 0 018 1 Hallway A Exit Sign S LED 2 1 5 N 24 365 1 11 96 N/A Exit Sign LED S N 2 1 5 24 365 1 11 96 0 0 019 1 Classroom (J6) Ceiling Mounted E 4'T8 28 2 32 Sw 8 261 10 2,072 4,326 C Ceiling Mounted 4'T8 E OS 28 2 32 6 261 10 2072 3245 0 1082 108220 1 Classroom (J6A) Ceiling Mounted E 4'T8 4 2 32 Sw 8 261 10 296 618 C Ceiling Mounted 4'T8 E OS 4 2 32 6 261 10 296 464 0 155 15521 1 Classroom (J6B) Ceiling Mounted E 4'T8 3 2 32 Sw 8 261 10 222 464 C Ceiling Mounted 4'T8 E OS 3 2 32 6 261 10 222 348 0 116 11622 1 Storage (J6) Ceiling Mounted E 4'T8 2 2 32 Sw 8 261 10 148 309 N/A Ceiling Mounted 4'T8 E Sw 2 2 32 8 261 10 148 309 0 0 023 1 Shop (J11) Ceiling Mounted E 4'T8 44 2 32 Sw 8 261 10 3,256 6,799 C Ceiling Mounted 4'T8 E OS 44 2 32 6 261 10 3256 5099 0 1700 170024 1 Locker (J11) Ceiling Mounted E 4'T8 2 2 32 Sw 8 261 10 148 309 N/A Ceiling Mounted 4'T8 E Sw 2 2 32 8 261 10 148 309 0 0 025 1 Bathroom (J11) Ceiling Mounted E 4'T8 1 2 32 Sw 8 261 10 74 155 C Ceiling Mounted 4'T8 E OS 1 2 32 6 261 10 74 116 0 39 3926 1 Office (J11) Ceiling Mounted E 4'T8 1 1 32 Sw 8 261 5 37 77 C Ceiling Mounted 4'T8 E OS 1 1 32 6 261 5 37 58 0 19 1927 1 Classroom (J11) Ceiling Mounted E 4'T8 8 2 32 Sw 8 261 10 592 1,236 C Ceiling Mounted 4'T8 E OS 8 2 32 6 261 10 592 927 0 309 30928 1 Shop (J11) Wall Mounted S Inc 2 1 60 Sw 9 261 0 120 282 CFL Wall Mounted CFL S Sw 2 1 20 9 261 0 40 94 188 0 18829 1 Shop (J13) Ceiling Mounted E 4'T8 42 2 32 Sw 8 261 10 3,108 6,490 C Ceiling Mounted 4'T8 E OS 42 2 32 6 261 10 3108 4867 0 1622 162230 1 Shop (J13) Exit Sign S LED 1 1 5 N 24 365 1 6 48 N/A Exit Sign LED S N 1 1 5 24 365 1 6 48 0 0 031 1 Locker (J13) Ceiling Mounted E 4'T8 2 2 32 Sw 8 261 10 148 309 N/A Ceiling Mounted 4'T8 E Sw 2 2 32 8 261 10 148 309 0 0 032 1 Shop (J13) Ceiling Mounted E 4'T8 1 6 32 Sw 8 261 30 222 464 N/A Ceiling Mounted 4'T8 E Sw 1 6 32 8 261 30 222 464 0 0 033 1 Bathroom (J13) Ceiling Mounted E 4'T8 1 2 32 Sw 8 261 10 74 155 C Ceiling Mounted 4'T8 E OS 1 2 32 6 261 10 74 116 0 39 3934 1 Classroom (J14) Ceiling Mounted E 4'T8 8 2 32 Sw 8 261 10 592 1,236 C Ceiling Mounted 4'T8 E OS 8 2 32 6 261 10 592 927 0 309 30935 1 Server Rm (J14) Ceiling Mounted E 4'T8 1 2 32 Sw 8 261 10 74 155 C Ceiling Mounted 4'T8 E OS 1 2 32 6 261 10 74 116 0 39 3936 1 Shop (J15) Ceiling Mounted E 4'T8 102 2 32 Sw 8 261 10 7,548 15,760 C Ceiling Mounted 4'T8 E OS 102 2 32 6 261 10 7548 11820 0 3940 394037 1 Shop (J15) Wall Mounted S Inc 2 1 60 Sw 9 261 0 120 282 CFL Wall Mounted CFL S Sw 2 1 20 9 261 0 40 94 188 0 18838 1 Bathroom (J15) Ceiling Mounted E 4'T8 1 2 32 Sw 8 261 10 74 155 C Ceiling Mounted 4'T8 E OS 1 2 32 6 261 10 74 116 0 39 3939 1 Classroom (J16) Ceiling Mounted E 4'T8 8 2 32 Sw 8 261 10 592 1,236 C Ceiling Mounted 4'T8 E OS 8 2 32 6 261 10 592 927 0 309 30940 1 Office (J16) Ceiling Mounted E 4'T8 1 2 32 Sw 8 261 10 74 155 C Ceiling Mounted 4'T8 E OS 1 2 32 6 261 10 74 116 0 39 3941 1 Classroom (J16) Exit Sign S LED 1 1 5 N 24 365 1 6 48 N/A Exit Sign LED S N 1 1 5 24 365 1 6 48 0 0 042 1 Hallway B Ceiling Mounted E 2'T8 2 2 17 Sw 8 261 4 76 159 N/A Ceiling Mounted 2'T8 E Sw 2 2 17 8 261 4 76 159 0 0 043 1 Shop (J17) Ceiling Mounted E 4'T8 70 2 32 Sw 8 261 10 5,180 10,816 C Ceiling Mounted 4'T8 E OS 70 2 32 6 261 10 5180 8112 0 2704 