NWE Info Session Operational & contractual changes for Dutch wholesale market organization

Transcript of NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a...

Page 1: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

NWE Info Session Operational & contractual changes

for Dutch wholesale market

organization

Page 2: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

OPERATIONAL PRINCIPLES

& POSSIBLE SCENARIOS

General principles

Page 3: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Price Coupling Process

General term for ATC and/or FB parameters used = CZCs : Cross Zonal Capacities

3

Page 4: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

NWE Business Process

4

CZCs and allocation constraints

submission and integration

Final Confirmation of the results

10:30

CZCs and allocation

constraints submitted

to PCR

12:00

Orderbooks closure Global Preliminary PX

Confirmation

12:55

Global Final Confirmation

Publication

Trading confirmation

and scheduled exchanges notification

12:55 – 14:00

Nominations

PCR process: • CZCs and allocation constraints

process • Orderbook processing • PMB calculation • Preliminary confirmation process

Market Coupling Results and

Scheduled Exchanges transfer

Final confirmation

process

Page 5: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

PCR Process Timings for NWE

Normal process – 55 minutes

5

12:00 OBK GCT

12:00 – 12:10 Check of OBK and sending to PMB

12:10 – 12:27 Calculation

12:28 – 12:41 Preliminary PX validation

12:42 Publication of preliminary results (incl. market clearing price) to the

market and in parallel sending of these preliminary results for final

confirmation/approval to the TSOs

12:42 – 12:54 Final TSO validation

12:55 Publication of Final Results (incl. market clearing price)

Start of Notification Process

Page 6: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Process is delayed

6

Partial

Coupling/Full

Decoupling

Deadline

Target

Time

Latest Time

to Start an

IC

TIME

Normal Procedure Normal procedures can still apply after

target time

Backup procedure can apply before the

target time Backup procedures

Fallback procedures can apply before fallback time

Fallback procedures

Decoupling preparation

decoupling

Page 7: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Process delayed – assumptions

Pre-coupling • Deadline to solve incidents with Network Data (CZCs)

publication is 11:45 CET

Coupling • Time allowance for technical problem solving up to 55 min

• Time allowance for special market procedures such as handling of curtailment situations or price threshold reached via a second auction used by CWE PXs or the NPS-applied regulated routines that include peak load capacity (production/load) reserves activation.

• Deadline for final Market Results is 13:50 CET

Post-coupling • Final notification deadline of 15:30 in CWE, CWE-GB and

CWE-Nordic interconnectors

7

2nd Auction CWE/ GB

48 min

Max. Time /Flexibility to solve technical problems

55min

Page 8: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Second Auction

• A Second Auction is triggered in case at least one of the CWE/GB prices reach or exceed the predefined price thresholds

• The routine consists in • Reopening the PXs order books for 10 minutes to give the Market Participants

the opportunity to modify their bids in order to improve the market situation

• Execution of a second calculation with the new Order Data

• The thresholds to trigger a 2nd auction in CWE remain the same: • + 500 EUR/MWh and -150 EUR/MWh

• In GB thresholds will be introduced: • + 500 GBP/MWh and -150 GBP/MWh

• In case the prices still reach the thresholds after the Second Auction calculation, no additional Second Auction will be triggered

8

2nd Auction CWE/ GB

48 min

Page 9: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

PCR PROCESS TIMINGS for NWE

9

• * This is the maximum time which could be used to solve a technical problem in order to avoid a decoupling. If the technical

problem is resolved in less than 55 min than the next processes will start earlier.

• ** the Second Auction in CWE / GB is a single process taking 48 minutes.

• *** the Special Procedure for the Nordics is an iterative process which will run the number of times necessary taking into the

13.50 full decoupling deadline when NWE is coupled.

