NPPD announces final line route, substation site for Muddy Creek to ...

3
NPPD announces final line route, substation site for Muddy Creek to Ord Transmission Line Project Transmission Line PROJECT Muddy Creek 115 kV October 2015 (continued on back page) A fter a one-year routing and public involvement process, NPPD has selected a final line route for its Muddy Creek to Ord Transmission Line Project. (See inside pages.) The project consists of constructing a 115,000-volt electric transmission line from a new substation, to be called Muddy Creek and located near an existing transmission line east of Broken Bow, to an existing substation near Ord. The line is estimated to be 40 miles in length. This transmission line project will address voltage and loading issues in the immediate area and meet the North American Electric Reliability Corporation’s Reliability Standards. Landowners adjacent or in close proximity to the final line route or substation site were notified recently via letter. Since announcing the need for the Muddy Creek to Ord Transmission Line Project about a year ago, NPPD met with stakeholders, performed field studies, reviewed maps and held three rounds of open house meetings in both Broken Bow and Ord. NPPD hosted public hearings for the project on Aug. 26 in Broken Bow and Ord. The public hearings were preceded by a one-hour open house. NPPD representatives reviewed the comments provided at the public hearing and after, as they continued to study the possible line routes. The group determined the proposed route communicated at the hearing was the best route. “I’d like to thank the landowners for their feedback during the public involvement process,” said Senior Project Manager Mike Hasenkamp. “We had excellent participation from NPPD hosted a one-hour open house prior to each public hearing for the Muddy Creek to Ord Transmission Line Project. landowners whether in person, by phone or via written communications. By letting us know of any future plans for their land or any special circumstances, we were able to make better, informed decisions. Our goal throughout this project was to find the most suitable line route and substation site with the least overall impact to landowners. We believe the process has resulted in identification of a good route.” Right-of-entry to begin soon Now that the final line route and substation site have been identified, property owners along the final transmission line route can expect an NPPD representative to contact them to obtain a right-of-entry agreement. The right-of- entry agreement will allow NPPD and its representatives access across property to conduct a variety of preliminary activities prior to the time easements are acquired. The right-of-entry is also an opportunity for landowners to meet project members on-site and provide input on locating structures and identifying access routes to use to design the

Transcript of NPPD announces final line route, substation site for Muddy Creek to ...

Page 1: NPPD announces final line route, substation site for Muddy Creek to ...

NPPD announces final line route, substation site for Muddy Creek to Ord Transmission Line Project

Transmission Line

PROJECTMuddy Creek 115 kV

O c t o b e r 2 0 1 5

(continued on back page)

After a one-year routing and public involvement process, NPPD has selected a final line route for its Muddy Creek to Ord Transmission Line Project.

(See inside pages.) The project consists of constructing a 115,000-volt electric transmission line from a new substation, to be called Muddy Creek and located near an existing transmission line east of Broken Bow, to an existing substation near Ord. The line is estimated to be 40 miles in length. This transmission line project will address voltage and loading issues in the immediate area and meet the North American Electric Reliability Corporation’s Reliability Standards. Landowners adjacent or in close proximity to the final line route or substation site were notified recently via letter. Since announcing the need for the Muddy Creek to Ord Transmission Line Project about a year ago, NPPD met with stakeholders, performed field studies, reviewed maps and held three rounds of open house meetings in both Broken Bow and Ord. NPPD hosted public hearings for the project on Aug. 26 in Broken Bow and Ord. The public hearings were preceded by a one-hour open house. NPPD representatives reviewed the comments provided at the public hearing and after, as they continued to study the possible line routes. The group determined the proposed route communicated at the hearing was the best route. “I’d like to thank the landowners for their feedback during the public involvement process,” said Senior Project Manager Mike Hasenkamp. “We had excellent participation from

NPPD hosted a one-hour open house prior to each public hearing for the Muddy Creek to Ord Transmission Line Project.

landowners whether in person, by phone or via written communications. By letting us know of any future plans for their land or any special circumstances, we were able to make better, informed decisions. Our goal throughout this project was to find the most suitable line route and substation site with the least overall impact to landowners. We believe the process has resulted in identification of a good route.” Right-of-entry to begin soon Now that the final line route and substation site have been identified, property owners along the final transmission line route can expect an NPPD representative to contact them to obtain a right-of-entry agreement. The right-of-entry agreement will allow NPPD and its representatives access across property to conduct a variety of preliminary activities prior to the time easements are acquired. The right-of-entry is also an opportunity for landowners to meet project members on-site and provide input on locating structures and identifying access routes to use to design the

Page 2: NPPD announces final line route, substation site for Muddy Creek to ...

