Transcript of NUOPC IOC Status Report to COPC November 16, 2010
NUOPC IOC Status Report to COPC
November 16, 2010
Allan DarlingDeputy Director, NCEP Central OperationsNOAA NWS [email protected]
ID Task Name
1 Augment TOC Infrastructure
3 TOC Augmentati on Compl ete
4 Implement additional members to 16 days
11 Addit ional members to 16 days Accepted
12 Transition to GRIB2
21 GRIB2 and Bundle Accepted
22 Implement additional parameters
29 Ful l delivery of FNMOC members
30 Integrate FNMOC members
37 EMC CCB - Integration Completed and Accepted
38 Transition to operations
48 Implementati on
100%
7/6
100%
6/15
100%
7/20
100%
8/6
100%
10/19
21%
1/11
F T S W S T M F T S W S T M FMay 2, '10 Jun 13, '10 Jul 25, '10 Sep 5, '10 Oct 17, '10 Nov 28, '10 Jan 9, '11
NUOPC IOC-1 / NAEFS
PM: Fred Toepfer
Objective
G
Key Issues/Risks/Mitigation
Risk: Schedule has slipped due to effect of required maintenance on availability of development system. Completion of external evaluation the week of 20 December pushes project completion to the first possible post-holiday implementation date of 11 January 2011.
Mitigation: None
ScheduleRequirement: Combine the NOAA and Navy ensemble members as the National Ensemble. Combine this National Ensemble and the CMC ensemble in the NAEFS. With the addition of FNMOC, increase NAEFS members from 126 to 166, forecasts to 16 days, and standardize variables.
Goal: Enhance the multi-model ensemble system to produce bias corrected ensemble variables and probabilistic products for use by the OperationalCenters.
Resources
November 10, 2010
FNMOCDr. M. SestakMr. J. ErtlNWS Telecommunication Operations CenterMr. R. BungeNCEP Environmental Modeling CenterDr. W. LapentaMr. Y. ZhuNCEP Central OperationsMr. A. DarlingMr. D. StarostaMs. R. CosgroveMs. M. Mainelli
GY
Y
Implementation slip from 22 Dec to 11 Jan
3
NUOPC IOC – Task StatusDATMS-U upgrade (JAG/CCM) - CompleteInfrastructure augmentation (TOC) - CompleteEnsemble delivery (FNMOC) - Complete
GRIB2384H72 variablesNew file structure for communication and processing efficiency
Routine delivery (FNMOC, TOC, NCEP) - CompleteEnsemble integration (NCEP, FNMOC) - CompleteTransition to operations (NCEP) – In process
NUOPC IOC – Planned ImplementationAdding FNMOC ensemble to NAEFS FNMOC 20+(1) members, out to 16 days, twice per day Bias correction based on its FNMOC analysis Four variables to include NCEP, CMC and FNMOC ensembles
2 meter temperature 10 meter zonal wind 10 meter meridional wind 850mb temperature
Expected Benefits Multi-model, multi-center ensembles Improve the forecast skill for near surface variable
Continued evaluation of the benefits derived from the addition of the FNMOC ensemble data is required
Scope change may be required if pre-implementation testing reveals negative impact on skill for any of the four variables listed above
5
NUOPC – Next StepsDevelop UEO Implementation and Management Plan
Dissemination requirements12-24 month work planBackup requirementsDevelopment coordination
Rationalize NUOPC and NAEFS requirements
Establish NUOPC / NAEFS coordination process
Potential supporting infrastructure upgradesFNMOC interface system upgradesNext Generation COPC Enterprise Network (AI 2008-2.11)
Action Item – Management AgreementCOPC Action Item 2010-1.4: Develop and submit to COPC for
approval a Unified Multi-Model Ensemble Operations annex to the DAPE MOA to address NAEFS and/or NUOPC operations management, alignment of performance requirements, change management, and data dissemination.
Priority: HAdvocate: WG/CSAB, JAG/OCM, and JAG/CCMSuspense: October 2010
CSAB is evaluating whether an appendix to the DAPE MOA is appropriate or if a new MOA is required to accomplish this agreement.
Management details regarding performance and alignment with change are still under evaluation.
CSAB recommends this action be kept open.