Page 10: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Fallback procedures

10

Partial

Coupling/Full

Decoupling

Deadline

Target

Time

Latest Time

to Start an

IC

TIME

Normal Procedure Normal procedures can still apply after

target time

Backup procedure can apply before the

target time Backup procedures

Fallback procedures can apply before fallback time

Fallback procedures

Decoupling preparation

decoupling

Page 11: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Fallback procedures

11

Partial

Coupling/Full

Decoupling

Deadline

Target

Time

Latest Time

to Start an

IC

TIME

Normal Procedure Normal procedures can still apply after

target time

Backup procedure can apply before the

target time Backup procedures

Fallback procedures can apply before fallback time

Fallback procedures

Decoupling preparation

decoupling

Page 12: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Full Decoupling of NWE (1)

• Internally in CWE and for the CWE – Nordic interconnectors (except Baltic Cable): • Shadow auctions organized by CASC will be held and results published

• The 3 PXs within CWE will reopen the order books (20 min) and perform local DA spot market calculations without using cross border capacities

• The notification deadline of 15.30 is applicable for the notification by market parties of utilization of Explicit Capacity bought in Shadow Auctions

• Fallback for Baltic cable : capacity goes back to the cable owner

• In GB • Shadow auctions organized by RTE/NGIC are applicable for FR/GB border only (IFA

interconnector), this consists of daily explicit auctions

• Capacity of virtual interconnector set to zero

• The 2 PXs will reopen the order books (APX UK 15 min) and perform local DA spot market calculations without using cross border capacities

• Fallback for BritNed : capacity goes to intraday

• For the Nordic – Baltic area including the link with Poland • Shadow auctions on 3 CWE-Nordic links

• Re-opening of NPS order books

• Price coupling will be performed by NPS utilizing the cross border capacities within this region

12

Page 13: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Shadow Auctions

• Bids submitted through the Shadow Auctions interface at CASC.EU are default bids :

• They are valid for every day of the year, for a specific border, direction and an hourly period (Volume in MW and a Price in €/MWh)

• Participants can update their default bids at any time before the freezing of the database when Shadow Auctions are run

• Description in “Harmonised Auction Rules for CWE, CSE and CH”

• Possibility to register only for Shadow Auctions, with a ‘lighter’ status: “Participant to Shadow Auctions Only"

• Market Participants need to submit a nomination towards the respective TSOs by the notification deadline of 15.30

13

Page 14: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Full Decoupling scenario

14

CWE : 4 local PX auctions

Nordic-Baltic Market Splitting

Virtual Capacity is set to Zero

2 local PX auctions

Shadow Auctions

“Local” matching process

In case of full decoupling the processes are local • Communication in case of fallback is organized locally (different

info, different timings)

Page 15: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

CWE TSO investigate flexibility

of notification deadline

• The CWE TSOs and 50 Hertz have agreed upon a joint target solution for the deadlines for submitting the different schedules towards the TSOs available as of Go-Live of the Price Coupling in the NWE region

• Taken into account that it is important for the TSOs to receive data of good quality, the TSOs agreed to extend the deadline for submitting generation schedules in the very rare cases of specific fallback situations to a later time than 15:30

• In these extraordinary situations, all CWE TSOs and 50 Hertz will extend the deadline for submitting generation schedules until at least 15:45. Some TSOs can extend this deadline even beyond 15:45 depending on local market rules

• This means that market participants have at least 60 minutes for the submission of generation schedules

15

Page 16: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

CWE TSO investigation on

flexibility of notification deadline –

impact on procedures

16

Notification Process 45 min

15:30

Crossborder Notification

Process 45 min

15:45

Generation Notification

Process At least 60 min

15:30

15:30

Exceptional cases

Page 17: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

PCR PROCESS TIMINGS for NWE

17

Page 18: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Full decoupling before OBK

GCT (12:00)

18

Notification

Process 60 min

Notification

Process 60 min

Notification Process

60 min

OBK GCT = 12:00

Final Notification deadline =15:30 which applies to:

Internal CWE, CWE-GB and CWE-Nordic interconnectors

Publication of prelimi-

nary results =12:42

• * This is the maximum time which could be used to solve a technical problem in order to avoid a decoupling. If the technical

problem is resolved in less than 55 min than the next processes will start earlier.