270444 1 Shop (J17) Wall Mounted S Inc 1 1 60 Sw 9 261 0 60 141 CFL Wall Mounted CFL S Sw 1 1 20 9 261 0 20 47 94 0 9445 1 Classroom (J18) Ceiling Mounted E 4'T8 8 2 32 Sw 8 261 10 592 1,236 C Ceiling Mounted 4'T8 E OS 8 2 32 6 261 10 592 927 0 309 30946 1 Office (J18) Ceiling Mounted E 4'T8 1 2 32 Sw 8 261 10 74 155 C Ceiling Mounted 4'T8 E OS 1 2 32 6 261 10 74 116 0 39 3947 1 Bathroom (J17) Ceiling Mounted E 4'T8 1 2 32 Sw 8 261 10 74 155 C Ceiling Mounted 4'T8 E OS 1 2 32 6 261 10 74 116 0 39 3948 1 Shop (J19) Ceiling Mounted E 4'T8 67 2 32 Sw 8 261 10 4,958 10,352 C Ceiling Mounted 4'T8 E OS 67 2 32 6 261 10 4958 7764 0 2588 258849 1 Shop (J19) Wall Mounted S Inc 1 1 60 Sw 9 261 0 60 141 CFL Wall Mounted CFL S Sw 1 1 20 9 261 0 20 47 94 0 9450 1 Classroom (J20) Ceiling Mounted E 4'T8 8 2 32 Sw 8 261 10 592 1,236 C Ceiling Mounted 4'T8 E OS 8 2 32 6 261 10 592 927 0 309 30951 1 Classroom (J20) Wall Mounted S Inc 1 1 60 Sw 9 261 0 60 141 CFL Wall Mounted CFL S Sw 1 1 20 9 261 0 20 47 94 0 9452 1 B-Vestibule Ceiling Mounted E 4'T8 1 2 32 Sw 8 261 10 74 155 N/A Ceiling Mounted 4'T8 E Sw 1 2 32 8 261 10 74 155 0 0 053 1 Bathroom (J22) Ceiling Mounted E 4'T8 1 2 32 Sw 8 261 10 74 155 C Ceiling Mounted 4'T8 E OS 1 2 32 6 261 10 74 116 0 39 3954 1 Garden (J22) Ceiling Mounted E 4'T8 96 2 32 Sw 8 261 10 7,104 14,833 N/A Ceiling Mounted 4'T8 E Sw 96 2 32 8 261 10 7104 14833 0 0 055 1 Garden (J22) Exit Sign S LED 2 1 5 N 24 365 1 11 96 N/A Exit Sign LED S N 2 1 5 24 365 1 11 96 0 0 056 1 Garden (J22) Wall Mounted S Inc 1 1 60 Sw 9 261 0 60 141 CFL Wall Mounted CFL S Sw 1 1 20 9 261 0 20 47 94 0 9457 1 Garden (J22) Track S Inc 7 1 75 Sw 4 261 0 525 548 CFL Track CFL S Sw 7 1 25 4 261 0 175 183 365 0 36558 1 Classroom (J21) Ceiling Mounted E 4'T8 8 2 32 Sw 8 261 10 592 1,236 C Ceiling Mounted 4'T8 E OS 8 2 32 6 261 10 592 927 0 309 30959 1 Storage (J22) Ceiling Mounted E 4'T8 4 2 32 Sw 8 261 10 296 618 N/A Ceiling Mounted 4'T8 E Sw 4 2 32 8 261 10 296 618 0 0 060 1 MER (J22) Ceiling Mounted E 4'T8 3 2 32 Sw 8 261 10 222 464 N/A Ceiling Mounted 4'T8 E Sw 3 2 32 8 261 10 222 464 0 0 061 1 Greenroom (J23) Ceiling Mounted E 4'T8 30 2 32 Sw 8 261 10 2,220 4,635 N/A Ceiling Mounted 4'T8 E Sw 30 2 32 8 261 10 2220 4635 0 0 062 1 Storage (J24) Ceiling Mounted E 4'T8 7 2 32 Sw 8 261 10 518 1,082 N/A Ceiling Mounted 4'T8 E Sw 7 2 32 8 261 10 518 1082 0 0 063 1 Mens Bathroom Ceiling Mounted E 2'T8 1 2 17 Sw 8 261 4 38 79 C Ceiling Mounted 2'T8 E OS 1 2 17 6 261 4 38 60 0 20 2064 1 Womens Bathroom Ceiling Mounted E 2'T8 1 2 17 Sw 8 261 4 38 79 C Ceiling Mounted 2'T8 E OS 1 2 17 6 261 4 38 60 0 20 2065 1 Computer Lab (J26) Exit Sign S LED 1 1 5 N 24 365 1 6 48 N/A Exit Sign LED S N 1 1 5 24 365 1 6 48 0 0 066 1 Computer Lab (J26) Ceiling Mounted E 4'T8 10 2 32 Sw 8 261 10 740 1,545 C Ceiling Mounted 4'T8 E OS 10 2 32 6 261 10 740 1159 0 386 38667 1 Shop (J25) Ceiling Mounted E 4'T8 72 2 32 Sw 8 261 10 5,328 11,125 C Ceiling Mounted 4'T8 E OS 72 2 32 6 261 10 5328 8344 0 2781 278168 1 Paint Room (J25) Ceiling Mounted E 4'T8 2 4 32 Sw 8 261 20 296 618 N/A Ceiling Mounted 4'T8 E Sw 2 4 32 8 261 20 296 618 0 0 069 1 Paint Room (J25) Ceiling Mounted E 4'T8 14 6 32 Sw 8 261 30 3,108 6,490 N/A Ceiling Mounted 4'T8 E Sw 14 6 32 8 261 30 3108 6490 0 0 0

