New Decade - New Challenges Annual Conference September 2010
Water Services Training Group
14th Annual Conference
New Decade – New Challenges9th September 2010
New Decade - New Challenges Annual Conference September 2010
Water Conservation / Mains Rehabilitation – Implementation 2010-2012
Gerry O’Donoghue
Senior Adviser, Water Inspectorate
DEHLG
Contents
Background WSIP 2010 – 2012 Present Status of Water Mains Rehab Specific Issues Going forward
New Decade - New Challenges Annual Conference September 2010
Background
Circular L6/2007 – Water Conservation Circular L6/09 – Needs Assessment Expectation that rehabilitation works
would have commenced by end 2010. WSIP 2010 - 2012
New Decade - New Challenges Annual Conference September 2010
WSIP 2010 -2012
€321m for contracts to commence 2010-2012
Potential replacement of 3% of the national public network
Challenge is managing the physical delivery
New Decade - New Challenges Annual Conference September 2010
Status of Water Conservation / Rehabilitation
A few Local Authorities have not yet fully completed stage 1 and stage 2 works.
21 have submitted Rehabilitation Strategies
14 have submitted Rehabilitation Works proposals under L6/2007.
Rehabilitation Works budgets have been approved for 10 of these Local Authorities
New Decade - New Challenges Annual Conference September 2010
Stages
Rehabilitation StrategyRehabilitation Works Schemes –
PlanningContract Document StageTender StageFinal Report Stage
New Decade - New Challenges Annual Conference September 2010
Specific Issues (1/2)
Prioritisation of Works / Role of Circular L6/2007
Flexibility of Scope Rehabilitation Works Proposals WSIP Allocations (carry-over or
redistribution) Conditions of Contract (CWMF) Backyard Connections
New Decade - New Challenges Annual Conference September 2010
Specific Issues (2/2)
Lead Services Leakage in New Developments Powers under Water Services Act Staffing Training
New Decade - New Challenges Annual Conference September 2010
Prioritisation of Works / Role of Circular L6/2007
L6/2007 is a procedural Circular. Rehabilitation Strategy includes DMA
prioritisation. Works Proposals list prioritised mains.
There is an underlying need for competent technical judgements to underpin the projects.
New Decade - New Challenges Annual Conference September 2010
Prioritisation of Works / Role of Circular L6/2007
“The information required in these Guidelines provides indicative measures of need and value. Nothing within the guidelines should prevent the identification and implementation of appropriate rehabilitation works yielding the best value. Accordingly the final decisions on works to be undertaken should allow discretionary technical judgements, supported by evidence. For example, while the general approach proposed is to prioritise initially on a DMA basis, proposals may include specific limited works to address particularly problematic mains within lower ranked DMAs.”
New Decade - New Challenges Annual Conference September 2010
Flexibility of Scope
Data is key to asset management, leakage control and rehabilitation planning.
Rehabilitation Works Proposals will rely on data collected at Stages 1 and 2, other available records and targeted investigations.
It is inevitable that following approval of a Rehabilitation works proposal further information can come to light.
New Decade - New Challenges Annual Conference September 2010
Flexibility of Scope
The procedure should not be a constraint on making appropriate adjustments based on improved data.
However; Adjustments to scope must be justifiable under the
principles of Circular L6/2007. Any such adjustments should preferably be
identified prior to construction works. Projects should be managed within approved
budgets, and where necessary prior DEHLG approval should be obtained for budget increases.
New Decade - New Challenges Annual Conference September 2010
Rehabilitation Works Proposals
Observations from submissions to date: Purpose is to demonstrate scope and value of
each element – different elements should not be grouped on a single form.
Ensure required A4 drawing is included. Economic assessment – value of water saved
– average or marginal cost? Average cost better reflects the potential longer term savings in capital investment.
New Decade - New Challenges Annual Conference September 2010
WSIP Allocations (carry-over or redistribution)
Overall expenditure targets should be met.