• ** the Second Auction in CWE / GB is a single process taking 48 minutes.

• *** the Special Procedure for the Nordics is an iterative process which will run the number of times necessary taking into the

13.50 full decoupling deadline when NWE is coupled.

Case X10 Case X12 Case X11 Full decoupling

before 12.00

X10 +

delay X10 +

2nd Auction

CWE

Full decoupling 42 min

Full decoupling 42 min

Full decoupling 42 min

Max. Time /Flexibility to

solve technical problems

55min*

2nd Auction CWE/ GB

28 min**

Page 19: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Partial (De)coupling within NWE

• Any scenario where one or more bidding areas and/or interconnectors are temporary not participating in NWE Market Coupling while the remaining bidding areas/interconnectors still participate in NWE Market Coupling

• The CZCs for the decoupled borders / interconnectors will be allocated via the fall back solution for these temporary not participating borders / interconnectors

• NWE parties will try to couple as many borders / interconnectors as possible

• Partial coupling is triggered • during the pre-coupling process, at the latest at 11:45

• during the coupling process, at the latest at 12:40

19

Page 20: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Partial Coupling Scenario

Example : CWE+GB <> Nordic

20

PCR coupling

Nordic-Baltic: Market Splitting

Shadow Auctions

“Local” matching process

PCR matching process

Page 21: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Partial Coupling Scenario

Example : NorNed

21

PCR coupling

Shadow Auctions

PCR matching process

Page 22: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Partial Coupling Scenario

Example : EPEX OBK missing

22

PCR coupling

Shadow Auctions

PCR matching process

“Local” matching process

Page 23: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Partial Coupling Scenario

Example: APX NL/Belpex OBK

missing

23

PCR coupling

Shadow Auctions

“Local” matching process

Page 24: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

24

PCR coupling

Shadow Auctions

PCR matching process

“Local” matching process

Partial Coupling Scenario

Example : no CWE CZCs in PMB

Page 25: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Decoupling scenarios

25

Where’s the problem What decouples? Resulting configuration

APX/Belpex CWE internal borders (FR-DE, FR-BE, BE-NL, NL-DE) and NorNed and BritNed and GB-GB

NL, BE and APX UK markets isolated

EPEX CWE internal borders and IFA, DK-DE, DE-SE

DE, FR, and BE markets isolated

NPS (Nordic) Nordic area, NorNed, DE-DK, DE-SE

Nordic markets isolated (but internally coupled)

N2EX GB-GB, IFA N2EX market isolated

CWE TSOs CWE internal borders BE market isolated

BritNed BritNed No market isolated

NorNed NorNed No market isolated

Any other individual interconnector

That interconnector No market isolated

PMB, or problem after 12:20

Entire region All markets isolated (but Nordic markets internally coupled)

25

Page 26: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

• * This is the maximum time which could be used to solve a technical problem in order to avoid a decoupling. If the technical

problem is resolved in less than 55 min than the next processes will start earlier.

• ** the Second Auction in CWE / GB is a single process taking 48 minutes.

• *** the Special Procedure for the Nordics is an iterative process which will run the number of times necessary taking into the

13.50 full decoupling deadline when NWE is coupled.

Partial Coupling before OBK

GCT (12:00)

26

Page 27: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

• * In case X6b, the NPS special procedure, being an iterative process, may take the same timeframe as when all

markets are still coupled, but this is not relevant in a full decoupling since Nordic and Baltic TSOs do not impose a

nomination deadline, but instead NPS can take as long time as needed to finish the Price Calculation and

subsequent notifications can be submitted (updated) by NPS and market parties to relevant TSOs until about 1

hour before delivery hour.