Location Existing Fixture Information Retrofit Information Annual Savings

Page 48: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 48/70

Proposed Lighting Summary Table Total Gross Floor Area (SF) 54,000

Average Power Cost ($/kWh) 0.1550 Exterior Lighting Existing Proposed Savings

Exterior Annual Consumption (kWh) 28,948 12,755 16,194 Exterior Power (watts) 6,609 2,912 3,697

Total Interior Lighting Existing Proposed Savings Annual Consumption (kWh) 155,897 128,300 27,598 Lighting Power (watts) 74,725 74,055 670 Lighting Power Density (watts/SF) 1.38 1.37 0.01 Estimated Cost of Fixture Replacement ($) 23,933 Estimated Cost of Controls Improvements ($) 7,800 Total Consumption Cost Savings ($) 11,130

Mar

ker

Floo

r

Roo

m

Iden

tific

atio

n

Fixt

ure

Type

Bal

last

Lam

p Ty

pe

# of

Fix

ture

s

# of

Lam

ps p

er

Fixt

ure

Wat

ts p

er L

amp

Con

trols

Ope

ratio

nal

Hou

rs p

er D

ay

Ope

ratio

nal

Day

s pe

r Yea

r

Bal

last

Wat

tage

Tota

l Wat

ts

Ene

rgy

Use

kW

h/ye

ar

Cat

egor

y

Fixt

ure

Type

Lam

p Ty

pe

Bal

last

Con

trol

s

# of

Fix

ture

s

# of

Lam

ps p

er

Fixt

ure

Wat

ts p

er L

amp

Ope

ratio

nal

Hou

rs p

er D

ay

Ope

ratio

nal

Day

s pe

r Yea

r

Bal

last

Wat

ts

Tota

l Wat

ts

Ene

rgy

Use

kW

h/ye

ar

Fixt

ure

Sav

ings

(k

Wh)

Con

trols

S

avin

gs (k

Wh)

Tota

l Sav

ings

(k

Wh)

70 1 Paint Room (J25) Ceiling Mounted E 4'T8 8 3 32 Sw 8 261 15 888 1,854 N/A Ceiling Mounted 4'T8 E Sw 8 3 32 8 261 15 888 1854 0 0 071 1 Paint Room (J25) Ceiling Mounted E 4'T8 8 2 32 Sw 8 261 10 592 1,236 N/A Ceiling Mounted 4'T8 E Sw 8 2 32 8 261 10 592 1236 0 0 072 1 Tool Room (J25) Ceiling Mounted E 4'T8 2 2 32 Sw 8 261 10 148 309 N/A Ceiling Mounted 4'T8 E Sw 2 2 32 8 261 10 148 309 0 0 073 1 Bathroom (J25) Ceiling Mounted E 4'T8 4 2 32 Sw 8 261 10 296 618 C Ceiling Mounted 4'T8 E OS 4 2 32 6 261 10 296 464 0 155 15574 1 Upper tool Rm. (J25) Ceiling Mounted E 4'T8 7 2 32 Sw 8 261 10 518 1,082 N/A Ceiling Mounted 4'T8 E Sw 7 2 32 8 261 10 518 1082 0 0 075 1 Classroom (J27) Ceiling Mounted E 4'T8 8 2 32 Sw 8 261 10 592 1,236 C Ceiling Mounted 4'T8 E OS 8 2 32 6 261 10 592 927 0 309 30976 1 Office (J27) Ceiling Mounted E 4'T8 1 2 32 Sw 8 261 10 74 155 C Ceiling Mounted 4'T8 E OS 1 2 32 6 261 10 74 116 0 39 3977 1 Shop (J28) Ceiling Mounted E 4'T8 36 2 32 Sw 8 261 10 2,664 5,562 C Ceiling Mounted 4'T8 E OS 36 2 32 6 261 10 2664 4172 0 1391 139178 1 Bathroom (J28) Ceiling Mounted E 4'T8 1 2 32 Sw 8 261 10 74 155 C Ceiling Mounted 4'T8 E OS 1 2 32 6 261 10 74 116 0 39 3979 1 Classroom (J29) Ceiling Mounted E 4'T8 8 2 32 Sw 8 261 10 592 1,236 C Ceiling Mounted 4'T8 E OS 8 2 32 6 261 10 592 927 0 309 30980 1 Office (J29) Ceiling Mounted E 4'T8 1 2 32 Sw 8 261 10 74 155 C Ceiling Mounted 4'T8 E OS 1 2 32 6 261 10 74 116 0 39 3981 1 Shop (J30) Ceiling Mounted E 4'T8 81 2 32 Sw 8 261 10 5,994 12,515 C Ceiling Mounted 4'T8 E OS 81 2 32 6 261 10 5994 9387 0 3129 312982 1 Bathroom (J30) Ceiling Mounted E 4'T8 1 2 32 Sw 8 261 10 74 155 C Ceiling Mounted 4'T8 E OS 1 2 32 6 261 10 74 116 0 39 3983 1 Classroom (J30) Ceiling Mounted E 4'T8 8 2 32 Sw 8 261 10 592 1,236 C Ceiling Mounted 4'T8 E OS 8 2 32 6 261 10 592 927 0 309 30984 1 Office (J30) Ceiling Mounted E 4'T8 1 2 32 Sw 8 261 10 74 155 C Ceiling Mounted 4'T8 E OS 1 2 32 6 261 10 74 116 0 39 3985 1 Custodial (J10) Ceiling Mounted E 4'T8 8 2 32 Sw 8 261 10 592 1,236 N/A Ceiling Mounted 4'T8 E Sw 8 2 32 8 261 10 592 1236 0 0 086 Ext Exterior Sconce S CFL 2 2 8 T 12 365 0 32 140 N/A Sconce CFL S T 2 2 8 12 365 0 32 140 0 0 087 Ext Exterior WallPack S HPS 13 1 165 T 12 365 33 2,574 11,274 PSMH Wallpack PSMH S T 13 1 100 12 365 20 1560 6833 4441 0 444188 Ext Exterior Landscape S HPS 4 1 166 T 12 365 33 797 3,490 PSMH Landscape PSMH S T 4 1 100 12 365 20 480 2102 1388 0 138889 Ext Exterior Landscape S HPS 4 4 167 T 12 365 134 3,206 14,044 PSMH Landscape PSMH S T 4 4 100 12 365 80 1920 8410 5634 0 5634

