NEW YORK STATE DEPARTMENT OF TRANSPORTATION
NY Route 347- Design Build Phase 2
Mount Pleasant Road to Terry Road
PIN 0054.22, contract D900014
Draft Request for Proposals
RFP Informational Meeting
December 19, 2013
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Rules of Contact
Catherine TrainaAttn: NY Route 347 – Mt. Pleasant Rd. to
Terry Rd.Office of Contracts Management
New York State Department of Transportation50 Wolf Road, 6th Floor
Albany, New York [email protected]
2
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Agenda
Project Overview Procurement Schedule Project Requirements Status of :
Adjacent Projects
ROW
Utilities General Contract Information RFP Content Quality Control & Quality Assurance Evaluation and Selection Additional Information and Submission Guidelines Questions and Answers
3
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road General Location
TOTAL FEIS PROJECT LIMIT
Design-Bid-Build Project (Completed)
Design-Build Phase 2 Project Location
Design-Build Phase 1 Project under construction
4
Bike
Path
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road General Location
5
EndStart
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Anticipated Procurement Schedule
Activity Due Date
Draft RFP Info Meeting December 19, 2013
Final RFP to Shortlisted Firms January 2, 2014
Final Date for Requests for Changes to Proposer’s Organization and Personnel February 19, 2014
Final Date for receipt of Proposer Questions February 26, 2014
Final Addendum and/or Responses to Proposer Questions March 5, 2014
Proposal Due March 19, 2014
Selection of Best Value Mid April, 2014
Execution of Contract Late May, 2014
Notice to Proceed June, 2014
6
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road General Scope of Work
Widening of NY Route 347 with additional travel lanes and shared-use path for pedestrians and bicyclists in a Manner that Maintains the Corridor Theme;
Pedestrian facility design and installation; Bus turnouts and enhanced bus stop design and
installation; Extensive landscape design and installation including,
but not limited to: vegetated screening, planted raised median, street trees, vegetated drainage features;
Invasive species removal as shown on the Indicative Plans
Concrete sound wall design and installation;
7
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road General Scope of Work (Continued)
Relocation and/or preservation of existing utilities;
ITS Installation and integration with the existing INFORM system;
Traffic signals; Installation of street and pedestrian lighting. Signing & pavement markings; Work Zone Traffic Control; Drainage; GreenLITES Certification at Evergreen Level;
8
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road General Scope of Work (Continued)
All Other Items of Work Necessary to Complete the Project Safely, On Schedule, and in Compliance with the Contract Documents including the NY Route 347 Aesthetic Design Guide.
9
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Proposed Typical Cross Section
New Sound Wall(s) or Low Screen
at/near ROW Line
10
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Proposed Typical Plan
11
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Proposed Greenway Stop
12
Think holistically about how the design and construction decisions will affect the final aesthetic design of the roadway.
Ensure the RFP requirements as it relates to the Aesthetic Design Guide are met throughout various stages of the project.
The Technical Solutions should reflect a collective design of related elements: Tree Inventory, anticipated vegetation removals, and proposed planting Aesthetic design of concrete materials ie. sound walls, retaining walls,
and median barrier Shared-use path alignment, Greenway Stop, and associated
transportation features ie. bio-swales, drainage basins, rain garden, etc Bus stop enhancements ie. decorative pavement, bus shelter, solar
lighting, bike racks
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Aesthetic Design
13
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Status
Status of : Adjacent Projects ROW Utilities and Suffolk Co Water
14
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Adjacent Projects
PIN/Description: 0054.20 (D900012) – NY 347
Safety and Mobility Improvements from NY 111 to Mt. Pleasant Road
This is a Design-Build project with anticipated completion date of May 2015.
WZTC: Long term lane closures Design Build team: Posillico Civil and
AECOM
15
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Right-of-Way
The Department anticipates that all additional ROW it deems necessary for the Project will be acquired prior to the Notice to Proceed (June, 2014) in accordance with DB §107-22. No relocations are required as a result of this project.Should the Design-Builder identify any additional ROW needs for the project, it shall be acquired in accordance with DB §107-22.