Partial Coupling before OBK

GCT (12:00)

Partial coupling followed by Full

Decoupling

+ Special Routine Nordics

Page 28: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Case X7

Publication of

preliminary results

=12:42

Case X9a

Partial coupling after OBK GCT

(12:00)

28

Case X9b Case X8

Page 29: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

DETAILED OPERATIONAL

PROCEDURES MRC

Timings and messages

Page 30: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

NORMAL NWE/PCR PROCESS

Page 31: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Normal NWE/PCR process

31

10:30 12:00

CZC publication

MP’s introduce orders

12:55

Coupling process

PX GCT Normal

timing 14:00

Notifications to TenneT

12:42

Preliminary result

publication

Final

results

* All timings are C.E.T

Page 32: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Normal process timeline

• CZC published at 10:30 on CASC website

• PX gate closure time at 12:00

• Publication of preliminary market results 12:42

• Publication of final market results 12:55

Notification

deadline

Belgium France Germany The Netherlands

Cross-Border 14:30 14:30 14:30 14:00 (E-program)

Local/hub Hub 1: 14:00

Hub 2: 14:30

Ex post 14:30 14:00 (E-program)

Consumption 14:30 n/a 14:30 14:45 (T-program)

Generation 15:00 16:30 14:30 14:45 (T-program)

Page 33: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

CASE 1 PROCESS DELAYED

WITH MAX TIMING

Page 34: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Case 1 Process delayed with

max timing

10:30 12:00 12:55

Coupling process / Backup procedures

PX GCT Normal

timing

15:00

12:42

Preliminary result

publication

Exceptional

timing

13:38 13:50

Technical problem

Message to MP

MP’s introduce orders

CZC publication

* All timings are C.E.T

13:00

Final

results

34

Notifications to TenneT

13:20

Page 35: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Case 1 Process delayed with

max timing

• CZC published at 10:30 on CASC website

• PX gate closure time at 12:00

• Delay in Market Coupling results

Timing Message Additional

actions for

MPs

Market

results

Publication

deadline

Local hub Notification Cross border

notification deadline

12:42 [ExC_02]: Delay in

Market Coupling

Results publication

CASC:

invitation to

update bids in

the Shadow

Auction system

before 13:40

13:50

14:00 14:00

13:00

TSO: Delay in Market

Coupling Results/

local Market Results

publication and

extension of Hub

Notification deadline

CASC:

invitation to

update bids in

the Shadow

Auction system

before 13:40

13:50 14:30

14:30

13:20

TSO: Delay in Market

Coupling Results/

local Market Results

publication and

extension of Hub

Notification deadline

CASC:

invitation to

update bids in

the Shadow

Auction system

before 13:40

13:50 15:00 15:00

Page 36: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Messages

PX : [ExC_02] TSO

36

Page 37: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

CASE 2A SECOND AUCTION

Page 38: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Case 2a second auction

10:30 12:00

CZC publication

MP’s introduce orders

Coupling process

PX GCT Normal

timing

Notifications to TenneT

Preliminary result

publication

* All timings are C.E.T

Exceptional

timing

>12:42 >12:55 15:00

12:30

Message to MP

14:00

13:00 <13:50

Final

results

Page 39: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Case 2a second auction

• CZC published at 10:30 on CASC website

• PX gate closure time at 12:00

• Threshold reached -€150 or €500 / -£150 or + £500

• Second Auction triggered (re-opening of Order Books)

Timing* Message Additional

actions for

MPs

Market results

Publication

deadline

Local hub

Notification

Cross border

notification deadline

±12:30

[ExC_01]: Thresholds

reached - Reopening of

the order books

PX: OBK open

for 10 minutes

after message

13:50

n/a

n/a

13:00

TSO: Delay in Market

Coupling Results/ local

Market Results

publication and

extension of Hub

Notification deadline

CASC:

invitation to

update bids in

the Shad ow

Auction system

before 13:40

13:50 15:00 15:00

Page 40: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Messages

CASC will add: Therefore, if relevant, we

advise you to update your shadow bids at

CASC EXAU platform before 13:40.