1,020 175 3,130 917 81,335 184,846 1,020 175 2,642 837 78,047 ###### 12,580 26,481 #####

Existing Fixture Information Retrofit Information Annual Savings

Totals:

Location

Page 49: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 49/70

CFL Compact Fluorescent T Autom. TimerInc Incadescent BL Bi-LevelLED Light Emitting Diode Ct ContactMH Metal Halide M Daylight & MotionMV Mercury Vapor DLSw Daylight & Switch

PSMH Pulse Start Metal Halide DL Daylight SensorHPS High Pressure Sodium DSw Delay SwitchLPS Low Pressure Sodium D DimmerFl Fluorescent MS Motion Sensor

4'T8 4 Feet long T8 Linear Lamp MSw Motion& Switch4'T8 U-shaped 4 Feet long T8 U-shaped Lamp N None

4'T5 4 Feet long T5 Linear Lamp OS Occupancy SensorOSCM Occupancy Sensor Ceiling Mounted

E Electronic PC PhotocellM Magnetic Sw SwitchS Self

Lamp Type

Ballast Type

ControlsLEGEND

Page 50: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

APPENDIX D: SOLAR PV SHADING ANALYSIS

Page 51: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 51/70

Page 52: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 52/70

Page 53: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 53/70

Page 54: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 54/70

APPENDIX E: EnergyMiser Calculations

Page 55: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 55/70

APPENDIX F: COST WORKS COST ESTIMATES

Page 56: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 56/70

Page 57: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 57/70

APPENDIX G: UPCOMING EQUIPMENT PHASEOUTS LIGHTING:

• As of July 1, 2010 magnetic ballasts most commonly used for the operation of T12 lamps are no longer being produced for commercial and industrial applications.

• As of January 1, 2012 100 watt incandescent bulbs have been phased out in accordance with the Energy Independence and Security Act of 2007.

• Starting July 2012 many non energy saver model T12 lamps will be phased out of

production.

• As of January 1, 2013 75 watt incandescent bulbs will be phased out in accordance with the Energy Independence and Security Act of 2007.

• As of January 1, 2014 60 and 40 watt incandescent bulbs will be phased out in

accordance with the Energy Independence and Security Act of 2007.

• Energy Independence and Security Act of 2007 incandescent lamp phase-out exclusions: 1. Appliance lamp (e.g. refrigerator or oven light) 2. Black light lamp 3. Bug lamp 4. Colored lamp 5. Infrared lamp 6. Left-hand thread lamp 7. Marine lamp 8. Marine signal service lamp 9. Mine service lamp 10. Plant light lamp 11. Reflector lamp 12. Rough service lamp 13. Shatter-resistant lamp (including a shatter-proof lamp and a shatter-protected lamp) 14. Sign service lamp 15. Silver bowl lamp 16. Showcase lamp 17. 3-way incandescent lamp 18. Traffic signal lamp 19. Vibration service lamp 20. Globe shaped “G” lamp (as defined in ANSI C78.20-2003 and C79.1-2002 with a

diameter of 5 inches or more 21. T shape lamp (as defined in ANSI C78.20-2003 and C79.1-2002) and that uses not

more than 40 watts or has a length of more than 10 inches 22. A B, BA, CA, F, G16-1/2, G-25, G30, S, or M-14 lamp (as defined in ANSI C79.1-

2002 and ANSI C78.20-2003) of 40 watts or less 23. Candelabra incandescent and other lights not having a medium Edison screw base.

• When installing compact fluorescent lamps (CFLs), be advised that they contain a very

small amount of mercury sealed within the glass tubing and EPA guidelines concerning

Page 58: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 58/70

cleanup and safe disposal of compact fluorescent light bulbs should be followed. Additionally, all lamps to be disposed should be recycled in accordance with EPA guidelines through state or local government collection or exchange programs instead.

HCFC (Hydrochlorofluorocarbons):

• As of January 1, 2010, no production and no importing of R-142b and R-22, except for use in equipment manufactured before January 1, 2010, in accordance with adherence to the Montreal Protocol.

• As of January 1, 2015, No production and no importing of any HCFCs, except for use as refrigerants in equipment manufactured before January 1, 2010.