16
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Utility Coordination – Existing Utilities
In accordance with Part 4 – Utility Requirements, Design-Builder is responsible for: Appointing a single dedicated person responsible for
managing all utility coordination; Verifying utility facility locations; Identifying & resolving potential conflicts not yet
documented; Providing information on the need for any additional utility
easements; Coordinating with owner for utility relocation; Provide stakeout and final layout for utility relocations Protecting existing utilities; Cost to repair utility damage caused by Design-Builder; Informing the Department of all meetings/correspondence
with utility owners; Being Party to and signing the Three-Party Utility
Agreement.
17
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Utility Coordination – Existing Utilities
Long Island Power Authority (LIPA) and Verizon (Aerial):– Approximately 62 poles carrying electric, telephone
and cable on both sides of NY 347 (to remain in service);
– Poles are owned by LIPA or Verizon- LIPA owns 36; Verizon owns 26. The current pole heights vary from approximately 35 feet to 45 feet;
– Service connections to businesses and homeowners originate from the pole line along NY 347 (to remain in service);
– There are third party attachments, including Cablevision and LI Fiber;
– There are 4 overhead transfer lines that feed to the communities to the north and south of NY 347.
18
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Utility Coordination – Existing Utilities
National Grid Gas− There is an existing 8” steel main in the center
median of NY 347;− National Grid shall perform all work to relocate this
main out of the center median;− This relocation is anticipated to take 6 weeks;− There are steel gas mains located on the east side of
Terry Rd. – a 4” main south of NY 347, and a 6” main north of NY 347. If offsets are required due to pavement widening and/or drainage modifications, National Grid anticipates requiring approximately 2 weeks to complete this work once the site has been marked out and made available.
19
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Utility Coordination – Existing Utilities
Verizon (Underground):− There is a seven (7) conduit - 4” PVC duct bank with a buried
copper cable along the existing south side of NY 347 from Mt Pleasant Road to Hidden Ponds Drive, with approximately 30” cover;
− There are 3 manholes associated with these conduits; these manholes are to be considered fixed objects which cannot be relocated;
− There is also an underground 15 conduit PVC duct bank (5 across and 3 deep) that runs along the east side of Terry Road that and crosses NY Route 347;
− Manholes associated with these conduits are located either side of NY Route 347; additional manholes exist within the project limits on Terry Road;
− Should complete relocation of duct bank and buried cable between manholes be required, Verizon will need at least 10 weeks to complete the work; Verizon shall be responsible for all relocation work;
− Verizon will require approximately 2 weeks to offset conduits and/or cable at each conflict location;
20
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Utility Coordination – Existing Utilities
Suffolk County Water
– There is a 12” water main on NY 347 in the vicinity of the center median from Mount Pleasant Road to Terry Road and beyond;
– These water mains shall be relocated to the south side of NY 347 by the Design-Builder;
– The Design Builder shall be responsible for all costs to design and reconstruct these mains as well as all service connections, hydrants and valves
– There is also a 12” water main that runs along the west side of Terry Road.