PX : [ExC_01]

40

Page 41: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

CASE 4 FULL DECOUPLING

Page 42: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Case 4 Full Decoupling

10:30 12:00

CZC publication

MP’s introduce bids

12:55

13:50

Process run

PX GCT Normal

timing

Exceptional

timing

15:30 13:05

Full

decoupling

preparation*

Full

decoupling

Exceptional procedures

13:20 12:42

Notifications to TenneT

MP’s update orders**

Shadow

Auction

results

Note:

*Shadow auction will be triggered at CASC

** Reopening of order book for 20 min

Final

results

>14:30

Message to MP

13:00

Page 43: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Case 4 Full Decoupling

• CZC published at 10:30 on CASC website

• PX gate closure time at 12:00

• Full decoupling announcement

• Shadow auctions

• Follow the local auction rules

Timing* Message Additional actions

for MPs

Market results

Publication

deadline

Local hub

Notification

Cross border

notification deadline

12:42

[ExC_02]: Delay in

Market Coupling Results

publication

13:50

14:00 14:00

13:00

TSO: Delay in Market

Coupling Results/ local

Market Results

publication and

extension of Hub

Notification deadline

CASC: invitation to

update bids in the

Shad ow Auction

system before

13:40

13:50 14:30 14:30

13:20

[ExC_03b]: Risk of Full

Decoupling

Bids update in the

Shadow Auction

system

n/a 15:00 15:00

13:50

[ExC_04b]: Full

Decoupling – Reopening

of the order books

OBK open for 20

minutes after

message

n/a 15:30

15:30

Page 44: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Messages

PX : [ExC_02]

44

Page 45: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Messages

CASC will add: Therefore, if relevant, we

advise you to update your shadow bids at

CASC EXAU platform before 13:40

PX : [ExC_03b] TSO

45

Page 46: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Messages

PX : [ExC_04b] TSO

46

Page 47: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

CASE 5A FULL DECOUPLING

+ 2ND AUCTION

Page 48: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Case 5a Full Decoupling + 2nd

Auction

10:30 12:00

CZC publication

MP’s introduce bids

12:55

13:50

PX GCT Normal

timing

Exceptional

timing

15:30 13:05

Full

decoupling

preparation* Full

decoupling

Exceptional procedures

13:20 12:42

Notifications to TenneT

MP’s update orders**

Shadow

Auction

results

Note:

*Shadow auction will be triggered at CASC

** Reopening of order book for 20 min

*** Reopening of order book “second auction” 10 min

**** PX publish at best effort base at 14:45

14:00

MP’s update orders***

14:25 14:45

Final****

results

Coupling process

Message to MP

13:00

Page 49: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Case 5a Full Decoupling + 2nd

Auction

• CZC published at 10:30 on CASC website

• PX gate closure time at 12:00

Timing* Message Additional actions

for MPs

Market results

Publication

deadline

Local hub

Notification

Cross border

notification deadline

12:42 [ExC_02]: Delay in Market

Coupling Results publication

CASC: invitation to

update bids in the

Shadow Auction

system before

13:40

13:50 14:00 14:00

13:00

TSO: Delay in Market

Coupling Results/ local

Market Results publication

and extension of Hub

Notification deadline

CASC: invitation to

update bids in the

Shadow Auction

system before

13:40

13:50 14:30 14:30

13:20 [ExC_03b]: Risk of Full

Decoupling

CASC: invitation to

update bids in the

Shadow Auction

system before

13:40

13:50

TSO: Delay in Market

Coupling Results/ local

Market Results publication

and extension of Hub

Notification deadline

13:50 15:00 15:00

Page 50: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Timing Message Additional actions for

MPs

Market results

Publication

deadline

Local hub

Notification

Cross border

notification

deadline

13:50

[ExC_04b]: Full Decoupling –

Reopening of the order books

PX: OBK open for 20

minutes after message

TSO: Extension of Notification

Deadlines due to full decoupling

declared/delay in local Market

Results publication

15:30 15:30

14:25

[CWE_UMM_05]: Thresholds

reached during local auction

PX: OBK open for 10

minutes after message

TSO: Extension of Generation

Notification Deadlines due to

Second Auction Triggered after Full

Decoupling

15:30 15:30

Case 5a Full Decoupling + 2nd

Auction

• Full decoupling announcement

• Shadow auctions

• Follow the local auction rules

Page 51: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Messages

PX : [ExC_02]