• As of January 1, 2020 No production and no importing of R-142b and R-22.

Page 59: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 59/70

APPENDIX H: THIRD PARTY ENERGY SUPPLIERS http://www.state.nj.us/bpu/commercial/shopping.html

Third Party Electric Suppliers for Atlantic City Electric Service Territory Telephone & Web Site

Hess Corporation (800) 437-7872 1 Hess Plaza www.hess.com

Woodbridge, NJ 07095 American Powernet Management, LP (877) 977-2636 437 North Grove St. www.americanpowernet.com

Berlin, NJ 08009 BOC Energy Services, Inc. (800) 247-2644 575 Mountain Avenue www.boc.com

Murray Hill, NJ 07974 Commerce Energy, Inc. (800) 556-8457 4400 Route 9 South, Suite 100 www.commerceenergy.com

Freehold, NJ 07728 ConEdison Solutions (888) 665-0955 535 State Highway 38 www.conedsolutions.com

Cherry Hill, NJ 08002 Constellation NewEnergy, Inc. (888) 635-0827 900A Lake Street, Suite 2 www.newenergy.com

Ramsey, NJ 07446 Direct Energy Services, LLC (866) 547-2722 120 Wood Avenue, Suite 611 www.directenergy.com

Iselin, NJ 08830 FirstEnergy Solutions (800) 977-0500 300 Madison Avenue www.fes.com

Morristown, NJ 07926 Glacial Energy of New Jersey, Inc. (877) 569-2841 207 LaRoche Avenue www.glacialenergy.com

Harrington Park, NJ 07640 Integrys Energy Services, Inc. (877) 763-9977 99 Wood Ave, South, Suite 802 www.integrysenergy.com

Iselin, NJ 08830 Liberty Power Delaware, LLC (866) 769-3799 Park 80 West Plaza II, Suite 200 www.libertypowercorp.com

Saddle Brook, NJ 07663 Liberty Power Holdings, LLC (800) 363-7499 Park 80 West Plaza II, Suite 200 www.libertypowercorp.com

Saddle Brook, NJ 07663 Pepco Energy Services, Inc. (800) 363-7499 112 Main St. www.pepco-services.com

Lebanon, NJ 08833 PPL EnergyPlus, LLC (800) 281-2000 811 Church Road www.pplenergyplus.com

Cherry Hill, NJ 08002

Page 60: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 60/70

Sempra Energy Solutions (877) 273-6772 581 Main Street, 8th Floor www.semprasolutions.com

Woodbridge, NJ 07095 South Jersey Energy Company (800) 756-3749 One South Jersey Plaza, Route 54 www.southjerseyenergy.com

Folsom, NJ 08037 Strategic Energy, LLC (888) 925-9115 55 Madison Avenue, Suite 400 www.sel.com

Morristown, NJ 07960 Suez Energy Resources NA, Inc. (888) 644-1014 333 Thornall Street, 6th Floor www.suezenergyresources.com

Edison, NJ 08837 UGI Energy Services, Inc. (856) 273-9995 704 East Main Street, Suite 1 www.ugienergyservices.com

Moorestown, NJ 08057

Page 61: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 61/70

APPENDIX I: GLOSSARY AND METHOD OF CALCULATIONS Net ECM Cost: The net ECM cost is the cost experienced by the customer, which is typically the total cost (materials + labor) of installing the measure minus any available incentives. Both the total cost and the incentive amounts are expressed in the summary for each ECM. Annual Energy Cost Savings (AECS): This value is determined by the audit firm based on the calculated energy savings (kWh or Therm) of each ECM and the calculated energy costs of the building. Lifetime Energy Cost Savings (LECS): This measure estimates the energy cost savings over the lifetime of the ECM. It can be a simple estimation based on fixed energy costs. If desired, this value can factor in an annual increase in energy costs as long as the source is provided. Simple Payback: This is a simple measure that displays how long the ECM will take to break-even based on the annual energy and maintenance savings of the measure. ECM Lifetime: This is included with each ECM so that the owner can see how long the ECM will be in place and whether or not it will exceed the simple payback period. Additional guidance for calculating ECM lifetimes can be found below. This value can come from manufacturer’s rated lifetime or warranty, the ASHRAE rated lifetime, or any other valid source. Operating Cost Savings (OCS): This calculation is an annual operating savings for the ECM. It is the difference in the operating, maintenance, and / or equipment replacement costs of the existing case versus the ECM. In the case where an ECM lifetime will be longer than the existing measures (such as LED lighting versus fluorescent) the operating savings will factor in the cost of replacing the units to match the lifetime of the ECM. In this case or in one where one-time repairs are made, the total replacement / repair sum is averaged over the lifetime of the ECM. Return on Investment (ROI): The ROI is expresses the percentage return of the investment based on the lifetime cost savings of the ECM. This value can be included as an annual or lifetime value, or both. Net Present Value (NPV): The NPV calculates the present value of an investment’s future cash flows based on the time value of money, which is accounted for by a discount rate (assumes bond rate of 3.2%). Internal Rate of Return (IRR): The IRR expresses an annual rate that results in a break-even point for the investment. If the owner is currently experiencing a lower return on their capital than the IRR, the project is financially advantageous. This measure also allows the owner to compare ECMs against each other to determine the most appealing choices. Fuel Oil Rate and Electric Rate ($/gallon and $/kWh): The gas rate and electric rate used in the financial analysis is the total annual energy cost divided by the total annual energy usage for the 12 month billing period studied. The graphs of the monthly fuel oil and electric rates reflect the total monthly energy costs divided by the monthly usage, and display how the average rate fluctuates throughout the year. The average annual rate is the only rate used in energy savings calculations.