#*

#*

!(

")

North LoupRiver

?ã?ã

?}

?m

?ã?°

?¼?Ø?}

Initial Study Area

R 21W R 20W R 19W R 18W R 17W R 16W R 15W R 14W R 13W

T 19N

T 18N

T 17N

T 16N

T 15N

Routing Corridor(White)

115kV Line Route

Existing Broken Bow Windfarm Substation

Existing OrdSubstation

Muddy Creek Substation

Site Location Canal

Canal

Middle Loup River

ARCADIATWNSHP.

ENTERPRISETWNSHP.

GERANIUMTWNSHP.

LIBERTYTWNSHP.

MICHIGANTWNSHP.

ORDTWNSHP.

VINTONTWNSHP.DOUGLAS

GROVE SOUTHTWNSHP.

GARFIELDWEST

TWNSHP.

MYRTLETWNSHP.

SPRINGCREEK

TWNSHP.

WESTERVILLENORTH TWNSHP.

BERWYNNORTH

TWNSHP.

COMSTOCKNORTH

TWNSHP.DOUGLAS

GROVE NORTHTWNSHP.

GARFIELDEAST

TWNSHP.

BROKENBOW CENTER

TWNSHP.

COMSTOCKSOUTH

TWNSHP.

SHERMAN COVALLEY CO

SHE

RM

AN

CO

CU

STE

R C

OVA

LLEY

CO

CU

STE

R C

O

Village ofWeissert

31 3136 36 3136 31

0601 01 0601 0606

36

01

36 313636 3131 31 36

0101 01 060106

01 06

36 31

0601 06 06

Berwyn

BrokenBow

Comstock

Sargent

Arcadia

Elyria

Ord

Westerville

Legend

#* Existing 115kV Substation

") Muddy Creek Substation

Final 115kV Line Route

Routing Corridor(White)Highway

Existing 115kV Transmission Line

Township

Municipal Limits

Waterway

County Boundary

Section

J

Muddy Creek to Ord115 kV Electric Transmission Line

Final Line Route and Substation Site

Page 3: NPPD announces final line route, substation site for Muddy Creek to ...

P.O. Box 499 Columbus, NE 68602-0499

Address Service Requested

PRSRT STD US POSTAGE

PAID COLUMBUS NE PERMIT NO. 3

The Muddy Creek-Ord 115 kV Transmission Line Newsletter is published by NPPD’s transmission project team. It is intended to provide a project overview and communicate project developments.

Contributors: Project Manager Mike Hasenkamp.Project Team: Al Beiermann, Brenda Blatchford, Ross DeBower, Larry Linder, Tom Pillen, Kevin Stachura, Ron Starzec and Dave Wolff.

Printing and artwork:Bill Haack, Dan Zastera and Scott Margheim.

Editor: Jill Novicki

Contact usEmail: [email protected] (toll-free): 888-677-3412

Mailing address: Muddy Creek-Ord 115 kV Transmission Line Project, NPPD, P.O. Box 499 Columbus, NE 68602-0499Attention Jill Novicki

Website: www.nppd.com/muddycreek-ord

A9D

33B

A4

(continued from front page)

line, as well as discussing any farming/ranching operational concerns that must be considered. Right-of-way agents will also begin landowner discussions regarding tree removal and off right-of-way access agreements where necessary. Survey work Surveyors will locate section corners, fences, utility (communication, electric, etc.) crossings, water tanks and windmills, and other items for consideration when designing the line. They will also stake locations where structures have been preliminarily spotted and complete site surveys at these locations. Engineering Engineers will view structure locations, access routes, line crossings, and other parameters as they consider line design and construction needs. The engineers value input from landowners in their effort to design the line and consider construction practices to best minimize impact to the property.

Soil borings will be performed at various points along the line route. These samples will then be used to determine foundation sizes necessary to support the structures. The borings are six inches in diameter and will be backfilled when completed.

On Friday, Oct. 23, NPPD will open a field office in Ord. The office will provide a place for landowners to visit with the Muddy Creek to Ord Transmission

Line Project right-of-way agents. The office, located at 1518 J Street, will be open from 8 a.m. to 5 p.m. Monday-Friday. The phone number will be 308-728-7076. Be sure to stop in on Oct. 23 for coffee and cookies and to say hello to the right-of-way agents.

The right-of-way agents for the Muddy Creek to Ord Transmission Line Project are, from Left: Susan LeCavalier, Stephen Sykes and Art Eash. Not pictured, Christine Mullaney.

NPPD to open field office in Ord