21
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Contract Information
Lump Sum Design-Build Contract; Best Value Selection Process (50% Price, 50% Quality); Project Completion Date shall be the earlier of:
April 30, 2016; or The number of days past NTP proposed by the successful
Proposer on Form SCD (ITP Appendix D) There is one Interim Completion Milestone (Permanent
Transfer of all Traffic to Final Lane Configuration) There is a Payment Schedule provided in the RFP; $ 80,000.00 Stipend to Unsuccessful Proposers; Liquidated Damages may be imposed for not meeting
the Interim Completion Milestone date and the Project Completion date;
Escrow Submission of Bid Documents for Successful Proposer;
22
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Contract Information
There is a Buy America Clause There is an Iran Divestment Clause There is a DBE Participation Goal 15% All Environmental permits and ROW by the Department
based on 30% design plans, including NYSDEC and USACE Fresh Water Wetlands Permits
The Design-Builder is responsible for complying with the requirements of Environmental permits obtained by the Department, including submission of final detailed plans to permitting agencies for review and approval
The Design-Builder shall be responsible for all costs and/or delays associated with inconsistencies between the final plans and the approved permits, including any necessary re-permitting and/or redesign. modification
All Construction Related Permits (i.e., SPDES) by Design-Builder
23
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Contract Information (Continued)
RFP Documents: Instructions to Proposers Part 1: D-B Agreement Part 2: General Provisions, Section DB 100, Part 3: Project Requirements (Scope of Work) Part 4: Utility Requirements Part 5: Special Provisions (Standard Specification Changes For DB
Use) Part 6: RFP Plans (Indicative Plans Only) Part 7: Engineering Data (NY Route 347 - Aesthetic Design Guide) Part 8: Special Specifications (New DB Specifications) Part 9: The Design Builder’s Proposal Part 10: Addenda (If Any)
Reference Documents: On Department’s web site (Not Part of the Contract Documents)
24
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Quality Control (QC)
QC is Design-Builder’s Responsibility Design-Builder shall appoint a QC Manager
responsible for QC Plan for both Design and Construction
Design QC shall be by the Designer in accordance with the QC Plan
Construction Inspection shall be by an Independent Engineering Firm (Hired by the Design-Builder)
Materials Testing shall be by an Independent Testing Firm or Laboratory (Hired by the Design-Builder)
The Independent Testing Firm shall report to the Construction Inspection Firm
Offsite Plant Quality Control will be performed by the Department
25
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Quality Assurance (QA)
Design and Construction QA is the Department’s Responsibility
The Department may perform QA on any of the Design-Builder’s activities
The Department will utilize an independent Consultant to perform QA of the Design-Builder’s Designs
Construction QA will be performed by Department staff
Offsite Plant Quality Assurance will be performed by the Department
26
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road RFP Evaluation and Selection
Pass/Fail Evaluation Factors Legal – Financial – Administrative – DBE Compliance - Price Proposal
(Bond/Conformance)
Quality Evaluation Factors (50%) Key Personnel (28%) Management Approach (35%)
Overall Design-Build Team Organization (12%) Design Management Plan (5%) Construction Management Plan (8%) Quality Control Plan (10%)
Technical Solutions (27%) Design Approach (7%) Construction Approach (10%) CPM Schedule (10%)
Project Support (10%)
Price (50%)
Proposers must obtain a minimum
score of 60% of Quality Evaluation
factors
27
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Additional Information – Submission Guidelines
All proposals must be self-contained.• Proposals should not have links to external
web sites.• Proposals should contain all information
needed for evaluation. Do not “assume the Department knows” your
firm and it’s experience/qualifications. Make sure the schedule you propose includes all
anticipated time associated with the final design, QC/QA review, production, and construction of project materials such as the concrete sound walls.
28
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Additional Information – Submission Guidelines
Submit ALL Forms required. Do not alter any Form unless indicated on the
Form. Do not add any appendices or attachments to the
Forms. Do not include photographs or illustrations unless
specifically indicated. Do not submit
Form SA (Stipend Amendment) Form BDEA (Bid Document Escrow Agreement) PAB (Payment Bond (Labor and Material Bond)) PEB (Performance Bond (Faithful Performance Bond))
29
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Additional Information – Submission Guidelines
Responses to Proposer Questions will be posted on the Department’s Project Web Site
Reference Documents are Posted on the Department’s Project Web Site:
https://www.dot.ny.gov/main/business-center/designbuildproject4
Reference Documents include: Design Report / FEIS “As Builts” Record Plans Regional Design Sheets Other Documents
30
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Rules of Contact
Catherine TrainaAttn: NY Route 347 – Mt. Pleasant Rd. to
Terry Rd.Office of Contracts ManagementNew York State Department of
Transportation50 Wolf Road, 6th Floor
Albany, New York [email protected]
31
NY Route 347- Design Build Phase 2Mount Pleasant Road to Terry Road Questions and Answers
Questions ?
32