Page 62: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 62/70

Calculation References

Term Definition ECM Energy Conservation Measure

AOCS Annual Operating Cost Savings AECS Annual Energy Cost Savings LOCS* Lifetime Operating Cost Savings LECS Lifetime Energy Cost Savings LCS Lifetime Cost Savings NPV Net Present Value IRR Internal Rate of Return DR Discount Rate

Net ECM Cost Total ECM Cost – Incentive LECS AECS X ECM Lifetime AOCS LOCS / ECM Lifetime LCS LOCS+LECS

Simple Payback Net ECM Cost / (AECS + AOCS) Lifetime ROI (LECS + LOCS – Net ECM Cost) / Net ECM Cost Annual ROI (Lifetime ROI / Lifetime) = [(AECS + OCS) / Net ECM Cost – (1 / Lifetime)]

* The lifetime operating cost savings are all avoided operating, maintenance, and/or component replacement costs over the lifetime of the ECM. This can be the sum of any annual operating savings, recurring or bulk (i.e. one-time repairs) maintenance savings, or the savings that comes from avoiding equipment replacement needed for the existing measure to meet the lifetime of the ECM (e.g. lighting change outs).

Excel NPV and IRR Calculation In Excel, function =IRR (values) and =NPV (rate, values) are used to quickly calculate the IRR and NPV of a series of annual cash flows. The investment cost will typically be a negative cash flow at year 0 (total cost - incentive) with years 1 through the lifetime receiving a positive cash flow from the annual energy cost savings and annual maintenance savings. The calculations in the example below are for an ECM that saves $850 annually in energy and maintenance costs (over a 10 year lifetime) and takes $5,000 to purchase and install after incentives:

Page 63: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 63/70

Solar PV ECM Calculation There are several components to the calculation: Costs: Material of PV system including panels, mounting and net-metering +

Labor Energy Savings: Reduction of kWh electric cost for life of panel, 25 years Solar Renewable Energy Credits (SRECs) – Market-rate incentive.

Calculations assume $145/Megawatt hour consumed per year for a maximum of 15 years; added to annual energy cost savings for a period of 15 years. (Megawatt hour used is rounded to nearest 1,000 kWh)

Assumptions: A Solar Pathfinder device is used to analyze site shading for the building and determine maximum amount of full load operation based on available sunlight. When the Solar Pathfinder device is not implemented, amount of full load operation based on available sunlight is assumed to be 1,180 hours in New Jersey.

Total lifetime PV energy cost savings = kWh produced by panel * [$/kWh cost * 25 years + $145/Megawatt hour /1000 * 15 years]

ECM and Equipment Lifetimes Determining a lifetime for equipment and ECM’s can sometimes be difficult. The following table contains a list of lifetimes that the NJCEP uses in its commercial and industrial programs. Other valid sources are also used to determine lifetimes, such as the DOE, ASHRAE, or the manufacturer’s warranty. Lighting is typically the most difficult lifetime to calculate because the fixture, ballast, and bulb can all have different lifetimes. Essentially the ECM analysis will have different operating cost savings (avoided equipment replacement) depending on which lifetime is used. When the bulb lifetime is used (rated burn hours / annual burn hours), the operating cost savings is just reflecting the theoretical cost of replacing the existing case bulb and ballast over the life of the recommended bulb. Dividing by the bulb lifetime will give an annual operating cost savings. When a fixture lifetime is used (e.g. 15 years) the operating cost savings reflects the avoided bulb and ballast replacement cost of the existing case over 15 years minus the projected bulb and ballast replacement cost of the proposed case over 15 years. This will give the difference of the equipment replacement costs between the proposed and existing cases and when divided by 15 years will give the annual operating cost savings.

Page 64: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 64/70

New Jersey Clean Energy Program Commercial Equipment Life Span

Measure Life Span Commercial Lighting — New 15 Commercial Lighting — Remodel/Replacement 15 Commercial Custom — New 18 Commercial Chiller Optimization 18 Commercial Unitary HVAC — New - Tier 1 15 Commercial Unitary HVAC — Replacement - Tier 1 15 Commercial Unitary HVAC — New - Tier 2 15 Commercial Unitary HVAC — Replacement Tier 2 15 Commercial Chillers — New 25 Commercial Chillers — Replacement 25 Commercial Small Motors (1-10 HP) — New or Replacement 20 Commercial Medium Motors (11-75 HP) — New or Replacement 20 Commercial Large Motors (76-200 HP) — New or Replacement 20 Commercial VSDs — New 15 Commercial VSDs — Retrofit 15 Commercial Comprehensive New Construction Design 18 Commercial Custom — Replacement 18 Industrial Lighting — New 15 Industrial Lighting — Remodel/Replacement 15 Industrial Unitary HVAC — New - Tier 1 15 Industrial Unitary HVAC — Replacement - Tier 1 15 Industrial Unitary HVAC — New - Tier 2 15 Industrial Unitary HVAC — Replacement Tier 2 15 Industrial Chillers — New 25 Industrial Chillers — Replacement 25 Industrial Small Motors (1-10 HP) — New or Replacement 20 Industrial Medium Motors (11-75 HP) — New or Replacement 20 Industrial Large Motors (76-200 HP) — New or Replacement 20 Industrial VSDs — New 15 Industrial VSDs — Retrofit 15 Industrial Custom — Non-Process 18 Industrial Custom — Process 10 Small Commercial Gas Furnace — New or Replacement 20 Small Commercial Gas Boiler — New or Replacement 20 Small Commercial Gas DHW — New or Replacement 10 C&I Gas Absorption Chiller — New or Replacement 25 C&I Gas Custom — New or Replacement (Engine Driven Chiller) 25 C&I Gas Custom — New or Replacement (Gas Efficiency Measures) 18 O&M savings 3 Compressed Air (GWh participant) 8