51

Page 52: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

CASC will add: Therefore, if relevant, we

advise you to update your shadow bids at

CASC EXAU platform before 13:40

Messages

PX : [ExC_03b] TSO

52

Page 53: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Messages

PX : [ExC_04b] TSO

53

Page 54: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Messages

PX : [UMM_05] TSO

54

Page 55: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

CASE X3A PARTIAL

COUPLING BEFORE OBK GCT

+ SECOND AUCTION

Page 56: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Case X3a partial coupling before

OBK GCT + Second Auction

10:30

12:00

PX GCT Normal

timing

Exceptional

timing

Shadow

Auction

results

CZC publication

MP’s introduce orders

Message to MP

11:15 11:45

Coupling process

14:00

Notifications to TenneT

Preliminary result

publication

* All timings are C.E.T

>12:42 >12:55 15:30

12:30

13:00 <13:50

Final

results

13:20

Partial coupling

before OBK GCT

56

Page 57: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Timing Message Additional actions for

MPs

Market

results

Publication

deadline

Local hub

Notification

Deadline

Cross Border

Notification

Deadline

11:15

[UMM_02]: Risk of partial

decoupling for one or more

interconnectors

CASC: invitation to update

bids in the Shadow Auction

system before 11:35

13:50

11:45 [UMM_03]: One or more

interconnectors decoupled

13:50

±12:30 [ExC_01]: Thresholds reached -

Reopening of the order books

PX: OBK open for 10

minutes after message 13:50

13:00

TSO: Delay in Market Coupling

Results/ local Market Results

publication and extension of Hub

Notification deadline

CASC: invitation to update

bids in the Shadow Auction

system before 13:40

13:50 14:30 14:30

13:20

TSO: Delay in Market Coupling

Results/ local Market Results

publication and extension of Hub

Notification deadline

13:50 15:00 15:00

Case X3a partial coupling before

OBK GCT + Second Auction • CZC published at 10:30 on CASC website

• PX gate closure time at 12:00

• Threshold reached -150€/MWh or 500€/MWh (-150£/MWh or + 500£/MWh)

• Second Auction triggered (re-opening of Order Books)

• Publication of final market results before 13:50

57

Page 58: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Message

CASC will add: Therefore, if relevant, we

advise you to update your shadow bids at

CASC EXAU platform before 13:40

PX : [UMM_02]

58

Page 59: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Messages

PX : [ExC_01]

59

Page 60: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

CASE X7 PARTIAL COUPLING

AFTER GCT

Page 61: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Case X7 partial coupling after

GCT

10:30 12:00

13:50

PX GCT

Partial

coupling

preparation* Partial

coupling

12:40 12:20

Normal

timing

Exceptional

timing

Coupling process / backup procedures

Notifications to TenneT

12:30

Shadow

Auction

results Final

results

Preliminary result

publication

13:38

CZC publication

MP’s introduce orders

MP’s update orders**

15:00

Note:

*Shadow auction will be triggered at CASC

** Reopening of order book for 10 min

13:00

Message to MP

13:20

Page 62: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Case X7 partial coupling after

GCT

• CZC published at 10:30 on CASC website

• PX gate closure time at 12:00

• Publication of preliminary market results at the latest 13:38

• Publication of final market results at the latest 13:50

Timing* Message Additional

actions for MPs

Market results

Publication

deadline

Local hub

Notification

Cross border

notification

deadline

12:20 [ExC_03a]: Risk of Partial

Decoupling

CASC: invitation

to update bids in

the Shadow

Auction system

before 12:30

n/a n/a n/a

12:40

[ExC_04a]: Partial

Decoupling – Reopening of

the PX order books

PX: OBK open

for 10 minutes

after message

13:50

14:00

14:00

13:00

TSO: Delay in Market

Coupling Results/ local

Market Results publication

and extension of Hub

Notification deadline

CASC: invitation

to update bids in

the Shadow

Auction system

before 13:40

13:50

14:30

14:30

13:20

TSO: Delay in Market

Coupling Results/ local

Market Results publication

and extension of Hub

Notification deadline

CASC: invitation

to update bids in

the Shadow

Auction system

before 13:40

13:50 15:00 15:00

Page 63: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

CASC will add: Therefore, if relevant, we

advise you to update your shadow bids at

CASC EXAU platform before 12:30.

