Context
Plan Year Comments
Castleberry Hill Master Plan 2000 Envisions Northside Dr. as a key boulevard, as well as a potential
entrance to the neighborhood; strive to be a gateway to Downtown
Vine City Redevelopment
Plan 2004 Emphasis on streetscaping, pedestrian improvements, and economic
development
Northside Drive Corridor Study 2005 Evaluation of existing infrastructure and recommendations for future
development
Green Line 2007 Improves Downtown connectivity and attractiveness
Connect Atlanta 2008 Emphasis on expanding and improving transit and bicycle and pedestrian facilities in the City, but does not focus on Northside Dr
Imagine Downtown 2009 [update]
Increase density along eastside of Northside Dr. and infill development in Castleberry Hill
Washington Park/Vine City LCI
Plan 2009 Internal neighborhood connections and plans for community greenspace
Proctor Creek Watershed Report 2010 Analysis of stormwater issues in the Westside and how to mitigate the
flooding in Westside neighborhoods
Previous Area Studies
Community benefits from the new stadium Connectivity between Westside and Downtown Neighborhood stability
Key Issues
Critical Intersections
Missing Connections
Land Use
Vine City Station
Martin Luther King at Northside
Centennial Olympic Park Dr at Martin Luther King
Atlanta University Center Gateway
Scope of Design Locations
A
D
C
A
B
B
C
D
A. Vine City Station Existing Conditions
A. Vine City Station Road Design
Possible Lane Conversions
A. Vine City Station Redevelopment Concept
Underground parking and “green” tailgating (possible
future development)
Vine City Promenade
Transit-oriented infill development
Stormwater mitigation park
feature
New stadium
A. Vine City Station Redevelopment Concept
http://www.fhwa.dot.gov/livability/fact_sheets/images/marta_station.png
Decatur MARTA
http://www.verdantenterprises.com/wp-content/uploads/2012/08/Stormwater.jpg
Stormwater Feature
B. MLK @ Northside Existing Conditions
B. MLK @ Northside Intersection Design
Possible Lane Conversions
B. MLK @ Northside Redevelopment Concept
New stadium
Mixed use infill development
B. MLK @ Northside Redevelopment Concept
http://www.zackhample.com/baseball_collection/lists/photos/1998_wrigley_field2.jpg
http://l.yimg.com/g/images/spaceout.gif
Wrigley Field
Coors Field
C. COP @ MLK Existing Conditions
C. COP @ MLK Intersection Design Possible Lane Conversions
C. COP @ MLK Redevelopment Concept
New stadium
Multi-Modal Passenger Terminal
Mixed use, transit-oriented infill development
Underground parking and
“green” tailgating (possible
future development)
C. COP @ MLK Redevelopment Concept
http://www.junctionatl.org/wp-content/uploads/2012/07/Public-Meeting-No2-
Presentation_2012-0710.jpg
MMPT Concept
http://lcweb2.loc.gov/service/pnp/highsm/17000/17028v.jpg
Union Station, D.C
D. AUC Gateway Existing Conditions
D. AUC Gateway Intersection Design Possible Lane Conversions
D. AUC Gateway Redevelopment Concept
CLEOPAS R. JOHNSON PARK
Mixed use infill development
Student housing, hotel and conference
center for AUC
D. AUC Gateway Redevelopment Concept
http://www.pdx.edu/cecs/our-commitment-to-green
http://alt.coxnewsweb.com/cnishared/tools/shared/mediahub/02/17/26/slideshow_1261723_auc.0909g.jpg
PSU Streetcar
AUC Ped-way
Connections to: • Attractions
– Dome – Philips Arena – Centennial Park
• Schools – AUC & Library – GA Tech
• Transportation – MMPT – Edgewood
Streetcar – MARTA Rail
Streetcar Concept
Phasing Timeline
1 to 3 years 3 to 7 years 7 to 10 years
Site A Vine City Station
Vine City Promenade, sidewalk & streetscape enhancements, build
stormwater mitigation
New stadium: new streets connecting
through GWCC campus to Downtown
Expand development of Vine City Station TOD, continue developing
GWCC campus
Site B MLK @ Northside
Minor streetscape enhancements, close Mitchell St. jog, bike facility on MLK, infill development, new
greenspace
New stadium: new streets connecting the
N-S grid to MLK, mixed-use infill surrounding
stadium
Extend Streetcar down MLK to Northside
Site C COP @ MLK
Sidewalk & streetscape enhancements,
conversion of COP to 2-way, convert vacant lots
into temporary stormwater catchment
New stadium: new streets connecting east
into Downtown and south to Castleberry, capping of the Gulch
Development over the newly capped Gulch, MMPT construction,
Streetcar down COP to MLK
Site D AUC Gateway
2-way conversion of Trenholm & Hills, bike facility on Greensferry,
Brawley & Lowery, streetcar projections
Redevelopment of vacant land for AUC
housing/hotel/conference center, other mixed
use infill
Extension of streetcar down Fair St
Questions/Discussion