Page 65: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 65/70

APPENDIX J: STATEMENT OF ENERGY PERFORMANCE FROM ENERGY STAR®

Page 66: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 66/70

APPENDIX K: INCENTIVE PROGRAMS New Jersey Clean Energy Pay for Performance The NJ Clean Energy Pay for Performance (P4P) Program relies on a network of Partners who provide technical services to clients. LGEA participating clients who are not receiving Direct Energy Efficiency and Conservation Block Grants are eligible for P4P. SWA is an eligible Partner and can develop an Energy Reduction Plan for each project with a whole-building traditional energy audit, a financial plan for funding the energy measures and an installation construction schedule. The Energy Reduction Plan must define a comprehensive package of measures capable of reducing a building’s energy consumption by 15+%. P4P incentives are awarded upon the satisfactory completion of three program milestones: submittal of an Energy Reduction Plan prepared by an approved Program Partner, installation of the recommended measures, and completion of a Post-Construction Benchmarking Report. The incentives for electricity and natural gas savings will be paid based on actual savings, provided that the minimum 15% performance threshold savings has been achieved. Energy Provider Incentives

• South Jersey Gas - Offers financing up to $100,000 on the customer’s portion of project cost through private lender. In addition to available financing, it provides matching incentive on gas P4P incentives #2 and #3 up to $100,000 (not to exceed total project cost).

For further information, please see: http://www.njcleanenergy.com/commercial-industrial/programs/pay-performance/existing-buildings . Direct Install 2011 Program* Direct Install is a division of the New Jersey Clean Energy Programs’ Smart Start Buildings. It is a turn-key program for small to mid-sized facilities to aid in upgrading equipment to more efficient types. It is designed to cut overall energy costs by upgrading lighting, HVAC, and other equipment with energy efficient alternatives. The program pays up to 70% of the retrofit costs, including equipment cost and installation costs. Each project is limited to $75,000 in incentives. Eligibility:

• Existing small and mid-sized commercial and industrial facilities with peak electrical demand below 150 kW within 12 months of applying (the 150 kW peak demand threshold has been waived for local government entities who receive and utilize their Energy Efficiency and Conservation Block Grant in conjunction with Direct Install)

• Must be located in New Jersey • Must be served by one of the state’s public, regulated or natural gas companies

Energy Provider Incentives

• South Jersey Gas – Program offers financing up to $25,000 on customer's 40% portion of the project and combines financing rate based on portion of the project devoted to gas

Page 67: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 67/70

and electric measures. All gas measures financed at 0%, all electric measures financed at normal rate. Does not offer financing on projects that only include electric measures.

• Atlantic City Electric – Provides a free audit, and additional incentives up to 20% of the current incentive up to a maximum of $5,000 per customer.

For the most up to date information on contractors in New Jersey who participate in this program, go to: http://www.njcleanenergy.com/commercial-industrial/programs/direct-install or visit the utility web sites. Smart Start New Jersey’s SmartStart Building Program is administered by New Jersey’s Office of Clean Energy. The program also offers design support for larger projects and technical assistance for smaller projects. If your project specifications do not fit into anything defined by the program, there are even incentives available for custom projects. There are a number of improvement options for commercial, industrial, institutional, government, and agricultural projects throughout New Jersey. Alternatives are designed to enhance quality while building in energy efficiency to save money. Project categories included in this program are New Construction and Additions, Renovations, Remodeling and Equipment Replacement. Energy Provider Incentives

• South Jersey Gas – Program to finance projects up to $25,000 not covered by incentive • New Jersey Natural Gas – Will match SSB incentives on gas equipment

PSE&G - Provides funding for site-specific uses of emerging technology. The incentives are determined on a case by case basis.

For the most up to date information on how to participate in this program, go to: http://www.njcleanenergy.com/commercial-industrial/programs/nj-smartstart-buildings/nj-smartstart-buildings. Renewable Energy Incentive Program* The Renewable Energy Incentive Program (REIP) provides incentives that reduce the upfront cost of installing renewable energy systems, including solar, wind, and sustainable biomass. Incentives vary depending upon technology, system size, and building type. Current incentive levels, participation information, and application forms can be found at the website listed below. Solar Renewable Energy Credits (SRECs) represent all the clean energy benefits of electricity generated from a solar energy system. SRECs can be sold or traded separately from the power, providing owners a source of revenue to help offset the cost of installation. All solar project owners in New Jersey with electric distribution grid-connected systems are eligible to generate SRECs. Each time a system generates 1,000 kWh of electricity an SREC is earned and placed in the customer's account on the web-based SREC tracking system. For the most up to date information on how to participate in this program, go to: http://www.njcleanenergy.com/renewable-energy/home/home.

Page 68: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

Steven Winter Associates, Inc. - LGEA Report OCVTS - Jackson Center School Page 68/70

Combined Heat and Power (CHP) Energy Provider Incentives

• South Jersey Gas - Provides additional incentive of $1.00/watt up to $1,000,000 on top of NJCEP incentive.