Messages

PX : [ExC_03a]

63

Page 64: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Messages

PX : [ExC_04a] TSO

64

Page 65: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

NWE process overview

10:30 12:00

15:30

CZC publication

MP’s introduce bids

Exceptional procedures

12:55

13:50

Process run

Full

decoupling

preparation

Full

decoupling

PX GCT

13:05

Partial coupling

preparation

Partial

coupling

12:40 12:20 11:45

Partial coupling due

CZC reason

Normal

timing

Exceptional

timing

Notifications to TenneT

Page 66: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Decoupling scenarios

66

Where’s the problem What decouples? Resulting configuration

APX/Belpex CWE internal borders (FR-DE, FR-BE, BE-NL, NL-DE) and NorNed and BritNed and GB-GB

NL, BE and APX UK markets isolated

EPEX CWE internal borders and IFA, DK-DE, DE-SE

DE, FR, and BE markets isolated

NPS (Nordic) Nordic area, NorNed, DE-DK, DE-SE

Nordic markets isolated (but internally coupled)

N2EX GB-GB, IFA N2EX market isolated

CWE TSOs CWE internal borders BE market isolated

BritNed BritNed No market isolated

NorNed NorNed No market isolated

Any other individual interconnector

That interconnector No market isolated

PMB, or problem after 12:20 Entire region All markets isolated (but Nordic markets internally coupled)

Page 67: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Communication to the market -

summarized Time/ Deadline

Communication Message number

Other messages

CASC TSO Local PX

10:00 Risk of Partial/full Decoupling known in advance

[ExC_03a/b]

X

10:30 Partial/full Decoupling known in advance [ExC_05a/b]

11:15 Risk of partial decoupling for one or more interconnectors

[UMM_02] X

11:45 One or more interconnectors decoupled

[UMM_03]

12:20 Risk of Partial Decoupling in certain regions [ExC_03a]

X

~ 12:30 Second Auction [ExC_01] X

12:40 Partial Decoupling – Reopening of order books [ExC_04a] X

Regular publication time (12:42)

Delay in Market Coupling Results publication [ExC_02]

X

NB 1. The fallback solutions and processes as well as their associated contents and timings are organized on local / regional level and not on NWE level. Timings are

therefore indicative and additional messages can be sent (e.g. IFA CMS will also sent messages in case of a fall back situation)

NB 2. The shift of notification deadlines only applies for CWE internally and CWE borders.

67

Page 68: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Communication to the market -

summarized Time/ Deadline

Communication Message number

Other messages

CASC TSO Local PX

13:00 • Delay in Market Coupling Results publication -> Extension of notification deadlines

X

13:20 • Risk of Full Decoupling • Delay in Market Coupling Results publication ->

Extension of notification deadlines

[EXC_03b] X

13:50 • Decision of Full decoupling • Extension of notification deadlines

[EXC_04b] X

14:25 • Thresholds reached during local auction [UMM_05] X X

68

Page 69: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

PUBLICATIONS

Capacities – Flows – Prices – …

69

Page 70: NWE Info Session - APX Group · PDF fileGlobal Preliminary PX Confirmation 12:55 ... via a second auction used by CWE PXs or the NPS-applied ... • Description in “Harmonised Auction

Publications

• www.apxgroup.com • Market prices & auction volumes

• www.tennet.eu & energieinfo.tennet.org • NTC values, ATC values, flows

• www.casc.eu • ATC values, Shadow Auction results (if any)

• Yearly, monthly capacity auction results

• www.europeanpricecoupling.com • Daily prices, ATC values & flows

70