NuScale Refueling Process - NRC

17
NON-PROPRIETARY NuScale Refueling Process Mr. Ross Snuggerud Operations Manager NuScale Power Inc. April 2, 2009 U.S. Nuclear Regulatory Commission PreApplication Meeting Rockville, MD NP-DEM-PM-RFOP-003-NP 1

Transcript of NuScale Refueling Process - NRC

Page 1: NuScale Refueling Process - NRC

NON-PROPRIETARY

NuScale Refueling Process

Mr. Ross SnuggerudOperations ManagerNuScale Power Inc.

April 2, 2009

U.S. Nuclear Regulatory CommissionPre‐Application Meeting

Rockville, MD

NP-DEM-PM-RFOP-003-NP

1

Page 2: NuScale Refueling Process - NRC

IntroductionIntroduction

l f Goals of Presentation

Provide an overview of the refueling process

Cover unique aspects of refueling the NuScale Nuclear Power Module Cover unique aspects of refueling the NuScale Nuclear Power Module

Communicate recognized challenges and allow for early dialog

CaveatsCaveats

The drawings that have been provided are illustrative

Details of the process are subject to change pending completion of detailed design 

2NP-DEM-PM-RFOP-003-NP

Page 3: NuScale Refueling Process - NRC

Reactor and Refueling PoolReactor and Refueling Pool Building Layout

4a,b

3NP-DEM-PM-RFOP-003-NP

Page 4: NuScale Refueling Process - NRC

Reactor Shutdown and LongReactor Shutdown and Long Term Cooling Alignment

4a,b

Module shut down and tripped

Primary system is boratedy y

Cooled using steam generators

Containment flooded

Decay Heat Removal System placed in‐service

4a b

4a,b

4NP-DEM-PM-RFOP-003-NP

Page 5: NuScale Refueling Process - NRC

Module Access and Rigging

h ld Shield covers are removed

M d l h d

4a,b

Module attached to crane

No disassembly occurs til th d l iuntil the module is 

secured

W ki l tf t i Working platforms put in place

5NP-DEM-PM-RFOP-003-NP

Page 6: NuScale Refueling Process - NRC

Module Disassembly andModule Disassembly and Instrumentation

Shi ldi h4a,b

Shielding hung as necessary

4a b

4a,b

Piping disconnected and cappedand capped

6NP-DEM-PM-RFOP-003-NP

Page 7: NuScale Refueling Process - NRC

Disconnections and Verification

d l d d f Module is designed to support transfer

The design of disconnects will include evaluation off Ease of operation

Durability

EEQ considerations

Trunion cap designs will allow local removal by plant personnel

Verification of disconnection

7NP-DEM-PM-RFOP-003-NP

Page 8: NuScale Refueling Process - NRC

M d l T fModule Transfer4a,b

8NP-DEM-PM-RFOP-003-NP

Page 9: NuScale Refueling Process - NRC

Containment Disassembly

Containment flange disassembled

4a,b

d sasse b ed

Reactor and upper section of Containment moved to Reactor flange stand

9NP-DEM-PM-RFOP-003-NP

Page 10: NuScale Refueling Process - NRC

Reactor DisassemblyReactor Disassembly

R t fl i d4a,b

Reactor flange is opened

Reactor moved into f li itirefueling position

Control rods are moved with fuelfuel

In Mast sipping

Upper Containment and Reactor are moved to test pitpit

10NP-DEM-PM-RFOP-003-NP

Page 11: NuScale Refueling Process - NRC

Module Testing and SteamModule Testing and Steam Generator Access

4a,b

Testing access will be a focus of designdesign

The test pit will be equipped toequipped to support all valve, instrument and penetration testing

11NP-DEM-PM-RFOP-003-NP

Page 12: NuScale Refueling Process - NRC

V l ClVessel Closure

h fl l d

4a,b

Both flanges are closed in the stands that were used to disassemble the vesselsto disassemble the vessels

Verification and testing of the restored flanges willthe restored flanges will occur in the refueling pool

12NP-DEM-PM-RFOP-003-NP

Page 13: NuScale Refueling Process - NRC

M d l R t tiModule Restoration4a,b

Restoration is the reverse of the disassembly process

Crane stays attached until all connections are restored

Containment remains flooded until steam 

t i igenerators are in‐service

13NP-DEM-PM-RFOP-003-NP

Page 14: NuScale Refueling Process - NRC

Spent Fuel Pool Design

4a,b

14NP-DEM-PM-RFOP-003-NP

Page 15: NuScale Refueling Process - NRC

Safety Advantages of NuScaleSafety Advantages of NuScale Refueling System

b l Very robust Decay Heat Removal system

Dedicated Refueling Crew – part of plant staff

Dedicated Refueling Location – Equipment pre‐staged

Potential to use spare module and associated reduction in schedule pressure

Improved contamination control

15NP-DEM-PM-RFOP-003-NP

Page 16: NuScale Refueling Process - NRC

C l iConclusions

h l f l The NuScale refueling process is unique

NuScale has reviewed the refueling plan to ensure that h ll d b h id d i hchallenges presented by the process are considered in the design and future validation

O ll thi f li l ill i b th f t d Overall this refueling plan will improve both safety and performance over existing facilities

16NP-DEM-PM-RFOP-003-NP

Page 17: NuScale Refueling Process - NRC