Utility Sponsored Programs Check with your local utility companies for further opportunities that may be available. Energy Efficiency and Conservation Block Grant Rebate Program The Energy Efficiency and Conservation Block Grant (EECBG) Rebate Program provides supplemental funding up to $20,000 for eligible New Jersey local government entities to lower the cost of installing energy conservation measures. Funding for the EECBG Rebate Program is provided through the American Recovery and Reinvestment Act (ARRA). For the most up to date information on how to participate in this program, go to: http://njcleanenergy.com/EECBG. Other Federal and State Sponsored Programs Other federal and state sponsored funding opportunities may be available, including BLOCK and R&D grant funding. For more information, please check http://www.dsireusa.org/. *Subject to availability. Incentive program timelines might not be sufficient to meet the 25% in 12 months spending requirement outlined in the LGEA program.

Page 69: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

APPENDIX L: ENERGY CONSERVATION MEASURES

Assumptions: Discount Rate: 3.2%; Energy Price Escalation Rate: 0% Note: A 0.0 electrical demand reduction/month indicates that it is very low/negligible

EC

M #

ECM description

est.

inst

alle

d co

st, $

est.

ince

ntiv

es, $

net e

st. E

CM

cos

t w

ith in

cent

ives

, $

kWh,

1st

yr s

avin

gs

kW, d

eman

d re

duct

ion/

mo

ther

ms,

1st

yr

savi

ngs

kBtu

/sq

ft, 1

st y

r sa

ving

s

est.

oper

atin

g co

st,

1st y

r sav

ings

, $

tota

l 1st

yr s

avin

gs, $

life

of m

easu

re, y

rs

est.

lifet

ime

cost

sa

ving

s, $

sim

ple

payb

ack,

yrs

lifet

ime

retu

rn o

n in

vest

men

t, %

annu

al re

turn

on

inve

stm

ent,

%

inte

rnal

rate

of r

etur

n,

%

net p

rese

nt v

alue

, $

CO

2 re

duce

d, lb

s/yr

1 Retro-commissioning 10,800 none at this time 10,800 69,843 0 3,328 10.6 0 21,600 3 64,800 0.5 500 167 192 48,511 161,735

2 Upgrade (15)

Incandescent to CFL140 0 140 1,117 0 0 0.1 47 220 5 1,100 0.6 686 137 156 835 2,000

3Retrofit 1 refrigerated

vending machine with a VendingMiser™ device

199 none at this time 199 1,525 0 0 0.1 0 236 12 2,830 0.8 1,322 110 118 2,055 2,731

4Install 39 occupancy

sensors8,580 780 7,800 26,481 6 0 1.7 0 4,104 15 61,560 1.9 689 46 53 39,236 47,414

520 New T8 fixtures to be installed with incentives

14,693 0 14,693 11,752 2 0 0.7 4,247 6,069 5 30,345 2.4 107 21 30 12,542 21,042

6Retrofit 1 vending machine with a

SnackMiser™ device180 none at this time 180 366 0 0 0.0 0 57 12 679 3.2 277 23 30 365 655

7Install 134.16 kW Solar

Photovoltaic system670,800 0 670,800 162,422 134 0 10.3 1,442 144,485 25 3,612,114 4.6 438 18 20 1,123,311 290,817

8Upgrade (13) High

Pressure Sodium fixtures to pulse start MH

9,425 325 9,100 4,441 1 0 0.3 48 736 15 11,040 12.4 21 1 3 -426 7,952

Page 70: Ocean County Vocational Technical School€¦ · the school consumed approximately 393,453 kWh, or $60,841 of electricity, from January 2011 to December 2011. The chart below shows

APPENDIX M: METHOD OF ANALYSIS

Assumptions and tools

Cost estimates: RS Means 2009 (Facilities Maintenance & Repair Cost Data) RS Means 2009 (Building Construction Cost Data) RS Means 2009 (Mechanical Cost Data)

Published and established specialized equipment material and labor costs Cost estimates also based on utility bill analysis and prior experience with similar projects

Disclaimer

This engineering audit was prepared using the most current and accurate fuel consumption data available for the site. The estimates that it projects are intended to help guide the owner toward best energy choices. The costs and savings are subject to fluctuations in weather, variations in quality of maintenance, changes in prices of fuel, materials, and labor, and other factors. Although we cannot guarantee savings or costs, we suggest that you use this report for economic analysis of the building and as a means to estimate future cash flow.

THE RECOMMENDATIONS PRESENTED IN THIS REPORT ARE BASED ON THE RESULTS OF ANALYSIS, INSPECTION, AND PERFORMANCE TESTING OF A SAMPLE OF COMPONENTS OF THE BUILDING SITE. ALTHOUGH CODE-RELATED ISSUES MAY BE NOTED, SWA STAFF HAVE NOT COMPLETED A COMPREHENSIVE EVALUATION FOR CODE-COMPLIANCE OR HEALTH AND SAFETY ISSUES. THE OWNER(S) AND MANAGER(S) OF THE BUILDING(S) CONTAINED IN THIS REPORT ARE REMINDED THAT ANY IMPROVEMENTS SUGGESTED IN THIS SCOPE OF WORK MUST BE PERFORMED IN ACCORDANCE WITH ALL LOCAL, STATE, AND FEDERAL LAWS AND REGULATIONS THAT APPLY TO SAID WORK. PARTICULAR ATTENTION MUST BE PAID TO ANY WORK WHICH INVOLVES HEATING AND AIR MOVEMENT SYSTEMS, AND ANY WORK WHICH WILL INVOLVE THE DISTURBANCE OF PRODUCTS CONTAINING MOLD, ASBESTOS, OR LEAD.