Where allocations will not be drawn down within the term of the Programme, funding may be reallocated by the Department.
New Decade - New Challenges Annual Conference September 2010
Conditions of Contract (CWMF)
All construction related contracts to be under the Capital Works Management Framework.
“Public Works Contract for Civil Engineering Works designed by the Employer” has been used. Adequate site investigation (location of
mains and services) Change Orders – plan to ensure value
New Decade - New Challenges Annual Conference September 2010
Backyard Services
Part 5 of Circular L6/2007 – Private Side Leakage “Where justified under the criteria for prioritising
rehabilitation works, the cost of providing alternative communication pipes and connections to the front of properties is eligible for funding under the rehabilitation programme.”
“This work should only be undertaken where all the property owners will connect to the new pipes, as the saving is only realised when the backyard services can be decommissioned.”
New Decade - New Challenges Annual Conference September 2010
Backyard Services
Only works on public side are eligible for Department funding.
Grants may be available to homeowners under specific circumstances, e.g. Housing Aid for Older Persons Scheme.
New Decade - New Challenges Annual Conference September 2010
Backyard Services
New Decade - New Challenges Annual Conference September 2010
Backyard Services
New Decade - New Challenges Annual Conference September 2010
Waterworks
Service ConnectionDistribution System
Backyard Services
New Decade - New Challenges Annual Conference September 2010
Waterworks
Service connectionDistribution System?
Lead Services
WSIP 2010-2012:
“Funding is available for the replacement of lead connections on the public side, in order to meet the current and 2013 limits for lead in water. It is expected that Water Services authorities would prioritise any such works required in developing their Mains Rehabilitation Strategies, taking account of EPA guidance”.
New Decade - New Challenges Annual Conference September 2010
Lead Services
New Decade - New Challenges Annual Conference September 2010
Lead Services
Local authorities should identify and remove as a matter of priority any remaining lead distribution mains.
Opportunistic replacement. Planned and targeted replacement of lead
communication pipes over time, prioritising lead service connections and lead plumbing in Local Authority own buildings.
2013 parametric limit 10ug/l
New Decade - New Challenges Annual Conference September 2010
Lead Services
Water Conservation/ Mains Rehabilitation Programme:Replacement of lead mains should be
prioritised,Replacement of lead connections (Public
side) eligible as a component of Rehabilitation Works Proposals.
New Decade - New Challenges Annual Conference September 2010
Leakage in New Developments
Part 5 of Circular L6/2007 Developer responsible until taken in
charge Some Local Authorities charge for water
on metered basis at commercial rates until taken over.
New Decade - New Challenges Annual Conference September 2010
Powers under Water Services Act
Local Authorities have been serving notices under Water Conservation Regulations 2008, SI 527 of 2008
New Decade - New Challenges Annual Conference September 2010
Staffing
To date no request for approval to numbers for temporary staff for DEHLG Water Services projects has been refused. This applies to RE and Project Office staff where Posts funded by DEHLG Applications supported by Water Services
DEHLG.
New Decade - New Challenges Annual Conference September 2010
Staffing
It is likely that a regional approach to project offices would reinforce this position.
For other staff, the overall restriction on numbers apply.
New Decade - New Challenges Annual Conference September 2010
Training
WSTG Courses Distribution System Operation and
MaintenanceWater ConservationWater Treatment & Distribution -
AppreciationLeakage Control - ManagersLeakage Control - Operatives Drinking Water Incident Management
training
New Decade - New Challenges Annual Conference September 2010
Training
New Decade - New Challenges Annual Conference September 2010
In Conclusion
Straightforward Procedures Maximised devolution consistent with
Departments oversight role Funding available A great need for works to be done Operational benefits for Local Authorities
and Customers
New Decade - New Challenges Annual Conference September 2010
In Conclusion
Full delivery of Water Rehab element of the WSIP (€321m), and demonstrated benefits, will support the case for continued funding.